Anda di halaman 1dari 162

HARINI ENTERPRISES

BARBENDING SCHEDULE JOINTLY ARRIVED BY M/S. DSWE and HARINI ENTERPRISES


PROJECT : 33/11 KVA SUB STATION WORK NORTH CHENNAI.
SITE : KOLATHUR
CLIENT : M/S. DRAKE & SCULL WATER & ENERGY PVT LTD.
BBS DONE ARRIVED BY: Mr.Mohammed Nazer ( Manager Civil,DSWE) and Mr.Rajaraman (Project Engg,Harini),Mr.Anbarasan (Site Engg)
CHECKED & RE-ARRIVED BY : Mr.Sivasubramanian(Engineer Civil,DSWE) and Mr.Anbarasan(Site Engg)
S.
No
A.1

Member Details

Dia of
Bar
mm

No of
No of
Membe
Bar
r

Total
Nos

Bar Bending
Schedule

Cutting
Length

Total
Cutting
Length

8 mm

10 mm

12 mm

Isolated Footings
Foundation F1-Main Rod

12

23

14

322

3.6

1159.20

1159.20

Distribution rod

12

23

14

322

3.6

1159.20

1159.20

Foundationn F2-main rod

12

22

44

3.4

149.60

149.60

Distribution rod

12

22

44

3.4

149.60

149.60

Column C1

25

10

14

140

5.6

784

Ties outer spacing 100mm c/c

10

38

14

532

1.64

872.48

872.48

Ties Inner spacing 100mm c/c

10

38

14

532

1.24

659.68

659.68

column C1 over lap above plinth

25

10

14

140

1.25

175.00

Column C2

20

10

20

5.35

107.00

Ties outer spacing 100mm c/c

38

76

1.28

97.28

97.28

Ties Inner spacing 100mm c/c

38

76

1.12

85.12

85.12

Middle Hook

38

76

0.23

17.48

17.48

20

10

20

20.00

Top Main Rod

25

12

72.00

Top Extra at end support

25

12

4.15

49.80

Bottom Main Rod

25

12

72.00

2 Column up plinth

Column C2 over Lap above plinth


3 Grade Beam
GB1

Page 1 of 162

S.
No

Member Details

Dia of
Bar
mm

No of
No of
Membe
Bar
r

Total
Nos

Bar Bending
Schedule

Cutting
Length

Total
Cutting
Length

8 mm

25

8.8

52.80

2 Leg Stirips c/c 100mm

66

198

1.74

344.52

344.52

2 Leg Stirips c/c 200mm

20

60

1.74

104.40

104.40

Top Main Rod

25

12

48.00

Over lap at end for stair riser beam GB1

25

3.15

12.60

Top Extra at end support

25

4.15

16.60

Top Extra at continious support

25

5.65

22.60

Bottom Main Rod

25

12

48.00

Over lap at end for stair riser beam GB1

25

3.15

12.60

Bottom Extra Rod

Bottom Extra Rod

GB1 (continious) with stair riser

25

8.8

35.20

2 Leg Stirips c/c 100mm

81

162

1.74

281.88

281.88

2 Leg Stirips c/c 200mm

20

40

1.74

69.60

69.60

Top Main Rod

16

12

48.00

Top Extra at end support

16

12

2.475

29.70

Top Extra at mid support

16

3.95

23.70

Bottom Main Rod

16

12

72.00

Bottom Extra Rod for 5750 beam

16

4.425

8.85

Bottom Extra Rod for 5250 beam

16

3.93

7.86

2 Leg Stirips c/c 100mm

68

136

1.02

138.72

138.72

2 Leg Stirips c/c 200mm for

16

32

1.02

32.64

32.64

Top Main Rod including GB4

20

24

96.00

Top Extra at end support GB3

20

1.65

3.30

Top Extra at mid support GB3

20

2.6

20.80

Bottom Main Rod

16

19.86

79.44

Bottom Extra Rod at intermediate beams

20

2.6

20.80

34

10

340

0.96

326.40

GB2(continious)

GB3 continious

2 Leg Stirips
GB4

Page 2 of 162

326.40

10 mm

12 mm

S.
No

Member Details

Dia of
Bar
mm

No of
No of
Membe
Bar
r

Total
Nos

Bar Bending
Schedule

Cutting
Length

Total
Cutting
Length
10.40

8 mm

Top for cont beam (already considered in GB3)


Top Extra at mid support

20

2.6

Top Extra at end support

20

1.81

7.24

Bottom Main Rod

20

4.72

18.88

Bottom Extra

16

4.72

18.88

2 Leg Stirips

34

68

1.32

89.76

Top for beam in stair area

20

4.72

9.44

Top Extra at end support

20

1.81

7.24

Bottom Main Rod

20

4.72

9.44

Bottom Extra

16

4.72

9.44

2 Leg Stirips

34

34

1.32

44.88

Top Main Rod

25

12

24.00

Top Extra Rod

25

4.36

26.16

skin bar at side

16

11.45

22.90

Bottom Main Rod

25

12

24.00

Bottom Extra Rod

25

8.8

26.40

2 Leg Stirips c/c 100

66

66

2.06

135.96

135.96

2 Leg Stirips c/c 200

20

20

2.06

41.20

41.20

Top Main Rod (L rod)

16

12

72.00

Top Extra at end support

20

12

2.535

30.42

Top Extra at mid support

20

3.95

23.70

Bottom Main L Rod

20

12

72.00

102

204

1.2

244.80

Top Main Rod

16

19.86

39.72

Top Extra at end support

20

1.7

5.10

Top Extra mid support

20

15

2.6

39.00

Bottom Main Rod

16

19.1

57.30

89.76

44.88

4 PLINTH BEAM
PB1

PB2 CONTINIOUS

2 Leg Stirips
PB3 CONTINIOUS at C grid

Page 3 of 162

244.80

10 mm

12 mm

S.
No

Member Details

Dia of
Bar
mm

No of
No of
Membe
Bar
r

Total
Nos

Bar Bending
Schedule

Cutting
Length

Total
Cutting
Length

8 mm

10 mm

12 mm

16

2.8

14.00

34

170

0.94

159.80

Top Main Rod from A/6 to A/2

16

12

24.00

Top Extra mid support

20

15

2.6

39.00

Bottom Main Rod

16

16

48.00

Bottom Extra Rod

16

2.8

11.20

34

136

0.94

127.84

Top Main Rod over lap with PB3

20

6.31

37.86

Top Extra at end support

20

1.8

10.80

Bottom Main Rod at continious

20

4.4

39.60

Bottom Extra Rod

20

2.8

16.80

33

132

1.24

163.68

Top & Bottom Main

20

4.58

22.90

Top extra

20

1.65

6.60

Bottom Extra Rod

20

2.8

5.60

34

34

1.24

42.16

Top Main Rod

12

4.58

18.32

Top Extra at end support

12

1.6

12.80

12.4

Bottom Main Rod

12

3.88

15.52

15.52

Bottom extra

12

2.62

10.48

2 Leg Stirips

35

70

1.24

86.80

Top Main Rod continious with PB3

16

4.075

32.60

Bottom Main Rod

16

12

2.35

28.20

16

64

1.24

79.36

Bottom Extra Rod


2 Leg Stirips

159.80

PB3 CONTINIOUS at A grid

2 Leg Stirips

127.84

PB4

2 Leg Stirips

163.68

PB4 AT TOILET AREA

2 Leg Stirips

42.16

PB5
18.32

10.48
86.80

PB6

2 Leg Stirips @ 100 c/c

Page 4 of 162

79.36

S.
No

Member Details

Dia of
Bar
mm

No of
No of
Membe
Bar
r

Total
Nos

Bar Bending
Schedule

Cutting
Length

Total
Cutting
Length

8 mm

10 mm

12 mm

Additional beam at toilet area


for short wall

12

2.1

16.80

16.80

long wall

12

4.05

16.20

16.20

40

40

0.71

28.40

12

4.05

16.20

20

20

0.96

19.20

12

12

24

1.55

37.20

distribution for above

11

22

1.7

37.40

Starter bar inside face

12

12

24

1.2

28.80

distribution for above

11

22

1.7

37.40

12

12

24

4.66

111.84

21

42

1.7

71.40

12

12

24

1.7

40.80

distribution for above

12

1.7

20.40

scissor bar at FGL lvl

12

12

24

1.7

40.80

slab short side bar double layer

12

24

48

4.93

236.64

slab long side bar double layer

44

88

2.36

207.68

Raft bottom along grid A & C- short side & wall external U shaped bar
@125mm c/c for a length 13.285m

10

107

214
5.55

1187.70

1187.70

Distributor for above 200mm c/c- only for full raft

10

10

20

18.135

362.70

362.70

over lap for above

10

10

20

0.5

10.00

10.00

Distributor for above18.135m long wall 200mm c/c

10

20

18.135

362.70

362.70

over lap for above

10

20

0.4

8.00

8.00
249.60

Stirrups
beam below battery room wall
Stirrups

28.40
16.20
19.20

5 STAIR FROM 00M To +1.60 M


Starter bar outside

waist slab bottom bar at FGL lvl


distribution for above
waist slab top at FGL lvl

37.20
37.40
28.80
37.40
111.84
71.40
40.80
20.40
40.80

landing at +1.5m lvl


236.64
207.68

6 CABLE TRENCH

10

40

6.24

249.60

Raft top short bar at 175 mmc/c for length 13.285m

10

77

154

2.04

314.16

314.16

Distributor for above 200mm c/c for full raft length

10

10

20

18.135

362.70

362.70

over lap for above

10

10

20

0.5

10.00

10.00

Distributor for 13.285 m long 2 part walls

Page 5 of 162

S.
No

Member Details

Dia of
Bar
mm

No of
No of
Membe
Bar
r

Total
Nos

Bar Bending
Schedule

Cutting
Length

Total
Cutting
Length

8 mm

10 mm

10

77

308

2.1

646.80

Distribution for above for 18.135m length with lap

10

20

18.535

370.70

over lap for above

10

20

0.4

8.00

8.00

Distribution for above for 13.285m length

10

40

6.24

249.60

249.60

Raft bottom along grid 7 & 2- short side & wall external U shaped bar
@125mm c/c for a length (7.10)m

10

58

116
5.55

643.80

643.80

Distributor for above 200mm c/c- only for full raft

10

10

20

10.45

209.00

209.00

Distributor for above 10.5m long wall 200mm c/c

10

20

11.25

225.00

225.00

Distributor for above 7.10m long wall 200mm c/c

10

20

7.5

150.00

150.00

Raft top short bar at 125 mmc/c for length 7.1m

10

58

116

2.04

236.64

236.64

Distributor for above 200mm c/c for full length

10

10

20

10.45

209.00

209.00

wall innerface vertical bar on either side

10

58

232

2.05

475.60

10

20

11.25

225.00

225.00
158.00

Wall innerface vertical bar on either side for 13.285m

Distribution for above for 10.5m length with lap

646.80
370.70

475.60

10

20

7.9

158.00

Chair bar for cable trench raft

10

34

34

1.2

40.50

40.50

Trench at mid of controll room -Raft bottom short side & wall
external U shaped bar @125mm c/c for a length (7.1)m

10

58

58
5.55

321.90

321.90

Distributor for above 200mm c/c- only for raft

10

10

10

7.1

71.00

71.00

Over lap for above on both end

10

10

10

10.00

10.00

20

40

7.1

284.00

Raft top short bar at 125 mmc/c for length 7.17m

10

58

58

2.04

118.32

118.32

Distributor for above 200mm c/c

10

10

10

7.1

71.00

71.00

Over lap for above on both end

10

10

10

10.00

10.00

wall innerface vertical bar on either side

10

58

116

2.1

243.60

10

20

7.1

142.00

Raft bottom- L rod

10

15

10

146

3.6

525.60

525.60

Raft top bat -L rod

10

15

10

150

1.95

292.50

292.50

wall inner face vertical bar on only one side

10

15

10

146

292.00

292.00

Distribution for above for 7.1m length with lap

Distributor for above only for vrtical 200mm c/c

Distribution for above

284.00

243.60
142.00

Trench common corner portion for length 1.7m

Page 6 of 162

12 mm

S.
No

Member Details

Dia of
Bar
mm

No of
No of
Membe
Bar
r

Total
Nos

Bar Bending
Schedule

Cutting
Length

Total
Cutting
Length

8 mm

10 mm

12 mm

All Distributors are considred already


Trench cover slab
10

142

284

568.00

20

40

10.5

420.00

10

96

196

392.00

20

20

7.1

142.00

142.00

short bar

35

70.7

6.84

483.59

483.59

long bar

33

65.5

7.1

465.05

465.05

Both top and bottom for Length 10.5m


Distributor for both top & bottom

568.00
420.00

Mid area trench cover


Both top and bottom for Length 7.1m
Distributor for both top & bottom

392.00

SLAB ON GRADE
SIZE-6.84M x7.1M AT 200MM C/C

FIRST STAGE REBAR SUB TOTAL

Total length
Unit Wt
Wt in MT -Dia Wise
Total Wt in Mtonne
B

7079.40
0.40
2.80

9156.68
0.617
5.650

COLUMN ABOVE PLINTH TO FIRST FLOOR


Column C1

25

10

14

140

4.4

616.00

Ties outer spacing 100mm c/c

10

20

14

280

1.64

459.20

459.20

Ties Inner spacing 100mm c/c

10

20

14

280

1.24

347.20

347.20

Normal Ties c/c 250mm (Outer)

10

14

28

1.64

45.92

45.92

Normal Ties c/c 250mm (Inner)

10

14

28

1.24

34.72

34.72

column C1 over lap above ffloor

25

10

14

140

1.25

175.00

Column C2

20

10

20

4.4

88.00

Ties outer spacing 100mm c/c

20

40

1.28

51.20

51.20

Ties Inner spacing 100mm c/c

20

40

1.12

44.80

44.80

Middle Hook

22

44

0.23

10.12

10.12

Normal ties c/c 200mm (Outer)

1.34

5.36

5.36

1.34

5.36

5.36

20

10

20

20.00

Column C2 over Lap above plinth

Page 7 of 162

0.888
2.859

19.8

1 COLUMN

Normal ties c/c 200mm (Outer)

3219.6

S.
No

Member Details

Dia of
Bar
mm

No of
No of
Membe
Bar
r

Total
Nos

Bar Bending
Schedule

Cutting
Length

Total
Cutting
Length

23.45

140.70

8 mm

10 mm

12 mm

2 LINTEL & SUNSHADE


Lintel -length-22.6
Ties
Lintel -length-18.9m

12

23

138

0.96

132.48

12

19.75

118.50

140.7
132.48
118.5

23

115

0.96

110.40

12

18

11.85

213.30

209

209

0.96

200.64

12

4.05

16.20

20

20

0.71

14.20

10

12

12

140

1.44

201.60

12

72

1.57

113.04

Top Main from FB6 towards FB1

25

10

12

120.00

over lap FB1

25

10

3.07

30.70

Top main from Fb1 towards FB6

25

10

12

120.00

over lap FB6(cantilever)

25

10

4.5

45.00

Top Extra at end support

25

20

4.4

88.00

Top Extra at mid support

25

20

5.55

111.00

Bottom Main for FB1

25

20

12

240.00

Bottom Extra For FB1

25

20

8.1

162.00

skin bar at sides

12

10

10.92

109.20

2 Leg Stirips @ 130 c/c

10

52

260

2.1

546.00

546.00

2 Leg Stirips @ 230 c/c

10

18

90

2.1

189.00

189.00

Spacer Bar FB1

25

14

70

0.4

28.00

Bottom Main

20

14

2.45

34.30

bottom main

25

2.45

17.15

Ties
lintel- length-10.50m
Ties

110.40
213.30
200.64

Lntel at toilet area


At door
ties

16.20
14.20

Sun shade-12nos
Main bar
Distributor

201.60
113.04

3 GROUND FLOOR ROOF (FIRST FLOOR )SLAB


FB1& FB6continious

FB6 cantilever
Top and extra support is considered in FB1

Page 8 of 162

109.20

S.
No

Member Details

Dia of
Bar
mm

No of
No of
Membe
Bar
r

Total
Nos

Bar Bending
Schedule

Cutting
Length

Total
Cutting
Length

8 mm
104.16

12

84

1.24

104.16

Top Main Rod (over laped with FB6)

20

12

72.00

Top Extra at end support

25

2.75

11.00

Top Extra at mid support

25

4.1

16.40

Bottom Main Rod

20

12

72.00

Bottom Extra Rod

20

2.95

11.80

Bottom Extra Rod

20

3.45

13.80

2 Leg Stirips at 100mm c/c

16

128

1.5

192.00

192.00

2 Leg Stirips at 200mm c/c

10

40

1.5

60.00

60.00

FB6 Grid A1 & A2 Top bar

25

4.55

36.40

Top Extra FB6 Grid A1 & A2

25

4.45

35.60

25

14

28

0.4

11.20

Top Main continious from FB4 To FB5

20

24

48.00

Top extra at at end support at Fb4 & FB5

20

1.8

7.20

Top Extra at mid support

20

10

2.7

27.00

Bottom main continious for FB4

20

12

24.00

Bottom lap for FB4 up to column at C/2

20

8.12

16.24

Bottom Extra for FB4

20

10

2.6

26.00

Bottom Main for FB5

16

4.4

13.20

2 Leg Stirips at 100mm c/c for FB4

24

120

1.1

132.00

132.00

2 Leg Stirips at 150mm c/c for FB4

40

1.1

44.00

44.00

2 Leg Stirips at 100mm c/c for FB5

24

24

1.5

36.00

36.00

2 Leg Stirips at 150mm c/c for FB5

1.5

12.00

12.00

25

14

70

0.4

28.00

Top Main

20

4.93

19.72

Top extra at end support

20

1.78

14.24

Bottom main

16

4.93

19.72

Ties 8 at 130c/c
FB2/FB3 & FB6

ties & bottom bor considered in FB6 cantilever


Spacer Bar FB2
FB4 & FB5 at grid C

Spacer Bar FB4


FB5 STAIR & IN TOILET SUNKEN AREA

Page 9 of 162

10 mm

12 mm

S.
No

Member Details

Dia of
Bar
mm

No of
No of
Membe
Bar
r

Total
Nos

Bar Bending
Schedule

Cutting
Length

Total
Cutting
Length

8 mm

10 mm

2 Leg Stirips at 100mm c/c for FB5

24

48

1.5

72.00

72.00

2 Leg Stirips at 150mm c/c for FB5

16

1.5

24.00

24.00

Top Main continious from FB4 To FB8

20

12

24.00

Top main over lap at FB8

20

12

24.00

Top extra at at end support at Fb4 & FB8

20

1.8

7.20

Top Extra at mid support

20

10

2.7

27.00

Bottom main continious for FB4

20

12

24.00

Bottom lap for FB4 & FB8

20

12

24.00

Bottom Extra for FB4 & FB8

20

12

2.6

31.20

2 Leg Stirips at 100mm c/c for FB4

24

120

1.1

132.00

132.00

2 Leg Stirips at 150mm c/c for FB4

40

1.1

44.00

44.00

2 Leg Stirips at 100mm c/c for FB8

24

24

1.3

31.20

31.20

2 Leg Stirips at 150mm c/c for FB8

1.3

10.40

10.40

Top continious from One end

16

12

24.00

Top over lab from other end

16

12

24.00

Top Extra at end support

16

1.63

3.26

Top Extra at mid support

16

2.7

13.50

Bottom Main Rod from one end

16

12

24.00

Bottom main from other end

16

12

24.00

Bottom Extara

16

2.6

15.60

2 Leg Stirips at 100mm c/c

24

144

0.9

129.60

129.60

2 Leg Stirips at 200mm c/c

36

0.9

32.40

32.40

Short bar at bottom at 125mmc/c

10

43

86

4.12

354.32

354.32

Short bar at bottom at 125mmc/c

10

42

84

5.27

442.68

442.68

long bar at bottom at 175mmc/c

10

20

10.99

219.80

219.80

long bar at bottom at 175mmc/c

10

20

11.575

231.50

231.50

10

43

86

1.52

130.72

FB4 & FB8 atgrid A

FB7

SLAB
FS1end pannel

Top extra at end support short side 250mm c/c

Page 10 of 162

130.72

12 mm

S.
No

Member Details

Dia of
Bar
mm

No of
No of
Membe
Bar
r

Total
Nos

Bar Bending
Schedule

Cutting
Length

Total
Cutting
Length

8 mm

Distribution for above at 250mmc/c

10

10.95

109.50

109.50

Top extra at end support long side 350mm c/c

10

20

3.5

70.00

70.00

Distribution for above at 350mmc/c

18

72.00

72.00

Top extra at mid support long side 350mm c/c

10

20

4.115

82.30

82.30

Distribution for above at 350mmc/c

18

72.00

72.00

Short bar at bottom at 125mmc/c

10

85

255

5.3

1351.50

long bar at bottom at 175mmc/c

10

30

10.99

329.70

329.70

long bar at bottom at 175mmc/c

10

30

11.575

347.25

347.25

10

43

172

2.7

464.40

10 mm

12 mm

FS1mid pannel

Top extra at mid support short side 250mm c/c

1351.50

464.40

Distribution for above at 250mmc/c

32

10.95

350.40

350.40

Top extra at end support long side 350mm c/c

10

30

3.5

105.00

105.00

Distribution for above at 350mmc/c

27

108.00

108.00

Top extra at mid support long side 350mm c/c

10

30

5.03

150.90

150.90
108.00

27

108.00

10

20

100

100.00

Bottom short side at 175c/c

19

95

190.00

190.00

Bottom long side at 175c/c for end panells

5.08

25.40

25.40

Bottom long side at 175c/c for end panells

3.93

15.72

15.72

Top extra at short side at end 350mm c/c

10

50

1.13

56.50

56.50

distribution for above

10

40.00

40.00

Top extra at long side at end support 350mmc/c

10

1.58

15.80

15.80

distribution for above

12.00

12.00

Top extra at long side at mid support 50mmc/c

16

2.53

40.48

40.48

Distribution for above

24

48.00

48.00

10

15

15.00

Short bar at bottom at 150mm c/c

12

37

37

3.85

142.45

Long bar at bottom at 150mm c/c

10

23

23

5.81

133.63

Distribution for above at 350mmc/c


chair rod

100.00

FS2

Distribution is already available from FS1


chair rod

15.00

FS3

Page 11 of 162

142.45
133.63

S.
No

Member Details

Dia of
Bar
mm

No of
No of
Membe
Bar
r

Total
Nos

Bar Bending
Schedule

Cutting
Length

Total
Cutting
Length

Top extra at short side

12

18

36

1.38

49.68

Distribution for above

5.81

46.48

Top extra at long side

10

12

24

1.9

45.60

distribution for above

12

3.85

46.20

8 mm

45.60
46.20

10

8.00

213

213

1.7

362.10

362.10

Distribution for above

26.4

184.80

184.80

Top bar at +1.5m lvl

16

12

12

2.73

32.76

Distribution for above

10

10

10

1.55

15.50

Scissor bar from top to bottom

16

12

12

1.83

21.96

Bottom bar

16

12

12

6.81

81.72

Distribution for above only for waist vslab

10

23

23

1.55

35.65

Top bar at mid landing

16

12

12

3.38

40.56

Distribution for above

16

16

16

3.86

61.76

scissor bar at mid landing from top bottom

16

12

12

2.3

27.60

distributor for above

16

3.86

23.16

Top main bar

20

4.57

9.14

Top extra

20

1.7

3.40

Bottom main

20

4.57

9.14

Bottom extra

20

2.98

2.98

31

31

1.2

37.20

16

12

12

2.59

31.08

8.00

Stair case slab


waist slab 1
15.50

35.65

Mid landing Beam

Ties

37.20

waist slab 2
Top bar from mid landing
Distribution for landing area covered already
Distribution for lwaist area

10

1.55

7.75

Scissor bar from top to bottom at mid landing

16

12

12

2.485

29.82

Bottom bar

16

12

12

7.6

91.20

Page 12 of 162

12 mm
49.68

46.48

Balcony drops 120mm c/c

chair rod

10 mm

7.75

S.
No

Member Details

Dia of
Bar
mm

No of
No of
Membe
Bar
r

Total
Nos

Bar Bending
Schedule

Cutting
Length

Total
Cutting
Length

8 mm

10 mm

over lap for above

16

12

12

0.8

9.60

Distribution for above for waist only

10

23

23

1.6

36.80

36.80

Top bar at floor landing

10

12

12

3.63

43.56

43.56

Distribution for above at floor landing

10

11

11

3.76

41.36

41.36

Distribution for above at waist slab

10

1.55

13.95

13.95

scissor bar at floor landing

16

12

12

1.89

22.68

10

11

11

3.76

41.36

41.36

Main bar on short vside

10

23

23

2.2

50.60

50.60

Main bar on long side

10

11

11

44.00

44.00

Extrav rod at to short side


Distribution for above on either side

10
8

23
8

1
1

23
8

0.6
4.05

13.80
32.40

12 mm

Floor landing Slab


Distribution only bottom
Floor landing

13.80
32.40

SUB TOTAL FOR SECOND STAGE OF WORKS


8.00

Total length
Unit Wt
Wt in MT -Dia Wise
Total Wt in Mtonne

5252.79
0.40
2.07

10
5213.82
0.617
3.217

0.888
0.702

15.9

C FIRST FLOOR TO ROOF SLAB


1 COLUMN
Column C1

25

10

12

120

4.4

528.00

Column C1

25

10

20

3.5

70.00

Ties outer spacing 100mm c/c

10

20

14

280

1.64

459.20

459.20

Ties Inner spacing 100mm c/c

10

20

14

280

1.24

347.20

347.20

Normal Ties c/c 250mm (Outer)

10

14

84

1.64

137.76

137.76

Normal Ties c/c 250mm (Inner)

10

14

84

1.24

104.16

104.16

Column C2

20

10

20

3.5

70.00

Ties outer spacing 100mm c/c

20

40

1.28

51.20

51.20

Ties Inner spacing 100mm c/c

20

40

1.12

44.80

44.80

Page 13 of 162

12
790.03

S.
No

Member Details

Dia of
Bar
mm

No of
No of
Membe
Bar
r

Total
Nos

Bar Bending
Schedule

Cutting
Length

Total
Cutting
Length

8 mm

Middle Hook

26

52

0.23

11.96

11.96

Normal ties c/c 200mm (Outer)

12

1.28

15.36

15.36

Normal ties c/c 200mm (Outer)

12

1.12

13.44

13.44

12

23.45

140.70

23

138

0.96

132.48

12

19.75

118.50

23

115

0.96

110.40

12

18

11.85

213.30

209

209

0.96

200.64

12

2.56

10.24

17

17

0.71

12.07

12

2.87

11.48

19

19

0.71

13.49

10

12

96

1.44

138.24

48

1.57

75.36

10

124

248

0.6

148.80

10 mm

12 mm

2 LINTEL & SUNSHADE


Lintel -length-22.6 at grid C
Ties
Lintel -length-18.9m
Ties
lintel- length-10.50m
Ties

140.7
132.48
118.5
110.40
213.30
200.64

Lntel at toilet area


At door d2 of gents
ties
At door d2 of ladies
ties

10.24
12.07
11.48
13.49

Sun shade-8nos
Main bar
Distributor

138.24
75.36

LOFT
Short bar for 18 .615m

18.965

151.72

10

62

124

0.6

74.40

10.45

83.60

Top Main from RB5 towards RB1

25

10

12

120.00

Top main from RB1 towards FB5

25

10

12

120.00

over lap RB1

25

10

3.07

30.70

distribution
Short bar for 10 .5m
distribution
3 ROOF LVL SLAB
ROOF BEAMS
RB1& RB5 continious

Page 14 of 162

148.80
151.72
74.40
83.60

S.
No

Member Details

Dia of
Bar
mm

No of
No of
Membe
Bar
r

Total
Nos

Bar Bending
Schedule

Cutting
Length

Total
Cutting
Length

8 mm

10 mm

12 mm

over lap FB6(cantilever)

25

10

4.6

46.00

Top Extra at end support

20

15

4.35

65.25

Top Extra at mid support

20

15

5.6

84.00

Bottom Main for RB1

25

20

12

240.00

Bottom Extra For RB1

20

15

8.4

126.00

skin bar at sides

12

10

10.92

109.20

2 Leg Stirips @ 100 c/c

66

330

2.08

686.40

686.40

2 Leg Stirips @ 200 c/c

20

100

2.08

208.00

208.00

25

14

70

0.4

28.00

Bottom Main

20

10

2.77

27.70

bottom main

25

2.77

13.85

15

75

1.38

103.50

Top Main Rod (over laped with RB6)

20

12

48.00

over lap RB6(cantilever)

25

4.6

36.80

Top Extra at end support for RB6

25

2.65

10.60

Top Extra at mid support at RB5

20

4.55

27.30

Bottom Main Rod from RB6 to RB5

12

12

72.00

Bottom Extra Rod at RB6

16

3.2

25.60

2 Leg Stirips at 100mm c/c

18

144

1.24

178.56

178.56

2 Leg Stirips at 200mm c/c

10

40

1.24

49.60

49.60

Bottom Main RB5

20

2.77

11.08

Bottom main RB5

25

2.77

5.54

Ties 8 at 100c/c

15

30

1.38

41.40

Spacer Bar RB6

25

13

26

0.4

10.40

Top Main continious from one end

12

12

24.00

24.00

Top main continious from other end

12

12

24.00

24.00

Top extra at at end supports

16

1.8

7.20

Spacer Bar RB1

109.20

RB5 cantilever
Top and extra support is considered in RB1

Ties 8 at 100c/c

103.50

RB6 & RB5

72.00

41.40

RB4 ALONG GRID C

Page 15 of 162

S.
No

Member Details

Dia of
Bar
mm

No of
No of
Membe
Bar
r

Total
Nos

Bar Bending
Schedule

Cutting
Length

Total
Cutting
Length

8 mm

10 mm

12 mm

Top Extra at mid support

16

10

2.7

27.00

Bottom main continious from one end

12

12

24.00

24.00

Bottom main continious from other end

12

12

24.00

24.00

Bottom Extra

16

12

1.4

16.80

2 Leg Stirips at 100mm c/c

12

12

144

1.04

149.76

149.76

2 Leg Stirips at 200mm c/c

48

1.04

49.92

49.92

25

13

65

0.4

26.00

Top Main continious from RB4 To RB7

12

12

24.00

24.00

Top main over lap at RB7

12

12

24.00

24.00

Top extra at at end support at RB4

16

1.8

3.60

Top Extra at mid support for RB4

16

2.7

21.60

Top extra at at end support at RB7

20

1.8

3.60

Top Extra at mid support for RB7

20

2.7

5.40

Bottom main continious from RB4 to RB7

12

12

24.00

24.00

Bottom Main from RB7 to RB4

12

12

24.00

24.00

Bottom Extra for RB4

16

10

1.4

14.00

Bottom Extra for RB7

16

4.05

4.05

2 Leg Stirips at 100mm c/c for RB4

24

120

1.04

124.80

124.80

2 Leg Stirips at 200mm c/c for RB4

25

1.04

26.00

26.00

2 Leg Stirips at 100mm c/c for RB7

24

24

1.24

29.76

29.76

2 Leg Stirips at 2000mm c/c for FB7

1.24

6.20

6.20

Top Main

12

4.48

8.96

Top extra at end support

16

1.65

6.60

Bottom main

12

4.48

17.92

Bottom Extra

16

1.4

5.60

2 Leg Stirips at 100mm c/c for FB5

12

24

1.04

24.96

24.96

2 Leg Stirips at 200mm c/c for FB5

1.04

5.20

5.20

12

12

24.00

Spacer Bar RB4


RB4 & RB7 ALONG GRID A

RB4 SUNKEN AREA


8.96
17.92

RB3
Top continious from One end

Page 16 of 162

24.00

S.
No

Member Details

Dia of
Bar
mm

No of
No of
Membe
Bar
r

Total
Nos

Bar Bending
Schedule

Cutting
Length

Total
Cutting
Length

8 mm

10 mm

12 mm

Top over lab from other end

12

12

24.00

Top Extra at end support

16

1.55

3.10

Top Extra at mid support

16

2.53

12.65

Bottom Main Rod from one end

12

12

24.00

24.00

Bottom main from other end

12

12

24.00

24.00

Bottom Extara

16

1.4

8.40

2 Leg Stirips at 100mm c/c

24

144

0.9

129.60

129.60

2 Leg Stirips at 200mm c/c

10

60

0.9

54.00

54.00

Short bar at bottom at 150mmc/c

10

36

72

4.1

295.20

295.20

Short bar at bottom at 150mmc/c

10

35

70

5.25

367.50

367.50

long bar at bottom at 175mmc/c

10

20

11

220.00

220.00

long bar at bottom at 175mmc/c

10

20

11.585

231.70

231.70

10

36

72

1.52

109.44

Distribution for above at 350mmc/c

10.95

87.60

87.60

Top extra at end support long side 350mm c/c

10

20

3.5

70.00

70.00

10

20

4.115

82.30

82.30

10

20

40

40.00

40.00

Short bar at bottom at 150mmc/c

10

71

213

5.25

1118.25

1118.25

long bar at bottom at 175mmc/c

10

30

11

330.00

330.00

long bar at bottom at 175mmc/c

10

30

11.585

347.55

347.55

10

36

144

2.7

388.80

Distribution for above at 300mmc/c

32

10.95

350.40

350.40

Top extra at end support long side 350mm c/c

10

30

3.5

105.00

105.00

10

30

4.115

123.45

123.45

10

20

60

60.00

24.00

SLAB
RS1end pannel

Top extra at end support short side 300mm c/c

109.44

distribution for above given below seperately


Top extra at mid support long side 350mm c/c
distribution for above given below seperately
chair rod
RS1mid pannel

Top extra at mid support short side 300mm c/c

388.80

distribution for above given below seperately


Top extra at mid support long side 350mm c/c
distribution for above given below seperately
chair rod

Page 17 of 162

60.00

S.
No

Member Details

Dia of
Bar
mm

No of
No of
Membe
Bar
r

Total
Nos

Bar Bending
Schedule

Cutting
Length

Total
Cutting
Length

8 mm

10 mm

RS2 END PANNEL


Bottom short side at 175c/c

20

40

80.00

80.00

Bottom long side at 175c/c for end panells

10

5.15

51.50

51.50

Bottom long side at 175c/c for end panells

10

3.76

37.60

37.60

Top extra at short side at end 350mm c/c

10

20

0.9

18.00

18.00

Top extra at long side at end support 350mmc/c

10

1.55

15.50

15.50

distribution for above

1.95

11.70

11.70

10

12

12.00

Bottom short side at 175c/c

20

80

160.00

160.00

Bottom long side at 175c/c for end panells

20

5.15

103.00

103.00

Bottom long side at 175c/c for end panells

20

3.76

75.20

75.20

Top extra at short side at end 350mm c/c

10

60

0.9

54.00

54.00

Top extra at long side at mid support 350mmc/c

25

2.53

63.25

63.25

distribution for above

40

1.95

78.00

78.00

10

24

24.00

RS 1 -5 pannels on either side

22

22

19.25

423.50

423.50

RS 2 -6 pannels on either side

22.95

91.80

91.80

Short bar at bottom at 150mm c/c

10

18

18

3.93

70.74

Short bar at bottom at 150mm c/c

10

19

19

5.08

96.52

Long bar at bottom at 175mm c/c

20

20

5.865

117.30

117.30

Top extra at short side at end support 300mmc/c

18

1.75

31.50

31.50

Distribution for above

10

5.9

59.00

59.00

Top extra at long side mid support

18

18

2.53

45.54

45.54

distribution for above given below seperately

Distribution is already available from RS1


chair rod

12.00

RS2

distribution for above given below seperately

Distribution is already available from RS1


chair rod

24.00

DISTRIBUTION

RS3

Page 18 of 162

70.74
96.52

12 mm

S.
No

Member Details

Dia of
Bar
mm

No of
No of
Membe
Bar
r

Total
Nos

Bar Bending
Schedule

Cutting
Length

Total
Cutting
Length

8 mm

Top extra at long side end support

18

18

1.38

24.84

24.84

distribution for above

5.815

34.89

34.89

10 mm

10

10

10

10.00

Balcony drops 120mm c/c

213

213

1.7

362.10

362.10

Distribution for above

26.4

184.80

184.80

Top bar at first floor lvl

16

12

12

24.00

Distribution for above

10

12

12

1.55

18.60

Scissor bar at floor lvl

16

12

12

2.8

33.60

Bottom bar

16

12

12

5.55

66.60

over lap for above

16

12

12

0.8

9.60

Distribution for above

10

17

17

1.6

27.20

27.20

Distribution for above at floor lavl

10

1.6

9.60

9.60

Distribution for above at mid landing floor lvl

16

3.93

35.37

Bottom bar from mid landing to top

16

12

12

3.2

38.40

Distribution for above at landing

16

3.93

35.37

scissor bar at mid landing lvl

16

12

12

2.35

28.20

Top main bar

20

4.75

9.50

Top extra

20

1.73

3.46

Bottom main

20

4.75

4.75

Bottom extra

20

2.98

2.98

22

22

1.2

26.40

Top bar at mid landing lvl

16

12

12

2.56

30.72

Scissor bar at mid landing lvl

16

12

12

2.25

27.00

Distribution for above at waist slab

10

1.55

6.20

Bottom bar

16

12

12

5.92

71.04

Chair rod

10.00

Stair case slab


waist slab 3
18.60

Mid landing Beam

Ties
waist slab 4

Page 19 of 162

26.40

12 mm

S.
No

Member Details

Dia of
Bar
mm

No of
No of
Membe
Bar
r

Total
Nos

Bar Bending
Schedule

Cutting
Length

Total
Cutting
Length

8 mm

10 mm

12 mm

16

12

12

0.8

9.60

Distribution for above at waist slab

10

16

16

1.6

25.60

Top bar of waist slab at second floor landing lvl

16

12

12

2.7

32.40

Distribution for above at waist slab

10

10

10

1.55

15.50

15.50

distribution at floor slab lvl

10

3.93

19.65

19.65

scissor bar at floor landing

16

12

12

1.86

22.32

chairs rod for stair area

12

7.00

Column C1

25

10

20

2.7

54.00

Ties outer spacing 100mm c/c

10

22

44

1.64

72.16

72.16

Ties Inner spacing 100mm c/c

10

22

44

1.24

54.56

54.56

Column C2

20

10

20

2.7

54.00

Ties outer spacing 100mm c/c

22

44

1.28

56.32

56.32

Ties Inner spacing 100mm c/c

22

44

1.12

49.28

49.28

Middle Hook

22

44

0.23

10.12

10.12

Top main bar

12

4.63

27.78

27.78

Bottom main bar

12

4.53

27.18

27.18

Stirrups @ 100mm c/c

24

48

1.24

59.52

59.52

Stirrups @ 200mm c/c

14

1.24

17.36

17.36

25

0.23

1.38

Top main bar

12

7.8

31.20

Top extra at end support

16

2.45

9.80

Top extra at mid support with cantilever

16

3.8

15.20

Bottom main bar

16

7.8

31.20

Bottom extra

16

3.75

7.50

over lap for above


Distribution for above at landing considered

25.60

7.00

HEAD ROOM COLUMNS, BEAMS & SLAB


COLUMN

HB1

Spacer bar
HB2

Page 20 of 162

31.20

S.
No

Member Details

Dia of
Bar
mm

No of
No of
Membe
Bar
r

Total
Nos

Bar Bending
Schedule

Cutting
Length

Total
Cutting
Length

8 mm

10 mm

Stirrups @ 100mm c/c

47

94

1.24

116.56

116.56

Stirrups @ 200mm c/c

15

30

1.24

37.20

37.20

25

10

0.23

2.30

Top main bar

12

4.33

8.66

Top main bar

16

4.33

4.33

Bottom main bar

12

4.33

8.66

Bottom main bar

16

4.33

4.33

Stirrups @ 100mm c/c

24

24

0.96

23.04

23.04

Stirrups @ 200mm c/c

0.96

6.72

6.72

25

0.23

0.69

Short side bar @ 150mm c/c

10

43

43

4.1

176.30

176.30

Short side extra @ 300mm c/c

10

43

86

1.5

129.00

129.00

16

7.065

113.04

Long side bar @ 150mm c/c

10

22

22

7.115

156.53

Long side extra @ 300mm c/c

10

22

44

1.33

58.52

16

4.05

64.80

10

6.00

Spacer bar

12 mm

HB3

Spacer bar

8.66
8.66

HS1

Distributors for above

Distributors for above


Chairs

113.04
156.53
58.52
64.80
6.00

SUB TOTAL FOR SECOND STAGE OF WORKS


8.00

Total length
Unit Wt
Wt in MT -Dia Wise
Total Wt in Mtonne
D

7435.56
0.395
2.94

10
4771.43
0.617
2.944

12
1100.78
0.888
0.977

14.5

WORKS AT YARD
Raft for transformer plinth
Short side top & bottom bar at 120mmc/c

12

78

156

3.38

527.28

Long Side Top & bottom bar at 120mmc/c

10

28

56

9.48

530.88

16

16

9.58

153.28

strab beam 2nos


Both Top & bottom

Page 21 of 162

527.28
530.88

S.
No

Member Details

Dia of
Bar
mm

No of
No of
Membe
Bar
r

Total
Nos

Bar Bending
Schedule

Cutting
Length

Total
Cutting
Length

8 mm

10 mm

12 mm

Top Extra at end support

16

2.625

10.50

Top Extra at mid support

16

0.91

7.28

Top Extra at mid support

16

1.48

5.92

Bottom extra at end

16

1.55

12.40

Bottom extra at miid support

16

12

1.7

20.40

Ties at 150mmc/c

12

63

126

1.98

249.48

249.48

chairs at raft

12

14

14

14.00

14.00

Main Bar

16

32

2.9

92.80

Main Bar

12

32

2.9

92.80

Ties at 150mmc/c

10

14

112

1.04

116.48

116.48

Ties diagonal at 150mmc/c

10

14

112

1.04

116.48

116.48

16

16

6.8

108.80

Column C1
92.80

Column C2
Main bar
Ties at 150mm c/c

10

40

80

1.5

120.00

120.00

Ties at 150mm c/c

10

40

80

1.44

115.20

115.20

Main Bar at both Bottom & top

20

24

3.4

81.60

Ties

30

120

1.38

165.60

Main bar both bottom & top

20

32

3.4

108.80

Ties

20

160

1.44

230.40

Grade beam
B1
165.60

B2
230.40

Extra at Top

20

32

1.4

44.80

Extra at Bottom

20

16

32.00

Beam

12

24

4.9

117.60

ties

37

111

1.2

133.20

133.20

wall rood vertical

31

62

5.05

313.10

313.10

Fire Wall

Page 22 of 162

117.60

S.
No

Member Details

Dia of
Bar
mm

No of
No of
Membe
Bar
r

Total
Nos

Bar Bending
Schedule

Cutting
Length

Total
Cutting
Length

8 mm

wall rood horizondal

26

52

4.55

236.60

236.60

u bar for stability

16

16.00

16.00

4.61

774.48

Cable tyrench arround Trs Plinth


Raft bottom short side & wall external U shaped bar @150mm c/c for
a length 3.0m

10

21

168

10

64

192.00

Distributor for vertical 6m long wall 200mm c/c

56

6.35

355.60

355.60

Distributor for verrtical 3 m long wall

56

3.15

176.40

176.40

10

21

168

1.65

277.20

Distributor for above 200mm c/c- only for full raft

Raft top short bar at 150 mmc/c for length 3m

10 mm

774.48
192.00

277.20

Distributor for above 200mm c/c for full raft length

64

192.00

192.00

Wall innerface vertical bar

20

16

320

1.8

576.00

576.00

Distribution for above in external wall

64

6.15

393.60

393.60

Distribution for above in external wall

64

3.35

214.40

214.40

Raft bottom- L rod

10

10

16

160

3.55

568.00

Raft top mat -L rod

10

10

16

160

2.14

342.40

16

128

1.8

230.40

10

242

484

1.61

779.24

64

4.8

307.20

10

52

52

6.5

338.00

34

34

6.74

229.16

10

37

74

1.75

129.50

Trench common corner portion for length 1.5m

wall inner face vertical bar on only one side

568.00
342.40
230.40

Distributors are considred already


Trench cover slab
Both top and bottom for Length 6m
Distributor for both top & bottom

779.24
307.20

Trench from Yard to Controll Room


Length 6.4m
bottom main- u Shape 125mm c/c
distribution for above
inner face main vertical bars outer

338.00
229.16
129.50

16

6.74

107.84

inner face main vertical bars middle

10

52

104

1.75

182.00

182.00

distribution for above

10

16

6.74

107.84

107.84

cover slab main T & B

10

36

288

1.96

564.48

564.48

distribution for above

Page 23 of 162

107.84

12 mm

S.
No

Member Details
distribution ring shape for above

Dia of
Bar
mm

No of
No of
Membe
Bar
r

Total
Nos

Bar Bending
Schedule

Cutting
Length

Total
Cutting
Length

8 mm
486.00

15

36

540

0.9

486.00

10

31

62

4.75

294.50

24

48

4.5

216.00

10

26

104

1.75

182.00

10 mm

12 mm

Incoming Cable trench


bottom main- u Shape 150mm c/c
distribution for above at 200mmc/c
inner face main vertical bars 175mm c/c
distribution for above at 200mm c/c

32

4.5

144.00

cover slab main T & B at 150mm c/c

10

31

124

1.91

236.84

distribution for above at 200mm c/c

10

40

4.5

180.00

10

-24

-48

1.75

-84.00

-8

-16

3.6

-57.60

10

-10

-20

1.45

-29.00

-8

-16

3.6

-57.60

10

-10

-40

1.45

-58.00

-8

-32

1.95

-62.40

294.50
216.00
182.00
144.00
236.84
180.00

Deductions at the junction of Cable duct


At control room and yard for 3.6m width
Coth vertical bars 125 mm c/c
distribution

-84.00
-57.60

At cable trench in transformer plinth


vertical wall bar at 150mm c/c
disortributor

-29.00
-57.60

At at cable trench Entry


vertical wall bar at 150mm c/c
disortributor

-58.00
-62.40

8.00

Total length
Unit Wt
Wt in MT -Dia Wise
Total Wt in M.Tonne

Total Steel for the project in M.Tonne

Page 24 of 162

4725.90
0.40
1.87

10
5796.52
0.617
3.576

12
1001.16
0.888
0.889

7.64

57.9

16 mm

20 mm

25 mm

0 2324.4288

2324

784

175
107.00

20.00

78.9526 945.34272

314.96 3699.822

72.00
49.80
72.00

Page 25 of 162

5039

16 mm

20 mm

25 mm
52.80

48.00
12.60
16.60
22.60
48.00
12.60
35.20

48.00
29.70
23.70
72.00
8.85
7.86

96.00
3.30
20.80
79.44
20.80

591.7258 945.34272

0 423.1935

664.392 5405.8296

Page 26 of 162

8030

16 mm

20 mm

25 mm

10.40
7.24
18.88
18.88
9.44
7.24
9.44
9.44

565.956

0 467.6559 504.7792 1706.0076

24.00
26.16
22.90
24.00
26.4

72.00
30.42
23.70
72.00

39.72
5.10
39.00
57.30

Page 27 of 162

3244

16 mm

20 mm

25 mm

14.00

24.00
39.00
48.00
11.20

37.86
10.80
39.60
16.80

22.90
6.60
5.60

32.60
41.3

Page 28 of 162

16 mm

20 mm

25 mm

446.034

147.8406

0 94.05696 569.9414 866.4624 387.96048

0 440.51904

Page 29 of 162

2364

588

16 mm

20 mm

25 mm

Page 30 of 162

16 mm

20 mm

25 mm

1182.867 4704.3288

5887

375

46.1518 547.30368

267.84 3051.678

3913

374.71201
660.89
1.58
1.044

679.92
2.47
1.679

1501.76
3.858
5.794

822

616

175
88.00

20.00

Page 31 of 162

16 mm

20 mm

25 mm

225.4502 124.3872 433.9656

120.00
30.70
120.00
45.00
88.00
111.00
256.4
162.00

28.00

34.30
17.15

Page 32 of 162

784

16 mm

20 mm

25 mm

72.00
11.00
16.40
41.7
13.8
13.8

36.40
35.60
11.20

48.00
7.20
27.00
24.00
16.24
26.00
13.20

28.00

19.72
14.24
19.72

Page 33 of 162

16 mm

20 mm

25 mm

24.00
24.00
7.20
27.00
24.00
24.00
31.20

24.00
24.00
3.26
13.50
24.00
24.00
15.60

417.0252

453.495

96.9696 253.2096 1288.112 4308.8073

Page 34 of 162

6818

16 mm

20 mm

25 mm

Page 35 of 162

16 mm

20 mm

25 mm

1358.7329 1879.2895 170.61144

32.76
21.96
81.72
40.56
61.76
27.60
23.16

9.14
3.40
9.14
2.98

31.08

29.82
91.20

Page 36 of 162

3409

16 mm

20 mm

25 mm

9.60

22.68

27.492 212.45161

16
635.18
1.58
1.004

20
652.06
2.47
1.611

744.023

61.1568

25
1907.85
3.858
7.360

968

528
70

70.00

Page 37 of 162

1045

16 mm

20 mm

25 mm

54.0202 646.81344

308.0052 223.00848 438.86736

173.6 2307.084

120.00
120.00
30.70

Page 38 of 162

3182

970

16 mm

20 mm

25 mm
46.00

65.25
84.00
256.4
126.00

28.00

27.70
13.85

48.00
36.80
10.60
27.30
25.60

11.08
5.54
10.40

7.20

Page 39 of 162

16 mm

20 mm

25 mm

27.00

16.80

26.00

3.60
21.60
3.60
5.40

14.00
4.05

6.60
5.60

Page 40 of 162

16 mm

20 mm

25 mm

3.10
12.65

8.40

737.7257

0 440.51904

245.234 987.8584 2717.1508

Page 41 of 162

5128

16 mm

20 mm

25 mm

Page 42 of 162

16 mm

20 mm

25 mm

1608.0529 1599.5417

24.00
33.60
66.60
9.60

35.37
38.40
35.37
28.20

9.50
3.46
4.75
2.98

30.72
27.00
71.04

Page 43 of 162

3208

16 mm

20 mm

25 mm

9.60

32.40

22.32

10.428 71.66455

6.216 728.8254

51.3112

54.00

54.00

1.38

9.80
15.20
31.20
7.50

Page 44 of 162

868

16 mm

20 mm

25 mm

2.30

4.33
4.33

0.69

218.8142 402.94419 91.89024 114.3288

16
692.78
1.580
1.095

20
543.02
2.470
1.341

133.38 225.19146

25
1360.66
3.858
5.249

544

153.28

Page 45 of 162

1187

16 mm

20 mm

25 mm

10.50
7.28
5.92
12.40
20.40

92.80

108.80

81.60

108.80
44.80
32.00

Page 46 of 162

16 mm

20 mm

25 mm

432.4855 616.40768 889.03008 645.8666

966.012 1809.8584

662.656

3246

2776

Page 47 of 162

16 mm

20 mm

16
411.38
1.58
0.650

20
267.20
2.47
0.660

25 mm

325.085 815.56294

1141

143.148 334.62378

478

25
0.00
3.858
0.000

66004.47475

642

.98

Page 48 of 162

HARINI ENTERPRISES
MEASUREMENT SHEET JOINTLY ARRIVED BY M/S. DSWE and HARINI ENTERPRISES
PROJECT : 33/11 KVA SUB STATION WORK NORTH CHENNAI.
SITE : KOLATHUR
CLIENT : M/S. DRAKE & SCULL WATER & ENERGY PVT LTD.
MEASUREMNT ARRIVED BY: Mr.Mohammed Nazer ( Manager Civil,DSWE) and Mr.Rajaraman (Projec
Engg,Harini),Mr.Anbarasan (Site Engg)
CHECKED & RE-ARRIVED BY : Mr.Sivasubramanian(Engineer Civil,DSWE) and Mr.Anbarasan(Site En
Sl No

DESCRIPTION OF ACTIVITIES

NOS

HEIGHT
LENGTH WIDTH
/ DEPTH
IN M
IN M
IN M

QTY

A SUB STRUCTURE
1(a) EARTH WORK IN EXCAVATION
2
1

26.4
7.9

4.2
4

2
2

443.52
63.2

ALONG GRID B1 TO B2

2
1

26.4
7.9

4.2
4

0.18
0.18

39.9168
5.688

2 RIVER SAND BEDDING


ALONG GRID A & C
ALONG GRID B1 TO B2

14
2

3.6
3.4

3.6
3.4

0.1
0.1

18.144
2.312

3 PCC FOR FOOTINGS


ii PCC ALONG GRID A & C
PCC ALONG GRID B1 TO B2

14
2

3.6
3.4

3.6
3.4

0.075
0.075

13.608
1.734

4 FOOTING
i SHUTTERING
ATF1
ATF2

14
2

13.6
12.8

0.25
0.25

47.6
6.4

ALONG GRID A1 TO A7*& C1 TO C7

ALONG GRID B1 TO B2
1.(b) EXCAVATION BELOW 2M
ALONG GRID A1 TO A7*& C1 TO C7

ii REBAR (from BBS sheet )


iii RCC
AT F1
AT F1
AT F2
AT F1

(RECTANGULAR)
(TRAPEZOIDAL)
(RECTANGULAR)
(TRAPEZOIDAL)

5 COLUMN UP TO PLINTH LVL


SHUTTERING
i AT C1
AT C2
DEDUCTIONS AT GRADE LEVEL
AT GB3 BEAM JUNCTIONS FOR C1
AT GB4 BEAM JUNCTIONS FOR C1
AT GB1 BEAM JUNCTIONS FOR C1
AT GB2 BEAM JUNCTIONS FOR C1
AT GB1 IN CANTILEVER FOR C2

2.3244

14
14
2
2

3.4

3.4

3.2

3.2

14
2

3.65
3.65

1.8
1.46

-20
-6
-10
-8
-2

Page 49 of 162

0.23
0.23
0.30
0.23
0.23

0.25
2.06
0.25
1.77

40.46
28.84
5.12
3.54

91.98
10.658
0.3
0.45
0.6
0.45
0.6

-1.38
-0.621
-1.8
-0.828
-0.276

Sl No

DESCRIPTION OF ACTIVITIES

DEDUCTIONS AT PLINTH LEVEL


AT BEAM PB3 JUNCTIONS FOR C1
AT BEAM PB2 JUNCTIONS FOR C1 & C2
AT BEAM PB4 JUNCTIONS FOR C1
AT BEAM PB1 JUNCTIONS FOR C1
AT BEAM PB6 JUNCTIONS FOR C1

ii REBAR

NOS

HEIGHT
LENGTH WIDTH
/ DEPTH
IN M
IN M
IN M

-20
-8
-6
-2
-4

0.23
0.23
0.23
0.3
0.23

0.3
0.45
0.45
0.75
0.45

QTY

-1.38
-0.828
-0.621
-0.45
-0.414

5.0391

iii RCC COLUMN


AT C1
AT C2

14
2

3.65
3.65

0.4
0.23

0.5
0.5

10.22
0.84

6 GRADE BEAM
i PCC
AT GB-1
AT GB-2
AT GB-2
AT GB-3
AT GB-4

5
2
2
10
3

10.5
4.75
5.25
3.3
3.3

0.5
0.43
0.43
0.43
0.43

0.075
0.075
0.075
0.075
0.075

1.97
0.31
0.34
1.06
0.32

iiI REBAR
IV SHURTTERING FOR GBEAMS
AT GB-1
AT GB-2
AT GB-2
AT GB-3
AT GB-4

v RCC
AT GB-1
AT GB-2
AT GB-2
AT GB-3
AT GB-4
GB1 FOR STAIR
7 BACK FILLING STAGE 1
REFER EXCAVTION QTY
DEDUCTIONS
RIVER SAND FILLING BELOW FOOTING
PCC BELOW FOOTING
RCC FOOTING
COLUMN
GARDE BEAM PCC

3.24

10
4
4
20
6

10.5
4.75
5.25
3.3
3.3

5
2
2
10
3
2

10.5
4.75
5.25
3.3
3.3
1.5

0.3
0.23
0.23
0.23
0.23
0.3

0.6
0.45
0.45
0.3
0.45

63
8.55
9.45
19.8
8.91

0.6
0.45
0.45
0.3
0.45
0.6

9.45
0.98
1.09
2.28
1.02
0.54

552.32

552.32

-1
-1
-1
-1
-1

20.456
15.342
77.96
11.06
4.00

-20.456
-15.342
-77.960
-11.060
-3.997

Page 50 of 162

Sl No

DESCRIPTION OF ACTIVITIES

7 PLINTH BEAM
SHUTTERING
AT PB-1
AT PB-2
AT PB-2
AT PB-3
AT PB-4
AT PB-5
AT PB-6
REBAR
RCC
AT PB-1
AT PB-2
AT PB-2
AT PB-3
AT PB-4
AT PB-5
AT PB-6
8 STAIRS FROM FGL TO +1.60M
i SHUTTERING
FOR RISER WALL
GROUND LANDING
WAIST SLAB
EDGE SIDE
LANDING

NOS

2
4
4
18
6
4
8

HEIGHT
LENGTH WIDTH
/ DEPTH
IN M
IN M
IN M

10.5
4.75
5.25
3.3
3.3
3.35
1.23

0.75
0.45
0.45
0.3
0.45
0.45
0.45

QTY

15.75
8.55
9.45
17.82
8.91
6.03
4.428
2.3645

1
2
2
9
4
2
4

10.5
4.75
5.25
3.3
3.3
3.47
1.5

4
2
2
2
2

1.5
1
3.06
4.06
3.3

0.3
0.23
0.23
0.23
0.23
0.23
0.23

0.75
0.45
0.45
0.3
0.45
0.45
0.45

2.36
0.98
1.09
2.05
1.37
0.72
0.62

0.2

1.20
3.50
10.71
1.22
11.55

1.75
1.75
0.15
1.75

ii REBAR

0.588

iii RCC
RAISER WALL
GROUND LANDING
WAIST SLAB
LANDING

2
2
2
2

1.5
1
3.06
3.3

0.15
1.77
1.77
1.77

0.2
0.15
0.15
0.15

0.09
0.53
1.62
1.75

9 BRICK WORK BELOW PLINTH


AT PB1
AT PB2
AT PB2
AT PB3
AT PB4
AT PB5
AT PB6

1
2
2
9
4
2
2

10.5
4.75
5.25
3.3
3.3
3.3
1.5

0.23
0.23
0.23
0.23
0.23
0.23
0.23

1.1
1.4
1.4
1.55
1.4
1.95
1.95

2.66
3.06
3.38
10.59
4.25
2.96
1.35

1.75

0.23

0.15

0.54

18.185

0.1

7.27

STEPS FROM 0M LVL TO +1.5 M LVL


10 CABLE TRENCH

Page 51 of 162

Sl No

DESCRIPTION OF ACTIVITIES

NOS

HEIGHT
LENGTH WIDTH
/ DEPTH
IN M
IN M
IN M

QTY

i RIVER SAND FILLING


RIVER SAND FILLING (Middle)

2
1

6.5
6.5

2
2.1

0.1
0.1

2.60
1.37

ii PCC

2
2
1

18.185
6.5
6.5

2
2
2.1

0.075
0.075
0.075

5.46
1.95
1.02

2
4
2
2
4
4
4
4
3
4
1

12.485
6.7
17.785
10.1
6.6425
6.2425
7.1
6.7
7.1
1.5
2

0.2
0.2
1.65
1.5
1.5
1.5
1.5
1.5

4.994
5.36
58.6905
30.3
39.855
37.455
42.6
40.2
31.95
9
3

-2
-4
-1

1.5
1.9
3.25

1.5
0.15
1.5

-4.5
-1.14
-4.875

iii SHUTTERING
SHUTTERING FOR RAFT
SHUTTERING FOR WALL

SHUTTERING FOR COVER SLAB

DEDUCTIONS
JUN OF IN COMING CABLE DUCT
WALL
Deduction of corners
JUNCTION OF CABLE DUCT FROM PLINTH
iv REBAR

1.5
1.5
1.5

v RCC
AT RAFT
AT WALL

COVER SLAB

RCC (FOR THE PLAN AREA OTHER THAN


CABLE DUCT)- SLAB ON GRADE
DEDUCTION
JUN OF IN COMING CABLE DUCT
corners
JUNCTION OF CABLE DUCT FROM PLINTH

5.8872

2
3
2
2
4
4
3
4
1

18.185
6.7
18.185
10.1
6.443
6.9
7.1
1.7
2

1.9
1.9
0.2
0.2
0.2
0.2
1.9
1.9
1.9

0.2
0.2
1.65
1.5
1.5
1.5
0.15
0.15
0.15

13.82
7.64
12.00
6.06
7.73
8.28
6.07
1.94
0.57

7.1

6.243

0.1

8.87

-2
-4
-1

1.5
1.9
3.25

1.5
0.2
1.5

0.2
0.15
0.2

-0.90
-0.23
-0.98

1
1

12.74
3.3

6.7
10.27

2.12
2.12

180.96
71.85

-4

10.50

0.3

0.6

-7.56

11 BACK FILLING STAGE 2


QTY ABOVE NGL TO CONTROL ROOM
TOILET SATIR AREA
DEDUCTIONS
GRADE BEAM GB1

Page 52 of 162

Sl No

DESCRIPTION OF ACTIVITIES

NOS

HEIGHT
LENGTH WIDTH
/ DEPTH
IN M
IN M
IN M

QTY

i RIVER SAND FILLING

1
1

12.485
10.27

6.7
3.3

0.08
0.08

6.69
2.71

ii PCC

1
1

12.485
10.27

6.7
3.3

0.1
0.1

8.36
3.39

iii REBAR

0.37

TOTAL(A)
B SUPER STRUCTURE UP TO FF
1 COLUMN UP TO FF
i REBAR
ii SHUTTERING
AT C1
AT C2
DEDUCTIONS AT BEAM LEVEL
AT BEAM FB4 JUNCTIONS FOR C1
AT BEAM FB5 JUNCTIONS IN C1
AT BEAM FB8 JUNCTIONS IN C1
AT BEAM FB1 JUNCTIONS IN C1
AT BEAM FB2&FB3 JUNCTIONS IN C1
AT BEAM FB6 JUNCTIONS FOR C1
Lintel Junction
AT BEAM JUNCTION C2

-20
-4
-2
-10
-8
-7
-32
-2

iii RCC
AT C1
AT C2

14
2

2 LINTEL ,SSHADE& LATH (DROP)


i SHUTTERING FOR SUN SHADE
SHUTTERING FOR LINTEL

Toilet & Battery room

DROP ABOVE VARANDAH


II REBAR
iii RCC SUN SHADE
RCC LINTEL

TOILET FLOOR LVL BEAM

3.91
14
2

4.42
4.42

1.8
1.46

111.38
12.91

0.23
0.23
0.23
0.4
0.23
0.23
0.3
0.23

0.4
0.6
0.5
0.75
0.6
0.4
0.23
0.45

-1.84
-0.552
-0.23
-3
-1.104
-0.644
-2.208
-0.207

4.42
4.42

0.4
0.23

0.5
0.5

12.38
1.02

12

1.6

0.7

13.44

6
22
4
4

10.5
3.3
3.3
1.9

0.3
0.3
0.3
0.3

18.90
21.78
3.96
2.28

25.5

1
12
1
1
1
1
Page 53 of 162

25.50
0.78

1.6
66.8
3.3
3.3
10.4

0.6
0.23
0.23
0.115
0.23

0.1
0.3
0.3
0.3
0.3

1.15
4.61
0.23
0.11
0.72

Sl No

DESCRIPTION OF ACTIVITIES

NOS

HEIGHT
LENGTH WIDTH
/ DEPTH
IN M
IN M
IN M

QTY

MID LVL 4.5"

3.8

0.115

0.3

0.13

DROP ABOVE VARANDAH

25.60

0.08

2.05

3 FF BEAM
i REBAR
SHUTTEREING
AT FB-1
AT FB-2
AT FB-3
AT FB-4
AT FB-5
AT FB-6
AT FB-7
AT FB-8

5
2
2
10
2
7
6
1

10.5
4.75
5.25
3.3
3.3
1.52
3.3
3.3

1.42
1.29
1.13
0.75
1.13
1.03
0.57
0.83

iii RCC
AT FB-1
AT FB-2
AT FB-3
AT FB-4
AT FB-5
AT FB-6
AT FB-7
AT FB-8

5
2
2
10
3
7
6
1

10.5
4.75
5.25
3.3
3.3
1.5
3.4
3.3

0.4
0.23
0.23
0.23
0.23
0.3
0.23
0.23

10.54
5.45
1.45
34.20

3.3000
3.3000
3.3000

6.8176

4 FF SLAB
i SHUTTERING
FS 1
FS3
FS2
OUTER SIDES

5
1
6
2

ii REBAR
iii RCC
FS-1
FS-1
FS-2
FB-3

74.55
12.26
11.87
24.75
7.46
10.96
11.29
2.74

0.75
0.6
0.6
0.4
0.6
0.4
0.3
0.5

15.75
1.31
1.45
3.04
1.37
1.26
1.41
0.38

0.1500

173.91
17.99
28.71
10.26

5 STAIR FROM +1.5M TO- 5.85M LVL


i SHUTTERING FOR STAIR UP TO FF
MID LANDING BEAM AT +3.675M
MID LANDING SLAB AT +3.675M
WAIST SLABS 1 &2

3.41

4
1
6
1

10.5
10.5
3.4
5.385

3.3
3.385
1.52
3.385

1
1
2

3.745
3.745
4.05

0.83
1.385
2.03

Ii REBAR

0.14
0.14
0.14
0.15

19.40
4.98
4.34
2.73

3.11
5.19
16.44
1.05

IiI RCC
Page 54 of 162

Sl No

DESCRIPTION OF ACTIVITIES
STAIR FROM +1.5M TO- 5.85M LVL
MID LANDING BEAM AT +3.675M
MID LANDING SLAB AT +3.675M
WAIST SLABS 1 &2

6 BRICK WORKS AT GF
ALONG GRID A&C
ALONG GRID 1,2
ALONG GRID 7
WALL BETWEEN GRID B& C
STEPS FROM +1.5 TO FF
DEDUCTIONS
WINDOW -W
VENTILATORS-V
VENTILATORS-V
DOOR D1
ROLLING SHUTTER
COLLAPSABLE GATE
JOLLEY
7 HALF BRICK WALL
WALL AT GRID B
WALL AT TOILET
DEDUCTIONS
DOOR D2

NOS

1
1
2

HEIGHT
LENGTH WIDTH
/ DEPTH
IN M
IN M
IN M

QTY

3.3
3.385
4.06

0.23
1.385
1.6

0.45
0.2
0.2

0.34
0.94
2.60

12
2
1
1
14

3.3
10
10.5
3.3
1.72

0.23
0.23
0.23
0.23
0.25

3.7
3.65
3.65
3.5
0.145

33.70
16.79
8.81
2.66
0.87

-12
-9
-3
-3
-1
-1
-1

1.18
1.18
0.8
0.9
2.75
1.5
1.2

0.23
0.23
0.23
0.23
0.23
0.23
0.23

1.48
0.58
0.58
2.1
4
2.4
1.2

-4.82
-1.42
-0.32
-1.30
-2.53
-0.83
-0.33

1
2
2
-2

3.3
1.9
1.05
0.9

3.5
3.5
3.5
2.1

11.55
13.30
7.35
-3.78

TOTAL(B)
C SUP STRUC. FROM FF TO ROOF
1 COLUMN UP TO ROOF
i REBAR
ii SHUTTERING
AT C1
AT C2
DEDUCTIONS AT BEAM LEVEL
AT BEAM RB4 JUNCTIONS IN C1
AT BEAM RB7 JUNCTIONS IN C1
AT BEAM RB1 JUNCTIONS IN C1
AT BEAM RB6 JUNCTIONS IN C1
AT BEAM RB5 JUNCTIONS IN C1
ATBEAM JUNCTION C2

-22
-2
-10
-4
-7
-6

iii RCC
AT C1
AT C2

14
2

8
24
1

2 LINTEL ,SSHADE& LATH (DROP)


i SHUTTERING FOR SUN SHADE
SHUTTERING FOR LINTEL

3.18
14
2

Page 55 of 162

3.5
3.5

1.8
1.46

88.20
10.22

0.23
0.23
0.4
0.23
0.23
0.23

0.4
0.5
0.75
0.5
0.5
0.5

-2.024
-0.23
-3
-0.46
-0.805
-0.69

3.5
3.5

0.4
0.23

0.5
0.5

9.80
0.81

1.6
3.3
10.5

0.7
0.3
0.6

8.96
23.76
6.30

Sl No

DESCRIPTION OF ACTIVITIES

LOFT
DROP ABOVE VARANDAH

NOS
2
2
2
1

HEIGHT
LENGTH WIDTH
/ DEPTH
IN M
IN M
IN M

10
18.185
9.3
25.6

0.6
0.68
0.68
1

II REBAR
iii RCC SUN SHADE
RCC LINTEL
ABOVE 4.5" WALL
LOFT
DROP ABOVE VARANDAH
3 ROOF BEAM
i SHUTTERING
AT RB1
AT RB3
AT RB4
AT RB5
AT RB6
AT RB7
ii REBAR
iii RCC
AT RB1
AT RB3
AT RB4
AT RB5
AT RB6
AT RB7

QTY
12.00
24.73
12.65
25.60
0.97

8
12
1
1
1
2
2
1

1.6
3.3
10.5
2.775
3.76
18.185
9.34
25.6

0.6
0.23
0.23
0.115
0.23
0.6
0.6
0.08

5
6
11
7
2
1

10.5
3.4
3.3
0.75
10
3.3

1.62
0.69
0.8
1.27
0.72
0.95

0.1
0.3
0.3
0.3
0.3
0.08
0.08
1

0.77
2.73
0.72
0.10
0.26
1.75
0.90
2.05

85.05
14.08
29.04
6.67
14.40
3.14
5.13

5
6
11
7
2
1

10.5
3.4
3.3
1.5
10
3.3

0.4
0.23
0.23
0.3
0.23
0.23

10.50
5.25
1.54
34.06

3.30
3.30
3.30

0.75
0.3
0.4
0.5
0.5
0.5

15.75
1.41
3.34
1.58
2.30
0.38

0.15

173.25
17.33
30.49
10.22

4 ROOF SLAB
i SHUTTERING

OUTER SIDES
ii REBAR
iii RCC
RSI
RSI
RS3
RS2

5
1
6
2

3.21
4
1
1
6

5 9" BRICK WORKS AT FF


Page 56 of 162

10.50
10.50
5.39
1.52

3.30
3.39
3.39
3.40

0.14
0.14
0.14
0.14

19.40
4.98
2.55
4.34

Sl No

DESCRIPTION OF ACTIVITIES
ALONG GRID A&C
ALONG GRID 1,2
ALONG GRID 1,2&7
WALL BETWEEN GRID A& C
STEPS
DEDUCTIONS
WINDOW -W
VENTILATORS-V
DOOR D1
DOOR D
JOLLY

HEIGHT
LENGTH WIDTH
/ DEPTH
IN M
IN M
IN M

NOS

QTY

11
2
1
2
11

3.3
10
10.5
3.3
1.73

0.23
0.23
0.23
0.23
0.25

2.8
2.75
2.45
2.6
0.145

23.38
12.65
5.92
3.95
0.69

-11
-7
-2
-2
-1

1.18
0.8
0.9
0.9
1.2

0.23
0.23
0.23
0.23
0.23

1.48
0.58
2.1
2.1
1.2

-4.42
-0.75
-0.87
-0.87
-0.33

2
2
1
2
-4

1.5
1.05
1.5
1.15
0.9

3.05
3.05
3.05
3.05
2.1

9.15
6.41
4.58
7.02
-7.56

5(a) 9' BRICK WORKS AT VARANDAH

25

0.23

0.9

5.18

7 STAIR CASE STRUCTURE


i SHUTTERING
STAIR FROM + 5.85M TO 9.04
MID LANDING BEAM AT +7.445M
MID LANDING SLAB AT +9.04M
SMALL LANDING AT +5.85MLVL
WAIST SLAB 3 & 4

1
1
1
2

3.745
3.745
1.6
3.182

0.83
1.385
0.75
2.03

ii REBAR FOR STAIR

iii RCC FOR STAIR


STAIR FROM + 5.85M TO 9.04
MID LANDING BEAM AT +7.445M
MID LANDING SLAB AT +9.04M
SMALL LANDING AT +5.85MLVL
WAIST SLAB 3&4

1
1
1
2

6 4.5"WALL AT FF
WALL AT GEN TOILET
WALL AT LADIES TOILET
DEDUCTIONS -DOOR D2

8 ROOF WORKS
a. ROOF LVL RCC & head room
i SHUTTEREING
HB1 Outer side
HB1 Inner side
HB2 Outer side
HB2 Inner side
HB3 Outer side
HB3 Inner side
HS1
C1

0.87

3.745
3.745
1.6
3.182

1
3
2
2
1
1
1
2
Page 57 of 162

3.11
5.19
1.20
12.92

3.930
3.470
7.115
6.425
3.930
3.470
7.115
1.800

0.23
1.385
0.75
1.6

0.45
0.2
0.2
0.2

0.39
1.04
0.24
2.04

0.500
0.360
0.500
0.360
0.300
0.160

1.965
3.748
7.115
4.626
1.179
0.555
27.962
7.920

3.930
2.200

Sl No

DESCRIPTION OF ACTIVITIES

HEIGHT
LENGTH WIDTH
/ DEPTH
IN M
IN M
IN M

NOS

C2

ii REBAR
iii RCC
COLUMN C1 AT PARAPET
COLUMN C1
COLUMN C2
BEAM HB1
BEAM HB2
BEAM H3
SLAB HS1

1.460

2.200

QTY
6.424
1.19

8
2
2
2
2
1
1

0.90
2.40
2.40
3.30
5.87
3.3
6.425

0.40
0.40
0.23
0.23
0.23
0.23
3.47

0.50
0.50
0.50
0.50
0.50
0.3
0.14

1.44
0.96
0.55
0.76
1.35
0.23
3.12

6
1
1
1
1

3.3
10.5
5.25
16.17
20.9

0.23
0.23
0.23
0.23
0.23

0.9
0.9
0.9
1.9
0.3

4.10
2.17
1.09
7.07
1.44

-1
-1
-1

0.9
1.18
1.2

0.23
0.23
0.23

1.9
1.48
1.2

-0.39
-0.40
-0.33

25

0.23

0.9

5.18

1
2
2
1
1

3.9
1.9
3
12.5
12.5

10
12.58
1.9
6.2
6.2

2.2
1.1
1.1
0.1
0.075

85.80
52.58
12.54
7.75
5.81

25.22
19.76
1.2
1.36

BEAM B1
BEAM B2
SLAB
FIRE WALL
CABLE DUCT RAFT ALONG PLINTH

1
2
8
2
8
4
1
2
2

0.25
0.35
2.10
2.10
0.325
0.325
4.50
0.20

35.963
35.963
20.160
5.712
35.963
35.963
11.223
35.963
35.963

CABLE DUCT RAFT ARROUND PLINTH-WALL

72

1.30

35.963

b BRICK WORK 9"


AT PARAPET

AT HEAD ROOM
HEAD ROOM PARAPET
DEDUCTIONS
DOOR D1
WINDOW
JOLLY
c BRICK WORKS-9"
TOTAL ( C)
D EXTERNAL FINISHING AND YARD WORKS
1 EXTERNAL WORKS & YARD
a EXCAVATION TRANS FTNG
EXCAVATION TRANS FTNG
CABLE TRENCH
b RIVER SAND
c PCC
d SHUTTERING
TRANSFORMER FOUNDATION & FIRE WALLBASE
STRAP BEAM
COLUMN

Page 58 of 162

2.475
2.475
3.35
4.23
18

3.35

Sl No

DESCRIPTION OF ACTIVITIES
COVER SLAB
DEDUCTIONS
JUN OF CABLE DUCT FROM CNT. ROOM

e
f

REBAR FOR TRS. FORMER FND


RCC
TRANSFORMER FOUNDATION
STRAP BEAM
COLUMN C1
BELOW GROUND C2
ABOVE GROND C2
BEAM AT FLOOR LEVEL B1
BEAM AT FLOOR LEVEL B2
SLAB AT PLINT
FIRE WALL
CABLE DUCT AROUND PLINTH
RAFT

NOS

HEIGHT
LENGTH WIDTH
/ DEPTH
IN M
IN M
IN M

18

-2

3.25

1.2

QTY
43.200

1.30

-8.450
6.0223

1
2
8
2
2
4
8
2
1

9.38
9.38
0.3
0.45
0.45
2.175
2.175
3
4.5

3.275
0.5
0.3
0.3
0.23
0.3
0.3
3
0.23

0.25
0.35
2.10
1.00
1.10
0.33
0.33
0.18
4.95

7.68
3.28
1.51
0.27
0.23
0.85
1.70
3.15
5.12

2
4
1
8
2
4

12.07
3
46.94
2.175
12.07
3

1.5
1.5
0.15
0.15
1.2
1.2

0.20
0.20
1.55
1.55
0.15
0.15

7.24
3.60
10.91
4.05
4.35
2.16

DEDUCTIONS
JUN OF CABLE DUCT FROM CNT. ROOM

-2

3.25

1.3

0.15

-1.268

2
a

CABLE DUCT FROM PLINTH TO


BUILDING
EARTHB WORK EXCAVATION

6.34

4.2

1.00

26.63

b
c
d

RIVER SAND
PCC
SHUTTEREING

1
1

6.34
6.34

3.8
3.8

0.08
0.10

1.93
2.41

2
1
6
6
2
2
2
1
2
1

5
2
4.8
1.5
5
1.5
5
3.65
1.5
3.65

0.20

2.000
8.100
25.920
13.500
15.000
4.800
3.000
1.095
0.450
0.548

WALL
COVER SLAB

CABLE DUCT FROM TRANSFORMER TO


BUILDING
RAFT
Flight bottom
Wall
COVER SALB
COVER SALB SIDE

e
f

REBAR
RCC
RAFT

4.05
0.90
1.5
1.5
1.6
0.30
0.30
0.15
0.15

1.141
1
Page 59 of 162

6.35

3.65

0.20

4.64

Sl No

DESCRIPTION OF ACTIVITIES
WALL HEIGHT VARIES
WALL FOR 4M
BEAM
BEAM
COVER SLAB

3
a
b
c
d

INCOMING CABLE TRENCH


EXCAVATION
SAND FILLING
PCC
SHUTTERING
RAFT
WALLL
COVER

e
f

REBAR
RCC
RAFT
WALL
COVER

NOS

HEIGHT
LENGTH WIDTH
/ DEPTH
IN M
IN M
IN M

QTY

2
1
2
1
2
1
1
1

2.34
2.34
4
4
3.65
3.65
4.85
1.5

0.2
0.25
0.2
0.25
0.3
0.35
3.65
3.65

0.65
0.65
0.90
0.90
0.30
0.20
0.30
0.15

0.61
0.38
1.44
0.90
0.66
0.26
5.31
0.82

2
2
2

4.5
4.5
4.5

2.5
2.1
2.1

1.50
0.08
0.10

33.75
1.51
1.89

2
4
4
2

10.9
4.5
4.5
4.5

0.20
1.30
1.15

4.36
23.40
20.70
13.50

1.5

0.48
2
4
2

4.5
4.5
4.5

1.9
1.2
1.9

0.20
0.20
0.15

BACK FILLING 3RD STAGE


REFER QTY OF EXCAVATION
DEDUCTION
R SAND FILLING OF TRANS FDN
PCC OF TRANS FDN
RCC OF TRANS FDN

3.42
4.32
2.57

150.92
-7.75
-5.81
-54.83

4 PAVING
5 ROAD

1
1

6 UG SUMP
12 RIVER SAND FILLING
a PCC
b SHUTTERING
c FLOOR
WALL
COVER SLAB
REBAR 22KG/SQM OF SURFACE AREA
d RCC FLOOR
e RCC WALL
RCC COVER SLAB
7 BOUNDARY WALL

66.40
21.00

1
1

4.10
4.10

1
1
1

12.00
22.80
3.90

1
1
1
1
1

44.70
3.90
11.40
3.90
80.00

Page 60 of 162

1
6

2.3
2.3

66.40
126.00

0.1
0.1

0.94
0.94

0.2
2.1

2.40
47.88
8.19

22
0.2
0.15
0.15

0.98
1.64
3.59
1.23
80.00

2.1

2.1
2.1
2.1

Sl No

DESCRIPTION OF ACTIVITIES

NOS

HEIGHT
LENGTH WIDTH
/ DEPTH
IN M
IN M
IN M

10 WEATHERING COURSE & TILING

21.7

10.5

16 YARD OPEN AREA FILLING 4TH STAGE


SIZE OF THE PLTOT
DEDUCTION FOR BLG AREA
TRANSFORMER YARD
CABLE TRENCE AREA
INCOMING TRENCH AREA
WATER TANNK
STAIR AREA
TOTAL OF (D )

1
-1
-1
-1
-2
-1
-2

36.5
22.2
12.30
6.34
4.50
3.00
7.40

25.03
11
6
3.6
1.9
2.5
1.75

E FINISHING WORKS
1 PLASTERING INTERNAL
GF
WALL-CONTROL ROOM
DEDUCTIONS
W
V
RS
D1
D1
Beam Surface on Wall
BATTERY ROOM
GENTS TOILET
DEDUCTIONS
Bath & Toilet walls
D1 & D2
URINAL ENTRY
VENTILATOR
D1 BATTERY ROOM
STAIR ROOM
DEDUCTION FOR CG
DEDUCTION FOR JOLLEY
b FF
WALL OFFICE
DEDUCTIONS
W
D1
D
GENTS TOILET/BATH
WALL URINAL/PASSAGE
DEDUCTION FOR DOORS-D2& D1
VENTILATORS
LADIES TOILET
DEDUCTION FOR DOORS-D1
PASSAGE
DEDUCTIONS D1 & D2

QTY
227.85

0.7
0.7
0.7
0.7
0.7
0.7
0.7

639.52
-170.94
-51.66
-15.98
-11.97
-5.25
-18.13

57.31

4.25

243.57

-12
-9
-1
-2
-1
-8
1
1

1.18
1.18
2.75
0.9
1.2
0.4
11.25
27.17

1.48
0.58
4.1
2.1
2.1
0.61
3.8
3.8

-20.96
-6.16
-11.28
-3.78
-2.52
-1.95
42.75
103.25

-4
-5
-2
-3
-1
1
-1
-1

0.115
0.9
1.05
0.8
1.2
17.27
1.5
1.2

3.8
2.1
3.8
0.6
2.1
4.25
2.1
1.2

-1.75
-9.45
-7.98
-1.44
-2.52
73.40
-3.15
-1.44

57.3

3.3

189.09

-11
-2
-2
2
1
-5
-5
2
-2
1
-5

1.18
0.9
1.1
5.1
12.4
0.8
0.8
5.5
0.8
8.32
0.8

1.48
2.1
2.1
3.3
3.3
2.1
0.6
3.3
2
3.3
2.1

-19.21
-3.78
-4.62
33.66
40.92
-8.40
-2.40
36.30
-3.20
27.46
-8.40

Page 61 of 162

Sl No

DESCRIPTION OF ACTIVITIES
VENTILATORS
STAIR ROOM AT FIRST FLOOR
DEDUCTION AT ENTRANCE
JOLLY

NOS

HEIGHT
LENGTH WIDTH
/ DEPTH
IN M
IN M
IN M

QTY

-2
1
-1
-1

0.8
17.27
3.3
1.2

0.6
3.3
3.1
1.2

-0.96
56.99
-10.23
-1.44

c HEAD ROOM
WALL
DEDUCTION DOOR
WINDOW
JOLLY

1
-1
-1
-1

16.58
0.9
1.18
1.2

2.25
2.1
1.48
1.2

37.31
-1.89
-1.75
-1.44

2 CEILING PLASTERING
a GF
CEILING
FB1 BEAM DROP
WET AREAS
BATTERY ROOM
STAIR MID LANDING
WAIST 1 &2

1
4
1
1
1
2

18.185
10.5
3.385
3.385
3.385
1.87

VARANDAH
FB6 BEAM DROP
FB7 BEAM DROP

1
7
6

22
1.5
3.3

1.75

SRAIR AT 00 LVL
WAIST
SOFFIT
BEAM PP 5 &6 DROP

2
2
2

3.13847
3.385
6.47

1.5
1.5

1
1
1
1
4
6
6

18.18
55
3.385
22.2
10.5
1.5
3.3

10.5
1.2
5
1.75

1
1
2

3.745
1.6
3.182

1.385
0.75
2.03

5.19
1.20
12.92

1
1
2

6.885
3.38
1.5

3.38

23.27
0.51
1.05

b FF
OFFICE
LOFT
WEWT AREA
VARANDAH
RB1 BEAM DROP
RB5 BEAM DROP
RB3 BEAM DROP
STAIR AREA
MID LANDING
SMALL LANDING
WAIST SLAB 3 & 4
HEAD ROOM
CEILING
BEAM DROP HB3
BEAM DROP HB2
3 FLOORING

Page 62 of 162

10.5
1.2
3.015
2.24
1.4
4.06

190.94
50.40
10.21
7.58
4.74
15.18

0.52
0.16

38.50
5.46
3.17

0.25

9.42
10.16
3.24

1.2
0.72
0.39

190.89
65.96
16.93
38.85
50.40
6.48
7.72

0.15
0.35

Sl No

DESCRIPTION OF ACTIVITIES

a GF
CERAMIC FLOORING
DEDUCTION FOR CABLE TRENCH

Breaker Area 33KVA Side


Breaker Area 1KVA Side
GENTS TOILET-FLOORING
BATTERY ROOM
ACCESS STEPS & STAIR
FLOOR LANDING SLAB AT +0.00M LVL
STEPS
STAIR PASSAGE AT ENTRANCE
b FLOOR TILING GF STAIR
MID LANDING AT +3.675M LVL
STEPS
c FF
FF-FLOORING
GENTS TOILET-FLOORING
LADIES TOILET
PASSAGE AT VARANDAH
STAIR
STEPS FROM FF TO ROOF
SMALL LANDING AT +5.85MLVL
MID LANDING SLAB
LANDING AT +9.04MLVL
4 WALL DADO
a GF
WALL TOILET/BATH
WALL URINAL
BATH PASSAGE
DEDUCTION FOR DOORS-D2
VENTILATORS
DEDUCTION FOR DOORS-D1
WALL SKIRTING
STAIR AREA
DEDUCTION FO CG
CONTROLL ROOM WALL TILING
DEDUCTION
WINDOW
DOORS
DOORS
ROLLING SHUTTER
b WALL DADO FF

NOS

HEIGHT
LENGTH WIDTH
/ DEPTH
IN M
IN M
IN M

QTY

18.185

10.5

190.94

-1
-1
-1
-1
1
1

14.385
12.585
2
0.73
3.155
3.385

1.9
1.9
8
7.8
2.9
2.24

-27.33
-23.91
-16.00
-5.69
9.15
7.58

2
20
1

3.7
1.75
5.25

1.75

1
29

3.385
1.6

1.25

18.185
3.385
3.385
22.2

10.5
2.635
2.635
1.63

1
1
1
1
20
1
1
1

1.6
3.385
3.385
3.385

2
1
1
-4
-3
-1
1
-1
2
2
-12
-2
-1
-1

Page 63 of 162

0.46
3.385

0.395

12.95
16.10
17.77

4.23
18.33

190.94
8.92
8.92
36.19
0.395

12.64
2.54
4.23
3.79

5.9
4.755
8.77
0.8
0.8
0.8

2.1
2.1
2.1
2.1
0.6
2.1

24.78
9.99
18.42
-6.72
-1.44
-1.68

17.27
1.5
18.185
10.5

0.1
0.1
2.1
2.1

1.73
-0.15
76.38
44.10

1.18
0.9
1.2
2.75

1.48
2.1
2.1
2.1

-20.96
-3.78
-2.52
-5.78

0.75
1.25
1.12

Sl No

DESCRIPTION OF ACTIVITIES
GENTS TOILET/BATH
WALL URINAL/PASSAGE
DEDUCTION FOR DOORS-D2& D1
VENTILATORS
LADIES TOILET
DEDUCTION FOR DOORS-D1
PASSAGE
DEDUCTIONS D1 & D2
VENTILATORS
SKIRTING
OFFICE
DEDUCTION DOOR D
DOOR D1
STAIR AREA
DEDUCTION FOR ENTRANCE
PASSAGE
DEDUCTIONS FOR D

NOS

HEIGHT
LENGTH WIDTH
/ DEPTH
IN M
IN M
IN M

QTY

2
1
-5
-5
2
-2
1
-5
-2

5.1
12.4
0.8
0.8
5.5
0.8
8.32
0.8
0.8

2.1
2.1
2.1
0.6
2.1
2
2.1
2.1
0.6

21.42
26.04
-8.40
-2.40
23.10
-3.20
17.47
-8.40
-0.96

1
-2
-2
1
-1
2
-2

57.37
1.1
0.9
17.27
3.3
23.5
1.1

0.1
0.1
0.1
0.1
0.1
0.1
0.1

5.74
-0.22
-0.18
1.73
-0.33
4.70
-0.22

5 PAINTING
a PAINTING INTERNAL GF
WALL RFEFER QTY FROM PLASTER
DEDUCT WALL TILING
CEILING
b PAINTING INTERNAL FF
WALL REF QTY FROM PLASTER
DEDUCT WALL TILING
CEILING

388.59
-132.36
326.18
354.01
-75.89
421.37

6 EXTERNAL FINISHING WORKS


a PLASTERING EXTERENAL WALL
CORNICHE AT PARAPET LVL
AT HEAD ROOM ROOF
COLUMN PEOJECTIONS @ SOUTH
COLUMN PEOJECTIONS @ EAST/WEST
WARANDAH PARAPET WALL AT FF
DROPS AT FIRST FLOOR LVL
COLUMN AT NORTH
ROOF LEVEL DROP ABOVE VARANDAH
b SUNSHADES AT GF
SUNSHADES AT FF
c HEAD ROOM PLASTERING EXTERNAL
HEAD ROOM PARAPET
COLUMN FACES
PARAPET IN PASSAGE AT ROOF
DEDUCTIONS
WINDOWS
CG
RS

1
1
1
12
3
1
1
12
1
8
8
1
1
1
2
-24
-1
-1

Page 64 of 162

68.2
66.4
22.2
0.25
0.17
25
25
0.25
25.7
3.4
3.4
18.13
22.2
1.81
1.5
0.72
1.04
2.29

11.14

10.75
10.75
1.8
2.1
9.3
2.1

759.75
66.40
22.20
32.25
5.48
45.00
52.50
27.90
53.97

2.4
0.6
2.7
1.9

32.64
32.64
43.51
13.32
4.89
5.70

1.02
1.87
3.87

-17.63
-1.94
-8.86

1.2
1.2

Sl No

DESCRIPTION OF ACTIVITIES
DOORS D AT FF
DEDUCTION FOR STAIR ENTRY @FF
DOOD D AT ROOF D1
JOLLY
FIRE WALL

NOS
-2
-1
-1
-3
1

HEIGHT
LENGTH WIDTH
/ DEPTH
IN M
IN M
IN M

0.64
3.3
0.44
0.74
9.25

1.87
3.87
1.87
0.74
9.5

7 PAINTING EXTERNAL

QTY
-2.39
-12.77
-0.82
-1.64
87.88
1239.96

8 SS HAND RAILS
HANDRAIL AT O TO 1.5M
HANDRAIL AT STAIR
WAIST SLABS 1 &2
WAIST SLAB 3&4
9 WATER TANK 1000 LITER
10 BATERY ROOM WALL ACID RESISTANT
11 ELECTRICAL WORKS WITH FITTINGS
12 PLUMPING & SANITARYWERES
13 SEWAGE/ DRAINAGE WORKS
14 SEPTIC TANK& SOAKWAY WITH COVERS
15 RAIN WATER LINE & HARVESTING
ENTRANCE GATE 6m wide+ 2M WICKED
16 GATE
17 INSPECTION CHAMBER
18 GULLY TRAP
19 JOINERIES
a DOOR D (CW H C FLUSH DOOR)
DOOR D1 (CW HC FLUSH DOOR)

16.00

2
2

4.05
3.182

8.10
6.36

2
1
1
1
1
1
1

10.25

2.1

21.53

30.00

1
3
2
2
6

1.1
0.9

2.1
2.1

4.62
11.34

6
1
1

0.9
2.75
1.5

2.1
4.05
2.1

11.34
11.14
3.15

e WINDOW(ALUMINIUM)
VENTILATOR IN CONTROL ROOM
VENTILATOR IN TOILETS
WINDOW IN THE PLACE OF JOLLY

23
10
9
1

1.18
1.18
0.8
1.2

1.48
0.58
0.58
1.2

40.17
6.84
4.18
1.44

f GRILL WITH PAINTING W1


WINDOW IN THE PLACE OF JOLLY

23
1

1.18
1.2

1.48
1.2

40.17
1.44

20 BOREWELL
21 ACCESS LADDER MS- 4M AT ROOF

1
1

b DOOR D2 (PVC DOOR)


c ROLLING SHUTTER
d COLLAPSIBLE GATE(MS)

SUB TOTAL (E)


TOTAL

Page 65 of 162

1.00
1.00

Sl No

DESCRIPTION OF ACTIVITIES

NOS

HEIGHT
LENGTH WIDTH
/ DEPTH
IN M
IN M
IN M

NOTE : ALL SPECIAL WORKS BOQS ARE DIRECTLY POSTED IN ABSTRACT

IMPORTED EARTH FOR FILLING =FILLING-EXCAVATION

Page 66 of 162

QTY

ERPRISES

an (Project

an(Site Engg)

RIVER
SAND
EXCAVATION EXCAVATION FILLING IN
IN CUM (1a) IN CUM (1b)
CUM

SUB
TOTAL

506.72

45.6048

20.456

15.342

PCC IN
CUM

SHUTTERI REBAR IN RCC IN GF


NG IN SQM
MT
CUM

506.72

45.60

20.456

15.342

54

54

2.3244

2.3244

77.96

77.96

Page 67 of 162

SUB
TOTAL

RIVER
SAND
EXCAVATION EXCAVATION FILLING IN
IN CUM (1a) IN CUM (1b)
CUM

PCC IN
CUM

94.04

SHUTTERI REBAR IN RCC IN GF


NG IN SQM
MT
CUM

94.04

5.0391

5.0391

11.06

11.06

4.00

4.00

3.24

3.24

109.71

109.71

15.36

15.36

423.510

Page 68 of 162

SUB
TOTAL

RIVER
SAND
EXCAVATION EXCAVATION FILLING IN
IN CUM (1a) IN CUM (1b)
CUM

PCC IN
CUM

70.938

SHUTTERI REBAR IN RCC IN GF


NG IN SQM
MT
CUM

70.938

2.3645

2.3645

9.19

9.19

28.18

28.18

0.588

0.588

4.00

4.00

28.78

Page 69 of 162

SUB
TOTAL
11.24

RIVER
SAND
EXCAVATION EXCAVATION FILLING IN
IN CUM (1a) IN CUM (1b)
CUM

PCC IN
CUM

SHUTTERI REBAR IN RCC IN GF


NG IN SQM
MT
CUM

11.24

8.43

8.43

292.8895

292.8895

5.8872

5.8872

70.87

70.87

245.25

Page 70 of 162

SUB
TOTAL

RIVER
SAND
EXCAVATION EXCAVATION FILLING IN
IN CUM (1a) IN CUM (1b)
CUM

9.40

PCC IN
CUM

SHUTTERI REBAR IN RCC IN GF


NG IN SQM
MT
CUM

9.40

11.75

11.75

0.37

0.374712

506.72

45.60

41.10

39.52

649.76

3.91

19.82

3.91

114.51

114.51

13.39

85.86

85.86
0.78

Page 71 of 162

188.44

SUB
TOTAL

RIVER
SAND
EXCAVATION EXCAVATION FILLING IN
IN CUM (1a) IN CUM (1b)
CUM

PCC IN
CUM

SHUTTERI REBAR IN RCC IN GF


NG IN SQM
MT
CUM

9.00

6.82

6.82

155.86

155.86

25.96

230.87

230.87

3.41

3.41

31.46

24.74

24.74

1.05

1.05

Page 72 of 162

SUB
TOTAL

RIVER
SAND
EXCAVATION EXCAVATION FILLING IN
IN CUM (1a) IN CUM (1b)
CUM

PCC IN
CUM

SHUTTERI REBAR IN RCC IN GF


NG IN SQM
MT
CUM

3.88

51.28

28.42
0

0 611.8308 15.96815

3.18

3.18

91.21

91.21

10.61

Page 73 of 162

SUB
TOTAL

RIVER
SAND
EXCAVATION EXCAVATION FILLING IN
IN CUM (1a) IN CUM (1b)
CUM

PCC IN
CUM

114.00

SHUTTERI REBAR IN RCC IN GF


NG IN SQM
MT
CUM

114.00
0.97

9.27

152.37

152.37

5.13

5.13

24.75

231.29

231.29

3.21

3.21

31.27

Page 74 of 162

SUB
TOTAL

RIVER
SAND
EXCAVATION EXCAVATION FILLING IN
IN CUM (1a) IN CUM (1b)
CUM

PCC IN
CUM

SHUTTERI REBAR IN RCC IN GF


NG IN SQM
MT
CUM

39.35

19.59
5.18

22.41

22.41

0.87

0.87

3.70

Page 75 of 162

SUB
TOTAL

RIVER
SAND
EXCAVATION EXCAVATION FILLING IN
IN CUM (1a) IN CUM (1b)
CUM

PCC IN
CUM

SHUTTERI REBAR IN RCC IN GF


NG IN SQM
MT
CUM
61.494

61.494
1.19

1.19

8.41

14.74
5.18
0

85.80
52.58
12.54
7.75
5.81

0 672.77195 14.542475

85.80
52.58
12.54
7.75
5.81

Page 76 of 162

SUB
TOTAL

RIVER
SAND
EXCAVATION EXCAVATION FILLING IN
IN CUM (1a) IN CUM (1b)
CUM

PCC IN
CUM

323.58

SHUTTERI REBAR IN RCC IN GF


NG IN SQM
MT
CUM

323.58

6.02

6.02

54.83

26.63

54.83

26.63
1.93
2.41

74.41

74.41

1.14

Page 77 of 162

SUB
TOTAL

RIVER
SAND
EXCAVATION EXCAVATION FILLING IN
IN CUM (1a) IN CUM (1b)
CUM

PCC IN
CUM

SHUTTERI REBAR IN RCC IN GF


NG IN SQM
MT
CUM

15.01

33.75

15.01

33.75
1.51
1.89

61.96

61.96

0.48

10.31

10.31

82.53
66.40
126.00

0.94
0.94

58.47
0.98

6.46
80.00
Page 78 of 162

SUB
TOTAL

RIVER
SAND
EXCAVATION EXCAVATION FILLING IN
IN CUM (1a) IN CUM (1b)
CUM

PCC IN
CUM

SHUTTERI REBAR IN RCC IN GF


NG IN SQM
MT
CUM

227.85

365.59
211.30

0.00

11.19

10.11

388.59

Page 79 of 162

459.95

7.64

80.14

SUB
TOTAL

RIVER
SAND
EXCAVATION EXCAVATION FILLING IN
IN CUM (1a) IN CUM (1b)
CUM

PCC IN
CUM

354.01

348.99

421.37

Page 80 of 162

SHUTTERI REBAR IN RCC IN GF


NG IN SQM
MT
CUM

SUB
TOTAL

RIVER
SAND
EXCAVATION EXCAVATION FILLING IN
IN CUM (1a) IN CUM (1b)
CUM

PCC IN
CUM

181.56

22.56

268.17

132.36

Page 81 of 162

SHUTTERI REBAR IN RCC IN GF


NG IN SQM
MT
CUM

SUB
TOTAL

RIVER
SAND
EXCAVATION EXCAVATION FILLING IN
IN CUM (1a) IN CUM (1b)
CUM

PCC IN
CUM

75.89

256.22
326.18

278.12
421.37

Page 82 of 162

SHUTTERI REBAR IN RCC IN GF


NG IN SQM
MT
CUM

RIVER
SAND
EXCAVATION EXCAVATION FILLING IN
IN CUM (1a) IN CUM (1b)
CUM

SUB
TOTAL

PCC IN
CUM

SHUTTERI REBAR IN RCC IN GF


NG IN SQM
MT
CUM

1239.96
1239.96

30.46
2
21.53
1
1
30
1
1
1
3
2

15.96
11.34
11.14
3.15

52.63

1165.00
1
1

718.02

45.60

52.29

49.63

2394.31

57.97

268.58

Page 83 of 162

SUB
TOTAL

RIVER
SAND
EXCAVATION EXCAVATION FILLING IN
IN CUM (1a) IN CUM (1b)
CUM

PCC IN
CUM

398.86

Page 84 of 162

SHUTTERI REBAR IN RCC IN GF


NG IN SQM
MT
CUM

RCC
OTHERS
CUM

9"BRICK
WORKS IN 4.5"BW IN
CUM
SQM

INT ER.
PLASTER
IN SQM

CEILING
PLASTER
IN SQM

Page 85 of 162

EXTL
PLASTER

BACK
FLOOR
FILLING IN TILING IN
CUM
SQM

RCC
OTHERS
CUM

9"BRICK
WORKS IN 4.5"BW IN
CUM
SQM

INT ER.
PLASTER
IN SQM

CEILING
PLASTER
IN SQM

EXTL
PLASTER

BACK
FLOOR
FILLING IN TILING IN
CUM
SQM

423.51003

Page 86 of 162

RCC
OTHERS
CUM

9"BRICK
WORKS IN 4.5"BW IN
CUM
SQM

INT ER.
PLASTER
IN SQM

CEILING
PLASTER
IN SQM

28.78

Page 87 of 162

EXTL
PLASTER

BACK
FLOOR
FILLING IN TILING IN
CUM
SQM

RCC
OTHERS
CUM

9"BRICK
WORKS IN 4.5"BW IN
CUM
SQM

INT ER.
PLASTER
IN SQM

CEILING
PLASTER
IN SQM

EXTL
PLASTER

BACK
FLOOR
FILLING IN TILING IN
CUM
SQM

245.25

Page 88 of 162

RCC
OTHERS
CUM

0.00

9"BRICK
WORKS IN 4.5"BW IN
CUM
SQM

28.78

0.00

INT ER.
PLASTER
IN SQM

0.00

CEILING
PLASTER
IN SQM

0.00

13.39

Page 89 of 162

EXTL
PLASTER

0.00

BACK
FLOOR
FILLING IN TILING IN
CUM
SQM

668.76

0.00

RCC
OTHERS
CUM

9"BRICK
WORKS IN 4.5"BW IN
CUM
SQM

INT ER.
PLASTER
IN SQM

CEILING
PLASTER
IN SQM

9.00

25.96

31.46

Page 90 of 162

EXTL
PLASTER

BACK
FLOOR
FILLING IN TILING IN
CUM
SQM

RCC
OTHERS
CUM

9"BRICK
WORKS IN 4.5"BW IN
CUM
SQM

INT ER.
PLASTER
IN SQM

CEILING
PLASTER
IN SQM

BACK
FLOOR
FILLING IN TILING IN
CUM
SQM

EXTL
PLASTER

3.9

51.28

28.42
83.70665 51.28352

28.42

10.61

Page 91 of 162

RCC
OTHERS
CUM

9"BRICK
WORKS IN 4.5"BW IN
CUM
SQM

INT ER.
PLASTER
IN SQM

CEILING
PLASTER
IN SQM

9.27

24.75

31.27

Page 92 of 162

EXTL
PLASTER

BACK
FLOOR
FILLING IN TILING IN
CUM
SQM

RCC
OTHERS
CUM

9"BRICK
WORKS IN 4.5"BW IN
CUM
SQM

INT ER.
PLASTER
IN SQM

CEILING
PLASTER
IN SQM

39.35

19.59
5.18

3.70

Page 93 of 162

EXTL
PLASTER

BACK
FLOOR
FILLING IN TILING IN
CUM
SQM

RCC
OTHERS
CUM

9"BRICK
WORKS IN 4.5"BW IN
CUM
SQM

INT ER.
PLASTER
IN SQM

CEILING
PLASTER
IN SQM

BACK
FLOOR
FILLING IN TILING IN
CUM
SQM

EXTL
PLASTER

8.41

14.74
5.18
88.010567 64.436224

19.585

Page 94 of 162

RCC
OTHERS
CUM

9"BRICK
WORKS IN 4.5"BW IN
CUM
SQM

INT ER.
PLASTER
IN SQM

CEILING
PLASTER
IN SQM

Page 95 of 162

EXTL
PLASTER

BACK
FLOOR
FILLING IN TILING IN
CUM
SQM

RCC
OTHERS
CUM

9"BRICK
WORKS IN 4.5"BW IN
CUM
SQM

INT ER.
PLASTER
IN SQM

CEILING
PLASTER
IN SQM

EXTL
PLASTER

BACK
FLOOR
FILLING IN TILING IN
CUM
SQM

82.53

Page 96 of 162

RCC
OTHERS
CUM

0.00

9"BRICK
WORKS IN 4.5"BW IN
CUM
SQM

0.00

0.00

INT ER.
PLASTER
IN SQM

0.00

CEILING
PLASTER
IN SQM

0.00

388.59

Page 97 of 162

EXTL
PLASTER

0.00

BACK
FLOOR
FILLING IN TILING IN
CUM
SQM

365.59
448.12

0.00

RCC
OTHERS
CUM

9"BRICK
WORKS IN 4.5"BW IN
CUM
SQM

INT ER.
PLASTER
IN SQM

CEILING
PLASTER
IN SQM

354.01

348.99

421.37

Page 98 of 162

EXTL
PLASTER

BACK
FLOOR
FILLING IN TILING IN
CUM
SQM

RCC
OTHERS
CUM

9"BRICK
WORKS IN 4.5"BW IN
CUM
SQM

INT ER.
PLASTER
IN SQM

CEILING
PLASTER
IN SQM

EXTL
PLASTER

BACK
FLOOR
FILLING IN TILING IN
CUM
SQM

181.56

22.56

268.17

Page 99 of 162

RCC
OTHERS
CUM

9"BRICK
WORKS IN 4.5"BW IN
CUM
SQM

INT ER.
PLASTER
IN SQM

CEILING
PLASTER
IN SQM

Page 100 of 162

EXTL
PLASTER

BACK
FLOOR
FILLING IN TILING IN
CUM
SQM

RCC
OTHERS
CUM

9"BRICK
WORKS IN 4.5"BW IN
CUM
SQM

INT ER.
PLASTER
IN SQM

CEILING
PLASTER
IN SQM

EXTL
PLASTER

BACK
FLOOR
FILLING IN TILING IN
CUM
SQM

1239.96

171.72

144.50

48.01

742.5948 770.35253 1239.9616


742.59

770.35

Page 101 of 162

1239.96

0 472.28655
1116.88

472.29

RCC
OTHERS
CUM

9"BRICK
WORKS IN 4.5"BW IN
CUM
SQM

INT ER.
PLASTER
IN SQM

CEILING
PLASTER
IN SQM

Page 102 of 162

EXTL
PLASTER

BACK
FLOOR
FILLING IN TILING IN
CUM
SQM

WALL
TILING IN
SQM

PAINT
INTERNAL
SQM

EXTER
PAINTING

Page 103 of 162

WALL
TILING IN
SQM

PAINT
INTERNAL
SQM

EXTER
PAINTING

Page 104 of 162

WALL
TILING IN
SQM

PAINT
INTERNAL
SQM

EXTER
PAINTING

Page 105 of 162

WALL
TILING IN
SQM

PAINT
INTERNAL
SQM

EXTER
PAINTING

Page 106 of 162

WALL
TILING IN
SQM

0.00

PAINT
INTERNAL
SQM

0.00

EXTER
PAINTING

0.00

Page 107 of 162

WALL
TILING IN
SQM

PAINT
INTERNAL
SQM

EXTER
PAINTING

Page 108 of 162

WALL
TILING IN
SQM

PAINT
INTERNAL
SQM

EXTER
PAINTING

Page 109 of 162

WALL
TILING IN
SQM

PAINT
INTERNAL
SQM

EXTER
PAINTING

Page 110 of 162

WALL
TILING IN
SQM

PAINT
INTERNAL
SQM

EXTER
PAINTING

Page 111 of 162

WALL
TILING IN
SQM

PAINT
INTERNAL
SQM

EXTER
PAINTING

Page 112 of 162

WALL
TILING IN
SQM

PAINT
INTERNAL
SQM

EXTER
PAINTING

Page 113 of 162

WALL
TILING IN
SQM

PAINT
INTERNAL
SQM

EXTER
PAINTING

Page 114 of 162

WALL
TILING IN
SQM

0.00

PAINT
INTERNAL
SQM

0.00

EXTER
PAINTING

0.00

Page 115 of 162

WALL
TILING IN
SQM

PAINT
INTERNAL
SQM

EXTER
PAINTING

Page 116 of 162

WALL
TILING IN
SQM

PAINT
INTERNAL
SQM

EXTER
PAINTING

Page 117 of 162

WALL
TILING IN
SQM

PAINT
INTERNAL
SQM

EXTER
PAINTING

75.89

256.22
326.18

278.12
421.37

Page 118 of 162

WALL
TILING IN
SQM

PAINT
INTERNAL
SQM

EXTER
PAINTING

1239.96

75.886 1281.8912 1239.9616


75.89

1281.89

1239.96

Page 119 of 162

WALL
TILING IN
SQM

PAINT
INTERNAL
SQM

EXTER
PAINTING

Page 120 of 162

SUB STATION AT KOLATHUR-ABSTRACT


Sl
No

DESCRIPTION OF ACTIVITIES

SCOPE
QTY
UNIT REDUCED RATE

Total BOQ cost for this site =Rs. 11,903,840.27


A SUB STRUCTURE UP TO PLINTH LVL
AREA PREPARATION WORK
1087.25 SQM
EXCAVTION UP TO 2M
506.72 CUM
EXCAVTION BEYOND 2M
45.60 CUM
RIVER SAND BEDDING
41.10 CUM
PCC
39.52 CUM
SHUTTERING
649.76 SQM
REBAR
19.82 MT
RCC
188.44 CUM
BACK BFILLING- STAGE 1&2
552.32 CUM
BACK FILLING BY IMPORTED EARTH
116.43 CUM
BRICK WORKS BELOW PLINTH BEAM
28.78 CUM
ANTI TERMITTE TREATMENT
900.00 SQFT

Initial Work cost (Additional works) (Breakup


attached end of this BOQ )

55.00
132.99
159.59
2305.16
3369.08
487.63
51422.80
5142.28

66.495
650.00
5300.00
5.50
Actual cost at this s
20% of BOQ Cost

Total (B)
Total (A) + (B)
Previus Actual Bil
Balance Amount at th

B SUPER STR FROM GF LVL TO FF LVL


SHUTTERING
REBAR
RCC
BRICK WORKS 9"
BRICK WORK 4.5"

611.83 SQM
15.97 MT
83.71 CUM
51.28 CUM
28.42 SQM

C SUPER STRUCTURE FROM FF TO ROOF


SHUTTERING
REBAR
RCC
BRICK WORKS 9"
BRICK WORK 4.5"

672.77 SQM
14.54 MT
88.01 CUM
64.44 CUM
19.59 SQM

487.63
51422.80
5585.58
5300.00
850.00

D EXTERNAL WORKS AND YARD


EXCAVTION UP TO 2.5M
RIVER SAND BEDDING
PCC
SHUTTERING
REBAR
RCC

211.30 CUM
11.19 CUM
10.11 CUM
459.95 SQM
7.64 MT
80.14 CUM

132.99
2305.16
3369.08
487.63
51422.80
5142.28

487.63
51422.80
5585.58
5300.00
850.00
Actual cost at this s
20% of BOQ Cost
Previus Actual Bil
Balance Amount at th

Sl
No

DESCRIPTION OF ACTIVITIES
BACK BFILLING
IMPORTED EARTH FILLING
PAVING
SUMP/TANK
WEATHERING COURSE & TILING
PLASTERING INT
CEILING PLASTERING
EXTERNAL PLASTERING

SCOPE
QTY
UNIT REDUCED RATE
211.30 CUM
66.50
236.82 CUM
650.00
66.40 SQM
842.27
1.00 NOS
70928.00
227.85 SQM
715.4862
742.59 SQM
372.37
770.35 SQM
372.37
1239.96 SQM
372.37

FINISHING
FLOOR TILING
WALL TILING
PAINTING INTERNAL
EXTERNAL PAINTING
SS HAND RAILS
PVC WATER TANK 1000 LITER
BATERY ROOM WALL ACID RESISTANT PAINT
ELECTRICAL WORKS WITH FITTINGS
PLUMPING WORKS & SANITARY WERES
DRAINAGE LINE UG WORKS
SEPTIC TANK AND SOAKAWAY
RAINWATER LINE & HARVESTING
ENTRANCE GATE 6M +2M WICKED GATE
INSPECTION CHAMBER
GULLY TRAP
DOOR D (CW H C FLUSH DOOR) 1200x 2100
DOOR D1 (CW FLUSH DOOR) 900MM 2100
DOOR D2 (PVC DOOR) 900MMX 2100MM
ROLLING SHUTTER
COLLAPSIBLE GATE(MS)
WINDOWS (ALUMINIUM)
VENTILATOR LOUVER(1180x580) Z
VENTILATOR AT TOILET 800X580
MS GRILL WITH PAINTING 25KG/SQM
NAME BOARD
ACCESS LADDER MS 4M AT ROOF
NOT APPLICABLE ITEMS
EXPANSION JOINT
BOUNDARY WALL
ROAD
STROM WATER DRAIN

472.29 SQM
75.89 SQM
1281.89 SQM
1239.96 SQM
30.46 LM
2.00 NOS

1170.31
1100.00
115.258
115.258
753.61
4433.00

21.53 SQM
1.00 LS
1.00 LS
30.00 m
1.00 LS
1.00 LS
1.00 NO
3.00 NOS
2.00 NOS
2.00 NOS
6.00 NOS
11.34 SQM
11.14 SQM
3.15 SQM
45.93 SQM
9.00 NOS
10.00 NOS
1165.00 SQM
Err:509
NA
1.00 NO

975.26
664950.00
106392.00
797.40
79794.00
31031.00
84227.00
3989.70
531.60
17150.00
14680.00
2910.00
7600.00
7500.00
3800.00
3700.00
2700.00
105.00
0.00
13500.00

120.00 LM
172.00 CUM
1.00 LS
60.00 LM

203.92
5230.90
310310.00
975.26

Sl
No

DESCRIPTION OF ACTIVITIES
TOTAL BOQ COST REQUIRED

SCOPE
QTY
UNIT REDUCED RATE

N AT KOLATHUR-ABSTRACT
AMOUNT

REMARKS

59,798.75 ADDITION
67,388.69 BOQ ITEM 1
7,278.07 BOQ ITEM 2
94,738.02 BOQ ITEM 4
133,154.72 BOQ ITEM 5
316,840.27 BOQ ITEM 8
1,019,335.01 BOQ ITEM 9
969,008.47 BOQ ITEM 6
36,726.84 BOQ ITEM 3
75,681.52 ADDITION
152,554.80 ADDITION
4,950.00 ADDITION
Actual cost at this stage
2,937,455.16
20% of BOQ Cost (A)
2,380,768.05
Total (B)
Total (A) + (B)
Previus Actual Billing
Balance Amount at this stage

186,285.00
2,567,053.05
2,120,000.00
447,053.05

298,347.04 BOQ ITEM 8


821,127.10 BOQ ITEM 9
467,550.21 BOQ ITEM 7
271,802.65 ADDITION
24,157.00 ADDITION
Actual cost at this stage
1,882,984.00
20% of BOQ Cost (A)
2,380,768.05
Previus Actual Billing
2,120,000.00
Balance Amount at this stage
260,768.05
328,063.78 BOQ ITEM 8
747,814.80 BOQ ITEM 9
491,590.06 BOQ ITEM 7
341,511.98 ADDITION
16,647.25 ADDITION
1,925,627.87
28,101.11 BOQ
25,793.27 BOQ
34,067.13 BOQ
224,287.61 BOQ
392,908.04 BOQ
412,117.62 BOQ

ITEM
ITEM
ITEM
ITEM
ITEM
ITEM

1
4
5
8
9
6

AMOUNT

REMARKS

14,050.55 BOQ ITEM 3


153,932.92 ADDITION
55,926.73 BOQ ITEM 10
70,928.00 BOQ ITEM 20
163,023.53 BOQ ITEM 28
276,521.51 BOQ ITEM 12
286,856.17 BOQ ITEM 12
461,724.50 BOQ ITEM 12
2,600,238.68

552,721.67 BOQ ITEM


83,474.60 ADDITION
147,748.22 BOQ ITEM
142,915.49 BOQ ITEM
22,957.98 BOQ ITEM
8,866.00 BOQ ITEM

14
13
13
30
21

20,992.47 BOQ ITEM 29


664,950.00 BOQ ITEM 18
106,392.00 BOQ ITEM 22
23,922.00 BOQ ITEM 25
79,794.00 BOQ ITEM 26
31,031.00 BOQ ITEM 27
84,227.00 BOQ ITEM 16
11,969.10 BOQ ITEM 23
1,063.20 BOQ ITEM 24
34,300.00 ADDITION
88,080.00 ADDITION
32,999.40 ADDITION
84,645.00 ADDITION
23,625.00 ADDITION
174,534.00 ADDITION
33,300.00 ADDITION
27,000.00 ADDITION
122,325.17 ADDITION
N/A ADDITION
13,500.00 ADDITION
2,617,333.30
N/A
N/A
N/A
N/A

BOQ
BOQ
BOQ
BOQ

ITEM
ITEM
ITEM
ITEM

15
11
19
17

AMOUNT
11,903,840.27

REMARKS

HARINI ENTERPRISES

ABSTRACT SHEET JOINTLY ARRIVED BY M/S.DSWE and HARINI ENTERP


PROJECT : 33/11KVA SUB STATION WORK NORTH CHENNAI.
SITE : KOLATHUR
CLIENT : M/S.DRAKE & SCULL WATER & ENERGY PVT LTD

ABSTRACT ARRIVED BY : Mr.Mohammed Nazer(Manager Civil,DSWE) and Mr.Rajaraman(Project


Mr.Anbarasan(Site Engg,HECEC)
ABSTRACT CHECKED & RE-ARRIVED BY : Mr.Sivasubramanian(Engineer Civil,DSWE) and Mr.A

SUB STATION AT KOLATHUR-ABSTRACT


Sl
No

DESCRIPTION OF ACTIVITIES

SCOPE
QTY
UNIT

REDUCED
RATE

Total BOQ cost for this site = Rs. 13,241,368.00


A SUB STRUCTURE UP TO PLINTH LVL
AREA PREPARATION WORK
EXCAVTION UP TO 2M
EXCAVTION BEYOND 2M
RIVER SAND BEDDING
PCC
SHUTTERING
REBAR
RCC
BACK BFILLING- STAGE 1&2
BACK FILLING BY IMPORTED EARTH
BRICK WORKS BELOW PLINTH BEAM
ANTI TERMITE TREATMENT

1087.25 SQM
506.72 CUM
45.60 CUM
41.10 CUM
39.52 CUM
649.76 SQM
19.82 MT
188.44 CUM
552.32 CUM
116.43 CUM
28.78 CUM
900.00 SQFT

55.00
150.00
180.00
2600.00
3800.00
550.00
58000.00
5800.00

75.00
650.00
5300.00
5.50

Initial Work cost (Additional works) (Breakup


attached end of this BOQ )

Actual cost at this stage


Previus Actual Billing
Balance Amount at this st
B SUPER STR FROM GF LVL TO FF LVL
SHUTTERING
REBAR
RCC
BRICK WORKS 9"
BRICK WORK 4.5"

611.83 SQM
550.00
15.97 MT
58000.00
83.71 CUM
6300.00
51.28 CUM
5300.00
28.42 SQM
850.00
Actual cost at this stage
Previus Actual Billing
Balance Amount at this st

C G.F AND TRANSFORMER YARD FINISHING WORKS


EXCAVTION UP TO 2.5M
211.30 CUM
RIVER SAND BEDDING
11.19 CUM
PCC
10.11 CUM
SHUTTERING
459.95 SQM
REBAR
7.64 MT
RCC
80.14 CUM
BACK BFILLING
211.30 CUM

150.00
2600.00
3800.00
550.00
58000.00
5800.00
75.00

Sl
No

DESCRIPTION OF ACTIVITIES
PLASTERING INT
CEILING PLASTERING
EXTERNAL PLASTERING
FLOOR TILING
WALL TILING
PAINTING INTERNAL
BATERY ROOM WALL ACID RESISTANT PAINT
ELECTRICAL WORKS WITH FITTINGS
PLUMPING WORKS & SANITARY WERES
DRAINAGE LINE UG WORKS
SOAKAWAY AND SANETARY WORKS
INSPECTION CHAMBER
GULLY TRAP
DOOR D (CW H C FLUSH DOOR) 1200x 2100
DOOR D1 (CW FLUSH DOOR) 900MM 2100
DOOR D2 (PVC DOOR) 900MMX 2100MM
ROLLING SHUTTER
WINDOWS (ALUMINIUM)
VENTILATOR LOUVER(1180x580) Z
VENTILATOR AT TOILET 800X580
MS GRILL WITH PAINTING 25KG/SQM

SCOPE
QTY
UNIT
445.56 SQM
385.18 SQM
867.97 SQM
212.53 SQM
56.91 SQM
769.13 SQM
21.53 SQM
1 LOT LS
1 LOT LS
30.00 m
1.00 LS
3.00 NOS
2.00 NOS
1.00 NOS
2.00 NOS
5.67 SQM
11.14 SQM
22.97 SQM
9.00 NOS
5.00 NOS
582.50 Kg

REDUCED
RATE
420.00
420.00
420.00
1320.00
1100.00
130.00
1100.00
450000.00
80000.00
900.00
90000.00
4500.00
599.59
17150.00
14680.00
2910.00
7600.00
3800.00
3700.00
2700.00
105.00

Actual cost at this stage


Previus Actual Billing
Completion Advance Rece
Balance Amount at this st
D SUPER STRUCTURE FROM FF TO ROOF
SHUTTERING
REBAR
RCC
BRICK WORKS 9"
BRICK WORK 4.5"

E FIRST FLOOR AND EXTERNAL FINISHING WORKS


PLASTERING INT
CEILING PLASTERING
EXTERNAL PLASTERING
FLOOR TILING
WALL TILING
PAINTING INTERNAL
ELECTRICAL WORKS WITH FITTINGS
PLUMPING WORKS & SANITARY WERES
DOOR D (CW H C FLUSH DOOR) 1200x 2100
DOOR D1 (CW FLUSH DOOR) 900MM 2100

672.77 SQM
550.00
14.54 MT
58000.00
88.01 CUM
6300.00
64.44 CUM
5300.00
19.59 SQM
850.00
Actual cost at this stage
Previus Actual Billing
Balance Amount at this st
297.04 SQM
385.18 SQM
371.99 SQM
259.76 SQM
18.97 SQM
512.76 SQM
1 LOT LS
1 LOT LS
1.00 NOS
4.00 NOS

420.00
420.00
420.00
1320.00
1100.00
130.00
300000.00
40000.00
17150.00
14680.00

Sl
No

DESCRIPTION OF ACTIVITIES
DOOR D2 (PVC DOOR) 900MMX 2100MM
COLLAPSIBLE GATE(MS)
WINDOWS (ALUMINIUM)
VENTILATOR AT TOILET 800X580
MS GRILL WITH PAINTING 25KG/SQM
EXTERNAL PAINTING
SS HAND RAILS
PVC WATER TANK 1000 LITER
RAINWATER LINE & HARVESTING
ENTRANCE GATE 6M +2M WICKED GATE
ACCESS LADDER MS 4M AT ROOF
PAVING
WEATHERING COURSE & TILING

SCOPE
REDUCED
QTY
UNIT
RATE
5.67 SQM
2910.00
3.15 SQM
7500.00
22.97 SQM
3800.00
5.00 NOS
2700.00
582.50 Kg
105.00
1239.96 SQM
130.00
30.46 LM
3280.00
2.00 NOS
5000.00
1.00 LS
35000.00
1.00 NO
95000.00
1.00 NO
13500.00
66.40 SQM
950.00
227.85 SQM
807.00
Actual cost at this stage
Previus Actual Billing
Balance Amount at this st

TOTAL BOQ COST REQUIRED

NOT APPLICABLE ITEMS


BOUNDARY WALL
ROAD
STROM WATER DRAIN
OUT SOURCE EARTH

13,241,368

CUM
1.00 LS
60.00 LM
469.80 CUM

72.00

6000.00
350000.00
975.26
650.00

RINI ENTERPRISES

aman(Project Engg,HECEC),

WE) and Mr.Anbarasan(Site Engg,HECEC)

T
AMOUNT

REMARKS

59,798.75 ADDITION
76,008.00 BOQ ITEM
8,208.97 BOQ ITEM
106,855.42 BOQ ITEM
150,185.79 BOQ ITEM
357,365.53 BOQ ITEM
1,149,712.40 BOQ ITEM
1,092,948.87 BOQ ITEM
41,424.36 BOQ ITEM
75,681.52 ADDITION
152,554.80 ADDITION
4,950.00 ADDITION

1
2
4
5
8
9
6
3

140,050.00 ADDITION
this stage
3,415,744.40
Billing
2,120,000.00
nt at this stage
1,295,744.40

13

45

0.6

33

0.6

IMPORTED

236.82

336,506.93 BOQ ITEM 8


926,152.84 BOQ ITEM 9
527,351.92 BOQ ITEM 7
271,802.65 ADDITION
24,157.00 ADDITION
this stage
2,085,971.33
Billing
2,120,000.00
nt at this stage
-34,028.67
31,695.36 BOQ
29,092.34 BOQ
38,424.46 BOQ
252,974.98 BOQ
443,162.69 BOQ
464,829.26 BOQ
15,847.68 BOQ

ITEM
ITEM
ITEM
ITEM
ITEM
ITEM
ITEM

1
4
5
8
9
6
3

SUMP/TANK

1.00

AMOUNT

REMARKS

187,133.89 BOQ ITEM


161,773.16 BOQ ITEM
364,546.75 BOQ ITEM
280,537.73 BOQ ITEM
62,605.95 ADDITION
99,987.52 BOQ ITEM
23,677.50 BOQ ITEM
450,000.00 BOQ ITEM
80,000.00 BOQ ITEM
27,000.00 BOQ ITEM
90,000.00 BOQ ITEM
13,500.00 BOQ ITEM
1,199.19 BOQ ITEM
17,150.00 ADDITION
29,360.00 ADDITION
16,499.70 ADDITION
84,645.00 ADDITION
87,267.00 ADDITION
33,300.00 ADDITION
13,500.00 ADDITION
61,162.58 ADDITION

this stage
Billing
vance Received
nt at this stage

12
12
12
14
13
29
18
22
25
26
23
24

3,460,872.73
1,000,000.00
977,000.00
1,483,872.73

370,024.57 BOQ ITEM 8


843,463.56 BOQ ITEM 9
554,466.57 BOQ ITEM 7
341,511.98 ADDITION
16,647.25 ADDITION
this stage
2,126,113.94
Billing
0.00
nt at this stage
2,126,113.94
124,755.93 BOQ ITEM
161,773.16 BOQ ITEM
156,234.32 BOQ ITEM
342,879.45 BOQ ITEM
20,868.65 ADDITION
66,658.34 BOQ ITEM
300,000.00 BOQ ITEM
40,000.00 BOQ ITEM
17,150.00 ADDITION
58,720.00 ADDITION

12
12
12
14
13
18
22

HERE
70
45
75
60

267.3341 GF
192.5881 GF
607.5812 GF
95.63803
42.68588
461.4808

178.22 FF
192.588133 FF
260.39 FF
116.89
14.23
307.65

450000
80000

0.00
0.00

50%
2
50%
100%
50%
100%
50%
50%

50%
4.00
50%

1000000 AS BILLING

NIL
50%
NIL
50%
50%

300000
40000

AMOUNT

REMARKS

16,499.70 ADDITION
23,625.00 ADDITION
87,267.00 ADDITION
13,500.00 ADDITION
61,162.58 ADDITION
161,195.01 BOQ ITEM 13
99,921.92 BOQ ITEM 30
10,000.00 BOQ ITEM 21
35,000.00 BOQ ITEM 27
95,000.00 BOQ ITEM 16
13,500.00 ADDITION
63,080.00 BOQ ITEM 10
183,874.95 BOQ ITEM 28
this stage
2,152,666.02
Billing
0.00
nt at this stage
2,152,666.02

,241,368.40

432,000.00 ADDITION
350,000.00 BOQ ITEM 19
58,515.60 BOQ ITEM 17
305,370.00 ADDITION
1,145,885.60

351
118.8
469.8

CUM

650.00

NOS

80000.00

153,932.92 ADDITION
80,000.00 BOQ ITEM 20

457000

HARINI ENTERPRISES

SUMMARY OF QUANTITIES JOINTLY ARRIVED BY M/S.DSWE and HARINI EN


PROJECT : 33/11KVA SUB STATION WORK NORTH CHENNAI.
SITE : KOLATHUR
CLIENT : M/S.DRAKE & SCULL WATER & ENERGY PVT LTD

ARRIVED BY : Mr.Mohammed Nazer(Manager Civil,DSWE) and Mr.Rajaraman(Project Engg,HECE


Engg,HECEC)

CHECKED & RE-ARRIVED BY : Mr.Sivasubramanian(Engineer Civil,DSWE) and Mr.Anbarasan(Sit


Sl
No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36

DESCRIPTION OF ACTIVITIES
AREA PREPARATION WORK
EXCAVTION UP TO 2.0M
EXCAVTION BEYOND 2.M
ANTI TERMITTE TREATMENT
RIVER SAND BEDDING
PCC
SHUTTERING
REBAR
RCC IN GROUND
RCC ABOVE GROUND
BACK FILLING
BACK FILLING BY IMPORTED EARTH
9" BRICK WORKS
BRICK WORK 4.5"
PLASTERING INT
CEILING PLASTERING
EXTERNAL PLASTERING
FLOOR TILING
WALL TILING
PAINTING INTERNAL
EXTERNAL PAINTING
PAVING
WEATHERING COURSE & TILING
SS HAND RAILS
PVC WATER TANK 1000 LITER
BATERY ROOM WALL ACID RESISTANT PAINT
ELECTRICAL WORKS WITH FITTINGS
PLUMPING WORKS & SANITARYWERES
DRAINAGE LINE
SOAKAWAY AND SANETARY WORKS
RAIN WATER LINE & HARVESTING
ENTRANCE GATE 6M +2M WICKED GATE
INSPECTION CHAMBER
GULLY TRAP
DOOR D (CW H C FLUSH DOOR) 1200x 2100
DOOR D1 (CW FLUSH DOOR) 900MM 2100

Page 136 of 162

ACTUAL
UNIT
QTY
1087.25 SQM
718.02 CUM
45.60 CUM
900.00 SQFT
52.29 CUM
49.63 CUM
2394.31 SQM
57.97 MT
268.58 CUM
171.72 CUM
763.63 CUM
116.43 CUM
144.50 CUM
48.01 SQM
742.59 SQM
770.35 SQM
1239.96 SQM
472.29 SQM
75.89 SQM
1281.89 SQM
1239.96 SQM
66.40 SQM
227.85 SQM
30.46 LM
2.00 NOS
21.53 SQM
1.00 LS
1.00 LS
30.00 M
1.00 NOS
1.00 LM
1.00 NO
3.00 NOS
2.00 NOS
2.00 NOS
6.00 NOS

REDUCED
RATE
55.00
150.00
180.00
5.50
2600.00
3800.00
550.00
58000.00
5800.00
6300.00
75.00
650.00
5300.00
850.00
420.00
420.00
420.00
1320.00
1100.00
130.00
130.00
950.00
807.00
3280.00
5000.00
1100.00
750000.00
120000.00
900.00
90000.00
35000.00
95000.00
4500.00
600.00
17150.00
14680.00

Sl
No
37
38
39
40
41
42
43
44
45

ACTUAL
REDUCED
UNIT
QTY
RATE
DOOR D2 (PVC DOOR) 900MMX 2100MM
11.34 SQM
2910.00
ROLLING SHUTTER
11.14 SQM
7600.00
COLLAPSIBLE GATE(MS)
3.15 SQM
7500.00
WINDOWS (ALUMINIUM)
45.93 SQM
3800.00
VENTILATOR LOUVER(1180x580) Z
9.00 NOS
3700.00
VENTILATOR AT TOILET 800X580
10.00 NOS
2700.00
MS GRILL WITH PAINTING 25KG/SQM
1165.00 SQM
105.00
ACCESS LADDER
1.00 NO
13500.00
Initial Work cost (Additional works) (Breakup attached end of this BOQ )
TOTAL BOQ COST REQUIRED
DESCRIPTION OF ACTIVITIES

Initial Work cost (Additional works)


2 Construction Water
3 DG (For 1 month Rent)
4 DG Diesel Consumption (For 1 Month)
5
Main board Wiring arrangement Charge With cable
6 BORE WELL
TOTAL (B)

Page 137 of 162

15 Load
1 No
1 No
L.S L.S
1.00 NO

2000.00
8000.00
32000.00
8000.00
48500.00

Sl
No

DESCRIPTION OF ACTIVITIES
TOTAL (A) + (B)

Page 138 of 162

ACTUAL
QTY

UNIT

REDUCED
RATE

RINI ENTERPRISES

TLY ARRIVED BY M/S.DSWE and HARINI ENTERPRISES

CHENNAI.

VT LTD

l,DSWE) and Mr.Rajaraman(Project Engg,HECEC),Mr.Anbarasan(Site

an(Engineer Civil,DSWE) and Mr.Anbarasan(Site Engg,HECEC)


AMOUNT

REMARKS

59,798.75 ADDITION
107,703.36 BOQ ITEM
8,208.86 BOQ ITEM
4,950.00 ADDITION
135,947.76 BOQ ITEM
188,610.25 BOQ ITEM
1,316,872.00 BOQ ITEM
3,362,491.49 BOQ ITEM
1,557,778.12 BOQ ITEM
1,081,818.49 BOQ ITEM
57,272.04 BOQ ITEM
75,681.52 ADDITION
765,869.43 ADDITION
40,804.25 ADDITION
311,888.14 BOQ ITEM
323,546.33 BOQ ITEM
520,781.07 BOQ ITEM
623,418.25 BOQ ITEM
83,474.60 ADDITION
166,645.86 BOQ ITEM
161,195.01 BOQ ITEM
63,080.00 BOQ ITEM
183,874.95 BOQ ITEM
99,908.80 BOQ ITEM
10,000.00 BOQ ITEM
23,683.00 BOQ ITEM
750,000.00 BOQ ITEM
120,000.00 BOQ ITEM
27,000.00 BOQ ITEM
90,000.00 BOQ ITEM
35,000.00 BOQ ITEM
95,000.00 BOQ ITEM
13,500.00 BOQ ITEM
1,200.00 BOQ ITEM
34,300.00 ADDITION
88,080.00 ADDITION

Page 139 of 162

1
2
4
5
8
9
6
7
3

12
12
12
14
13
13
10
28
30
21
29
18
22
25
26
27
16
23
24

AMOUNT

REMARKS

32,999.40 ADDITION
84,645.00 ADDITION
23,625.00 ADDITION
174,534.00 ADDITION
33,300.00 ADDITION
27,000.00 ADDITION
122,325.17 ADDITION
13,500.00 ADDITION
140,050.00 ADDITION
13,241,360.88

30,000.00
8,000.00
32,000.00
8,000.00
48,500.00
126,500.00

Page 140 of 162

AMOUNT

REMARKS

13,367,860.88

Page 141 of 162

Sl
No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46

DESCRIPTION OF ACTIVITIES
EXCAVTION UP TO 2.0M
EXCAVTION BEYOND 2.M
RIVER SAND BEDDING
PCC
SHUTTERING
REBAR
RCC IN GROUND
RCC ABOVE GROUND
BACK FILLING
BACK FILLING BY IMPORTED EARTH
9" BRICK WORKS
BRICK WORK 4.5"
PLASTERING INT
CEILING PLASTERING
EXTERNAL PLASTERING
FLOOR TILING
WALL TILING
PAINTING INTERNAL
EXTERNAL PAINTING
PAVING
ROAD
SUMP/TANK
BOUNDARY WALL
WEATHERING COURSE & TILING
SS HAND RAILS
PVC WATER TANK 1000 LITER
BATERY ROOM WALL ACID RESISTANT PAINT
ELECTRICAL WORKS WITH FITTINGS
PLUMPING WORKS & SANITARYWERES
DRAINAGE LINE
SEPTIC TANK & SOAK WAY
RAIN WATERE LINE & HARVESTING
ENTRANCE GATE 6M +2M WICKED GATE
INSPECTION CHAMBER
GULLY TRAP
DOOR D (CW H C FLUSH DOOR) 1200x 2100
DOOR D1 (CW FLUSH DOOR) 900MM 2100
DOOR D2 (PVC DOOR) 900MMX 2100MM
ROLLING SHUTTER
COLLAPSIBLE GATE(MS)
WINDOWS (ALUMINIUM)
VENTILATOR LOUVER(1180x580) Z
VENTILATOR AT TOILET 800X580
MS GRILL WITH PAINTING 25KG/SQM
NAME BOARD
ACCESS LADDER

SUB STATION AT KOLATHUR-SUMM


ACTUAL BOQ AS DIFF IN
UNIT
QTY
PER LPO
QTY
718.02
430.00
288.02 CUM
45.60
260.00 -214.40 CUM
52.29
42.60
9.69 CUM
49.63
48.80
0.83 CUM
2394.31 1680.00
714.31 SQM
57.97
43.20
14.77 MT
268.58
267.30
1.28 CUM
171.72
186.00
-14.28 CUM
763.63
820.00
-56.37 CUM
353.25
0.00
353.25 CUM
144.50
144.50 CUM
48.01
0.00
48.01 SQM
742.59
SQM
770.35 1860.00 892.91 SQM
1239.96
SQM
472.29
880.00 -407.71 SQM
75.89
0.00
75.89 SQM
1281.89
SQM
3010.00 661.85
1239.96
SQM
66.40
186.00 -119.60 SQM
126.00
126.00 N/A
1.00
1.00
0.00 LS
0.00
172.00 -172.00 N/A
227.85
250.00
-22.15 SQM
30.46
30.00
0.46 LM
2.00
2.00
0.00 NOS
21.53
60.00
-38.47 SQM
1.00
1.00
0.00 LS
1.00
1.00
0.00 LS
30.00
30.00
0.00 M
1.00
1.00
0.00 NOS
1.00
1.00
0.00 LM
1.00
1.00
0.00 NO
3.00
3.00
0.00 NOS
2.00
2.00
0.00 NOS
2.00
0.00
2.00 NOS
6.00
0.00
6.00 NOS
11.34
0.00
11.34 SQM
11.14
0.00
11.14 SQM
3.15
0.00
3.15 SQM
45.93
0.00
45.93 SQM
9.00
0.00
9.00 NOS
10.00
0.00
10.00 NOS
987.43
0.00
987.43 SQM
1.00
1.00 LOT
1.00
0.00
1.00 NO

Sl
No

DESCRIPTION OF ACTIVITIES

ACTUAL BOQ AS DIFF IN


QTY
PER LPO
QTY

UNIT

TOTAL BOQ COST REQUIRED (A)


Initial Work cost (Additional works)
Area preparation work with (Cutting & Removing
1 Trees)
2 Construction Water
3 DG (For 1 month Rent)
4
DG Diesel Consumption (For 1 Month)
5
Main board Wiring arrangement Charge With cable
6 BORE WELL
TOTAL (B)
TOTAL (A) + (B)

1087
15
1

SQM
Load
No

No

L.S
1.00

L.S
NO

AT KOLATHUR-SUMMARY
REDUCED
RATE
132.99
159.59
2305.16
3369.08
487.63
51422.80
5142.28
5585.58
66.50
650.00
5300.00
850.00
372.37
372.37
372.37
1170.31
1100.00
115.26
115.26
842.27
0.00
70928.00
5230.94
715.49
753.61
4433.00
975.26
664950.00
106392.00
797.40
79794.00
31031.00
84227.00
3989.70
531.60
17150.00
14680.00
2910.00
7600.00
7500.00
3800.00
3700.00
2700.00
105.00
0.00
13500.00

AMOUNT
38304.10
-34214.90
22331.47
2810.74
348320.31
759719.99
6594.64
-79777.61
-3748.51
229614.44
765869.43
40804.25
332494.29
-477151.94
83474.60
76283.83
-100735.49
0.00
0.00
-899721.68
-15848.02
0.00
-37518.25
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00

0.00
0.00

346.66
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
34300.00
88080.00
32999.40
84645.00
23625.00
174534.00
33300.00
27000.00
103680.65
0.00 N/A
13500.00

95,489.80
7,277.98
120,531.28
167,221.84
1,167,538.71
2,981,184.95
1,381,126.08
959,140.27
50,777.39
229,614.44
765,869.43
40,804.25
276,521.51
286,857.71
461,726.98
552,722.62
83,474.60
147,748.22
142,915.49
55,926.73
70,928.00
163,023.53
22,954.96
8,866.00
20,997.35
664,950.00
106,392.00
23,922.00
79,794.00
31,031.00
84,227.00
11,969.10
1,063.20
34,300.00
88,080.00
32,999.40
84,645.00
23,625.00
174,534.00
33,300.00
27,000.00
103,680.65
13,500.00

REMARKS

REDUCED
RATE

AMOUNT
11,880,252.49

55.00
2000.00
8000.00

59,785.00
30,000.00
8,000.00

32000.00

32,000.00

8000.00
48500.00

8,000.00
48,500.00
186,285.00
12,066,537.49

REMARKS

ANNEXURE II
BOQ & SCHEDULE OF PRICES
33 / 11 KV SUB-STATION WORKS AT NORTH CHENNAI, INDIA

SR. NO.

1
2

DESCRIPTION OF ITEM

Excavation in all soils 0.00mtr to2.00 mtr, including disposal of earth upto 10 mtr
from the point.
Excavation in all soils 2.01mtr to2.50 mtr, including disposal of earth upto 10 mtr
from the point.

Back filling with excavated earth including consolidation asper specfication.

Back filling with bought out earth including consolidation asper specfication.(River
sand)

PCC M10 (1:3:6) asper specification

RCC M25 for strip foundation(combined footing)Grade beam,grade slab,cable


trench wall & grade slab GF incl Trf plinth and fire wall.

RCC M25 for lintel,sunshade,beam and slab

P&F form work for all RCC items

P&F of reinforcement steel TMT for all RCC items

10

P&L paved area -Access

11

P&L BB masonary of 300mm thick compound wall

12

P&A plastering I&O.

13

P&A painting I&O I OBD O cement paint

14

Flooring

15

Expansion joint

16

Entrance gate - Double leaf with RCC Pillar

17

Storm water drain arrangements

18

Internal Electrical works

19

Internal Road

20

Clear water sump

146 of 162

WORLD CREST TOWER

PO REF: SC0227 DATED 03.05.14

21

OHT sintex -Toilet and lab requirements

22

Plumbing and sanitary - building toilet

23

inspection chamber

24

Gully Trap

25

UG Sewer line Bldg

26

Soak Pit and Spectic tank

27

Rain water harvesting

28

Roof Water proofing with tiles

29

Acid proof tile work - Battery room area

30

SS Handrail with Siutable vertical posts.

SUB-CONTRACT PACKAGE VALUE (INCLUDING TAXES / DUTIES / INSURANCES / FREIGHT ETC.) EXCEPT
PAID EXTRA @ 4.944% ON THE CONTRACT PACKAGE VALUE

NOTE:
QTY. INDICATED ABOVE ARE ESTIMATED QTY. ONLY. VENDOR SHALL CARRY OUT
THE ACTUAL MEASUREMNT AT SITE BEFORE INSTALLATION WORKS. THIS
CONTRACT WILL BE OPERATED ON A LUMPSUM AND PAYMENT SHALL BE MADE
AS PER INVOICE CERTIFICATION AT SITE.
THE FORMAT OF THE BILL OF QUANTITIES / SCHEDULE OF PRICE SHOULD NOT
BE MODIFIED / ALTERED BY ADDITION OR DELETION OF ROW(S) / COLUMN(S)
ETC.
CONTRACTOR SHALL FURNISH METHODOLOGY OF ALL PROCESSES PROPOSED
FOR THE PROJECT FOR ENGINEER'S APPROVAL BEFORE INSTALLATION.

THE RATES QUOTED SHALL ALSO INCLUDE SUBMISSION & APPROVAL OF SHOP
DRAWINGS, AS-BUILT DRAWINGS (IF ANY).

CONTRACTOR TO LIST DOWN UNIT RATES FOR ALL RELEVANT ACCESSORIES,


DEVICES OR ANY OTHER EQUIPMENTS NOT MENTIONED ABOVE HOWEVER
NECESSARY TO COMMISSION THE ABOVE MENTIONED SYSTEM. THE CONTRACT
PRICE WILL NOT BE SUBJECTED TO ANY ESCALATION DUE TO THE SAME.
R.O. - Rate Only

147 of 162

WORLD CREST TOWER

PO REF: SC0227 DATED 03.05.14

CIVIL WORKS

HARINI ENTERPRISES
SUPPLY & INSTALLATION
UNIT

QTY.

RATE in
Rs.

AMOUNT in
Rs.

CUM

1,720.00

132.99

228,742.80

CUM

1,040.00

159.588

165,971.52

CUM

3,280.00

66.495

218,103.60

CUM

170.40

2305.16

392,799.26

CUM

195.20

3369.08

657,644.42

CUM

1,069.20

5142.28

5,498,125.78

CUM

744.00

5585.58

4,155,671.52

SQM

6,720.00

487.63

3,276,873.60

MT

172.80

51422.8

8,885,859.84

SQM

744.00

842.27

CUM

688.00

5230.94

3,598,886.72

SQM

7,440.00

372.372

2,770,447.68

SQM

12,040.00

115.258

1,387,706.32

SQM

3,520.00

1170.312

4,119,498.24

RMT

480.00

203.918

97,880.64

NOS

4.00

84227

336,908.00

RMT

240.00

975.26

234,062.40

LUMPSUM

4.00

664950

2,659,800.00

LUMPSUM

4.00

310310

1,241,240.00

LUMPSUM

4.00

70928

148 of 162

626,648.88

283,712.00

WORLD CREST TOWER

PO REF: SC0227 DATED 03.05.14

LUMPSUM

4.00

8866

35,464.00

LUMPSUM

4.00

106392

425,568.00

NOS

12.00

3989.7

47,876.40

NOS

8.00

531.6

4,252.80

RMT

120.00

797.4

95,688.00

LUMPSUM

4.00

79794

319,176.00

LUMPSUM

4.00

31031

124,124.00

715.4862

715,486.20

SQM

1,000.00

SQM

240.00

975.26

234,062.40

RMT

120.00

753.61

90,433.20

EIGHT ETC.) EXCEPT SERVICE TAX WHICH SHALL BE


ACKAGE VALUE

149 of 162

42,928,714

WORLD CREST TOWER

PO REF: SC0227 DATED 03.05.14

HARINI ENTERPRISES

SUMMARY OF QUANTITIES JOINTLY ARRIVED BY M/S.DSWE and HARINI EN


PROJECT : 33/11KVA SUB STATION WORK NORTH CHENNAI.
SITE : KOLATHUR
CLIENT : M/S.DRAKE & SCULL WATER & ENERGY PVT LTD
ARRIVED BY : Mr.Mohammed Nazer(Manager Civil,DSWE) and Mr.Rajaraman(Project Engg),Mr.An
CHECKED & RE-ARRIVED BY : Mr.Sivasubramanian(Engineer Civil,DSWE) and Mr.Anbarasan(Sit
Sl
ACTUAL
REDUCED
DESCRIPTION OF ACTIVITIES
UNIT
No
QTY
RATE
1 AREA PREPARATION WORK
1087.25 SQM
55.00
2 EXCAVTION UP TO 2.0M
718.02 CUM
132.99
3 EXCAVTION BEYOND 2.M
45.60 CUM
159.59
4 ANTI TERMITTE TREATMENT
900.00 SQFT
5.50
5 RIVER SAND BEDDING
52.29 CUM
2305.16
6 PCC
49.63 CUM
3369.08
7 SHUTTERING
2394.31 SQM
487.63
8 REBAR
57.97 MT
51422.80
9 RCC IN GROUND
268.58 CUM
5142.28
10 RCC ABOVE GROUND
171.72 CUM
5585.58
11 BACK FILLING
763.63 CUM
66.50
12 BACK FILLING BY IMPORTED EARTH
116.43 CUM
650.00
13 9" BRICK WORKS
144.50 CUM
5300.00
14 BRICK WORK 4.5"
48.01 SQM
850.00
15 PLASTERING INT
742.59 SQM
372.37
16 CEILING PLASTERING
770.35 SQM
372.37
17 EXTERNAL PLASTERING
1239.96 SQM
372.37
18 FLOOR TILING
472.29 SQM
1170.31
19 WALL TILING
75.89 SQM
1100.00
20 PAINTING INTERNAL
115.26
1281.89 SQM
21 EXTERNAL PAINTING
115.26
1239.96 SQM
22 PAVING
66.40 SQM
842.27
23 WEATHERING COURSE & TILING
227.85 SQM
715.49
24 SS HAND RAILS
30.46 LM
753.61
2.00 NOS
4433.00
25 PVC WATER TANK 1000 LITER
26 BATERY ROOM WALL ACID RESISTANT PAINT
21.53 SQM
975.26
27 ELECTRICAL WORKS WITH FITTINGS
1.00 LS
664950.00
28 PLUMPING WORKS & SANITARYWERES
1.00 LS
106392.00
29 DRAINAGE LINE
30.00 M
797.94
30 SOAKAWAY AND SANETARY WORKS
1.00 NOS
79794.00
31 RAIN WATER LINE & HARVESTING
1.00 LM
31031.00
32 ENTRANCE GATE 6M +2M WICKED GATE
1.00 NO
84227.00
33 INSPECTION CHAMBER
3.00 NOS
3989.70
34 GULLY TRAP
2.00 NOS
531.96
35 DOOR D (CW H C FLUSH DOOR) 1200x 2100
2.00 NOS
17150.00
36 DOOR D1 (CW FLUSH DOOR) 900MM 2100
6.00 NOS
14680.00
37 DOOR D2 (PVC DOOR) 900MMX 2100MM
11.34 SQM
2910.00
38 ROLLING SHUTTER
11.14 SQM
7600.00
39 COLLAPSIBLE GATE(MS)
3.15 SQM
7500.00
40 WINDOWS (ALUMINIUM)
45.93 SQM
3800.00
41 VENTILATOR LOUVER(1180x580) Z
9.00 NOS
3700.00
42 VENTILATOR AT TOILET 800X580
10.00 NOS
2700.00
43 MS GRILL WITH PAINTING 25KG/SQM
1165.00 SQM
105.00
44 ACCESS LADDER
1.00 NO
13500.00
45 Initial Work cost (Additional works) (Breakup attached end of this BOQ )
TOTAL BOQ COST REQUIRED (A)

HARINI ENTERPRISES

SUMMARY OF INITIAL STAGE WORKS JOINTLY ARRIVED BY M/S.DSWE and HARIN


PROJECT : 33/11KVA SUB STATION WORK NORTH CHENNAI.
SITE : KOLATHUR
CLIENT : M/S.DRAKE & SCULL WATER & ENERGY PVT LTD
ARRIVED BY : Mr.Mohammed Nazer(Manager Civil,DSWE) and Mr.Rajaraman(Project Engg,HECE
Engg,HECEC)
CHECKED & RE-ARRIVED BY : Mr.Sivasubramanian(Engineer Civil,DSWE) and Mr.Anbarasan(Sit
Sl
ACTUAL
REDUCED
DESCRIPTION OF ACTIVITIES
UNIT
No
QTY
RATE
Initial Work cost (Additional works)
1 Construction Water
15 Load
2000.00
2 DG (For 1 month Rent)
1 No
8000.00
3 DG Diesel Consumption (For 1 Month)
1 No
32000.00
4
Main board Wiring arrangement Charge With cable
L.S L.S
20000.00
5 BORE WELL
1.00 NO
50050.00
TOTAL

RINI ENTERPRISES

TLY ARRIVED BY M/S.DSWE and HARINI ENTERPRISES


CHENNAI.

VT LTD
l,DSWE) and Mr.Rajaraman(Project Engg),Mr.Anbarasan(Site Engg)
an(Engineer Civil,DSWE) and Mr.Anbarasan(Site Engg)
AMOUNT

REMARKS

59,798.75 ADDITION
95,489.80 BOQ ITEM
7,277.98 BOQ ITEM
4,950.00 ADDITION
120,531.28 BOQ ITEM
167,221.84 BOQ ITEM
1,167,538.71 BOQ ITEM
2,981,184.95 BOQ ITEM
1,381,126.08 BOQ ITEM
959,140.27 BOQ ITEM
50,777.39 BOQ ITEM
75,681.52 ADDITION
765,869.43 ADDITION
40,804.25 ADDITION
276,520.03 BOQ ITEM
286,856.17 BOQ ITEM
461,724.50 BOQ ITEM
552,722.62 BOQ ITEM
83,474.60 ADDITION
147,748.22 BOQ ITEM
142,915.49 BOQ ITEM
55,926.73 BOQ ITEM
163,023.53 BOQ ITEM
22,954.96 BOQ ITEM
8,866.00 BOQ ITEM
20,997.35 BOQ ITEM
664,950.00 BOQ ITEM
106,392.00 BOQ ITEM
23,938.20 BOQ ITEM
79,794.00 BOQ ITEM
31,031.00 BOQ ITEM
84,227.00 BOQ ITEM
11,969.10 BOQ ITEM
1,063.92 BOQ ITEM
34,300.00 ADDITION
88,080.00 ADDITION
32,999.40 ADDITION
84,645.00 ADDITION
23,625.00 ADDITION
174,534.00 ADDITION
33,300.00 ADDITION
27,000.00 ADDITION
122,325.17 ADDITION
13,500.00 ADDITION
140,050.00 ADDITION
11,878,846.25

1
2
4
5
8
9
6
7
3

12
12
12
14
13
13
10
28
30
21
29
18
22
25
26
27
16
23
24

RINI ENTERPRISES

JOINTLY ARRIVED BY M/S.DSWE and HARINI ENTERPRISES


CHENNAI.

VT LTD
l,DSWE) and Mr.Rajaraman(Project Engg,HECEC), Mr.Anbarasan(Site

an(Engineer Civil,DSWE) and Mr.Anbarasan(Site Engg,HECEC)


AMOUNT
30,000.00
8,000.00
32,000.00
20000.00
50,050.00
140,050.00

REMARKS

HARINI ENTERPRISES

ABSTRACT SHEET JOINTLY ARRIVED BY M/S.DSWE and HARINI ENTERP


PROJECT : 33/11KVA SUB STATION WORK NORTH CHENNAI.
SITE : KOLATHUR
CLIENT : M/S.DRAKE & SCULL WATER & ENERGY PVT LTD

ABSTRACT ARRIVED BY : Mr.Mohammed Nazer(Manager Civil,DSWE) and Mr.Rajaraman(Project


Engg)
ABSTRACT CHECKED & RE-ARRIVED BY : Mr.Sivasubramanian(Engineer Civil,DSWE) and Mr.A

SUB STATION AT KOLATHUR-ABSTRACT


Sl
No

DESCRIPTION OF ACTIVITIES

SCOPE
QTY
UNIT

REDUCED
RATE

Total BOQ cost for this site = Rs. 12,197,091.00


A SUB STRUCTURE UP TO PLINTH LVL
AREA PREPARATION WORK
EXCAVTION UP TO 2M
EXCAVTION BEYOND 2M
RIVER SAND BEDDING
PCC
SHUTTERING
REBAR
RCC
BACK BFILLING- STAGE 1&2
BACK FILLING BY IMPORTED EARTH
BRICK WORKS BELOW PLINTH BEAM
ANTI TERMITE TREATMENT

1087.25 SQM
506.72 CUM
45.60 CUM
41.10 CUM
39.52 CUM
649.76 SQM
19.82 MT
188.44 CUM
552.32 CUM
116.43 CUM
28.78 CUM
900.00 SQFT

55.00
132.99
159.59
2305.16
3369.08
487.63
51422.80
5800.00

66.50
650.00
5300.00
5.50

Initial Work cost (Additional works) (Breakup


attached end of this BOQ )

Actual cost at this stage


Previus Actual Billing
Balance Amount at this st
B SUPER STR FROM GF LVL TO FF LVL
SHUTTERING
REBAR
RCC
BRICK WORKS 9"
BRICK WORK 4.5"

611.83 SQM
487.63
15.97 MT
51422.80
83.71 CUM
5585.58
51.28 CUM
5300.00
28.42 SQM
850.00
Actual cost at this stage
Previus Actual Billing
Balance Amount at this st

C G.F AND TRANSFORMER YARD FINISHING WORKS


EXCAVTION UP TO 2.5M
211.30 CUM
RIVER SAND BEDDING
11.19 CUM
PCC
10.11 CUM
SHUTTERING
459.95 SQM
REBAR
7.64 MT
RCC
80.14 CUM
BACK BFILLING
211.30 CUM

132.99
2305.16
3369.08
487.63
51422.80
5142.28
66.50

Sl
No

DESCRIPTION OF ACTIVITIES
PLASTERING INT
CEILING PLASTERING
EXTERNAL PLASTERING
FLOOR TILING
WALL TILING
PAINTING INTERNAL
BATERY ROOM WALL ACID RESISTANT PAINT
ELECTRICAL WORKS WITH FITTINGS
PLUMPING WORKS & SANITARY WERES
DRAINAGE LINE UG WORKS
SOAKAWAY AND SANETARY WORKS
INSPECTION CHAMBER
GULLY TRAP
DOOR D (CW H C FLUSH DOOR) 1200x 2100
DOOR D1 (CW FLUSH DOOR) 900MM 2100
DOOR D2 (PVC DOOR) 900MMX 2100MM
ROLLING SHUTTER
WINDOWS (ALUMINIUM)
VENTILATOR LOUVER(1180x580) Z
VENTILATOR AT TOILET 800X580
MS GRILL WITH PAINTING 25KG/SQM

SCOPE
QTY
UNIT
445.56 SQM
385.18 SQM
867.97 SQM
212.53 SQM
56.91 SQM
769.13 SQM
21.53 SQM
1 LOT LS
1 LOT LS
30.00 m
1.00 LS
3.00 NOS
2.00 NOS
1.00 NOS
2.00 NOS
5.67 SQM
11.14 SQM
22.97 SQM
9.00 NOS
5.00 NOS
582.50 Kg

REDUCED
RATE
372.37
372.37
372.37
1170.31
1100.00
115.26
975.26
450000.00
80000.00
797.94
79794.00
3989.70
531.60
17150.00
14680.00
2910.00
7600.00
3800.00
3700.00
2700.00
105.00

Actual cost at this stage


Previus Actual Billing
Completion Advance Rece
Balance Amount at this st
D SUPER STRUCTURE FROM FF TO ROOF
SHUTTERING
REBAR
RCC
BRICK WORKS 9"
BRICK WORK 4.5"

E FIRST FLOOR AND EXTERNAL FINISHING WORKS


PLASTERING INT
CEILING PLASTERING
EXTERNAL PLASTERING
FLOOR TILING
WALL TILING
PAINTING INTERNAL
ELECTRICAL WORKS WITH FITTINGS
PLUMPING WORKS & SANITARY WERES
DOOR D (CW H C FLUSH DOOR) 1200x 2100
DOOR D1 (CW FLUSH DOOR) 900MM 2100

672.77 SQM
487.63
14.54 MT
51422.80
88.01 CUM
5585.58
64.44 CUM
5300.00
19.59 SQM
850.00
Actual cost at this stage
Previus Actual Billing
Balance Amount at this st
297.04 SQM
385.18 SQM
371.99 SQM
259.76 SQM
18.97 SQM
512.76 SQM
1 LOT LS
1 LOT LS
1.00 NOS
4.00 NOS

372.37
372.37
372.37
1170.31
1100.00
115.26
300000.00
40000.00
17150.00
14680.00

Sl
No

DESCRIPTION OF ACTIVITIES
DOOR D2 (PVC DOOR) 900MMX 2100MM
COLLAPSIBLE GATE(MS)
WINDOWS (ALUMINIUM)
VENTILATOR AT TOILET 800X580
MS GRILL WITH PAINTING 25KG/SQM
EXTERNAL PAINTING
SS HAND RAILS
PVC WATER TANK 1000 LITER
RAINWATER LINE & HARVESTING
ENTRANCE GATE 6M +2M WICKED GATE
ACCESS LADDER MS 4M AT ROOF
PAVING
WEATHERING COURSE & TILING

SCOPE
REDUCED
QTY
UNIT
RATE
5.67 SQM
2910.00
3.15 SQM
7500.00
22.97 SQM
3800.00
5.00 NOS
2700.00
582.50 Kg
105.00
1239.96 SQM
115.26
30.46 LM
753.61
2.00 NOS
4433.00
1.00 LS
31031.00
1.00 NO
84227.00
1.00 NO
13500.00
66.40 SQM
842.27
227.85 SQM
715.49
Actual cost at this stage
Previus Actual Billing
Balance Amount at this st

TOTAL BOQ COST REQUIRED

NOT APPLICABLE ITEMS


BOUNDARY WALL
ROAD
STROM WATER DRAIN
OUT SOURCE EARTH

12,197,091

CUM
1.00 LS
60.00 LM
469.80 CUM

72.00

6000.00
350000.00
975.26
650.00

RINI ENTERPRISES

aman(Project Engg),Mr.Anbarasan(Site

WE) and Mr.Anbarasan(Site Engg)

T
AMOUNT

REMARKS

59,798.75 ADDITION
67,388.69 BOQ ITEM
7,278.07 BOQ ITEM
94,738.02 BOQ ITEM
133,154.72 BOQ ITEM
316,840.27 BOQ ITEM
1,019,335.01 BOQ ITEM
1,092,948.87 BOQ ITEM
36,726.84 BOQ ITEM
75,681.52 ADDITION
152,554.80 ADDITION
4,950.00 ADDITION

1
2
4
5
8
9
6
3

140,050.00 ADDITION
this stage
3,201,445.56
Billing
2,120,000.00
nt at this stage
1,081,445.56

13

45

0.6

33

0.6

IMPORTED

236.82

298,347.04 BOQ ITEM 8


821,127.10 BOQ ITEM 9
467,550.21 BOQ ITEM 7
271,802.65 ADDITION
24,157.00 ADDITION
this stage
1,882,984.00
Billing
2,120,000.00
nt at this stage
-237,016.00
28,101.11 BOQ
25,793.27 BOQ
34,067.13 BOQ
224,287.61 BOQ
392,908.04 BOQ
412,117.62 BOQ
14,050.55 BOQ

ITEM
ITEM
ITEM
ITEM
ITEM
ITEM
ITEM

1
4
5
8
9
6
3

SUMP/TANK

1.00

AMOUNT

REMARKS

165,912.91 BOQ ITEM


143,428.09 BOQ ITEM
323,207.15 BOQ ITEM
248,724.75 BOQ ITEM
62,605.95 ADDITION
88,648.93 BOQ ITEM
20,992.47 BOQ ITEM
450,000.00 BOQ ITEM
80,000.00 BOQ ITEM
23,938.20 BOQ ITEM
79,794.00 BOQ ITEM
11,969.10 BOQ ITEM
1,063.20 BOQ ITEM
17,150.00 ADDITION
29,360.00 ADDITION
16,499.70 ADDITION
84,645.00 ADDITION
87,267.00 ADDITION
33,300.00 ADDITION
13,500.00 ADDITION
61,162.58 ADDITION

this stage
Billing
vance Received
nt at this stage

12
12
12
14
13
29
18
22
25
26
23
24

3,174,494.35
1,000,000.00
977,000.00
1,197,494.35

328,063.78 BOQ ITEM 8


843,463.56 BOQ ITEM 9
491,590.06 BOQ ITEM 7
341,511.98 ADDITION
16,647.25 ADDITION
this stage
2,021,276.64
Billing
0.00
nt at this stage
2,021,276.64
110,608.60 BOQ ITEM
143,428.09 BOQ ITEM
138,517.35 BOQ ITEM
303,996.92 BOQ ITEM
20,868.65 ADDITION
59,099.29 BOQ ITEM
300,000.00 BOQ ITEM
40,000.00 BOQ ITEM
17,150.00 ADDITION
58,720.00 ADDITION

12
12
12
14
13
18
22

HERE
70
45
75
60

267.3341 GF
192.5881 GF
607.5812 GF
95.63803
42.68588
461.4808

178.22 FF
192.588133 FF
260.39 FF
116.89
14.23
307.65

450000
80000

0.00
0.00

50%
2
50%
100%
50%
100%
50%
50%

50%
4.00
50%

1000000 AS BILLING

NIL
50%
NIL
50%
50%

300000
40000

AMOUNT

REMARKS

16,499.70 ADDITION
23,625.00 ADDITION
87,267.00 ADDITION
13,500.00 ADDITION
61,162.58 ADDITION
142,915.49 BOQ ITEM 13
22,957.98 BOQ ITEM 30
8,866.00 BOQ ITEM 21
31,031.00 BOQ ITEM 27
84,227.00 BOQ ITEM 16
13,500.00 ADDITION
55,926.73 BOQ ITEM 10
163,023.53 BOQ ITEM 28
this stage
1,916,890.91
Billing
0.00
nt at this stage
1,916,890.91

,197,091.47

432,000.00 ADDITION
350,000.00 BOQ ITEM 19
58,515.60 BOQ ITEM 17
305,370.00 ADDITION
1,145,885.60

351
118.8
469.8

CUM

650.00

NOS

80000.00

153,932.92 ADDITION
80,000.00 BOQ ITEM 20

457000

Anda mungkin juga menyukai