Installation Guidelines
1. ODU will be grounded utilizing one of the following connection methods:
a. ODU to existing GND bar on top of Tower, with proper GND values,
(designated for antennas). Under customer responsibility
b. ODU will be connected with proper C-Clamp to required 95mm GND cable
running from lightning rod on top of tower to GND point.
2. A GND bar on top of the tower should be installed by the customer. If is not
available and is not in the customer standards then the second option should be
used after agreement with customer. If not installed and is within standards then
the customer should be responsible for the mentioned.
3. RG-8 GND kits (SI-0391-0) should be installed in the following points
a. Top of tower
b. Cable tray bend from horizontal to vertical
c. Before entrance to equipment room in cases where the distance between
the tower and the equipment room is longer then 5 meter.
Note: If, IF cable is longer then 100m a GND kit will be installed every 50m.
ODU
Lightning
protector
device
IDU
ANT
To GND
Antenna
cable
Lightning
protector
device
Antenna cable