INSPECTION CHECKLIST

Project Code: IQ347-BAZYAN Combined Cycle Power Plant Project


Completion Area:

Checklist Document Name:


LV/HV AC Motors

Completion System:

Checklist Document Number:


IQ347-300-EL-CHL-00016
Equipment Tag Description:

Equipment Taq #:
Taq Equipment Type:

No

Description of Item

OK

Verify name plate details against data sheet.

Check visible inspection of motor for external damage.

Check all equipment carries the correct circuit identification.

4
5

Check equipment fixings and mountings are secure and no external damage
exists.
Check equipment IP rating.

Motor shaft is free to rotate by hand.

Check earthing conforms to design requirements.

Ensure earthing to motor is connected.

Check all connections are correct, tight and cable markings are fitted.

10

Unused cable entries are blanked off with correct type of plugs.

11

No undue accumulation of dust and dirt.

12

Confirm connection of RTD's or thermistors - if applicable.

13
14

Check terminal box gaskets and seals are present and have been fitted
correctly.
Confirm all bolts are correct and none are missing.

15

On completion of all cable glanding confirm spare entires are correctly plugged.

16

Check all results recorded in attached form (IQ347-300-EL-CHL-00038 or IQ347300-EL-CHL-00039)

N/A

P/L

Remarks:

Name

Date

Signature

Owner / Owners Representative


ENKA QC

ENKA Construction

2015 ENKA naat ve Sanayi A..


All Rights Reserved. Contains confidential information proprietary to ENKA and may not be disclosed to a third-party without ENKA's prior written
permission.