Precision Apparels Imports Inc.

- Time in Action
Date:

Aug-18-2008

Customer:

Town Shoes

Style #:

PAL S09 5211

Requirements:

Date Received by P.A.:

1st Lab Dips /Desklooms

Approved dt 25th July'08

Trims

24th Sept'08

Labels and Tags

24th Sept'08

1st Fit Sample (2-M jumper and 2-M tee)

24th Sept'08

2nd Fit Sample(2-M jumper and 2-M tee if required)

Not Required

Production Fabric

22nd Oct'08

Pre-production Sample (2-M jumper and 2-M tee)

22nd Oct'08

In-house Test Results

22nd Oct'08
*TEST RESULTS MUST BE SENT FOR APPROVAL AS SOON AS PRODUCTION IS FINISHED
Production Sample (2-M jumper and 2-M tee)

22nd Nov'08

Production QC Report (of all sizes and colors)

10th Dec'08

Packing List

5th Dec'08

Shipping:
ETD Date

Dec 15th - 2008

ETA Date

Jan 20 - 2009

P.A. Cancel Date (in Toronto DC)

Date : 2nd Sept'08

Date : 2nd Sept'08

Precision Apparels Imports Inc. - Time in Action


Date:

Aug-18-2008

Customer:

Town Shoes

Style #:

PAM S09 4059

Requirements:

Date Received by P.A.:

1st Lab Dips /Desklooms

Sent on 2nd Aug'08- Await Approval

Trims

24th Oct'08

Labels and Tags

24th Oct'08

1st Fit Sample (2-sz 36)

24th Oct'08

2nd Fit Sample (2-sz 36 if required)

Not Applicable

Production Fabric

22nd Nov'08

Pre-production Sample (2-sz 36)

22nd Nov'08

In-house Test Results


22nd Nov'08
*TEST RESULTS MUST BE SENT FOR APPROVAL AS SOON AS PRODUCTION IS FINISHED
Production Sample (2-sz 36)

10th Jan'09

Production QC Report (of all sizes and colors)

17th Jan'09

Packing List

23rd Jan'09

Shipping:
ETD Date

Feb 05-2009

ETA Date

Mar 10 -2009

P.A. Cancel Date (in Toronto DC)

Date : 2nd Sept'08

Precision Apparels Imports Inc. - Time in Action


Date:
Customer:
Style #:

Requirements:
1st Lab Dips /Desklooms
Trims
Labels and Tags
1st Fit Sample (2-sz 36)
2nd Fit Sample (2-sz 36 if required)
Production Fabric
Pre-production Sample (2-sz 36)

In-house Test Results


*TEST RESULTS MUST BE SENT FOR APPROVAL AS SOON AS PRODUCTION IS FINISHED
Production Sample (2-sz 36)

Production QC Report (of all sizes and colors)


Packing List

Shipping:
ETD Date

ETA Date

P.A. Cancel Date (in Toronto DC)

Date : 2nd Sept'08

mports Inc. - Time in Action


Aug-20-2008
Town Shoes
PAM S09 4060

Date Received by P.A.:


Sent on 2nd Aug'08. Await Approval
24th Oct'08
24th Oct'08
24th Oct'08
Not Required
22nd Nov'08
22nd Nov'08

22nd Nov'08
AL AS SOON AS PRODUCTION IS FINISHED
10th Jan'09

17th Jan'09
23rd Jan'09

Feb 05 - 2009

Mar 08 - 2009