Project Management
Part 5
Project Scheduling
or
Activity
m
n
r
s
Predecessor
_
_
m, n
n
Install rough
electrical & plumbing
Pour
basement
floor
Install
drains
10
9
Erect
frame & roof
Excavate
& pour
footings
Pour
foundation
Install
finished
plumbing
Install
drywall
Install
cooling &
heating
11
Lay
flooring
12
Install
kitchen
equipment
Paint
4
Lay
brickwork
Finish
carpeting
16
Finish
electrical
work
Finish
roof
Lay
storm
drains
13
14
Finish
floors
Install
roof
drainage
(AOA network)
15
Part 5 - Project Scheduling
Finish
grading
18
Pour
walks;
Landscape
17
8
Dur.
c,d
e
f
e,g
h,i
1
4
5
6
1
10
c
a
g
j
k
11
12
13
Activity on Arrow
(Initial Network)
14
Activity on Arrow
(Final Network)
b
a
e
c
g
j
15
Activity on Node
16
Critical Path
path any route along the network from start to
finish
Critical Path path with the longest total duration
This is the shortest time in which the project can
be completed.
Critical Activity an activity on the critical path
*If a critical activity is delayed, the entire project
will be delayed. Close attention must be given
to critical activities to prevent project delay.
There may be more than one critical path.
Part 5 - Project Scheduling
17
Critical Path
Brute force approach to finding critical path:
1. identify all possible paths from start to finish
2. sum up durations for each path
3. largest total indicates critical path
(This approach is inefficient, but is instructive)
18
d=4
2
6
4
i=
4
f=
b=2
g=9
j=
h=9
19
Slack Times
ESTEarliest Start Time
Largest EFT of all predecessors
EFTEarliest Finish Time
EST + duration for this task
LFTLatest Finish Time
Smallest LST of following tasks
LSTLatest Start Time
LFT duration for this task
SlackLFT EFT or LST EST
Part 5 - Project Scheduling
20
EFT
Task = duration
slack = xxxx
LST
LFT
21
22
c=3
slack=
EST
Task=dur
slack=xxx
LST
g=1
slack=
a=4
slack=
EFT
LFT
j=6
slack=
d=2
slack=
Finish
Start
e=6
slack=
h=4
slack=
b=3
slack=
k=1
slack=
f=4
slack=
i=5
slack=
Part 5 - Project Scheduling
23
Gantt Charts
The main purpose of a Gantt chart is to display
the schedule of activities
They are easy to understand
They are flexible in that you can also show other
information on the chart, such as resources
required, who is responsible, critical activities,
percent complete, etc.
All project management software packages will
create Gantt charts
Part 5 - Project Scheduling
24
Gantt Chart
Activity
a
b
c
d
e
f
g
h
i
Time (weeks)
Part 5 - Project Scheduling
25
26
27
28
29
30
Start-to-Start
Linkage (SS)
Finish-to-Finish
Linkage (FF)
Start-to-Finish
Linkage (SF)
Activity 1
Activity 1
Activity 2
Activity 1
Activity 2
Activity 1
Activity 2
31
32
Ineffective Scheduling
Notice:
As of tomorrow, employees will only be
able to access the building using individual
security cards. Pictures will be taken next
Wednesday, and employees will receive
their cards in two weeks.
33