1.1.2)Hidrante H.2
Q(H2) = K x h
Q(H2) = 31,62 x 41,91
Q(H2) = 204,70l/min (3,41l/s)
Q(total) = 3,33 +3,41 = 6,74 l/s (404,40 l/min)
PCT (trecho B/C) - 66mm (COBRE)
- Desnvel entre B/C = 8,45 m
CR = 41,15m
CE = 58,20m
CT = 99,35m
j = 0,07916 m/m
PCT (B/C) = 7,86 m.c.a.P(B) = 41,91+8,45+7,86
P(B) = 58,22 mca
PCT (trecho A/B) - 79mm (COBRE)
- Desnvel entre A/B = 0,50m
CR = 1,40m
CE = 4,80m
CT = 6,20m
Q = 6,74 l/s (404,40 l/min)
j =0,03276 m/m
PCT (A/B) = 0,20 m.c.a.
P(Bomba) = 58,22+0,50+0,20
P(Bomba) = 58,92 mca
1.1.3)Bomba de Incndio
Hman = 58,92 mca
Q = 6,74 l/s = 404,40l/min = 24,26 m3/h
Q = 24,26m3/h