Anda di halaman 1dari 1

INSPECTION AND TEST PLAN FOR POWER AND CONTROL CABLE INSTALLATION

Project Name: Khelvachuri Hepp

Dok. No:

FR.752.38

Yay.Tar.

1/25/2013

Rev. No.

Rev. Tarihi
Point

ctivity

Relevant Document

Inspection / Test Requirements

KESIR
ENGINEERING

CUSTOMER

--

CONTRACTOR

Notes

POWER AND CONTROL CABLE INSTALLATION


* By checking completion of trays enough for cable pulling

Cable route ready for cable installation

Correct cable type and size which is free from damage


installed, as per requirement.

* Verify no undue mechanical stress is applied to cable during installation. *


Verify cable manufacturer's criteria for max. Tension on cables during pulling,
no kinking.
*
Verify correct segregation/layering of cables.
*
Verify correct cable ID.
* Verify correct splicing as per spec.
* Verify min. bending radius of cable as per cable manufacturer

Manufacturer's
instructions

Cable glanding/termination complete

* Verify terminating materials are of specified


type.
.* Verify cable connection tight and secure.

Manufacturer's
instructions

Insulation resistance test and continuity check after


glanding/lugging complete.

* Verify continuity and insulation resistance test complete and conformant.

Manufacturer's
instructions

Cable installation complete

* Verify all inspection and tests complete and conformant.

8
9

10

11
12
13
14
otes

Abbreviations
E : Works Execution

R
Revision
0

: Records review

Modifications

: Witness point
: Hold point

Prepared by

sw : Spot Witness point


A : Approval

Approved by

Date

1/1