TABEL PERHITUNGAN KAPASITAS PRODUKSI ALAT BERAT

1.
2.
3.
4.

TABEL PERHITUNGAN KAPASITAS PRODUKSI ALAT BERAT


BULLDOZER
WHEEL LOADER
HYDRAULIC EXCAVATOR
DUMP TRUCK

TABEL PERHITUNGAN KAPASITAS PRODUKSI ALAT BERAT


BULLDOZER
INPUT :
1.

TYPE BULLDOZER

D6

2.

BLADE FACTOR

Ringan

3.

HAULING DISTANCE (M')

20

4.

JOB EFFICIENCY
- Equpment Efficiency

90%

- Operator Efficiency

Sedang

- Natural Efficiency

Terang, segar

122.00

OUTPUT :
KAPASITAS PRODUKSI BULLDOZER

M3/Hr

KSI ALAT BERAT

(Loose Cubic Meter)

Bulldozer

CALCULATION OF PRODUCTION BULLDOZER CAPACITY


q x 60 x e x E
Cm

Q=

122.00 m3/hr (loose)

Where :
Q
q
e
E
Cm
1.

=
=
=
=
=

=
=
=
=
=

Hourly producion (m3/hr)


Production per cycle (m3)
Grade factor
Job effeciency
Cycle time (in minute)

=
=
=
=
=

Production per cycle (q)


For dozing operation, the blade capacity is theoritically
calculated as follow :

122.00 m3/hr
2.86 m3
1.00
0.53
0.74 min.
2.86

Min.

q = q' x a
Where :
q'
= Blade capacity
a
= Blade factor
2.

=
=

D6
Ringan

=
=

Cycle Time (Cm)


The time needed for a bulldozer to complete one cycle
(dozing, reversing and gear shifting) is calculated by
the following formula :
Cm

D
F

D
R

3.18 m3
0.90
0.74 Min.

( min)

Where :
D
= Haul distance (m)
F
= Forward Speed (m/min)
R
= Reverse speed (m/min)
Z
= Time required for gear shifting (min.)

=
=
=
=

=
=

(1).

Kecapatan maju, kecepatan mundur


Biasanya kecepatan maju berkisar antara 3 ~ 5 km/jam dan
kecepatan mundur antara 5 ~ 7 km/jam.
Jika mesin menggunakan TORQFLOW maka kecepatan maju diambil 0,75 dari maksimum sedangkan kecepatan mundur 0,85 maksimum.

(2).

Waktu yang diperlukan untuk ganti persnelling.

20.00
50
83
0.10

m'
m'/min
m'/min
min

Waktu untuk ganti persnelling


Mesin gerak langsung :
- dengan tongkat tunggal
- dengan tongkat ganda
Mesin-mesin TORQFLOW
3.

0.10 menit
0.20 menit
0.05 menit

Job Efficiency

0.53

E = E1 x E2 x E3
E1
E2
E3

= Equipment efficiency
= Operator efficiency
= Natural efficiency

=
=
=

Page 5

Sedang
Terang, segar

=
=
=

0.90
0.65
0.90

TABEL PERHITUNGAN KAPASITAS PRODUKSI ALAT BERAT


WHEEL LOADER
INPUT :
1.

TYPE WHEEL LOADER

WA250-1

2.

BUCKET FACTOR

Ringan

3.

HAULING DISTANCE (M')

10

4.

JOB EFFICIENCY
- Equpment Efficiency

0.90

- Operator Efficiency

Terampil

- Natural Efficiency

Terang, segar

122.00

OUTPUT :
KAPASITAS PRODUKSI WHEEL LOADER

M3/Hr

BERAT

(Loose Cubic Meter)

WA250-1
WA320-1

Ringan
Sedang
Agak sulit
Sulit

90% Terampil
80% Cukup
75% Sedang
Kurang

Terang, segar
Terang, panas, berdebu
Mendung
Gelap

10
20
30
40

DOZER SHOVELS AND WHEEL LOADERS


(LOAD AND CARRY)
XE
Q=
Where :
Q =
q =
Cm =
E =
1.

q X

60
Cm

XE

Hourly producion (m3/hr)


Production per cycle (m3)
Cycle time (Min.)
Job efeciency

=
=
=
=

122.00

=
=
=
=

122.00
2.10
0.67
0.65

Production per cycle (q)

2.1

q = q' x K
Where :
q'
= The heaped capacity given in the
specification sheet
K
= Bucket factor
2.

Cycle time (Cm)


D
D
=
+ VR + Z
Cm
VF
Where :
D
:
Hauling distance (m')
VF = Travel speed with load
VR = Return speed
Z
= Fixed time

WA250-1

Ringan

2.10
1.00
0.67

=
=
=

=
=
=
=

Ringan
Ringan

10.00
275.00
291.67
0.60

(1). Travel speed for wheel loader


Operation conditions
Good

Speed km/hr

Hauling on well compacted flat road, few bumps in road


surface, no meeting other machines, can concetrate on L&C.

Average

Few bumps on road surface, flat road,some auxiliary work


carrying large lumps of rock.

Rather poor

Bumps in road surface, high rate of auxiliary work.

Poor

large bumps in road,meeting other machines, difficult to


carry out smooth work,large amount of auxiliary work.

Loaded

Empty

10~23
16.5
10~18
14
10~15
12.5
9~12
10.5

11~24
17.5
11~19
15
10~16
13
9~14
11.50

(2). Fixed time (Z)

3.

Z = t1+t2+t3+t2

0.60

minute

Where :
Z :
0.60 ~ 0.75
t1 :
Loading time (0.20~0.35 min)
t2 :
Turning time (min.)
t3 :
Dumping time (min.)

0.20
0.15
0.10

minute
minute
minute

Job Efficiency
E = E1 x E2 x E3
E1 =
E2 =
E3 =

Equipment efficiency
Operator efficiency
Natural efficiency

0.648
=
=
=

Terampil
Terang, segar

=
=
=

0.90
0.80
0.90

m3/hr (loose)

m3/hr
m3
min

m3

m3

min.

m'
m/min
m/min
menit

TABEL PERHITUNGAN KAPASITAS PRODUKSI ALAT


HYDRAULIC EXCAVATOR
INPUT :
1.

TYPE EXCAVATOR

2.

BUCKET FACTOR

3.

CYCLE TIME
- Kedalaman & Kondisi Galian

- Sudut Swing Bucket

- Tempat Pembuangan

JOB EFFICIENCY
- Equpment Efficiency

- Operator Efficiency

- Natural Efficiency

4.

OUTPUT :
KAPASITAS PRODUKSI EXCAVATOR

GAN KAPASITAS PRODUKSI ALAT BERAT

YDRAULIC EXCAVATOR

PC200-6
Ringan
0m - 2m (ringan)
45o - 90o
Dumptruck

0.80
Terampil
Terang, segar

83.00

M3/Hr

(Loose Cubic Meter)

PC200-6
PC300-6

Ringan
Sedang
Agak sulit
Sulit

90% Terampil
80% Cukup
75% Sedang
Kurang

Terang, segar
Terang, panas, berdebu
Mendung
Gelap

10
20
30
40

0m - 2m (ringan)
2m - 4m (Ringan)
4m - lebih (Ringan)
0m - 2m (Rata2)
2m - 4m (Rata2)
4m - lebih (Rata2)
0m - 2m (Agak sulit)
2m - 4m (Agak sulit)
4m - lebih (Agak sulit)
0m - 2m (Sulit)
2m - 4m (Sulit)
4m - lebih (Sulit)

45o - 90o
90o - 180o

Dumptruck
Pembuangan

Backhoe

HYDRAULIC EXCAVATOR
EXCAVATION
Q=
Dimana
Q =
q =
Cm =
E =
1.

q X

3600
Cm

XE

83.00

m3/jam (loose)

:
Hourly producion (m3/hr)
Production per cycle (m3)
Cycle time (Min.)
Job efeciency

=
=
=
=

=
=
=
=

Production per cycle (q)

83.00 m3/jam
0.88 m3
22.00 Second
0.58
0.88

m3

q = q' x K
Where :
q' =
K
2.

The heaped capacity given in the


specification sheet
Bucket factor

PC200-6

Ringan

Cycle time (Cm)


Cm =

0.80 m3
1.10
22.00 second

Excavating time + swing time (loaded) +


dumping time + swing time (empty)

Where :
* Excavating time :
kedalaman gali dan kondisi galian.
Waktu gali (detik)
Kondisi gali/
Ringan
Rata-Rata
Kedalaman galian
0m - 2m
6
9
2m - 4m
7
11

6.00 second

Agak sulit

Sulit

15
17

26
28

Page 19

0m - 2m (ringan)

Backhoe

4m - lebih
*

3.

13

19

30

Waktu putar tergantung dari sudut dan kecepatan putar


Waktu putar (detik)
Sudut putar
45o - 90o
4~7
diambil
90o - 180o
5~8
diambil

5.00 second

45o - 90o

6.00 Second

Dumptruck

5
6

Waktu buang tergantung pada kondisi pembuangan material.


satuan (detik) :
Ke dalam
Dumptruck
5~8
diambil
Ke tempat
Pembuangan
3~6
diambil

6
5

Effisiensi Kerja.

Page 20

Backhoe

Lihat tabel 1.
E1 =
E2 =
E3 =

Faktor Kondisi Peralatan


Faktor Operator & Mekanik
Faktor Cuaca

Waktu gali (detik)


Kondisi gali/
Kedalaman galian
0m - 2m (ringan)
2m - 4m (Ringan)
4m - lebih (Ringan)
0m - 2m (Rata2)
2m - 4m (Rata2)
4m - lebih (Rata2)

=
=

Waktu
(detik)
6
7
8
9
11
13

Page 21

Terampil
Terang, se

=
=
=

0.80
0.80
0.90

Backhoe

0m - 2m (Agak sulit)
2m - 4m (Agak sulit)
4m - lebih (Agak sulit)
0m - 2m (Sulit)
2m - 4m (Sulit)
4m - lebih (Sulit)

15
17
19
26
28
30

Page 22

Backhoe

Perapian tebing :
A = (Lebar bucket - 0.3 m) x panjang perapian x 3600/Cm x E

Dimana :
A = produksi per jam (m2/jam)
Cm = Waktu siklus (detik)
E

1.

= Efesiensi Kerja
Lebar Bucket
Panjang perapian

54

54

10

=
PC200-6

=
=

Waktu siklus (Cm)

0.3

0.800

m'

1 m'
10 detik

Waktu siklus = Waktu perapian + waktu travel


Waktu Perapian =

Panjang perapian
Kecepatan perapian

Panjang
tebing
(m)
- 0.5
0.5 - 1
1-2
2-4
4 - lebih
Waktu travel = 8 ~ 12 detik
2.

Effisiensi kerja
Effisiensi kerja berkisar 0.2 ~ 0.4

1.00 m'

0.10 m/detik

Kecepatan
perapian
(m/detik)
0.20
0.10
0.08
0.05
0.02
=

10

detik

0.3

Page 23

Backhoe

Page 24

Backhoe

Page 25

Backhoe

Page 26

TABEL PERHITUNGAN KAPASITAS PRODUKSI ALAT BERA


DUMP TRUCK
INPUT :
1.

DUMP TRUCK CAPACITY

2.

LOADER EQUIPMENT

3.

EXCAVATION TYPE

4.

CYCLE TIME
- Hauling Distance (m')

- Average speed of loaded truck (Km/Hr)

- Average speed of empty truck (Km/Hr)

5.

JOB EFFICIENCY (Operating Condition)

OUTPUT :
KAPASITAS PRODUKSI EXCAVATOR

KAPASITAS PRODUKSI ALAT BERAT


DUMP TRUCK

11 Ton
Backhoe
Common
2000
20
40
Baik sekali

14.67

M3/Hr

(Loose Cubic Meter)

8 Ton
10 Ton
11 Ton
22 Ton

Wheel Loader
Backhoe

90% Terampil
80% Cukup
75% Sedang
Kurang

Terang, seg
Terang, pan
Mendung
Gelap

300 Common
500 Weathered Rock
1000 Rock
2000
3000
4000
5000
6000
7000
8000
9000
10000
15000

10
20
30
40
50
60
70
80

Baik sekali
Baik
Sedang
Buruk
Buruk sekali

Baik sekali

Buruk sekali

DUMP TRUCK 11 TON (Common)

q x 60 x Et
Cmt

Q=

Dimana :
Q = Hourly Production (m3/hr)
q = Production per Cycle (m3)
Et = Job Efficiency
Cmt = Cycle Time (min.)

=
=

14.67
11.74

=
=
=
=

14.67
4.06
0.81
13.43

1. Production per Cycle ( q )


q = n x q1 x K x E
Where :
n
:
q1
:
K
:
E
:

4.05504

Number of cycles required for backhoe to fill dump truck


Bucket capacity of Loader (m3)
Bucket factor of Loader
Job Effisiensi Loader

2. Cycle Time (Cmt)


The cycle time of a dump truck consist of the following factor :
1. Time required for backhoe to fill dump truck
2. Hauling Time
3. Time required for unloading (dumping)
4. Time required for returning
5. Time required for dump truck to be positioned for
loading and for the backhoe to start loading
Accordingly, the cycle time = (1)+(2)+(3)+(4)+(5)
The cycle time is calculated as follows :

Cmt

n. Cms
Loading
Time
(1)

D
V1
Hauling
Time
(2)

+ t1 +
Dumping
Time
(3)

D
V2

Returning
Time
(4)

=
=
=
=

8
0.80
1.10
0.58
13.43

+ t2
Spot and
Delay Time
(5)

=
=
=
=
=

2.93
6.00
0.50
3.00
1.00

13.43

Where,

n:

Cms:
D:
V1 :
V2 :
t1 :
t2 :

(1).

Number of cycle required for backhoe to fill dump truck


n = C1/q1 x K
C1
:
Rated capacity of Dump Truck
q1
:
Bucket capacity (m3) of Loader
K
:
Bucket factor of Loader.
Cycle time of backhoe (min.)
Hauling distance of dump truck (m)
Average speed of loaded truck (m/min)
Average speed of empty truck (m/min)
Time required for dumping + time required
for stand by until dumping is started (min.)
Time required for truck to be positioned and for backhoe
to start loading (min.)

Loading Time
The time required for a backhoe to load a dump truck
is obtained by the following calculation .

=
=
=
=
=
=
=
=
=

8
6.88
0.80
1.10
22.00
2000
20
40
0.5

2.93

22.00

Loading Time = Cycle time (Cms) x No. of cycles to


fill dump truck (n)
(a).

Cycle Time of Backhoe (Cms)


The cycle time of a backhoe is dependent on
the type of backhoe.

(b).

Number of cycles required for a backhoe to fill


dump truck full (n).
The payload of a dumptruck depends on its
capacity or weight.
- Where the payload is determined by the capacity,
Rated capacity (m3) of dump truck
n=
Bucket Capacity (m3) x bucket factor

Wheel Loader
Backhoe

2.10
0.80

1.00
1.10

0.65
0.58

40.24
22.00

m3/hr (loose)
m3/hr (bank)

m3/hr
m3
Baik sekali

m3

m3

minutes
minutes
minutes
minutes
minutes
minutes
minutes

Backhoe

11 Ton
Common
m3
m3
m3
Sec
m
Km/hr
Km/hr
min.
min.

Minutes

Sec.

Common
Weathered Rock
Rock
8 Ton

11.00
1.60
1.6
2
2.2
8

10 Ton

10

11 Ton

11

22 Ton

22

Spec

SEPESIFIKASI BULLDOZER
CATERPILLAR

Description

Merk

D6
D7
D8

Caterpillar
Caterpillar
Caterpillar

Capacity
(ton)
15
21
32

Blade Capacities
(m3)
3.18
5.16
8.68

Blade Dimension
Width
height
(m)
(m)
4.16
1.033
4.5
1.111
4.96
1.174

Capacity
(ton)
17
23

Blade Capacities
(m3)
4.52
7.8

Blade Dimension
Width
height
(m)
(mm)
3.415
1150
3.725
1450

Capacity
(ton)

Blade Capacities
(m3)

Kecepatan
Forward
Reverse
(km/hr)
(km/hr)

Capacity
(ton)

Blade Capacities
(m3)
2.1
2.5

Kecepatan
Forward
Reverse
(km/hr)
(km/hr)
7.6
8
7.1
7.7

Bucket Capacities
(m3)
0.8
1.2

Lebar
Bucket
(m)
1.045
1.145

KOMATSU

Description
D65E-8
D85A-21

Merk
Komatsu
Komatsu

SEPESIFIKASI WHEEL LOADER


CATERPILLAR

Description

Merk
Caterpillar

KOMATSU

Description

Merk

WA250-1
WA320-1

Komatsu
Komatsu

SEPESIFIKASI EXCAVATOR
KOMATSU

Description
PC200-6
PC300-6

Merk

Capacity
(ton)
19
31

Page 39

Spec

Kecepatan
Forward
Reverse
(km/hr)
(km/hr)
3.5
4.3
3.5
4.3
3.5
4.5

D6
D7
D8
D65E-8
D85A-21

Kecepatan
Forward
Reverse
(km/hr)
(km/hr)
3.9
5
3.8
4.9

Page 40

Tabel.1

Tabel 1. Efisiensi Kerja


Pemeliharaan Mesin
Kondisi operasi
Alat

Baik
sekali

Baik

sedang

Buruk

Buruk
sekali

Baik sekali

0.83

0.81

0.76

0.70

0.63

Baik

0.78

0.75

0.71

0.65

0.60

Sedang

0.72

0.69

0.65

0.60

0.54

Buruk

0.63

0.61

0.57

0.52

0.45

Buruk sekali

0.52

0.50

0.47

0.42

0.32

Page 41

Tabel.1

FAKTOR-FAKTOR YANG MEMPENGARUHI PRODUKSI PERALATAN


1. Faktor Kondisi Peralatan
Produksi suatu peralatan sangat dipengaruhi kondisi fisiknya.
Kondisi peralatan layak operasi ditinjau dari aspek ekonomi adalah antara :
K
= 100% sebagai kondisi maksimum, dan
K
= 60% sebagai kondisi minimum
Untuk perhitungan kondisi peralatan diambil :
2. Faktor Operator dan Mekanik
Kemampuan Operator dan Mekanik dibagi dalam 4 klasifikasi didasarkan atas
Curriculum Vitae (CV). Nilai kemampuan Operator dan Mekanik adalah sebagai
berikut :
KUALIFIKASI
IDENTITAS
(Curriculum Vitae)
Terampil
a. Pendidikan STM/Sederajat
b. Sertifikasi SIMP/SIPP (III)
dan atau
c. Pengalaman > 6000 jam
Cukup
a. Pendidikan STM/Sederajat
b. Sertifikasi SIMP/SIPP (II)
dan atau
c. Pengalaman 4000-6000 jam
Sedang
a. Pendidikan STM/Sederajat
b. Sertifikasi SIMP/SIPP (I)
dan atau
c. Pengalaman 2000-4000 jam
Kurang
a. Pendidikan STM/Sederajat
b. Sertifikasi; dan atau
c. Pengalaman <3000 jam

Fk =

NILAI
0.80

0.70

0.65

0.50

3. Faktor Cuaca
Keadaan cuaca yaitu kelengasan dan temperatur udara sangat mempengaruhi
prestasi kerja operator.
KONDISI CUACA
FAKTOR
KET.

Page 42

0.75

Tabel.1

Terang, segar

menit/jam
55/60

%
0.90

Terang, panas, berdebu

50/60

0.83

Mendung

45/60

0.75

Gelap

40/60

0.66

Page 43

Tabel.2

Tabel 2. : Faktor sudut dalam penggusuran


Derajat pelaksanaan penggusuran
Penggusuran
ringan

Penggusuran dapat dilaksanakan


dengan sudut penuh tanah lepas :
Kadar air rendah, tanah berpasir
tak dipadatkan, tanah biasa, bahan/material untuk timbunanpersediaan (stokpile).

Penggusuran

Tanah lepas, tetapi tidak mung-

sedang

kin menggusur dengan sudut

Faktor Sudut
1.1

0.9

0.7

0.6

penuh :
Tanah bercampur kerikil atau
split, pasir, batu pecah.
Penggusuran

Kadar air tinggi dan tanah liat,

agak sulit

pasir bercampur kerikil, tanah


liat yang sangat kering, dan tanah asli.

Penggusuran

Batu-batu hasil ledakan, batu-

sulit

batu berukuran besar-besar.

Page 44

Tabel.2

0.9

0.90

0.7

0.70

0.6

0.60

0.4

0.40

Ringan
Sedang
Agak sulit
Sulit

Page 45

Tabel.3

Tabel.3 : Factor Bucket


Kondisi Pemuatan

Faktor
Wheel Loader

Pemuatan
ringan
(A)

Pemuatan material/bahan dari stockpile


atau dari material yang telah dikeruk oleh
excavator lain, dengan tidak memerlukan
lagi daya gali dan bahan dapat dimuat
munjung ke dalam bucket.
Contoh : pasir, tanah berpasir,
tanah
colloidal dengan kadar air sedang dll.

Pemuatan
sedang
(B)

Pemuatan dari stockpile tanah lepas yang


lebih sukar dikeruk dan dimasukkan ke
dalam bucket tetapi dapat dimuat sampai
hampir munjung (antara peres dan
munjung (penuh)
Contoh : pasir kering, tanah berpasir,
tanah campur tanah liat, tanah liat, gravel
yang belum disaring, pasir padat dan
sebagainya, atau menggali dan memuat
gravel lunak langsung dari bukit asli

Pemuatan
agak sulit
(C)

Pemuatan batu belah atau batu cadas belah,


tanah liat yang keras pasir campur gravel,
tanah berpasir, tanah colloidal yang liat,
tanah liat dengan kadar air yang tinggi,
bahan-bahan
tersebut
telah
ada
padastockpile/persediaan sulit ntuk mengisi
bucket dengan material-material tersebut.

Pemuatan
sulit
(D)

Batu bongkah besar-besar dengan bentuk


yang tidak beraturan dengan banyak
ruangan di antara tumpukannya batu hasil
ledakan batu-batu bundar yang besarbesar, pasir campuran batu-batu bundar
tersebut, tanah berpasir, tanah campur
lempung, tanah liat yang tidak bisa
dimuat-gusur ke dalam bucket.

Page 46

Faktor
Backhoe

1.00

1.10

1.10 -

0.85

0.95

0.85

1.00 -

0.80

0.85

0.8

0.80 -

0.75

0.80

0.75

0.70 -

Tabel.3

Faktor
Backhoe
1.20

1.1

1.10

0.90

0.8

0.80

0.75

Page 47

Tabel Produksi

Tabel Produksi
Equipment

Kapasitas Produksi
M3/Jam

Direct Loading
Bulldozer
Backhoe
Wheel Loader
DT 8 Ton
DT 10 Ton
DT 11 Ton
DT 22 Ton

0.00
122.00
83.00
122.00
14.67
14.67
14.67
14.67
0