Completion System:
Equipment Taq #:
Taq Equipment Type:
No
1
2
3
Description of Item
Check for material in accordance to Project Specification, verify quality and
condition.
Check correct conduit size.
Check conduits are sloped towards the cable tray where their cables are to
enter - wherever this is not possible conduits must be sealed upon completion
of cable pulling.
Check that conduits enter the bottom of the devices wherever possible.
Check the conduit has no sharp edges where cables may be damaged and all
exposed ends have bushings installed.
Check the conduits are adequately supported.
7
8
9
Check to see flexible conduit used where equipment subject to vibration are
present.
Check all conduits laid as per the layout/drawings.
10
OK
N/A
P/L
Remarks:
Name
Date
Signature
ENKA Construction