November 05, 2015

Geri
S. Main Street
Texas
Re: Punch List
The following is a punch list of outstanding work to be completed as observed on the renovation of Ms.
Escobars residence on November 04, 2015:
Exterior

All of the exterior siding requires a close inspection to fully drive in all nail heads
All of the exterior siding requires a close inspection to touch up with paint all areas
that have been repaired.
All of the exterior siding requires a close inspection to fully seal the siding to trim
boards.
All of the exterior siding requires a close inspection to seal around all penetrations
with backer rod and sealant.
Trim boards and front and rear decks require repainting and to include the top and
bottom edges.
The posts on the front deck are to be sealed and the base and 4x4 wood angle
brackets added to the tops.
Add cedar trim to the corner of the front deck near the entry stairs.
Add wood colored sealant to all front and rear deck railing that does not meet flush.
The roof flashing on the north side of the building requires a seam to be added and
drip edge.
The electric service head pipe is insuciently anchored to the building, requires

All surfaces need to be wiped of construction dust.


Pipe penetration in floor of mechanical closet requires backrod and sealant.
Wall paint requires touch-up through out the building.

Interior

MG
Cc: Jim

Observation Report