001-16
SUBJECT
DATE
This Bid Bulletin No. 001-16 is issued to give notice to the prospective bidder the Change of Approved Budget for the
Contract (ABC), Contract Duration and Schedule of Procurement Activities relative to the Procurement of Civil Works under
PAMANA Projects Cluster I, II, III, IV & V as well as the proper description of the project. The Original Approved Budget for
the Contract (ABC), Contract Duration and the Original Schedule of Procurement Activities was published in the Philippine Daily
Inquirer and PhilGEPS on January 28, 2016.
The Proper Description of the projects with the Approved Budget for the Contract (ABC), Contract Duration and
Schedule of Procurement Activities as published in the Philippine Daily Inquirer and PhilGEPS are as follows:
Description
CLUSTER I:(Sulu I)
Ware House (21 Units) and Potable Water System (2 Units)
ABC
Php 16,781,000.00
Contract Duration
100 Cal. Days
Php 3,880,000.00
77 Cal. Days
Php 6,887,000.00
96 Cal. Days
Php 970,000.00
73 Cal. Days
Php 5,238,000.00
87 Cal. Days
The amended Approved Budget for the Contract (ABC), Contract Duration and Schedule of Procurement Activities
which shall form an integral part of the Bidding Documents for the Contract, viz:
Description
CLUSTER I:(Sulu I)
Ware House (20 Units) and Potable Water System (2 Units)
ABC
Php 16,004,997.20
Contract Duration
180 Cal. Days
Php 4,655,999.60
80 Cal. Days
Php 6,886,991.15
Php 969,992.99
P5,237,974.64
(SGD)BARLIE S. NAHUDAN
Director II, Bureau of Operations
BAC Chairman
Noted :
(SGD)DON MUSTAPHA A. LOONG
OIC-Regional Secretary