System testing can be considered a pure black box test because it focuses only on the functionality of the system without any knowledge of the internal structure or design.
A PERT chart was drawn for a software project with 5 tasks - T1 (3 weeks), T2 (2 weeks), T3 (3 weeks), T4 (5 weeks) and T5 (2 weeks). T2 and T4 start after T1, T3 starts after T2, and T5 starts after both T3 and T4. The latest start date for T3 is 5 weeks and the slack time for T4 is 0 weeks. Tasks T1, T3 and T4 are on the critical path.
System testing can be considered a pure black box test because it focuses only on the functionality of the system without any knowledge of the internal structure or design.
A PERT chart was drawn for a software project with 5 tasks - T1 (3 weeks), T2 (2 weeks), T3 (3 weeks), T4 (5 weeks) and T5 (2 weeks). T2 and T4 start after T1, T3 starts after T2, and T5 starts after both T3 and T4. The latest start date for T3 is 5 weeks and the slack time for T4 is 0 weeks. Tasks T1, T3 and T4 are on the critical path.
System testing can be considered a pure black box test because it focuses only on the functionality of the system without any knowledge of the internal structure or design.
A PERT chart was drawn for a software project with 5 tasks - T1 (3 weeks), T2 (2 weeks), T3 (3 weeks), T4 (5 weeks) and T5 (2 weeks). T2 and T4 start after T1, T3 starts after T2, and T5 starts after both T3 and T4. The latest start date for T3 is 5 weeks and the slack time for T4 is 0 weeks. Tasks T1, T3 and T4 are on the critical path.
Q1 Do you agree with the following statement System Testing can be considered a pure
black box test. Justify your answer.
Q2 Consider a software project with 5 tasks T1 T5. Duration of the 5 tasks in weeks is 3, 2, 3, 5 and 2 respectively. T2 and T4 can start when T1 is complete. T3 can start when T2 is complete. T5 can start when both T3 and T4 are completed. Draw the PERT chart representation of the project. When is the latest start date of the task T3? What is the slack time of the task T4? Which tasks are on the critical path?