PROYECTO
EJECUTA
UBICACIN
FECHA
TIEMPO
CODIGO
01
01.01
01.02
01.03
01.04
01.05
02
02.01
02.02
02.03
02.04
03
CRONOGRAMA DE AVANCE
PROYECTO
EJECUTA
UBICACIN
FECHA
TIEMPO
CODIGO
03.01
03.02
03.03
03.04
03.05
04
04.01
04.02
04.03
04.04
04.05
04.06
CRONOGRAMA DE AVANCE
PROYECTO
EJECUTA
UBICACIN
FECHA
TIEMPO
CODIGO
05
05.01
05.02
05.03
05.04
06
06.01
06.02
06.03
06.04
06.05
06.06
CRONOGRAMA DE AVANCE
PROYECTO
EJECUTA
UBICACIN
FECHA
TIEMPO
CODIGO
06.07
06.08
CRONOGRAMA DE AVANCE
PROYECTO
EJECUTA
UBICACIN
FECHA
TIEMPO
CODIGO
06.09
07
07.01
07.02
07.03
08
08.01
08.01.01
08.01.02
08.01.03
08.02
08.02.01
CRONOGRAMA DE AVANCE
PROYECTO
EJECUTA
UBICACIN
FECHA
TIEMPO
CODIGO
08.02.02
08.02.03
08.03
08.03.01
08.03.02
08.03.03
09
09.01
10
10.01
10.02
11
CRONOGRAMA DE AVANCE
PROYECTO
EJECUTA
UBICACIN
FECHA
TIEMPO
CODIGO
11.01
11.02
11.03
12
12.01
12.02
12.03
12.04
13
13.01
13.02
13.03
CRONOGRAMA DE AVANCE
PROYECTO
EJECUTA
UBICACIN
FECHA
TIEMPO
CODIGO
COSTO DIRECTO
% AVANCE PARCIAL
% AVANCE ACUMULADO
DESCRIPCION
OBRAS PROVISIONALES
ALMACEN,CASETA DE GUARDIANIA Y OFICINA DE RESIDENTE
AGUA PARA LA OBRA
CERCO PROVICIONAL DE ESTERAS
SERVICIOS HIGIENICOS PARA EL PERSONAL DE OBRA
MOVILIZACIN Y DESMOVILIZACIN DE MAQUINARIAS Y EQUIPOS
SEGURIDAD Y SALUD
EQUIPOS DE PROTECCION COLECTIVO
EQUIPOS DE PROTECCION INDIVIDUAL
SEALIZACION TEMPORAL DE SEGURIDAD
MITIGACION DEL IMPACTO AMBIENTAL
DESMONTAJES
DESCRIPCION
DESCRIPCION
OBRAS PRELIMINARES
LIMPIEZA DEL TERRENO MANUAL
TRAZADO Y REPLANTEO INICAL
TRAZADO Y REPLANTEO DURANTE LA EJECUCION DE LA OBRA
DESGASIFICACION DE TANQUE DE ALMACENAMIENTO
MOVIMIENTO DE TIERRAS
EXCAVACION DE ZANJAS P/ZAPATAS
EXCAVACION DE ZANJA P/SUB-ZAPATAS CON EQUIPO
EXCAVACION DE ZANJAS P/CIMIENTO
EXCAVACION EN TERRENO SUELTO P/SARDINEL SUMERGIDO EN FORMA MANUAL
RELLENO CON MATERIAL DE PRESTAMO
RELLENO CON MATERIAL PERMEABLE GRANULAR (PRESTAMO)
DESCRIPCION
DESCRIPCION
DESCRIPCION
DESCRIPCION
DESCRIPCION
COSTO DIRECTO
% AVANCE PARCIAL
% AVANCE ACUMULADO
PPTO
MES 01
MES 02
9,207.77
2,118.66
2,118.66
1,097.36
1,097.36
2,559.53
2,559.53
889.85
889.85
2,542.37
2,542.37
7,521.14
498.50
498.50
4,886.64
4,886.64
636.00
636.00
1,500.00
1,500.00
42,912.48
PPTO
MES 01
MES 02
2,960.82
2,960.82
328.98
328.98
10,243.89
10,243.89
23,277.06
23,277.06
6,101.73
6,101.73
95,857.17
3,859.70
3,859.70
12,051.87
10,378.00
1,673.87
27,919.64
27,686.98
232.66
1,751.27
1,532.36
218.91
30,252.70
30,252.70
20,021.99
20,021.99
PPTO
MES 01
MES 02
27,289.04
3,225.80
3,225.80
1,771.31
1,771.31
3,110.59
3,110.59
19,181.34
19,181.34
99,845.76
15,172.33
15,172.33
31,863.00
31,863.00
1,926.30
316.29
32,290.65
10,687.45
1,926.30
289.93
PPTO
MES 01
2,957.91
2,610.55
MES 02
2,883.96
PPTO
MES 01
MES 02
2,021.28
76,481.84
3,396.83
3,396.83
59,540.70
13,544.31
59,540.70
13,544.31
411,752.51
149,518.92
84,482.90
84,482.90
9,596.98
9,596.98
55,439.04
55,439.04
199,123.25
72,708.29
PPTO
MES 01
MES 02
44,569.87
23,956.31
81,845.09
56,609.52
63,110.34
14,812.55
14,812.55
34,507.06
21,207.46
13,790.73
13,790.73
6,359.94
6,359.94
31,663.62
26,714.88
4,948.74
32,100.09
26,714.88
13,299.60
PPTO
MES 01
MES 02
6,814.46
12,215.65
13,069.98
26,840.33
1,128.93
21,853.00
2,245.50
1,612.90
71,829.03
10,185.52
51,801.05
9,842.46
1,092.65
PPTO
939,660.72
MES 01
MES 02
253,134.97
26.94%
26.94%
379,272.61
40.36%
67.30%
MES 03
MES 03
MES 03
26.36
32,290.65
10,687.45
MES 03
73.95
2,610.55
MES 03
2,021.28
72,708.29
MES 03
20,613.56
25,235.57
6,359.94
4,948.74
MES 03
6,814.46
12,215.65
13,069.98
1,128.93
20,760.35
2,245.50
1,612.90
10,185.52
51,801.05
9,842.46
MES 03
307,253.14
32.70%
100.00%