GP 44-25
Applicability
Group
Date
GP 44-25
BP GROUP
GP 44-25
Guidance on Practice for Depressurisation
Foreword
This is the first issue of Engineering Technical Practice (ETP) BP GP 44-25. This Guidance on
Practice (GP) is based on parts of heritage documents from the merged BP companies as follows:
BP
RP 44-4
CP 37
Guide to Depressurisation.
BP Engineering Code of Practice CP 37 Guide to Depressurisation.
Copyright 2007, BP Group. All rights reserved. The information contained in this
document is subject to the terms and conditions of the agreement or contract under which
the document was supplied to the recipients organization. None of the information
contained in this document shall be disclosed outside the recipients own organization
without the prior written permission of BP Group, unless the terms of such agreement or
contract expressly allow.
Page 2 of 38
GP 44-25
Guidance on Practice for Depressurisation
Table of Contents
Page
Foreword ........................................................................................................................................ 2
Introduction ..................................................................................................................................... 6
1.
Scope .................................................................................................................................... 7
1.1. General....................................................................................................................... 7
1.2. Objective..................................................................................................................... 7
1.3. General requirements ................................................................................................. 7
1.4. Calculation methods ................................................................................................... 8
2.
Normative references............................................................................................................. 8
3.
4.
5.
General................................................................................................................................ 10
6.
7.
8.
9.
10.
Page 3 of 38
GP 44-25
Guidance on Practice for Depressurisation
11.
12.
Effects of depressurisation................................................................................................... 21
12.1. Auto-refrigeration ...................................................................................................... 21
12.2. Hydrates and ice ....................................................................................................... 22
13.
Repressurisation.................................................................................................................. 22
Proposed methods............................................................................................................... 33
B.2
B.3
B.4
Method 1.............................................................................................................................. 33
B.5
Method 2.............................................................................................................................. 33
B.6
Method 3.............................................................................................................................. 33
B.7
Method 4.............................................................................................................................. 33
Bibliography .................................................................................................................................. 33
List of Tables
Table A1 - High temperature tensile properties for typical carbon steel (1) ................................... 30
Table A2 - High temperature tensile properties for 18-8 stainless steel (1) ................................... 32
List of Figures
Figure A1 - API RP 521 figure on average rate of heating steel plates exposed to open gasoline
fire on one side .................................................................................................................... 28
Figure A2 - API RP 521 figure on effect of overheating steel (ASTM A515 grade 70) ................... 29
Figure A3 - Typical carbon steel (SA-515, grade 70) rupture stress versus time to rupture
(bibliographical reference [1], Page 20)................................................................................ 29
Figure A4 - Typical carbon steel (SA-515, grade 70) tensile strength and yield stress versus
temperature (bibliographical reference [1], Page 16)............................................................ 30
Downloaded Date: 6/17/2008 11:12:31 PM
The latest update of this document is located in the BP ETP and Projects Library
Page 4 of 38
GP 44-25
Guidance on Practice for Depressurisation
Figure A5 - Typical carbon steel (SA-515, grade 70) internal pressure versus pool fire exposure
time to minimize potential for vessel rupture ........................................................................ 31
Figure A6 18-8 grade stainless steel (304, 304L) rupture stress versus time to rupture
(bibliographical reference [1], Page 20)................................................................................ 31
Figure A7 18-8 stainless steel (304; 304L) tensile strength and yield stress versus temperature
(bibliographical reference [1], Page 140).............................................................................. 32
Figure A8 18-8 stainless steel (304; 304L) internal pressure versus pool fire exposure time to
minimize potential for vessel rupture.................................................................................... 33
Figure A9 - Effect of depressurisation on reduction of distance to overpressure effects (e.g., sideon overpressure).................................................................................................................. 33
Page 5 of 38
GP 44-25
Guidance on Practice for Depressurisation
Introduction
This Guidance on Practice (GP) provides guidance on depressurising systems that are within its stated
scope and is for use in determining the need for, and design of, specific depressuring systems.
This GP refers to National and International Standards that are widely accepted. Codes and Standards
of the country where the equipment is manufactured and/or operated should be considered and may be
accepted if they can be used to achieve an equivalent, safe, technical result. In any case, statutory and
local regulations must be complied with.
The value of this GP to its users is significantly enhanced by their regular participation in its
improvement and updating. For this reason, users are urged to inform BP of their experiences in all
aspects of its application using the shared learning folder on the ETP website.
Page 6 of 38
1.
1.1.
Scope
General
a.
b.
c.
1.2.
1.3.
GP 44-25
Guidance on Practice for Depressurisation
1.
Fluid flow may pass through any or all equipment and pipework in the system being
considered.
2.
Fluid may reverse flow direction to its expected flow path during either normal or
abnormal operation.
3.
This document describes and provides guidelines for the Emergency Depressuring (EDP)
system and the Emergency Shutdown (ESD) system as it relates to the EDP along with
briefly discussing depressurisation as it relates to maintenance. The EDP and ESD systems
are integral parts of the overall operations and safety systems provided for a facility.
Objective
a.
Early detection and isolation of hazardous releases and reduction of certain hazardous
inventories can substantially limit the consequences from an emergency situation such as a
major release of flammable materials, hydrocarbons or a fire. An emergency Shutdown
(ESD) and emergency vapour space depressurisation system shall be provided in situations
where rapid isolation of uncontrolled releases is desirable; to shut off secondary fuel
sources that could feed a fire or vapour cloud, and to minimize releases through the use of
rapid depressurisation. Coupled with a fire and gas detection system, strategically located
and properly designed ESD and EDP valves can significantly reduce exposure from fire
and vapour clouds.
b.
These systems do not replace any requirement for providing pressure safety valves (PSV)
as required by regulation, and are supplemental to plant pressure relief protection systems.
General requirements
a.
b.
Plants, systems, and facilities covered by this GP require some form of operational
depressurisation. Depressurisation can also be required for emergency situations. Clause 9
provides the information necessary to select a depressuring system and means of disposal
applicable to a particular facility.
c.
Contractors are to develop designs and apply their services in accordance with the
principles of this GP as amplified or modified by any accompanying supplementary
specification(s). Proposed depressurisation designs, services, calculation methodologies,
and the final depressurisation system design shall be subject to general discussion with and
written approval by BP.
Downloaded Date: 6/17/2008 11:12:31 PM
The latest update of this document is located in the BP ETP and Projects Library
Page 7 of 38
1.4.
GP 44-25
Guidance on Practice for Depressurisation
Calculation methods
This GP provides guidance on calculation methods to be used for determining:
2.
a.
Depressurisation loads.
b.
c.
Normative references
The following normative documents contain requirements that, through reference in this text,
constitute requirements of this technical practice. The latest edition of the following normative
documents apply.
BP
GP 24-03
GP 24-10
GP 24-20
GP 24-24
GP 30-35
GP 30-45
GP 30-76
GP 30-80
GP 30-85
GP 43-54
GP 44-70
GP 44-80
GP 62-01
PSS 10
gHSEr
Page 8 of 38
GP 44-25
Guidance on Practice for Depressurisation
Other
BLOWDOWN
3.
3.1.
3.2.
In this GP the term approve, as applied to BP, is used if BP does not wish a design to
proceed unless certain features have been agreed in writing with a contractor or supplier.
This does not imply that all details in a written document have been considered by BP and
does not affect the design responsibilities of the contractor or supplier.
b.
Throughout this document, the words should, shall and must, when used in the
context of actions by BP or others, have specific meanings. For the purposes of this GP,
the following terms and definitions apply:
1.
2.
3.
Definitions
Blowdown
Can be used interchangeably with depressurisation but more commonly taken to mean a rapid
relieving of all system pressure down to atmospheric or low pressure levels.
BP
BP p.l.c. and their associates.
Controlled Depressurisation
An instrument controlled depressurisation generally giving a lower maximum flow rate over a longer
period of time than uncontrolled depressurisation.
Depressurise or Depressurisation
To reduce the internal pressure of process equipment.
Draindown
Draining of liquid from vessels or storage to remove the source of flashing liquid that may feed a fire.
Emergency Depressurisation
The ability to rapidly depressurise, by release of gas, a plant or part of a plant in an emergency.
Downloaded Date: 6/17/2008 11:12:31 PM
The latest update of this document is located in the BP ETP and Projects Library
Page 9 of 38
GP 44-25
Guidance on Practice for Depressurisation
Operational Depressurisation
The ability to depressurise equipment, by release of gas, to permit decommissioning and maintenance
operations.
Yellow Shutdown
On an offshore production facility, the production process from wellhead valves to export lines is
shutdown and isolated. Other systems remain in operation. This type of shutdown normally includes
controlled depressurisation of the production facilities.
4.
5.
EDP
Emergency Depressuring
EDPV
ESD
Emergency shut-down
ESDV
LPG
MCR
PAS
PSD
SI
SIL
SIS
General
A depressurisation system is a means of reducing the pressure in a process plant or
pipeline below the normal operating pressure. The main reasons for this are:
Disposal is normally to a flare, but an atmospheric vent may be pursued for emergency
discharge in rare instances when the project can demonstrate flaring is not an option and
GP 44-80 conditions for venting with the required management approvals are obtained.
Downloaded Date: 6/17/2008 11:12:31 PM
The latest update of this document is located in the BP ETP and Projects Library
Page 10 of 38
GP 44-25
Guidance on Practice for Depressurisation
Vents must also follow applicable local regulations, discharge to a safe location (refer to
API 521, Section 5), and have appropriate dispersion analysis conducted.
b.
c.
Depressurisation systems shall be developed in accordance with the strategy and associated
performance standards for managing major hazard events in GP 24-03 and either GP 24-10
(for onshore facilities) or GP 24-20 (for offshore facilities) as appropriate.
d.
GP 44-70 and GP 44-80 contain further guidance on both system design and required
process components for depressurisation systems.
Dependent upon the nature of the contained fluid, depressurisation can cause low
temperatures (auto-refrigeration) which can form large volumes of liquid
condensate, plugging of the depressurisation system due to solids being formed
(freezing) or the need for more expensive materials to avoid brittle fracture issues.
6.
6.1.
The addition of supplemental fuel gas to the flared gas may be required to maintain
the minimum heating value required for proper flare operation when depressuring
vessels containing inert gas or other gas with a low heating value.
6.2.
6.3.
Sections of plant or individual plant items containing hydrocarbon gas and/or liquid should
normally be isolated, depressurised, drained, and purged to allow access for inspection and
maintenance.
b.
c.
In onshore applications, the system may be the same as offshore; although a dedicated
operational depressurisation valve is often used.
Pipelines
Pipeline depressurisation is not covered within this GP; refer to GP 43-54 for pipeline
depressurisation guidelines.
Occasionally depressurisation of pipelines may be required to allow for inspection
or repair. Generally, pipeline depressurising times are extensive, measured in days
rather than minutes, making the pipeline unavailable for transportation; which may
be particularly important when more than a single operator is reliant on the
pipeline availability.
Page 11 of 38
7.
7.1.
GP 44-25
Guidance on Practice for Depressurisation
7.2.
a.
Reducing the failure potential of pressure containment equipment for scenarios involving
over temperature from a fire, exothermic or runaway process reaction.
b.
Minimising the release of fuel that may be feeding a fire or could be ignited.
c.
d.
Mitigating the effect (i.e., size, impact, and/or duration) of a jet fire.
Provision may be made to insulate the vessel vapour space, or apply external water for
cooling, or to depressurise the vessel by means of a vapour depressurising system. When
dealing with vapour, the objective of a depressurising system should be to keep the internal
pressure of the exposed vessels and piping below the rupture pressure as the yield stress of
the wall reduces due to overheating.
b.
7.3.
c.
The platform topsides section of a subsea pipeline, including the pig launcher/receiver and
downstream pipework to the pipeline ESDV at the riser/topsides interface, should be
depressurised through the normal platform system. The platform design shall ensure that
the ESDV and downstream pipeline are fire protected, so the pipeline inventory can be
maintained.
d.
Deluge systems are designed to minimise the temperature rise of equipment in and
surrounding a fire. Passive fire protection may be considered for vessels particularly at risk
in a fire, in addition to or instead of deluge systems. Refer to fire protection
GP category 24 for more specific information and GP 30-85 on fire and gas detection.
Compressors
a.
b.
For compressors with seals not relying on a seal oil system to contain the gas, the
compressor may be considered as part of the depressurisation system.
Page 12 of 38
8.
8.1.
Depressurisation requirements
General
a.
ESD and EDP systems shall be reliable, failsafe, and based on proven design concepts
utilizing a SIS designed in accordance with GP 30-76 and GP 30-80. The SIS shall be
independent of the PAS though operators may view the ESD/EDP status through a
common human machine interface. See GP 30-45. The SIS for an ESD/EDP system shall
comply with the SIL determined during Front-End Engineering Design and detailed
design. The ESD and EDP systems shall have a simple interface with plant operators to
allow a safe shutdown and, if required, depressuring without plant operators having to
consider many alternatives.
b.
c.
8.2.
GP 44-25
Guidance on Practice for Depressurisation
1.
2.
3.
4.
5.
Impact on flare pilots (e.g. potential for extinguished pilots due to high
depressurisation rate).
6.
In case of an emergency, the ESD and EDP systems should perform, as a minimum, but
not be limited to, the following functions:
1.
Stop selected inlet and outlet hydrocarbon streams by closing dedicated ESDVs.
2.
Stop flow of incoming thermal energy or heat sources within ESD zone (Such as fuel
sources, furnaces, and steam to reboiler, if any).
3.
Stop selected drivers on pumps and compressors. Some facilities such as lube oil and
seal oil system for compressors, turbines, and lighting system are not stopped or
tripped.
4.
5.
Page 13 of 38
8.3.
GP 44-25
Guidance on Practice for Depressurisation
b.
Final ESDV locations should be reviewed by process hazard analyses and design hazard
reviews that address the impact of isolation on operations.
Some typical ESDV locations are potentially located at:
c.
ESDV location(s) and use shall be optimised based on the individual system configuration.
The minimum hydrocarbon liquid level contained in vessels and tanks shall: be specific to
the type of fluid, be determined by regulations and consequence analysis, and require that
an ESDV be installed.
d.
ESDVs on accumulator and process vessels should be placed as close as possible to the
vessel outlet flange.
e.
ESDVs for process area isolation shall be located at the edge or boundary of the process
area being isolated. Upon activation, the ESDV shall stop the flow of inlet and outlet
process streams, hazardous utility streams, and fuel supply to the affected area.
f.
It is important that the location and number of not only ESDVs but also depressuring
valves consider:
1.
2.
3.
g.
Generally, an ESDV shall be a tight shut-off, fail close (on loss of signal or power
source), air/pneumatic operated block valve. An ESDV and its accessories shall be of fire
safe design if located inside a fire zone.
h.
LNG service ESDVs should be located in accordance with NFPA 59A. For applications
not subject to NFPA 59A, ESDVs should not be located at long distances from the process
unit just to avoid installation in the fire zone without considering the consequences of
having a potentially larger hazardous material release.
Page 14 of 38
8.4.
GP 44-25
Guidance on Practice for Depressurisation
i.
j.
If necessary, a hydraulic actuating system in lieu of air may be used. If hydraulic valves
are selected, these shall be equipped with a secured supply of actuating fluid and back-up
system and be protected as necessary against potential hazards.
k.
In general, the use of spring return air operated valves shall be selected for the ESDVs at
first from reliability and maintainability points of view. However, for large size valves,
etc., which require large torque, the application of double acting air cylinder type or
hydraulic type, etc. shall be investigated with consideration of constructability and
maintainability. If double acting air cylinder or hydraulic valves are used as ESDVs, an air
bottle or hydraulic accumulators sized to provide an independent air or hydraulic supply
for at least three (3) cycles, i.e. Close-open-close-open, to provide motive energy to move
the valve to its fail safe position shall be provided. Additionally, valve and actuator
components, including wiring, air supply, etc, should be protected against potential
hazardous exposures. Inherently failsafe actuation is preferred.
l.
ESD valves shall not be provided with handwheels. ESD valve shall be equipped with
open/close position limit switch and the open/close indication shall be displayed on the
PAS.
m.
The scope and requirements to provide online testing of the ESDVs shall be developed
during the design to meet the required integrity levels. Control valves shall not be used as
ESDVs, unless specifically justified and failure of the control loop cannot cause a demand
on the ESD function.
n.
The type of ESDV shall be defined dependent on the service requirements and size of the
valve. Further guidance on ESD valve selection is provided in GP 62-01.
The scope of details of EDP shall be developed during design. EDP for each skid, process
area, or the total plant, if applicable, shall be enabled only after activation of the ESD
system.
Activation of EDP is typically accomplished via hard-wired manual switches that
are located in the MCR and, for some offshore installations, automatically on
confirmed detection of fire or gas release.
b.
The EDP system shall have adequate venting capacity to achieve reduction of stress in
selected equipment affected by fire to a level at which stress rupture is not an immediate
concern. In addition, it should be designed to enable minimization of fuel inventory that
might otherwise aggravate a fire and to minimize the uncontrolled release of flammable or
toxic gases.
c.
EDP system (once activated) shall be able to reduce the pressure of the system to the
pressure and maximum duration provided in Annex A.
d.
The design of piping and equipment shall consider the temperature reached during autorefrigeration. Vapours released during depressuring shall be vented to the flare system or
other BP approved location.
e.
Page 15 of 38
GP 44-25
Guidance on Practice for Depressurisation
9.
9.1.
Depressuring valves shall, in general, be tight shut-off (to avoid loss of hydrocarbons
during normal operation) air operated block valves. See GP 62-01.
b.
The EDPV is typically designed to fail close or fail in the last position. However, the
failure position of each valve shall be reviewed during the design hazard review. Should
the EDPVs fail open, operational upsets due to malfunctioning valves or inadvertent
opening of the valves should be considered as-well-as any single mode failure resulting in
the EDPVs simultaneously opening and potentially exceeding flare capacity.
c.
Use of a single control valve to serve as both an EDP and a letdown-to-flare should follow
GP 30-35. This common usage also needs review during the design hazard review to
ensure this design does not result in a common mode failure that could contribute to the
cause and thus defeat a protective system.
d.
The scope and requirement to provide online testing of the depressuring valves shall be
developed during design to meet required integrity levels.
If a depressurising system is not required by regulation, the risk and effectiveness of the
system should be considered. This entails developing a fire damage assessment, assessing
the viability of depressurising to mitigate undesirable leaks and spills, then fully evaluating
personnel risks and plant replacement costs with and without a depressurising system
installed. During this assessment the following points should be considered:
1.
2.
Stress rupture may not occur as the fire may die out or be extinguished. Note the
inventory of a gas plant is generally significantly less than an oil installation and
therefore oil fires could last appreciably longer.
3.
4.
Vessel design pressure may be substantially higher than the maximum operating
pressure; reducing the possibility of rupture.
5.
6.
7.
8.
Page 16 of 38
9.2.
9.3.
GP 44-25
Guidance on Practice for Depressurisation
b.
To minimise spurious trips, the shutdown and depressurisation should be the result of gas
detection by two detectors in a voting system. These detectors should produce a pre-alarm
signal to allow possible operator intervention before the plant trips and depressurises.
c.
On open deck platforms, gas detectors are unlikely to detect anything but very large leaks.
However if they are used they should initiate yellow shutdown and depressurisation. On
open deck platforms a vapour cloud is much less likely to form than in an enclosed
platform and if the leak is large, depressurisation is unlikely to be necessary after an ESD
has taken place.
d.
Floating production facilities are invariably manned and are therefore covered by the same,
above criteria.
b.
Gas or fire detection on unmanned platforms shall result in a process shutdown. The
depressurisation should be manual; either initiated by operators visiting the platform or if
there are no personnel on the platform, by operators at the controlling platform or terminal.
Initiation of depressurisation should consider helicopter operation in the platform vicinity.
c.
Use should be made of fire protection for systems most at risk from a delayed
depressurisation.
9.4.
9.4.1.
Gas terminals
If a terminal contains pipework and tankage but no process plant, depressurisation is unlikely to
be appropriate in emergency situations. Fire protection with water deluge and/or passive
protection should be used with drain down if appropriate.
9.4.2.
The protection and safety of pressurised LPG storage systems is covered by IP 9. Fire
protection, both passive and with water deluge, shall be used for fire protection, as appropriate,
and no vapour depressurisation is required.
Page 17 of 38
GP 44-25
Guidance on Practice for Depressurisation
9.5.
Hydrotreating/hydrocracking reactors
9.5.1.
General
9.5.2.
9.5.3.
a.
Hydroprocessing reactors above 34 barg (500 psig) separator operating pressure shall be
provided with a fail safe depressuring system that can be activated from the control room.
The main purpose of this depressuring system is for high pressure inventory disposal under
unit emergency conditions such as fire. Fail safe means that the valve(s) used for
depressuring the unit fails open on loss of signal or de-energisation. The depressuring
valve can also serve as the normal pressure control valve.
b.
The protection and safety of the pressurized reactor section of a Hydroprocessing unit shall
comply with BP Refining PSS 10.
a.
New build hydroprocessing reactors (post January 2000) containing catalyst with cracking
function and above 70 barg (1 000 psig) separator operating pressure shall be provided
with a fail safe depressuring system that can be activated from the control room and in the
field local to the plant. Fail safe means that the valve(s) used for depressuring the unit fail
open on loss of signal or de-energisation. The depressuring valve/s shall be dedicated
shutdown valve/s separate from normal unit controls.
b.
The depressuring system shall have automatic initiation by high reactor temperature. High
reactor temperature is defined as 30C (54F) above normal operating temperature or
reactor mechanical design temperature, whichever occurs first. Depressuring shall not be
able to be interrupted until all temperatures are 25C (45F) below trip setting. Initial
depressuring rate shall be maximized up to the industry practice of 21 bar/min
(300 psi/min) subject to reactor bed support and flare system constraints, but in no cases
shall be less than 14 bar/min (200 psi/min).
a.
Existing hydroprocessing reactors containing catalyst with cracking function and above
70 barg (1000 psig) separator operating pressure shall be provided with a fail safe
depressuring system that can be activated from the control room and in the field local to
the plant. Fail safe means that the valve/s used for depressuring the unit fail open on loss of
signal or de-energisation. The depressuring valve/s shall be dedicated shutdown valve/s
separate from normal unit controls.
b.
The depressuring system shall have manual or automatic initiation by high reactor
temperature. High reactor temperature is defined as 30C (54F) above normal operating
temperature or reactor mechanical design temperature, whichever occurs first.
Depressuring shall not be able to be interrupted until temperatures are 25C (45F) below
trip setting. Initial depressuring rate shall be at least 14 bar/min (200 psi/min).
Fire case
a.
If depressurisation is not the controlling rate for design of the flare, vessels designed to
BSI PD 5500 should be depressurised to 6,9 barg (100 psig) or 50% of the design pressure,
whichever is the lower pressure, in 15 minutes. Vessels designed to ASME VIII, BSI PD
5500 or equivalent which are 25 mm (1 in) wall thickness or greater, should be
depressurised to 50% of their design pressure in 15 minutes if the vessel is uninsulated
carbon steel construction (see Annex A).
b.
Vessels designed to ASME VIII and pipework of wall thickness less than 25 mm (1 in)
should be depressurised proportionately faster (see Annex A).
Downloaded Date: 6/17/2008 11:12:31 PM
The latest update of this document is located in the BP ETP and Projects Library
Page 18 of 38
GP 44-25
Guidance on Practice for Depressurisation
c.
If depressurisation governs flare design capacity, the rate of vessel(s) and pipework
depressurisation should be related to the reducing strength of the steel exposed to fire. The
depressurisation rate selected and method of calculation shall be subject to BP approval.
d.
If necessary to reduce the flow rate of gas to flare or vent, longer depressurisation times
may be proposed for BP approval for vessels containing liquid, having external insulation,
or having wall thickness greater than 25 mm (1 in).
Vessels containing liquid or having external insulation take longer to heat up than
non-wetted or bare vessels. Also vessels of wall thickness greater than 25 mm (1 in)
take longer to heat up than the 25 mm (1 in) thick vessels used as a basis in API
RP 521.
For equivalent wall thicknesses, stainless steel vessels generally allow lower
depressurisation rates than carbon steel (see Annex A) because stainless steel
begins to lose strength at a higher temperatures than carbon steel.
10.2.
Non-fire case
The 15 minute depressurisation guideline does not apply to non-fire case. Refer to formal risk
analysis, Annex A, and API RP 521 guidelines.
10.3.
Stopping depressurisation
Depressurisation should not be stopped on reaching the target pressure (See Annex A). Pressure
normally continues to reduce until atmospheric pressure or the flare or vent backpressure is
reached. Stopping the depressurising process should be evaluated on a case-by-case basis if it is
deemed discontinuing depressurisation can be conducted safely. See clause 13.
Uncontrolled depressurisation
In a normal uncontrolled depressurisation the total system is shutdown and isolated
and the pressure in the process equipment is discharged to flare or vent through the
emergency blowdown valves, restriction orifices, and headers. This creates an
initial peak flow rate that decays over the major portion of the depressurising
period.
The depressuring time and the end pressure (clause 10.3) are of great importance
when determining the load to flare or vent. In addition to the load from the system
being depressurised there is a possibility of continued in-flow into the system being
depressured, e.g. from wells that have not shut-in, and consequently more gas is
routed to flare increasing the total gas depressuring rate.
11.2.
Depressurisation by zone
Offshore, process plant often occupies a number of fire zones, i.e. areas separated
by firewalls within which a fire can be contained. Onshore, fire in one area can be
prevented from reaching other areas by distance and bunding or kerbing.
This division into fire zones is an important means to reduce the maximum flare load
in cases of emergency depressurisation. It is more applicable to onshore plants, but
can be applied offshore if good fire zone segregation is achieved.
a.
Consideration should be given to depressurising only those vessels and equipment within
the fire zone in which fire or gas is detected. Depressurisation of vessels and equipment in
Downloaded Date: 6/17/2008 11:12:31 PM
The latest update of this document is located in the BP ETP and Projects Library
Page 19 of 38
GP 44-25
Guidance on Practice for Depressurisation
adjacent fire zones should be timed to follow, or be at the discretion of the operator, but in
any case should be delayed to minimise the size of the flare or vent system. A reduction in
flare size by zoned depressurisation shall only be accepted if total depressurisation cannot
occur from a common cause (e.g. simultaneous loss of instrument air to all
depressurisation valves).
11.3.
b.
In exceptional circumstances, BP may approve a reduction in the peak discharge rate due
to the distributive nature of the relieving flow and the requirement for pressure build-up to
discharge the system inventory. The use of any such reduction shall require specific,
written approval of the BP responsible Engineering Authority (EA).
c.
The designer should be aware of and prevent common cause failures, e.g. breakdown of a
distributed control system in one area shall not affect any other process areas.
Controlled depressurisation
In a controlled depressurisation, the peak flow rate can be maintained for a
substantially longer period before the decaying phenomenon sets in. Since peak flow
is maintained over a longer time, the depressurisation flow rate is reduced in
magnitude compared to the peak flow rate of an uncontrolled depressurisation.
Flow from each section being depressurised is normally initiated by the opening of a
valve with the flow controlled by a restriction orifice. It is possible to limit the total
flow rate, but still depressurise in the designated time, by either controlling the flow
rate bypassing the orifice with a control valve or snap open valve(s) initiated by a
timing sequence. This increases the flow to flare after the peak flow has passed and
the system pressure has reduced.
The use of controlled depressurisation is subject to BP approval, since controlled
depressurisation instrumentation can be less reliable than that used for uncontrolled
depressurisation. Systems containing fail open or fail shut valves rather than control valves are
generally favoured, but in all cases reliability analysis shall be required for a controlled
depressurisation system.
11.4.
11.5.
Flow restriction orifices are used in conjunction with snap open valves to set the maximum
rate of depressurisation to flare or vent. Alternatively, depressurisation valves may be sized
to ensure the disposal system capacity is not exceeded when all valves go to the full open
position. Depressurisation valves may also be designed to fail closed or in the last position
to eliminate common mode failures provided that reliable valve actuation to the
appropriate SIL is assured.
b.
Depressurisation flow rates and the resulting system temperatures for gas and gas/liquid
systems shall be calculated in accordance with one of the methods given in Annex B.
Maximum depressurisation flow rates tied to a flare system shall not exceed the flare
system capacity.
c.
For controlled depressurisation, the flow may not be totally through single fixed orifice(s).
Alternative calculation methods that take this into account shall be considered for this case.
Draindown
a.
b.
Page 20 of 38
GP 44-25
Guidance on Practice for Depressurisation
during fire exposure, but could require special consideration of the electrical power and
utility system status.
c.
In many cases the advantages of retaining the liquid in the vessel to minimise the rate at
which the vessel heats up outweighs the benefits from removing the flammable liquid from
the fire zone. The reliability of the deluge system, the availability of separate liquid storage
and the fire resistance of the system shall be considered for each case, since this will
probably only be used when a fire has reached a high severity.
d.
Draindown can also be used to avoid low temperatures resulting from boil-off of highly
volatile liquids and hence reduce the requirement for expensive alloy steel.
Auto-refrigeration
12.1.1.
General
In general, if the vessel fluid is all vapour, the rate of heat transfer from the vessel to
vapour is negligible. The heat capacity of the vessel is also high compared to that of
the vapour and the reduction in wall temperature is low. An exception to this can be
exit nozzles where significant forced convection takes place during depressurisation
requiring the use of stainless steel nozzles, internal sleeves, or other mitigations to
accommodate these low temperature blowdown effects.
Available information should be carefully considered before selecting the thermodynamic
process for vessel depressurisation.
Downstream of the orifice where fluids are usually at their coolest and the flow very
turbulent, the rate of heat transfer is high, resulting in the pipework generally
approaching isenthalpic flash temperature. Note that flow up to the orifice throat is
an isentropic process while flow in the piping downstream of the orifice is generally
considered to be an isenthalpic process. Technical studies have yet to firmly
establish the type of process within the vessel being depressured (isentropic,
isothermal or somewhere in between). The isentropic assumption neglects heat gain
from the surrounding environment and can predict low temperatures upon
depressurisation, potentially suggesting a need for low temperature materials. In
contrast, an isothermal process may often suggest that plain carbon steel
construction would be appropriate, even though fluid kinetic energy gains
downstream of an orifice can limit available fluid thermal energy and push fluid
temperatures below those predicted by an isenthalpic flash calculation.
In a vessel containing liquid and vapour, vapour expansion and evaporation from
the liquid cools the liquid. The rate of heat transfer from the container to the liquid
is significant. Transfer of heat in from the surroundings often is not negligible in the
timescale of the depressurisation except for fire, sweating (re-condense water from
humidity), and sweating up to ice layer.
Annex B gives four methods of increasing complexity and accuracy when
calculating minimum wall temperatures resulting from depressurisation. The time
and effort expended on this calculation could depend on the likely equipment cost
savings. For example, if a simple flash (Method 1) shows stainless steel is required
for a large vessel by a small margin, it would be reasonable to go to a more complex
Downloaded Date: 6/17/2008 11:12:31 PM
The latest update of this document is located in the BP ETP and Projects Library
Page 21 of 38
GP 44-25
Guidance on Practice for Depressurisation
Under certain conditions it is possible for hydrates or ice to form in a hydrocarbon system
containing free water. In such systems, if the temperatures calculated on emergency
depressurisations using a simple adiabatic flash are low enough to support hydrates or ice;
consideration should be given to using Method 2 in Annex B to establish if a supporting
temperature and pressure can exist at the same time.
b.
13. Repressurisation
a.
b.
c.
d.
e.
Page 22 of 38
GP 44-25
Guidance on Practice for Depressurisation
Annex A
(Normative)
Depressurisation purpose
The two primary purposes for an emergency depressurisation system are:
A.2.
a.
Remove internal pressure from a gas-filled vessel(s) to reduce the applied stress on the
pressure boundary material, assumed to be a metal, exposed to a pool fire in order to
extend the time before failure occurs. This is needed because the strength or load carrying
ability of a metal decreases with temperature.
b.
Remove inventory from a vessel(s) to minimize the amount of material that would be
released through a leak or rupture. This would reduce or mitigate the consequences from
the leak or rupture.
b.
Note that the following approach is applicable to standard hydrocarbon pool fires.
Exposure to jet fires can result in intense, localized heating rates that significantly exceed
that of a standard hydrocarbon pool fire. Higher fire heat fluxes require higher
depressurisation rates than predicted below. If available, jet fire heat flux data should be
utilized that is representative of jet fires one might expect in a plant as opposed to
theoretical analyses or data obtained in strictly controlled tests.
c.
The normal starting point in specifying depressurisation criteria for a specific vessel would
be determining the vessel wall heat up time from pool fire exposure. Figure A1 of API
RP 521 provides data on average heat-up rates of steel plates exposed on one side to an
open gasoline pool fire. This Figure indicates it takes about 15 minutes for a 25,4 mm
(1 in) thick steel plate to heat from ambient temperature to 650C (1200F) in the pool fire.
The plate would reach an equilibrium temperature of about 760C (1400F) in
20 minutes. The equilibrium temperature is the temperature at which heat gain from a
typical pool fire is balanced by heat loss to the environment and assumes a bare, unwetted
plate that is exposed to fire on one side. There can be significant variability in the heat up
rate and ultimate temperature attained in a pool fire due to the influence of total heat
capacity of the vapour within the vessel, fire intensity, fire duration, presence of external
insulation, etc.
d.
Page 23 of 38
GP 44-25
Guidance on Practice for Depressurisation
For a pressure vessel exposed to a pool fire, an increase in the unwetted wall temperature
above the code allowable temperature causes a decrease in material strength. Immediate
failure may not be predicted because of conservative code design. However, as the metal
wall temperature gets quite high, short term failures can occur as predicted based on creep
or stress rupture data. Figure A2 (taken from API RP 521) shows the effect of temperature
increase on rupture strength of typical carbon steel pressure vessel plate (i.e., grade
SA-515). This data was obtained from bibliographical reference [1] (see Figure A3 for the
original source data) and is characteristic of all grades of carbon steel. These figures plot
rupture stress (i.e., load or stress on the pressure boundary material required to rupture a
vessel) versus the time to rupture for several elevated temperatures. For a carbon steel
vessel with a 138 MPa (20 ksi) design stress, Figure A2 (or Figure A3), predicts the vessel
would rupture in about 1 hour at 593C (1 100F) and 0,1 hour (6 minutes) at 650C
(1 200F). Hence, vessel rupture can occur in a relatively short time period once the metal
reaches a high temperature as long as the internal pressure remains high (e.g., near design
conditions).
f.
Note that the API curve shown in Figure A2 is extrapolated from the source data shown in
Figure A3 for exposure times less than 0,1 hours. Figure A3 also plots the Short Time
Tensile Strengths at or near the 0,1 hour data. The Short Time Tensile Strengths should be
considered the limiting stresses for a given temperature (i.e., exceeding these cause
failure). Hence, the extrapolations in Figure A1 at exposure times less than 0,1 hours
should not be used because the vessel integrity cannot be maintained with an internal
pressure that results in total stresses, including residual and applied, that exceed the
vessels tensile strength. It is also important to note that the vessel can be damaged (e.g.,
yielded) at stresses significantly lower than the rupture stress. Hence, any equipment
exposed to fire would need a follow-up inspection and assessment to determine fitness-forservice even if out-right failure did not occur.
g.
One way to extend the time before failure occurs is to reduce the internal pressure within a
vessel (i.e., depressure it). As long as the internal pressure results in stresses below the
rupture stress, the vessel should not rupture (unless there are material defects/ flaws/
previous damage or if one of the components such as a nozzle or flange is a weaker link).
The data in Figure A2 or A3 can be used to determine the maximum stresses to avoid
failure, but this requires a fairly comprehensive analysis. However, during the initial heatup phase, it can be easier to use the short-time tensile strength as a limiting stress that, if
exceeded even briefly, would cause vessel failure. Tensile and yield strength data for
typical carbon steel are given in Table A1 and illustrated in Figure A4. This data can be
used to determine depressurisation versus time for vessels using carbon steel with about
483 MPa (70 ksi) tensile strength when coupled with heat-up rates.
h.
For example, the effect of depressurisation on the time to rupture is required for a large
(say 25,4 mm (1 in) wall thickness) vessel fabricated from SA-516 Grade 70 carbon steel
with a design allowable stress of 138MPa (20 ksi). The scenario involves pool fire
exposure whereby the internal pressure increases to that equivalent to the design allowable
stress in the pressure boundary wall and then stays constant as the vessel continues to be
heated. Maintaining a constant pressure near the design allowable stress would be
comparable to having the vessel protected by a pressure relief valve. If the vessel was
Downloaded Date: 6/17/2008 11:12:31 PM
The latest update of this document is located in the BP ETP and Projects Library
Page 24 of 38
GP 44-25
Guidance on Practice for Depressurisation
initially at ambient temperature, Figure A1 indicates it will take slightly over 10 minutes
for the average vessel wall temperature to reach 538C (1 000F). Based on the data in
Table A1 and Figure A4, the vessel starts to yield at this temperature because the applied
stress (138 MPa (20 ksi)) would become equal to the yield stress. If the applied stress stays
constant at 138 MPa (20 ksi) and further wall heating occurs, then the vessel will rupture
when the wall temperature reaches about 650C (1 200F), about 14 minutes into the fire
(see Figure A1). Rupture can occur at lower temperatures if there are material defects or a
weaker component of the vessel construction than the base metal.
i.
API RP 521 suggests the internal pressure be reduced by 50% within 15 minutes of pool
fire exposure. Figure A1 indicates the average wall temperature 15 minutes into the pool
fire would be about 670C (1 240F). For our vessel with the 138 MPa (20 ksi) allowable
design stress (thus applied stress of only 69 MPa (10 ksi) once depressured to 50% internal
pressure), Figure A4 indicates that at 670C (1 240F) the 69 MPa (10 ksi) stress on the
carbon steel pressure boundary would exceed the yield point (about 62 MPa (9 ksi)), but
not the rupture stress (about 90 MPa (13 ksi)). Thus, the vessel will be damaged, typically
in the form of bulging. Note that this rupture stress is based on the vessel seeing a wall
temperature of 670C (1 240F) for the full 15 minutes of pool fire exposure (see
Figure A2 or A3). In other words, it ignores heat-up time and assumes the wall reaches
670C (1 240F) at the onset of fire exposure. At the other extreme would be the case
where the vessel wall temperature does not appreciably increase until the end of the
15 minute exposure in which case the metal wall sees 670C (1 240F) but only for a very
short time. In this case, the tensile strength would be the limiting factor (about 117 MPa
(17 ksi) at 670C (1 240F) from Figure A4). The actual internal pressure where rupture
occurs will likely be in between the rupture stress and tensile strength given the pool fire
heat-up rate is not instantaneous.
j.
It is important to note that the vessel wall temperature can continue to increase per
Figure A1. Based on a maximum wall temperature of 760C (1 400F), further
depressurisation would be required to avoid rupture. The bottom curve in Figure A2 (or
Figure A3) indicates the internal stress would need to be reduced to about 34,5 MPa (5 ksi)
or 34,5/138 (5/20) = 25% of the MAWP to extend the time to rupture to about one hour
and reduced to about 27,6 MPa (4 ksi) or 27,6/138 (4/20) = 20% of the MAWP to extend
the time to rupture to about 4 hours.
k.
The depressurisation path as a function of time for carbon steel of several thicknesses is
illustrated in Figure A5. This figure illustrates the depressurisation path to minimize failure
potential due to fire exposure as a function of percent of MAWP. Because of the faster
heat-up rate (see Figure A1), thinner walled vessels require faster depressurisation. These
varying rates of depressurisation become important when designing a common
depressurisation system for interconnected vessels of different sizes and/or design
pressures. In such cases, a fire could simultaneously expose multiple vessels of varying
wall thicknesses. Judgement needs to be taken as to which vessels are included in the
depressurisation system design. Rapid depressurisation required for small vessels must be
balanced not only with the available disposal system capacity but also with the failure
consequences of small versus large vessels.
l.
In addition to reducing the likelihood for rupture, depressurisation would reduce the
consequences in the event of rupture due to fire exposure. Upon rupture, the mechanical
energy (gas stored under pressure) is converted to a blast wave that can damage adjacent
equipment due to overpressure. In addition, fragments can be produced upon failure.
Possible impacts of the failure should be analysed on a case-by-case basis. The general
effect of depressurisation on distance to overpressure effects (e.g., side-on overpressures)
due to vessel failure is illustrated in Figure A9.
m.
The material data presented above applies to typical carbon steel. Alloy materials,
including low alloy steels, stainless steels, and nickel base alloys, show similar strength
loss with temperature as carbon steel, but less dramatic: a sample of rupture strength versus
Downloaded Date: 6/17/2008 11:12:31 PM
The latest update of this document is located in the BP ETP and Projects Library
Page 25 of 38
GP 44-25
Guidance on Practice for Depressurisation
temperature for type 304 stainless steel (i.e., 18-8 grade) is shown in Table A2 and
Figures A6 through A8.
n.
A.3.
A.4.
It is important to recognize that the tensile and rupture strength data given in this Annex
are used as an example of how depressurisation calculations for pool fire exposure can be
made. The sources for this data are typical industry data (1, 2, 3, and 4). However, the
designer should be aware that the values provided by all such references are not
necessarily consistent with each other. Variability in the pool fire (heat-up rate, maximum
equilibrium temperature, view factors, size, duration, extent) can further complicate
depressurisation requirements. Given the variability in assumptions, the designer should be
careful not to overanalyse the depressurisation system requirements but to select an
appropriate criteria for their specific facility requirements.
The second use of a depressurisation system is to mitigate the effects of a leak. A reduction
of vessel pressure through depressurisation to a safe location, such as a flare, reduces not
only the leak rate but also the leak duration through reduction in vessel inventory.
Depressurisation is one of the few mitigation measures for a jet fire whereby if the source
of the jet fire were depressurised, the size and effects are attenuated. Once depressurised to
near atmospheric pressure, the jet fire would in essence be turned off as the source of
fuel would be depleted.
b.
Nature and extent of consequence (toxicity hazard, flammability hazard (vapour cloud
explosion and/or flash fire extent and potential), jet fires, environmental release);
2.
3.
4.
5.
Inventory of fluid requiring depressurisation including liquid that can flash into
vapour upon depressurisation;
6.
Evacuation considerations.
c.
Generally, a starting point in the depressurisation system design would be using a total
instantaneous depressurisation rate equal to no more than the capacity of the disposal
system (e.g., flare). It is critical to stay within the disposal system capacity even during
utility failures such as loss of instrument air that may cause all the depressurisation valves
to open simultaneously (if so designed to fail in the open position upon air failure and
without a backup air supply).
d.
Page 26 of 38
GP 44-25
Guidance on Practice for Depressurisation
require subsequent verification from a more rigorous analysis, and can provide very
misleading results depending on the assumptions made and coefficients being used.
b.
A.5.
Process simulation users should recognise there often can be limitations to these built-in
depressurisation solutions. Some packaged software calculations fail to take proper
account of phase changes and heat transfer (or heat loss). As one example, high purity
liquids stored near their bubble point are not handled well.
Page 27 of 38
GP 44-25
Guidance on Practice for Depressurisation
Figure A1 - API RP 521 figure on average rate of heating steel plates exposed to open gasoline fire on
one side
Page 28 of 38
GP 44-25
Guidance on Practice for Depressurisation
Figure A2 - API RP 521 figure on effect of overheating steel (ASTM A515 grade 70)
Figure A3 - Typical carbon steel (SA-515, grade 70) rupture stress versus time to rupture
(bibliographical reference [1], Page 20)
Page 29 of 38
GP 44-25
Guidance on Practice for Depressurisation
Table A1 - High temperature tensile properties for typical carbon steel (1)
Temperature,
F
Temperature,
C
Tensile
Strength, psi
Tensile
Strength, MPa
Yield Stress
0,2% Set, psi
Yield Stress
0,2% Set, MPa
750
399
58 000
400
24 600
170
900
482
45 500
314
23 500
162
1 000
538
36 500
252
20 100
139
1 100
593
27 200
188
14 250
98
1 200
649
20 000
138
10 200
70
1 300
704
13 500
93
7 375
51
1 400
760
9 025
62
3 750
26
Figure A4 - Typical carbon steel (SA-515, grade 70) tensile strength and yield stress versus
temperature (bibliographical reference [1], Page 16)
40000
35000
30000
25000
20000
15000
10000
5000
0
1000
1100
1200
1300
1400
Degrees F
Tensile Strength
Yield Stress
Page 30 of 38
GP 44-25
Guidance on Practice for Depressurisation
Figure A5 - Typical carbon steel (SA-515, grade 70) internal pressure versus pool fire exposure time
to minimize potential for vessel rupture
100%
Maximum Pressure
to Avoid Failure
(% of MAWP)
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%
0
10
15
20
25
30
35
40
45
50
55
60
1 Inch Thick
Figure A6 18-8 grade stainless steel (304, 304L) rupture stress versus time to rupture
(bibliographical reference [1], Page 20)
Page 31 of 38
GP 44-25
Guidance on Practice for Depressurisation
Table A2 - High temperature tensile properties for 18-8 stainless steel (1)
Temperature,
F
Temperature,
C
Tensile
Strength, psi
Tensile
Strength, MPa
Yield Stress
0,2% Set, psi
Yield Stress
0,2% Set, MPa
1 000
538
53 000
365
14 000
97
1 100
593
48 500
334
12 000
83
1 200
649
43 000
296
11 000
76
1 300
704
35 000
241
11 000
76
1 400
760
27 000
186
10 500
72
1 500
816
20 500
141
10 000
69
1 600
871
17 650
122
---
---
1 800
982
9 600
66
---
---
2 000
1 093
4 900
34
---
---
Figure A7 18-8 stainless steel (304; 304L) tensile strength and yield stress versus temperature
(bibliographical reference [1], Page 140)
60000
50000
40000
30000
20000
10000
0
1000
1100
1200
1300
1400
Degrees F
Tensile Strength
Yield Stress
Page 32 of 38
GP 44-25
Guidance on Practice for Depressurisation
Figure A8 18-8 stainless steel (304; 304L) internal pressure versus pool fire exposure time to
minimize potential for vessel rupture
100%
90%
Maximum Pressure
(% of MAWP)
80%
70%
60%
50%
40%
30%
20%
10%
0%
0
10
20
30
40
50
60
1 Inch Thick
100
90
80
70
60
50
40
30
20
10
0
0
20
40
60
80
100
Page 33 of 38
GP 44-25
Guidance on Practice for Depressurisation
Annex B
(Normative)
Proposed methods
a.
There are four methods of increasing complexity and accuracy for estimating minimum
vessel and pipework temperatures during depressurisation:
1.
2.
3.
4.
B.2
b.
The first method requires only process data; the second additionally requires vessel design
data and the third and fourth additionally require details of the depressurising procedure.
c.
The first method is the most simple, least accurate, and most conservative, while the fourth
is the most complex and time consuming but most accurate/ least conservative.
General assumptions
a.
Process simulation programs generally assume the fluid is perfectly mixed in the vessel.
Specialist software such as BLOWDOWN0 shall be used to account for different fluid
strata within a vessel.
b.
Calculations are usually performed by depressurising from maximum design pressure and
minimum ambient temperature to atmospheric pressure. More reasonable starting
conditions might be maximum design pressure and minimum fluid flowing temperature, if
the contents of the vessel would not be shut-in long enough for the temperature to drop to
minimum ambient temperature.
c.
The vessel is warmed by the air surrounding it, but experience has shown that it may not
have a significant effect during the rapid depressurising timescale in certain cases
(particularly non-fire scenarios). However, it is possible for water in the air (i.e., humidity)
to condense on the vessel wall maintaining the wall temperature no lower than the water
dew point. It may be possible depending upon the rate of cooling for the vessel wall
temperature to fall below 0C (32F) at which time the vessel could get an insulating
covering of snow or ice. Further cooling of the wall temperature could then occur to
relatively low temperature, depending upon the fluid inside the vessel, depressurisation
rate, and so on.
d.
The heat transfer between vapour and vessel walls is usually much poorer than between a
liquid and the vessel walls. Additionally the thermal capacity of all but the highest pressure
gas is much lower than that of the vessel walls and temperature depressurising effects on
vessel walls containing only vapour are generally small and only of concern if the pressure
is very high (greater than 100 bar (1,450 psi)), or the vessel is normally operated at subambient temperatures. Heat transfer downstream of the depressurisation valve can be
sufficiently high that an internal sleeve, providing a convective separation gap between the
depressurised fluid and outer pipe wall, may often be required.
Page 34 of 38
B.3
B.4
Vessel contents
a.
Vessel fluid cooling comes from expansion of the contained gas and the liquid standard
enthalpy change of vaporisation (or heat of vaporisation). In processes where the liquid
phase is relatively non-volatile, the minimum temperature is experienced when vapour
volume is greater. Therefore, when using Methods 2 to 4 below, the lowest reasonable
liquid level (with maximum vapour volume) should be considered to accurately calculate
the expected minimum temperature.
b.
If the vessel liquid boils (or vapourises) significantly as pressure is reduced, such as in the
pressurised storage of pure gases as liquids, then the minimum possible temperature could
be experienced at maximum liquid levels, or it could be insensitive to liquid level. If
significant liquid vaporisation occurs, calculations should be done at both the reasonably
highest and lowest liquid levels that may occur in the vessel.
Method 1
a.
b.
B.5
B.6
GP 44-25
Guidance on Practice for Depressurisation
2.
3.
To perform this type of calculation, vessel contents are depressurised isenthalpically using
a process simulator such as HYSYS. The ensuing fluid temperature is taken to be the
minimum wall temperature.
Method 2
a.
In this method, the thermal mass of the vessel is taken into account. The heat transfer from
the vessel wall in contact with the liquid is assumed to be infinite, so that the liquid
contents of the vessel and the wetted wall are at the same temperature.
b.
The contents of the vessel are to be depressurised in steps corresponding to given small
temperature drops.
1.
2.
The height of liquid before each depressurising stage is calculated from the liquid
fraction.
3.
The thermal capacity of the wetted vessel walls is calculated, and the heat lost from
the vessel walls over the fall in temperature is added to the internal energy of the
vessel contents.
4.
The vessel is depressurised until the fluid temperature drop reaches the required
figure.
5.
The amount of vapour considered in the model is reduced so that the volume of fluid
corresponds to the vessel volume.
6.
7.
Return to stage 1 until the vessel pressure is down to the required figure.
Method 3
a.
This method is used for vapour filled vessels and also for vessels partially filled with liquid
where the liquid is removed before significant depressurising occurs. The method is similar
Downloaded Date: 6/17/2008 11:12:31 PM
The latest update of this document is located in the BP ETP and Projects Library
Page 35 of 38
GP 44-25
Guidance on Practice for Depressurisation
in theory to Method 2, but heat transfer between the fluid and the vessel is finite and either
calculated or estimated before depressurising starts. There are different heat transfer
coefficients for thermal flux into the liquid and vapour, and it may prove necessary to
recalculate the heat transfer coefficient as the depressurising continues. Warming of the
fluid by the vessel walls is now dependent upon the time taken for depressurising.
Therefore the time/ pressure relationship shall be calculated, usually by assuming choked
flow through the venting orifice. The depressurising shall be done in small time steps.
b.
B.7
1.
2.
Liquid height before each depressurising stage is calculated from the liquid fraction.
3.
The vessel is depressurised until the fluid temperature drops to the required value.
4.
5.
Heat flows from the vessel to the liquid and vapour are calculated.
6.
The amount of vapour considered in the model is reduced so that the volume of fluid
corresponds to the vessel volume.
7.
8.
Return to stage 1 until the vessel pressure is down to the required figure.
In practical terms, if liquid is still present in the vessel, the heat capacity of liquids are
much higher than vapour and heat transfer into the gas is generally much less than the
liquid temperature changes.
Method 4
a.
This method is based on the previous method, but entails a detailed analysis of the
temperature profiles within the vessel walls at each de-pressuring stage. This allows the
calculation of vessel wall stresses from the thermal gradients. This greater detail can allow
a lower minimum temperature to be withstood by a metal than would otherwise be
permissible.
b.
The stages are per Method 3 above, except for step 5 which is replaced as follows:
1.
The temperature profile throughout the vessel walls is calculated using a dynamic
finite element or finite difference model of the system.
2.
In a finite element model, the vessel is divided up into sections small enough that the
properties of the section can be assumed to be constant throughout the section. The
most important properties in this case are obviously the heat flows and temperature
gradients. Heat conduction between adjacent sections is calculated by a computer
program, and from this, the new temperature profile is determined.
3.
The finite difference model differs from the finite element model in that it represents
the vessel by a network of points, assigning heat capacities to the points, and thermal
conductivities to the connections between points. Each point corresponds to the centre
of the sections in the finite element model. The differences between the two
representations are more of mathematical and computing concern than of concern to
the engineer. The choice of method probably depends upon the software available to
the engineer.
4.
The number of sections or points depends upon the resolution of the temperature
profile required by the mechanical engineer, and upon the needs of the mathematical
method. If the model is too simple, the assumption that the properties can be assumed
constant across the section is no longer valid. The usual way to determine whether the
model is fine enough is to rerun the model with a finer grid, or smaller sections, and
Downloaded Date: 6/17/2008 11:12:31 PM
The latest update of this document is located in the BP ETP and Projects Library
Page 36 of 38
GP 44-25
Guidance on Practice for Depressurisation
see whether there is any significant change in the results. If there is, then the model
shall be rerun with a yet smaller grid, until two grids give consistent results.
Page 37 of 38
GP 44-25
Guidance on Practice for Depressurisation
Bibliography
th
[1]
Digest of Steels for High Temperature Service, 5 Edition, 1946, published by the Timken Roller
Bearing Company, Canton, Ohio.
[2]
An Evaluation of the Elevated Tensile and Creep-Rupture Properties of Wrought Carbon Steel,
ASTM Data Series DS 11S1, Supplement to Publication DS 11, formerly ASTM STP 180, ISBN
8031-2004-4, January, 1970.
[3]
[4]
Page 38 of 38