NAMA KEGIATAN
KODE REKENING
TAHUN ANGGARAN
LOKASI / JALAN
KELURAHAN
KECAMATAN
WILAYAH
No.
I
1
2
3
4
5
II
PEKERJAAN PENDAHULUAN
Papan nama proyek multiplek 8 mm
Foto proyek 3 phase colour
Sewa perancah / schafolding
Pembersihan lapangan
Buang puing Ex. Bongkaran keluar lokasi
Jumlah
Harga Satuan
( Rp. )
Volume
1.00
3.00
12.00
76.96
35.31
bh
set
unit
m2
m
615,441.50
65,200.00
43,270.70
18,187.05
100,419.52
137.60
137.60
137.60
137.60
17.20
42.40
17.20
m2
m2
11,871.01
27,945.58
m2
m2
m'
m'
m'
239,949.20
74,213.34
68,001.52
127,040.59
170,809.24
76.96
76.96
m2
m2
279,512.36
76.96
89.60
m2
m'
46,641.86
87,045.00
0.94
9.87
322,971.09
133,878.04
III
PEKERJAAN PLAFOND
1 Pembongkaran plafond (bongkaran tidak dipakai kembali)
2 Pasang rangka langit-langit hollow 40.40.2 modul 60x60
3 Pekerjaan langit-langit gypsum board (120x240) tebal 9mm
4 Pekerjaan list langit-langit gypsum lebar 10 cm
Jumlah
IV
1
2
3
4
5
17,806.52
9.87
9.87
11.20
m2
m2
m2
m'
29.60
m2
29.60
PEKERJAAN PENGECATAN
1 Mengikis/mengerok permukaan cat tembok lama
286.72
m2
17,277.10
128.00
57,774.31
158.72
m2
43,142.41
76.96
m2
44,399.41
Plesteran dinding 1 pc : 4 ps
Pekerjaan acian dinding
Pekerjaan ring balok beton bertulang (10 x 15) Cm
Jumlah
69,941.15
40,847.06
114,337.32
6,725.01
239,559.00
Jumlah
VI
3
4
Cat Dinding Exterior (1 Lapis Plamur : 1 Lapis Cat Dasar : 2 Lapis Cat Exterior)
Cat Dinding Interior (1 Lapis Plamur : 1 Lapis Cat Dasar : 2 Lapis Cat Interior)
Pengecatan Plafond 2 Lapis Dengan Cat Tembok interior dgn Kuas Roll Termasuk
Plamur
Pengecatan listplank ( 1 Lapis Plamur : 1 Lapis Cat Dasar : 2 Lapis Cat penutup)
Jumlah
8.48
m2
43,180.52
Jumlah Harga
( Rp. )
615,441.50
195,600.00
519,248.40
1,399,675.37
3,545,773.08
6,275,738.35
1,633,450.98
3,845,311.81
33,017,009.92
10,211,755.58
1,169,626.14
5,386,521.02
2,937,918.93
58,201,594.38
1,370,389.78
21,511,271.23
3,589,557.55
7,799,232.00
34,270,450.55
302,300.94
1,321,376.25
690,319.15
403,160.48
1,280,577.98
3,997,734.81
199,060.30
7,090,946.40
7,290,006.70
4,953,690.11
7,395,111.68
6,847,563.32
3,416,978.59
366,170.81
22,979,514.51
REKAPITULASI
RINCIAN ANGGARAN BIAYA (RAB)
UNIT/SATUAN KERJA
KODE REKENING
NAMA KEGIATAN
TAHUN ANGGARAN
LOKASI KEGIATAN
KELURAHAN
KECAMATAN
WILAYAH
NO.
URAIAN PEKERJAAN
I.
II.
III.
IV.
V.
VI.
JUMLAH (Rp.)
PEKERJAAN PENDAHULUAN
PEKERJAAN RANGKA ATAP DAN PENUTUP ATAP
PEKERJAAN PLAFOND
PEKERJAAN DINDING / SOPI-SOPI
PEKERJAAN PASANGAN LANTAI & KERAMIK
PEKERJAAN PENGECATAN
Terbilang :
6,275,738.35
58,201,594.38
34,270,450.55
3,997,734.81
7,290,006.70
22,979,514.51
133,015,039.30
13,301,503.93
146,316,543.23
DIBULATKAN
146,317,000.00
Seratus empat puluh enam juta tiga ratus tujuh belas ribu Rupiah
Catatan :
1. RAB ini dihitung berdasarkan harga satuan yang tercantum di sistem E-Budgeting tahun anggaran 2015
2. Item dan Volume dalam RAB ini tidak mengikat dalam Pelelangan, yang mengikat dalam pelelangan/
pelaksanaan adalah gambar, RKS dan Berita Acara Aanwizjing
Jakarta,
2015
Disetujui oleh,
Suku Dinas Perumahan Dan Gedung Pemda
Kota Administrasi Jakarta Pusat
Dibuat Oleh
Kasie.Perencanaan Teknis
Suku Dinas Perumahan Dan Gedung Pemda
Kota Administrasi Jakarta Pusat
Diketahui oleh,
Suku Dinas Pendidikan Wilayah II
Kota Administrasi Jakarta Pusat