URAIAN PEKERJAAN
1
1
2
3
4
5
6
7
8
9
10
11
12
PEKERJAAN PERSIAPAN
PEKERJAAN TANAH
JUMLAH HARGA
PEKERJAAN PONDASI
PEKERJAAN BETON
PEKERJAAN DINDING
PEKERJAAN KUSEN PINTU DAN JENDELA
PEKERJAAN ATAP
PEKERJAAN PLAFOND
PEKERJAAN LANTAI
PEKERJAAN INSTALASI LISTRIK
PEKERJAAN INSTALASI AIR DAN SANITASI
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
PEKERJAAN PENGECATAN
Rp
BAHAN
3
19,951,789
32,009,291
125,811,232
30,543,097
29,511,467
41,017,674
15,340,774
13,173,291
19,859,250
34,532,200
UPAH
4
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
7,067,318
7,389,684
7,242,445
22,876,906
20,043,260
9,202,506
4,901,671
6,595,512
8,859,752
17,940,000
3,340,597
5,850,898 Rp
21,335,291
H HARGA
TOTAL
ALAT
5
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
388,458
55,011
5,827,810
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
27,407,564
7,389,684
39,251,737
148,688,138
50,586,357
38,713,972
45,974,355
21,936,286
22,033,043
37,799,250
43,700,607
Rp
2,413,120
Jumlah I
Keuntungan Max 10 %
Jumlah II
Pajak 10 %
Rp
Rp
Rp
Rp
Rp
29,599,308
513,080,301
51,308,030
564,388,331
56,438,833
Jumlah III Rp
620,827,164