Anda di halaman 1dari 96

Appendix 2

NSRP Refinery and Petrochemical Complex Project


Coarse QRA Bidder 1

Prepared for
Foster Wheeler Energy Ltd
by
ABS Consulting Ltd.

Report No. 2514054 R01


Issue 4
February 2011

Report N . 2514054 R01


Issue 4

DOCUMENT APPROVAL SHEET


Project No:
o

Report N :
Report Title:
Client:
Contact:

2514054
2514054 R01
NSRP Refinery and Petrochemical Complex Project Coarse QRA Bidder 1
Foster Wheeler Energy Ltd
Ken Smith

ABS Consulting Limited


This document and any information or descriptive matter set out herein is subject to copyright and/or design right
ownership.
All rights reserved. No part of this document, nor any information or descriptive matter within it, may be disclosed,
loaned, reproduced, copied, photocopied, translated or reduced to any electronic medium or machine readable form or
used for any purpose whatsoever without the written permission of the Company, except in accordance with established
contract conditions pertaining to the production of this document

ISSUE

DATE

PREPARED

REVIEWED

APPROVED

1
DRAFT

03/02/11

Matthew Hart
(Project Engineer)

Xin Hao
(Project Engineer)

Pradeep Prakash
(Project Manager)

11/02/11

Matthew Hart
(Project Engineer)

Xin Hao
(Project Engineer)

Pradeep Prakash
(Project Manager)

15/02/11

Matthew Hart
(Project Engineer)

Xin Hao
(Project Engineer)

Pradeep Prakash
(Project Manager)

22/02/11

Matthew Hart
(Project Engineer)

Pradeep Prakash
(Project Manager)

Pradeep Prakash
(Project Manager)

24/02/11

Matthew Hart
(Project Engineer)

Pradeep Prakash
(Project Manager)

Pradeep Prakash
(Project Manager)

Page 2 of 96

Report N . 2514054 R01


Issue 4

DOCUMENT REVISION HISTORY


ISSUE

DESCRIPTION

Issue 1
DRAFT

First Draft issue for client comment.

Issue 1

Updated Jetty Area and incorporated client comments from DRAFT.

Issue 2

Incorporated client comments from Issue 1

Issue 3

Incorporated client comments from Issue 2

Issue 4

Removed the future Jetty from the study.

Page 3 of 96

Report N . 2514054 R01


Issue 4

EXECUTIVE SUMMARY

ABS Consulting Ltd (ABSC) preformed a quantitative risk assessment QRA for the proposed NSRP
refinery in Nghi Son, Vietnam for the FEED stage of the project for Foster Wheeler Energy Ltd
(FWEL). The results of the study [14], in addition to the site buildings risks, were used to check the
risks to the nearby villages and the adjacent road users. Based on those risks appropriate actions were
recommended.
Following on from previous work, the Client has now solicited definitive design proposals from
various bidders. This study has assessed the risks to the site buildings for the new proposed layout
from Bidder 1 by updating the previous study [14]. All the previous assumptions remain the same.
The three stage process for BRA is aimed at providing a structured risk assessment such that the
complexity of assessment is commensurate with the magnitude of the problem. Stage 1 is the
occupancy filtering step. At this stage, buildings which are not occupied or are not significant for the
safety of the operation are eliminated from the assessment. For stage II, worst credible consequences
are simulated and the buildings which are unaffected by the modelled hazards or for which simple
mitigations can be designed are eliminated. All the buildings which are occupied or functionally
significant AND are affected by the postulated hazards are then taken to Stage III risk assessment
process where not only the magnitude of the hazard but the frequency is taken into account to
calculate the risks to building occupants. Where risks are higher than the accepted criteria,
mitigations are considered to lower the risks to acceptable levels.
Of the on site buildings, 48 were assessed in the Stage 1 preliminary building screening as being At
Risk, due to their occupancy and functionality requirements.
The building risk assessment concluded that all occupied buildings at this site are shown to have
negligible Individual Risk (IR) due to explosion and fire.
Detailed recommendations for the mitigations for each building considered within the assessment in
Section 7.2 and are based on industry general practice. This risk assessment does not account to any
mitigation that may already be in place such as local deluge or passive fire protection on vessels. In
addition to the risk mitigations outlined, due attention should be paid to ensuring that a robust escape
and evacuation plan is in place within the overall emergency preparedness for the site.
The public risk was analysed on a societal risk perspective by the use of an F-N curve. Societal risk
is a measure of the collective risk to which a certain population is subjected as a whole. It is usually
depicted in form of a so-called FN curve, which shows the frequency (F), that a given number, N
people or more (hence N+) will be exposed to lethal consequences.
Based on the results of the study, it can be seen that there is the potential for thermal heat radiation to
impact the adjacent road. Fire risk (BLEVE) is predicted to affect the neighboring villages. By
inspecting the F-N curves presented previously, it can be seen that the risks to the villagers at the east
side are unacceptable.
Detailed recommendations for the mitigations for each building considered within the assessment in
Section 8 and are based on industry general practice. This risk assessment does not account to any
mitigation that may already be in place such as local deluge or passive fire protection on vessels. In
addition to the risk mitigations outlined, due attention should be paid to ensuring that a robust escape
and evacuation plan is in place within the overall emergency preparedness for the site.
Page 4 of 96

Report N . 2514054 R01


Issue 4

It is recommended that relocation of the villages should be considered as one of the mitigation
options. The risks to the adjacent road, south of the plant, should be mitigated by the use of a 500m
barrier, and if possible traffic control measures.
It should be noted that this QRA presents the hydrocarbon releases risk results only; occupational
risk, non-hydrocarbon events (e.g. dropped objects etc), external events (e.g. structural failure due to
extreme weather, fatigue etc), structural events (e.g. structural failures, etc), and Transportation
accidents are excluded from the scope of this study. It is assumed that the plant and buildings at the
site will be designed to withstand the appropriate seismic loading such that the hydrocarbon release
frequencies are unaffected. In cases where the plant design takes seismic risk into account, it is usual
practice to ignore the seismic considerations from the QRA.

Page 5 of 96

Report N . 2514054 R01


Issue 4

LIST OF ACRONYMS

ABSC

ABS Consulting Ltd

ACPH

Air Changes per Hour

ALARP

As Low As Reasonably Practicable

ARU

Amine Regeneration Unit

BLEVE

Boiling Liquid Expanding Vapour Explosion

BRA

Building Risk Assessment

CAM

Congested area Assessment Methodology

CDU

Crude Distillation Unit

CMU

Concrete Masonry Units

DOM

Design, Operation, Maintenance

ERPG

Emergency Response Planning Guidelines

ESD

Emergency Shutdown

FEED

Front End Engineering and Design

FWEL

Foster Wheeler Energy Limited

GOHDS

Gas Oil Hydrodesulphuriser Unit

HAZID

Hazard Identification

HCDS

Hydrogen Compression and Distribution System

HMU

Hydrogen Manufacturing Unit

HVAC

Heating, Ventilation and Air Conditioning

IR

Individual Risk (or Incident Radiation)

IRPA

Individual Risk Per Annum

InAlk

Indirect Alkylation Units

KEC

Kuwait Export Crude

KHDS

Kerosene Hydrodesulphuriser Unit

LC

Lethal Concentration

LFL

Lower Flammable Limit

LPG

Liquefied Petroleum Gas

LSIR

Location Specific Individual Risk

NAC

Naphtha and Aromatics Complex

NSRP

Nghi Son Refinery and Petrochemical

PHA

Preliminary Hazard Analysis

P&ID

Piping and Instrumentation Diagram

PFD

Process Flow Diagram

Page 6 of 96

Report N . 2514054 R01


Issue 4

PPU

Polypropylene Unit

PRU

Propylene Recovery Unit

QRA

Quantitative Risk Assessment

RHDS

Residue Hydrodesulphuriser Unit

RFCC

Residue Fluid Catalytic Cracker Unit

R2P2

Reducing risks, protecting people

SHU

Selective Hydrogenation

SRU

Sulphur Recovery Unit

SWS

Sour Water Stripper Units

TGT

Tail Gas Treating

UPS

Uninterrupted Power Supply

SCEs

Safety Critical Elements

ppm

parts per million

VCE

Vapour Cloud Explosion

Page 7 of 96

Report N . 2514054 R01


Issue 4

CONTENTS

Page
Document Approval .............................................................................................................. 2
Revision Record ................................................................................................................... 3
Summary .............................................................................................................................. 4
List of Acronyms ................................................................................................................... 6
Contents ............................................................................................................................... 7
List of Tables ........................................................................................................................ 9
List of Figures ..................................................................................................................... 10
List of Appendices ............................................................................................................... 11

INTRODUCTION .........................................................................................................12

GENERAL METHODOLOGY .....................................................................................13

DESCRIPTION OF FACILITY.....................................................................................14

3.1 Plant Description ..................................................................................................................................................... 14


3.1.1
Process Units ................................................................................................................................................... 15
3.1.2
Buildings .......................................................................................................................................................... 16

STAGE 1 ASSESSMENT ...........................................................................................19

4.1 Screening Criterion ................................................................................................................................................. 19


4.1.1
Occupancy Screening ...................................................................................................................................... 19
4.1.2
Functionality Screening ................................................................................................................................... 19
4.2

Stage One Results .................................................................................................................................................... 19

STAGE 2 ASSESSMENT (CONSEQUENCE ANALYSES) .......................................26

5.1 Explosion Analyses .................................................................................................................................................. 26


5.1.1
Credible Explosion Hazards ............................................................................................................................ 26
5.1.2
CAM Assessment ............................................................................................................................................ 26
5.1.3
Review of Hazard Consequences..................................................................................................................... 26
5.2 Fire Analysis ............................................................................................................................................................ 32
5.2.1
Credible Fire Hazards ...................................................................................................................................... 32
5.2.2
Boiling Liquid Expanding Vapour Explosion (BLEVE) Hazards ................................................................... 35
5.3 Toxic Analysis .......................................................................................................................................................... 39
5.3.1
Credible Toxic Hazards ................................................................................................................................... 39
5.3.2
Review of Hazard Consequences..................................................................................................................... 40
5.4

Stage II Screening ................................................................................................................................................... 43

STAGE 3 ASSESSMENT (RISK ANALYSIS) ............................................................43

6.1

Model Development................................................................................................................................................. 43
Page 8 of 96

Report N . 2514054 R01


Issue 4
6.2 SHEPHERD Parameters ........................................................................................................................................ 46
6.2.1
Equipment Count and Leak Frequencies ......................................................................................................... 46
6.2.2
Design, Operation & Maintenance Factors ...................................................................................................... 47
6.2.3
Probability of Emergency Shutdown ............................................................................................................... 47
6.2.4
Building Performance ...................................................................................................................................... 47
6.3 Fire & Toxic Hazard Modelling ............................................................................................................................. 50
6.3.1
Fatality Probabilities ........................................................................................................................................ 50
6.3.2
Ignition Probabilities ....................................................................................................................................... 50
6.3.3
Building Protection Features ........................................................................................................................... 51
6.3.4
Fire Resistance of Buildings ............................................................................................................................ 52
6.3.5
Boiling Liquid Expanding Vapour Explosion (BLEVE) Scenario .................................................................. 53
6.4 Risk Acceptance Criteria ........................................................................................................................................ 53
6.4.1
Individual Risks ............................................................................................................................................... 53
6.5 Evaluation of Building Risks .................................................................................................................................. 55
6.5.1
Explosion Risks ............................................................................................................................................... 55
6.5.2
Fire Risk .......................................................................................................................................................... 70

RISK ASSESSMENT ..................................................................................................79

7.1

On Site Risk ............................................................................................................................................................. 79

7.2 Off-site Risk ............................................................................................................................................................. 85


7.2.1
Villages to the East of the site ......................................................................................................................... 85
7.2.2
Road to the South of the site ............................................................................................................................ 86

CONCLUSIONS & RECOMMENDATIONS ................................................................89

8.1

Buildings at the site ................................................................................................................................................. 89

8.2 Off-site Population .................................................................................................................................................. 93


8.2.1
Villages to the East of the site ......................................................................................................................... 93
8.2.2
Road to the South of the plant ......................................................................................................................... 94

UNCERTAINTY IN QRA .............................................................................................95

10

REFERENCES............................................................................................................96

List of Tables
Table 1 Stage 1 Assessment ........................................................................................................................................... 20
Table 2 - Maximum Credible Explosion Hazard ........................................................................................................... 27
Table 3 - Maximum Credible Fire Hazard ..................................................................................................................... 37
Table 4 Toxic Gas (H2S) Dispersion modelling results for the 150mm hole size ..................................................... 40
Table 5 - Leak Frequencies used within the Process Blocks ......................................................................................... 46
Table 6 - Definition of Shell building types used in SHEPHERD ................................................................................. 47

Page 9 of 96

Report N . 2514054 R01


Issue 4
Table 7 -Vulnerability dependence on damage thresholds............................................................................................ 49
Table 8 - Definition of damage categories ....................................................................................................................... 49
Table 9- Fatality Probabilities from Exposure to Fires and Toxins ............................................................................. 50
Table 10 Immediate Ignition Probabilities .................................................................................................................. 51
Table 11 Delayed Ignition Probabilities ....................................................................................................................... 51
Table 12 - Levels of Building Protection against Fire & Toxic Hazards...................................................................... 52
Table 13 - Thermal Radiation Limits for Structures and Plant ................................................................................... 53
Table 14- Summary Explosion Damage for the 10-4/yr Hazard .................................................................................... 55
Table 15 Frequency of 15kW/m2 at buildings ............................................................................................................. 76
Table 16 - Summary Occupancy Risk Values ................................................................................................................ 79
Table 17 Overall Risk to Functionally Significant Buildings ..................................................................................... 81
Table 18 Recommendations ........................................................................................................................................... 89
Table 19 Recommendations Functional Significant Buildings .................................................................................. 91
Table 20 Recommendations vulnerability ................................................................................................................... 94

List of Figures
Figure 1 - Proposed Location [Image taken from Google Earth] ................................................................................. 14
Figure 2 NSRP Main Plant Plot Plan [6] ..................................................................................................................... 17
Figure 3 NSRP Plant Plot Plan (Jetty area) [7] ........................................................................................................... 18
Figure 4 2nd Stage Buildings .......................................................................................................................................... 25
Figure 5 Maximum Credible Overpressures Main Plant ........................................................................................... 30
Figure 6 Maximum Credible Overpressures Jetty Area ............................................................................................ 31
Figure 7 Maximum Potential Incident Radiation Flux Contours Main Plant.......................................................... 33
Figure 8 Maximum Potential Incident Radiation Flux Contours Jetty Area ........................................................... 34
Figure 9 BLEVE Fireballs Diameters .......................................................................................................................... 36
Figure 10 ERPG Levels ................................................................................................................................................. 41
Figure 11 ERPG Contours for the SRU ....................................................................................................................... 42
Figure 12 SHEPHERD Model Main Plant .................................................................................................................. 44
Figure 13 SHEPHERD model Jetty Area .................................................................................................................... 45
Figure 14 Building vulnerability by type ..................................................................................................................... 48
Page 10 of 96

Report N . 2514054 R01


Issue 4
Figure 15 - Levels of Risk and ALARP ........................................................................................................................... 54
Figure 16 Flammable Gas Frequency across the Main Plant .................................................................................... 58
Figure 17 Flammable Gas Frequency across the Jetty Area ..................................................................................... 59
Figure 18 - Frequency of Overpressure Exceeding 100 mbar Main Plant .................................................................. 60
Figure 19 - Frequency of Overpressure Exceeding 100 mbar Jetty Area .................................................................... 61
Figure 20 - Frequency of Overpressure Exceeding 30 mbar Main Plant .................................................................... 62
Figure 21 - Frequency of Overpressure Exceeding 30 mbar Jetty Area ...................................................................... 63
Figure 22 - Explosion Risk Plot for Building Type B2 Main Plant .............................................................................. 64
Figure 23 - Explosion Risk Plot for Building Type B2 Jetty Area ................................................................................ 65
Figure 24 - Explosion Risk Plot for Building Type B4 Main Plant .............................................................................. 66
Figure 25 - Explosion Risk Plot for Building Type B4 Jetty Area ................................................................................ 67
Figure 26 - Explosion Risk Plot for Building Type B5 Main Plant .............................................................................. 68
Figure 27 - Explosion Risk Plot for Building Type B5 Jetty Area ................................................................................ 69
Figure 28 - Cloud Fire Frequency Contour Plot Main Plant ........................................................................................ 71
Figure 29 - Cloud Fire Frequency Contour Plot Jetty Area ......................................................................................... 72
Figure 30 - Frequency Contour Plot for Heat Flux above 15kW/m2 Main Plant........................................................ 73
Figure 31 - Frequency Contour Plot for Heat Flux above 15kW/m2 Jetty Area ......................................................... 74
Figure 32 BLEVE Risk Plot .......................................................................................................................................... 75
Figure 33 F-N Curve (Villagers only)........................................................................................................................... 85
Figure 34 Total Fire and Explosion Risk Contour Level Main Plant ....................................................................... 87
Figure 35 Total Fire and Explosion Risk Contour Level Jetty Area ......................................................................... 88
Figure 36 Proposed concrete wall and traffic warning/control ................................................................................. 94

Page 11 of 96

Report N . 2514054 R01


Issue 4

INTRODUCTION

ABS Consulting Ltd (ABSC) preformed a coarse quantitative risk assessment (QRA) for the
proposed NSRP refinery in Vietnam for the FEED stage of the project for Foster Wheeler Energy
Ltd (FWEL). The results of the study [14], in addition to the site buildings risks, were used to check
the risks to the nearby villages and the adjacent road users. Based on those risks appropriate actions
were recommended.
Following on from the earlier work, the Client has now solicited definitive design proposals from
various bidders. This study assesses the risks to the site buildings, for the new proposed layout from
Bidder 1 by updating the previous study [14], by incorporating the new information in the risk
model.
For this assessment all the previous assumptions about the process conditions, release frequencies,
ignition probabilities, etc remains the same.
The results of the revised risk assessment study are detailed within this report. Although unchanged
from the previous study [14], for the sake of completeness the general methodology adopted for this
study is described in Section 2. Section 3 provides a general description of the facility. Section 4
presents the results of the Stage 1 assessment. Section 5 deals with the Stage 2 consequence
modelling with Stage 3 risk analysis being covered in Section 6. Section 7 presents the Risk
Assessment, where the risks are compared to the risk acceptance criteria. Section 8 presents the
conclusions and suggests suitable risk mitigation measures for accomplishing them or showing that
the risks are As Low as Reasonably Practicable (ALARP). Finally, discussion on the QRA
uncertainties is presented in Section 9.

Page 12 of 96

Report N . 2514054 R01


Issue 4

GENERAL METHODOLOGY

The methodology adopted for the BRA follows the recommendations of in the American Institute of
Petroleums Recommended Practice API RP 752 [1]. The assessment follows a three step process.
The philosophy of the stepped approach is to perform as simple an analysis as is consistent with the
hazards. For example if the building is not occupied or is not significant from the plant operation
aspect then no further assessment is needed. If the building is occupied or is functionally significant
then the next consideration is to check if the building is subject to a credible hazard and if simple
mitigation is feasible to mitigate the effects. No further assessment is needed if the occupied or
functionally significant building is not subject to a credible major hazard or the effects of the hazard
can be mitigated in a cost effective manner. Where the building is occupied or functionally
significant and is subject to a credible hazard which cannot be easily designed out or mitigated, a risk
assessment is undertaken to check if the risks to the building occupants are acceptable or the
frequency of significant damage to unoccupied but functionally significant building is reasonably
low. Based on the risk assessment, cost effective and proportional mitigation options can be devised.
The QRA has been performed based initially on the three steps of the BRA methodology that are
summarized below:
1.

Stage 1: A screening assessment based on building occupancy and its functional significance.
Only buildings considered to be occupied or functionally significant are taken to the Stage II
assessment. This is generally undertaken by the plant and confirmed by the consultant.

2.

Stage 2: This phase involves analysis of worst credible consequences of the potential hazards
to assess building vulnerability for explosions, fires, flammable and toxic gases. Only
buildings considered to be vulnerable to the assessed hazards need to be taken to the 3rd stage
of assessment.

3.

Stage 3: The 3rd stage of assessment involves calculation of risk to the building occupants and
where risks are high considers risk reduction measures.

4.

In addition to the standard building risk assessment, the risks to the offsite population were
also assessed using the societal risk criteria for which the F-N curves were generated.

The tool used for the stage 2 consequence modelling was Shell FRED V 5.1 which is a suite of Fire,
Release, Explosion and Dispersion models used to predict the consequences of the accidental or
design release of product from process, storage, transport or distribution operations [3].
For the stage III risk assessment Shell SHEPHERD V2.1 was used. The Shell SHEPHERD Risk
Tool forms a family of graphical risk integrators. The tool has been developed to carry out fit-forpurpose Quantified Risk Assessment (QRA) for a broad range of onshore industrial sites such as
Refineries, Gas plants, Chemicals plants, LPG distribution sites, pipeline systems etc. SHEPHERD
is used to systematically build up risk contributions starting from a release and working through
ignition sources to the calculation of the effects of cloud fires, jet fires, toxic gas and explosions.
Escalation to other parts of the plant via vessel failure through explosion over-pressure and/or flame
engulfment is handled automatically. The input required includes the mass flow rate and dispersion
distances to lower flammable limit in process blocks or point sources [4].

Page 13 of 96

Report N . 2514054 R01


Issue 4

DESCRIPTION OF FACILITY

3.1

Plant Description

The NSRP Refinery and Petrochemical Project will process 200,000 BPSD of imported Kuwait
Export Crude (KEC) oil. The fuels section of the refinery includes Residue Hydrodesulphurisation
and Residue Catalytic Cracking as the main upgrading units. The refinery is integrated with
petrochemical production. The Aromatics plant produces Paraxylene and Benzene. A key product
from the Residue Cracker is Propylene which is used to produce Polypropylene product [5].
The products produced include the following:

LPG

Gasoline 92/ 95 RON

Kerosene / Jet A-1

Diesel Premium and Regular

Paraxylene / Benzene

Polypropylene

Sulphur

The refinery is situated in Nghi Son, Tinh Gia District, Thanh Hoa Province, Vietnam (approx. 200
km south of Hanoi) - See Figure 1.

Figure 1 - Proposed Location [Image taken from Google Earth]


The NSRP Project includes all process units and associated utility, offsite and infrastructure facilities
to support the refinery operation.

Page 14 of 96

Report N . 2514054 R01


Issue 4

Complete utility facilities designed to meet the refinerys demands for cooling water, fuels,
power, steam, water, instrument and plant air, inert gas, etc.

Offsite facilities including tankage for feedstocks plus intermediate and final products as well
as systems for import and export of feed and products.

Other offsite facilities including flare, effluent treatment, firewater, interconnecting piping
and pipelines, etc.

Marine facilities include an SPM/ Crude import line and product loading jetties

3.1.1

Process Units

The complex will comprise the following licensed processing blocks:


The following unit description were based on the Refinery Design basis overall [5] supplied by
FWEL.
Refinery Process Units

Crude Distillation Unit (CDU)

LPG Recovery Unit

Saturated LPG Treater Unit

Kerosene Hydrodesulphuriser Unit (KHDS)

Gas Oil Hydrodesulphuriser Unit (GOHDS)

Residue Hydrodesulphuriser Unit (RHDS)

Residue Fluid Catalytic Cracker Unit (RFCC)

Propylene Recovery Unit (PRU)

RFCC LPG Treater Unit

RFCC Light Gasoline Treater Unit

Selective Hydrogenation (SHU) and Indirect Alkylation Units (InAlk)

Hydrogen Manufacturing Unit (HMU) and Hydrogen Compression and Distribution System
(HCDS)

Sour Water Stripper Units (SWS)

Amine Regeneration Unit (ARU)

Sulphur Recovery Unit (SRU) and Tail Gas Treating (TGT)

Petrochemical Process Units

Naphtha and Aromatics Complex (NAC)

Polypropylene Unit (PPU)

Page 15 of 96

Report N . 2514054 R01


Issue 4

Offsite Systems

Crude Oil Import, Storage and Pumping System

Inter Unit Storage and Pumping System

Product Component Storage and Pumping System

Product Storage and Pumping System

Slop Storage and Pumping System

Product Truck Loading System

Sulphur Forming and Storage Unit

Utility Systems

Demineralised water system,

Raw water/potable systems

Cooling water system,

Steam Power generation system,

Flue gas Desulphurisation,

Plant air/Instrument Air System,

Nitrogen System

Fuel Oil System

Fuel Gas System

Flushing oil system

Chemical Supply

Electricity and steam is generated at the Cogeneration plant.


3.1.2

Buildings

In all 59 buildings have been identified on the plant layout (See Figure 2 and Figure 3). On the
previous study [14] ABSC numbered these buildings consecutively from number 1 to number 66. To
allow direct comparison this system has been retained. These buildings are tabulated in Table 1.

Page 16 of 96

Report N . 2514054 R01


Issue 4

Figure 2 NSRP Main Plant Plot Plan [6]

Page 17 of 96

Report N . 2514054 R01


Issue 4

Figure 3 NSRP Plant Plot Plan (Jetty area) [7]

Page 18 of 96

Report N . 2514054 R01


Issue 4

STAGE 1 ASSESSMENT

The scope of the Stage one assessment is to carry out a building screening exercise in order to
eliminate buildings of no safety concern (unoccupied and not functionally significant) from the risk
assessment process.
The stage I screening has been completed by FWEL using the API 752 [1] criteria described below;
4.1

Screening Criterion

4.1.1

Occupancy Screening

For the purposes of occupancy screening a building is considered occupied if the building occupancy
load is 300 or more man-hours per week or if during peak occupancy, 5 people or more are routinely
expected in the building for at least one hour. If this criteria is exceeded the building is selected for
second stage (Stage 2) analysis.
4.1.2

Functionality Screening

A stage-two building evaluation is required if a building is functionally significant. A building is


defined as functionally significant if either:

4.2

People are expected to remain or take refuge in the building during an emergency. Possible
reasons for people to remain in a building include a lack of suitable evacuation options or the
need for occupants to perform emergency shutdown procedures.

The building is required for emergency response, such as fire stations or clinics.

The building is necessary for continued operation of plant units that may be able to continue
to operate or may be unaffected by an incident in another area. This includes control
buildings, process interface buildings (PIBs), or substations that control or provide power to
multiple process units.

The economic impact on operations of loss of buildings is significant.

Stage One Results

A summary of the occupancy details is provided in Table 1 along with whether the building is
functionally critical or required to provide shelter during an emergency. Previously the buildings
were numbered 1 to 66. The building numbering system has been retained within this study to
facilitate a direct comparison. However, please note that numbers 17, 29, 35, 47, 61, 63 and 64 have
not been used as they were either missing on the plot plan [6] or have been revised.
Twelve building are assessed as being occupied and thirty eight as functionally significant. Six
buildings are both occupied and functionally significant. Eleven building have been screened out as
being neither occupied nor functionally significant.
The buildings taken to the second stage of this assessment are shown in Figure 4.

Page 19 of 96

Report N . 2514054 R01


Issue 4

Table 1 Stage 1 Assessment


Project

Peak

Building

Building Name

Occupancy
Occupancy

Number

Total

(hr/week)

5 people or more
Functionally

routinely expected in

Significant

the building for at


least an hour?

High Occupancy
(>300 man-hours
per week)

Carry
Forward
For
Stage 2

Administration Building

172

6880

Yes

Yes

Yes

Yes

Canteen No1

120

6720

Yes

Yes

Yes

Yes

Medical Center

756

Yes

Yes

Yes

Yes

Main Guard House

756

Yes

Yes

Yes

Yes

Central Control Room

90

6260

Yes

Yes

Yes

Yes

CCR Oil Movements

Yes

No

No

No

Laboratory

55

2200

No

Yes

Yes

Yes

Maintenance Workshop

45

3812

No

Yes

Yes

Yes

Warehouse

11

440

No

Yes

Yes

Yes

10

Central Chemical Store

126

No

No

No

No

11

Central Catalyst Store

252

No

No

No

No

Page 20 of 96

Report N . 2514054 R01


Issue 4

Project

Peak

Building

Building Name

Occupancy
Occupancy

Number

12

Canteen No2

13

Total

(hr/week)

5 people or more
Functionally

routinely expected in

Significant

the building for at


least an hour?

High Occupancy
(>300 man-hours
per week)

Carry
Forward
For
Stage 2

120

6720

No

Yes

Yes

Yes

Fire Station

504

Yes

No

Yes

Yes

14

Main Substation SS-M01

Yes

No

No

Yes

15

Emergency Generator

Yes

No

No

Yes

16

Truck Loading Office

160

No

No

No

No

18

SS- U04

Yes

No

No

Yes

19

SS-O04

Yes

No

No

Yes

20

SS- U01

Yes

No

No

Yes

21

SS- P09

Yes

No

No

Yes

22

SS- P07

Yes

No

No

Yes

23

SS-P02

Yes

No

No

Yes

24

SS-P06

Yes

No

No

Yes

Page 21 of 96

Report N . 2514054 R01


Issue 4

Project

Peak

Building

Building Name

Occupancy
Occupancy

Number

Total

(hr/week)

5 people or more
Functionally

routinely expected in

Significant

the building for at


least an hour?

High Occupancy
(>300 man-hours
per week)

Carry
Forward
For
Stage 2

25

SS- P03

Yes

No

No

Yes

26

SS- P04

Yes

No

No

Yes

27

SS- P01

Yes

No

No

Yes

28

SS- P08

Yes

No

No

Yes

30

SS-P05

Yes

No

No

Yes

31

SS-U03

Yes

No

No

Yes

32

SS-O03

Yes

No

No

Yes

33

SS-U02

Yes

No

No

Yes

34

SS-O01

Yes

No

No

Yes

36

ISB-014

Yes

No

No

Yes

37

ISB-013

Yes

No

No

Yes

38

ISB-03

Yes

No

No

Yes

Page 22 of 96

Report N . 2514054 R01


Issue 4

Project

Peak

Building

Building Name

Occupancy
Occupancy

Number

Total

(hr/week)

5 people or more
Functionally

routinely expected in

Significant

the building for at


least an hour?

High Occupancy
(>300 man-hours
per week)

Carry
Forward
For
Stage 2

39

ISB-011

Yes

No

No

Yes

40

ISB-06

Yes

No

No

Yes

41

ISB-05

Yes

No

No

Yes

42

ISB-04

Yes

No

No

Yes

43

ISB-02

Yes

No

No

Yes

44

ISB-12

Yes

No

No

Yes

45

ISB-01

Yes

No

No

Yes

46

ISB-10

Yes

No

No

Yes

48

ISB-08

Yes

No

No

Yes

49

ISB-07

Yes

No

No

Yes

50

ISB-18

Yes

No

No

Yes

51

ISB-17

Yes

No

No

Yes

Page 23 of 96

Report N . 2514054 R01


Issue 4

Project

Peak

Building

Building Name

Occupancy
Occupancy

Number

Total

(hr/week)

5 people or more
Functionally

routinely expected in

Significant

the building for at


least an hour?

High Occupancy
(>300 man-hours
per week)

Carry
Forward
For
Stage 2

52

ISB-15

Yes

No

No

Yes

53

ISB-16

Yes

No

No

Yes

54

ISB-19

Yes

No

No

Yes

55

Local Guardhouse No1

252

No

No

No

No

56

Jetty Area Guardhouse

336

No

No

Yes

Yes

57

Operator Shelter No1

No

No

No

No

58

Operator Shelter No2

No

No

No

No

59

Solid Product Warehouse

No

No

No

No

60

Jetty Area Admin/Control Building

21

1442

Yes

Yes

Yes

Yes

62

Jetty Area Workshop

No

No

No

No

65

Jetty Area Storage Building

No

No

No

No

66

Crude Oil Terminal Spares Warehouse

No

No

No

No

Page 24 of 96

Report N . 2514054 R01


Issue 4

Figure 4 2nd Stage Buildings

Page 25 of 96

Report N . 2514054 R01


Issue 4

STAGE 2 ASSESSMENT (CONSEQUENCE ANALYSES)

5.1

Explosion Analyses

5.1.1

Credible Explosion Hazards

The flammable gas accumulating in a congested region and subsequent delayed ignition results in an
explosion. So for an explosion to occur there should be a source of flammable release near a
congested area. Considering both the PFD and the plot plan, the following potential sources of
explosion were identified for explosion consequence modeling.
CDU
LPG Recovery and Treater Unit
KHDS
GOHDS
RHDS
RFCC
PPU
SHU and Ind Alk
HMU
HCDS
NAC
Berth Area
Tanks pumping system
Fuel gas system

5.1.2

CAM Assessment

For the congested areas in the Aromatics Complex, RFCC Unit and Hydrogen Manufacturing plant,
the parameters were derived using Shells guidelines and based upon the plot plans provided. For the
remaining units an engineering judgment was use to set this parameters as more detailed plot plants
werent available at the time of this assessment.
5.1.3

Review of Hazard Consequences

The maximum credible overpressure and impulse for each building is provided in Table 2.

Page 26 of 96

Report N . 2514054 R01


Issue 4

Table 2 - Maximum Credible Explosion Hazard


Building

Building Name

Number

Overpressure

Impulse

(psi)

(psi-ms)

Administration Building

0.4

20

Canteen No1

0.3

18

Medical Center

0.3

17

Main Guard House

0.3

18

Central Control Room

0.6

29

Laboratory

0.4

24

Maintenance Workshop

0.7

31

Warehouse

0.6

29

12

Canteen No2

0.4

22

13

Fire Station

0.4

24

14

Main Substation

3.2

94

15

Emergency Generator

1.5

58

18

SS- U04

0.6

25

19

SS-O04

3.2

94

20

SS- U01

43.5

761

21

SS- P09

37.7

725

22

SS- P07

20.3

580

23

SS-P02

10.2

236

24

SS-P06

23.2

471

25

SS- P03

13.8

326

26

SS- P04

0.4

20

Page 27 of 96

Report N . 2514054 R01


Issue 4

Building

Building Name

Number

Overpressure

Impulse

(psi)

(psi-ms)

27

SS- P01

7.3

181

28

SS- P08

7.0

44

30

SS-P05

6.4

145

31

SS-U03

2.3

109

32

SS-O03

0.6

31

33

SS-U02

2.0

47

34

SS-O01

1.2

34

36

ISB-014

2.6

87

37

ISB-013

43.5

1233

38

ISB-03

16.0

290

39

ISB-011

58.0

1305

40

ISB-06

21.8

580

41

ISB-05

21.8

580

42

ISB-04

8.7

160

43

ISB-02

2.0

80

44

ISB-12

7.0

174

45

ISB-01

7.3

181

46

ISB-10

8.0

181

48

ISB-08

3.8

174

49

ISB-07

4.6

145

50

ISB-18

1.0

44

51

ISB-17

7.3

181

Page 28 of 96

Report N . 2514054 R01


Issue 4

Building

Building Name

Number

Overpressure

Impulse

(psi)

(psi-ms)

52

ISB-15

7.0

44

53

ISB-16

0.6

31

54

ISB-19

1.5

36

56

Jetty Area Guard House

0.1

60

Jetty Area Admin/Control Building

0.1

Figure 5 and Figure 6 shows the maximum credible overpressure values.

Page 29 of 96

Report N . 2514054 R01


Issue 4

Figure 5 Maximum Credible Overpressures Main Plant

Page 30 of 96

Report N . 2514054 R01


Issue 4

Figure 6 Maximum Credible Overpressures Jetty Area

Page 31 of 96

Report N . 2514054 R01


Issue 4

5.2

Fire Analysis

5.2.1

Credible Fire Hazards

The following list summarises the main potential fire sources for fire consequence modeling:
CDU
LPG Recovery and Treater Unit
KHDS
GOHDS
RHDS
RFCC
PPU
SHU and Ind Alk
HMU
HCDS
NAC
Berth Area
Storage Tanks and pumping system
Spheres
Propane loading
Fuel Gas system
Figure 7 and Figure 8 show the maximum potential incident radiation flux contours.

Page 32 of 96

Report N . 2514054 R01


Issue 4

Figure 7 Maximum Potential Incident Radiation Flux Contours Main Plant

Page 33 of 96

Report N . 2514054 R01


Issue 4

Figure 8 Maximum Potential Incident Radiation Flux Contours Jetty Area

Page 34 of 96

Report No. 2514054 R01


Issue 4

5.2.2

Boiling Liquid Expanding Vapour Explosion (BLEVE) Hazards

The potential BLEVE hazards identified are listed below. A consequence modeling has been
undertaken for these BLEVE scenarios.
Product storage (Spheres)
LPG Loading
True BLEVEs are associated with liquid gases such as propane which are stored as liquid by keeping
them under pressure at temperatures far in excess of the boiling points of the material. For example
the boiling point of propane is -42oC. Being kept at an ambient temperature of 30oC represents a very
large temperature difference for this liquid. Therefore, an increase in the temperature for the liquid
from a relatively small fire would tend to rapidly increase the pressure as the material tries to return
to a gaseous state. The material could go into a superheated state, and, given the sudden loss of
containment when the shell of the containing vessel fails due to the applied heat load and loss of
strength, the superheated liquid would instantly vaporize causing a rapid expansion in volume (of the
order of 100s of times the liquid volume) giving rise to the fireball that is inherent in the BLEVE
event.
The maximum fireball diameter contours are show in Figure 9.

Page 35 of 96

Report No. 2514054 R01


Issue 4

Figure 9 BLEVE Fireballs Diameters

Page 36 of 96

Report N . 2514054 R01


Issue 4

A summary of the Maximum Incident Radiation flux from the modeled fire scenarios for each
building is given in Table 3.
Table 3 - Maximum Credible Fire Hazard
Max. Incident

Building

Building Name

Number

Radiation
2

(kW/m )

Administration Building

Negligible

Canteen No1

Negligible

Medical Center

Negligible

Main Guard House

Negligible

Central Control Room

Laboratory

Maintenance Workshop

Warehouse

12

Canteen No2

Negligible

13

Fire Station

Negligible

14

Main Substation SS-M01

11

15

Emergency Generator

11

18

SS- U04

19

SS-O04

Negligible

20

SS- U01

23

21

SS- P09

>50

22

SS- P07

>50

23

SS-P02

>50

24

SS-P06

>50

4
Negligible

Page 37 of 96

Report N . 2514054 R01


Issue 4

Max. Incident

Building

Building Name

Number

Radiation
2

(kW/m )

25

SS- P03

>50

26

SS- P04

>50

27

SS- P01

>50

28

SS- P08

>50

30

SS-P05

>50

31

SS-U03

23

32

SS-O03

>50

33

SS-U02

>50

34

SS-O01

36

ISB-014

37

ISB-013

>50

38

ISB-03

>50

39

ISB-011

>50

40

ISB-06

>50

41

ISB-05

>50

42

ISB-04

>50

43

ISB-02

>50

44

ISB-12

>50

45

ISB-01

>50

46

ISB-10

>50

48

ISB-08

>50

Page 38 of 96

Report N . 2514054 R01


Issue 4

Max. Incident

Building

Building Name

Number

5.3

Radiation
2

(kW/m )

49

ISB-07

>50

50

ISB-18

>50

51

ISB-17

>50

52

ISB-15

53

ISB-16

20

54

ISB-19

>50

56

Local Guardhouse Jetty Area

60

Jetty Area Admin/Control Building

Negligible
4

Toxic Analysis

5.3.1

Credible Toxic Hazards

The following list summarises the locations of potential sources for toxic gas release and thus
included in consequence modeling:
CDU
SWS
ARU
SRU
RFCC
GOHDS
KHDS
RHDS

Page 39 of 96

Report N . 2514054 R01


Issue 4

5.3.2

Review of Hazard Consequences

The hazard distances for toxic H2S gas from maximum credible release scenarios were calculated for
each of the three Emergency Response Planning Guide (ERPG) values and are provided in Table 4.
Table 4 Toxic Gas (H2S) Dispersion modelling results for the 150mm hole size
Downwind distance (m)

Unit

ERPG1

ERPG2

ERPG3

(0.1 ppm)

(30 ppm)

(100 ppm)

D5 Weather

F2 Weather

D5 Weather

F2 Weather

D5 Weather

F2 Weather

24723

106764

1702

10831

826

4252

1398

6664

1398

6664

672

2857

1089

7809

39

55

33

48

25294

106764

902

3700

446

1710

25551

106764

1089

9182

540

3700

35256

106764

2378

18031

1126

6664

GOHDS014

18031

106764

720

2537

330

440

KHDS 013

25551

106764

880

4252

410

960

CDU 010

18031

106764

720

2537

330

440

ARU 084

24723

106764

1702

10831

826

4252

RHDS 020

47641

106764

2149

21449

999

7809

SRU
086/087/088

RFCC 020

SWS 080

Note: The dispersion modeling was performed for two Pasquill-Gifford categories:

D5: atmospheric stability class D with 5m/s wind speed.

F2: atmospheric stability class F with 2m/s wind speed.

The Emergency Response Planning Guidelines (ERPGs) are intended to be a planning tool to help
anticipate human adverse health effects to the general public caused by toxic chemical exposure.
The ERPGs are three-tiered guidelines, with a common denominator: 1 hour exposure duration. The
levels are defined as follows in Figure 10:

Page 40 of 96

Report N . 2514054 R01


Issue 4

Figure 10 ERPG Levels


In this assessment the AIHA ERPG-2008 values were adopted to investigate the potential for off-site
adverse effects to humans due to toxic H2S exposure [10].

ERPG-1: 0.1 ppm

ERPG-2: 30 ppm

ERPG-3: 100 ppm

Figure 11 shows the ERPG-2 and 3 contours to the Amine Acid gas on the SRU unit considering a
150mm hole size release for D5 condition.

Page 41 of 96

Report N . 2514054 R01


Issue 4

Figure 11 ERPG Contours for the SRU

Page 42 of 96

Report N . 2514054 R01


Issue 4

5.4

Stage II Screening

From the review of the credible hazards modeled, it is apparent that most of the buildings taken to
stage II screening are subject to significant fire and /or explosion hazard. Conservatively therefore
all the buildings considered in the stage II assessment have been retained for the Stage III risk
assessment.
6
6.1

STAGE 3 ASSESSMENT (RISK ANALYSIS)


Model Development

The SHEPHERD model was updated using the plot plans [6].
The mass and energy balance was used to define the process condition within each of the main plant
items so that process specific fluid could be used in the consequence assessment.
The plot plans and other documents were used to define the process areas for the QRA and also used
to define the congested areas.
A plot of the SHEPHERD model is given in Figure 12 and Figure 13. The offsite area to the west,
South and East are termed areas A, B and C respectively.

Page 43 of 96

Report N . 2514054 R01


Issue 4

Figure 12 SHEPHERD Model Main Plant

Page 44 of 96

Report N . 2514054 R01


Issue 4

Figure 13 SHEPHERD model Jetty Area

Page 45 of 96

Report N . 2514054 R01


Issue 4

6.2
6.2.1

SHEPHERD Parameters
Equipment Count and Leak Frequencies

The main plant items were identified and grouped depending on the fluid composition, with process
pressure and process temperature in the same order of magnitude into process blocks, which were
entered into the Shell SHEPHERD model. The model uses the Multiple Object as a single place
holder for defining more than one process block in the model to reduce the number of physical
objects drawn in the model. Using the generic parts count (e.g. vessels or compressors), a
distribution of flanges and connections etc are applied internally within the SHEPHERD model
based on a distribution defined by Shell. Each of the flanges, connections and fittings etc associated
with a generic piece of equipment thus provides the leak source and associated frequency.
The leak frequencies are generally based on the generic data from the Hydrocarbon Leak and
Ignition Database, EP Forum Risk Assessment Data Directory, EP Forum Report No. 11.8/250, E&P
Forum, (1996) [8].
The leak frequencies for the LPG filling station used are generally accepted on the onshore industry.
A summary of the leak frequencies used is presented in Table 5 below.
Table 5 - Leak Frequencies used within the Process Blocks
Holes
Size

Leak Type

Leak Frequency/
year
Process

LPG

Process Blocks
-4

10mm

Flange Leak

1.5x10

10mm

Seal Leak
(pump)

7x10

25mm

Fitting Leak

2.35x10

50mm

Connection
Leak

3.8x10

Pipe Leak
(*1/D)

3.5x10

100mm

-3

-4

5.2x10
-4

-5

-6

LPG Filling Station


10mm

General

5.22E-01

25mm

General

3.86E-04

50mm

General

4.41E-04

100mm

General

5.17E-02

Page 46 of 96

Report N . 2514054 R01


Issue 4

6.2.2

Design, Operation & Maintenance Factors

The failure rate data applied in the study represents industry average values, although in order to take
plant condition into account within the risk calculation, SHEPHERD allows for the effectiveness of
prevention and shutdown measures to be taken into account. Factors including design, operation and
maintenance (DOM) are considered. A DOM factor is used by SHEPHERD and is applied to
account for the effectiveness of the prevention measures, categorised as high, average or low. In
order to obtain a site-specific failure frequency, the average value is modified using the input
DOM factor. In selecting a low effectiveness, the failure frequency is multiplied by the DOM
factor and divided by the DOM factor for high effectiveness. Hence selecting the average does
not change the failure frequency value.
For the base case quantitative risk assessment, the effectiveness of the design, operation and
maintenance was assumed to be average. Therefore, the industry average failure rate data was used.
6.2.3

Probability of Emergency Shutdown

Inventory isolation time (response time) is assumed to be 20 minutes after start of a release except
for the RFCC for which inventory isolation within 5 minutes with a 50% probability and isolation
following fire detection with a probability of 80% is assumed. This assumption affects the only the
escalation potential, all the releases are modelled.
6.2.4

Building Performance

A number of studies have sought to generate guidance on building damage and collapse, and
consequent fatality rates, for different categories of buildings. Some studies have considered both
the overpressure and impulse resulting from the explosion, while others have only correlated the
effects against the overpressure. Analytical tools have also been developed to assist with this
analysis. The work reported here is based on the results of the 1995 Petroleum and Chemical
Processing Industry Technology Co-operative report on Conventional Building Blast Performance
Capabilities.
API RP-752 [1] defines a set of building classifications included within Shell SHEPHERD
Exceedance, given in Table 6 [4].
Table 6 - Definition of Shell building types used in SHEPHERD
Shell
Building

Description

Type
B1

Wood, temporary buildings, trailers

B2

Steel frame with metal siding

B3

Brick/un-reinforced masonry (load bearing wall)

B4

Steel or concrete frame with masonry fill or cladding

B5

Blast resistant (reinforced concrete)

B6

Brick/moderately reinforced masonry load bearing

Page 47 of 96

Report N . 2514054 R01


Issue 4

Shell
Building

Description

Type
B7

Steel frame building with pre-cast walls and concrete roof


Custom type specify the design free-field overpressure at 100ms

B8

pulse duration

Each building type has its own unique resistance to blast damage. The blast damage resistance of
various building types is shown in Figure 14.
Overpressure Versus Vulnerability
14.0

Peak Incident Overpressure (psi)

12.0

10.0

8.0

B1,B2 & B4
B5
B6
B3

6.0

4.0

2.0

0.0
0

0.2

0.4

0.6

0.8

1.2

Probability of Serious Injury/Fatality

Figure 14 Building vulnerability by type


The Co-Operative has also suggested a relationship between vulnerability and building damage level.
These are given in Table 7.

Page 48 of 96

Report N . 2514054 R01


Issue 4

Table 7 -Vulnerability dependence on damage thresholds


Vulnerability

Damage level
interface

0.01

1/2A

0.1

2A/2B

0.3

2B/3

0.6

3/4

1.0

4/5

The definition of blast damage levels from the Co-Operative study are given in Table 8.
Table 8 - Definition of damage categories
Discrete
damage
level

Brief

Full description

description

Minor
damage

Onset of visible damage. Repairs are only needed


for cosmetic reasons.

Building is reusable

following an explosion.
Localised building damage.

2A

Building performs

Moderate

function and can be used; however, major repairs

damage

are required to restore integrity of structural


envelope. Total cost of repairs is moderate.
Widespread building damage. Building cannot be

2B

Moderate

used until major repairs are completed. Total cost

damage

of repairs is significant, approaching replacement


cost of building.
Building has lost structural integrity and may

Major

collapse due to environmental conditions (i.e.

damage

wind, snow, rain). Total cost of repairs exceeds


replacement cost of building.

Collapse

Building fails completely. Repair not feasible.

Page 49 of 96

Report N . 2514054 R01


Issue 4

Discrete
damage
level
5

6.3

Brief

Full description

description

Annihilation

Occupant survival is not possible.

Fire & Toxic Hazard Modelling

Within the SHEPHERD fire and toxic model a number of user defined probabilities are required
which have an influence on the calculation of the individual risk contours. These are described in the
following sections. As well as these requirements, the model also requires results from the
consequence assessment e.g. mass flow rate, LFL distance and distance to 1% fatalities due to
exposure to a toxic substance.
6.3.1

Fatality Probabilities

The fatality probabilities used for a person located outside are listed in Table 9.
Table 9- Fatality Probabilities from Exposure to Fires and Toxins
Consequence

Fatality Probability
2

Flame engulfment (>50kW/m )

Thermal radiation (>10kW/m )


Toxic Gas

0.7
Based on probit functions published in the
TNO Purple Book (CPR18).
1.9

H2S Probit = -11.5+ln(C t) where t is the


exposure time in minutes set at 30 min and C
3
is the calculated concentration in mg/m .

It is highlighted that the fatality risk from exposure to the effects of fires and toxics will be different
for people depending on the location of the person from the hazard and if they are inside or outside a
building, due to the protection afforded by the building, i.e. lower hazard frequency within the
building. For instance anyone outdoors caught within a flash fire (the LFL envelope) would be killed
(i.e. fatality probability of 1), but if adequately protected from the flames indoors may not be.
6.3.2

Ignition Probabilities

The immediate ignition probabilities adopted in this assessment were derived from Cox Lees and
Ang Classification of Hazardous Locations [9] who have related the probability of ignition of
release of flammable material and discharge rate. These probabilities are those given in Table 10.

Page 50 of 96

Report N . 2514054 R01


Issue 4

Table 10 Immediate Ignition Probabilities


Probability of Ignition
Leak Rate (kg/s)
Gas

Liquid

<1

0.01

0.01

1 50

0.07

0.03

>50

0.30

0.08

A site background ignition probability of 1E-4/m2 of the facility was adopted for this assessment, in
order to address the potential for delayed ignition with the fire modelling. For the offsite urban
location a probability of ignition of 0.25E-4/m2 as suggested by the UKHSE has been adopted. The
additional ignition probability for the road to the south of the site is based on the traffic conditions
assuming that a vehicle represents a probability of ignition of 0.1.
For explosion modelling, the exceedance module has been used which requires a delayed ignition
probability to be specified. The delayed ignition probability used for explosion modelling is given in
Table 11.
Table 11 Delayed Ignition Probabilities
Probability of Ignition
Leak Rate (kg/s)

6.3.3

Gas

Liquid

<1

0.0004

0.0004

1 50

0.008

0.0036

>50

0.09

0.024

Building Protection Features

People located inside buildings will be protected to some extend from external hazards depending on
the type of building construction. These building protection levels are used to modify the probability
of fatality and are explained in Table 12.

Page 51 of 96

Report N . 2514054 R01


Issue 4

Table 12 - Levels of Building Protection against Fire & Toxic Hazards


Protection

Level of protection used

Description

for all buildings


0% (Building Types B1)

Combustible Gas
Protection (%)

This is the effectiveness (%) of the


protection provided against the ingress
of combustible gas.

50% (Building Types


B2,B3,B4,B6+)
90% (Building Type B5)
0% (Building Types B1)

This is the effectiveness (%) of the


Flame Protection

protection provided against jet flame


impingement.

90% (Building Types


B2,B3,B4,B6+)
90% (Building Type B5)
0% (Building Types B1)

This is the effectiveness (%) of the


Flux Protection

protection

provided

against

thermal

radiation.

90% (Building Types


B2,B3,B4,B6+)
90% (Building Type B5)
0 ACPH (Building Types

To estimate the toxic gas concentration

B1)

within a building the number of air


Toxic Gas Protection

changes per hour is required.

This

concentration is used in the probability

2 ACPH (Building Types


B2,B3,B4,B6+)

equation to estimate the fatalities due to


toxic gas exposure

2 ACPH (Building Type


B5)

6.3.4

Fire Resistance of Buildings

Impairment of structural integrity is defined as loss of ability to support the buildings and facilities.
This may be due to loss of stability or structural failure due to fire or explosion.
Accordingly, loss of integrity within one hour of the following is considered:

Structural integrity, including the supporting structure,

Life support integrity, including prevention and mitigation of smoke and gas ingress, and

Command support integrity.

Page 52 of 96

Report N . 2514054 R01


Issue 4

Table 13 provides details of design limits for various types of structure and plant.
Table 13 - Thermal Radiation Limits for Structures and Plant
Thermal Radiation Intensity

Thermal Limit

(kW/m )

37.5

25
18-20

15.6

6.3.5

Intensity at which damage is caused to process equipment and


tanks
Intensity at which non-piloted ignition of wood occurs
Intensity at which cable insulation degrades
Intensity at which operators are unlikely to be performing and
where shelter is unavailable.

14

Intensity which normal buildings should be design to withstand

12

Intensity at which plastics may begin to melt

Boiling Liquid Expanding Vapour Explosion (BLEVE) Scenario

The failure time for the pressurised liquid gas vessel such as product spheres from flame
impingement resulting in a BLEVE was taken as 10 minutes, which is considered to be accepted
practice within the industry.
6.4

Risk Acceptance Criteria

The purpose of risk assessment is to aid decision making and in order to do this some form of criteria
is required. In many cases risk assessment is used for comparative purposes or to identify areas or
scenarios that present the greatest risk so that risk reduction can be carried out in a sensible and cost
effective way. The use of risk assessment, however, must be performed with care, because of the
uncertainties inherent in the assessment. Furthermore there is no clear consensus with respect to the
values of tolerable or unacceptable risks, as this varies between organisations and countries.
The parameter used as a measure of risk in this study is the Individual Risk (IR).
6.4.1

Individual Risks

Individual risks involve the definition of the following elements:

An upper risk level, beyond which risks are deemed unacceptable;

A lower risk level, below which risks are deemed not to warrant concern; and

An intermediate region between the upper and lower levels where risk reduction measures are
required to achieve a level deemed to be As Low As Reasonably Practicable (ALARP).

The ALARP risk review process is illustrated in Figure 15.

Page 53 of 96

Report N . 2514054 R01


Issue 4

INTOLERABLE
LEVEL

UNACCEPTABLE
REGION
(Risk cannot be justified save
in extraordinary circumstances)

Tolerable only if risk reduction is


impracticable or if its cost is
grossly disproportionate to the
improvement gained

ALARP
REGION

Benchmark representing
the standard to be met
by new plant

(Risk is undertaken only if a


benefit is desired)

Tolerable if cost of
reduction would exceed
the improvement gained

BROADLY
ACCEPTABLE
REGION

Necessary to maintain assurance


that risk remains at this level

(No need for detailed working


to demonstrate ALARP)

NEGLIGIBLE RISK

Figure 15 - Levels of Risk and ALARP


This assessment uses the following framework as agreed with FWEL:
For Industrial workers

>10-3/year - Level at which mitigation of risk is required,

Page 54 of 96

Report N . 2514054 R01


Issue 4

>10-3/year but <10-5/year - Level at which risk reduction should be considered


(i.e. ALARP region),

<10-5/year - Level at which further risk reduction need not be considered.

For general population

>10-4/year - Level at which mitigation of risk is required,

>10-4/year but <10-6/year - Level at which risk reduction should be considered


(i.e. ALARP region),

<10-6/year - Level at which further risk reduction need not be considered


6.5

Evaluation of Building Risks

6.5.1

Explosion Risks

The flammable gas frequency for the site is shown in Figure 16 and Figure 17. Figure 18 to Figure
21 show the frequency of exceeding an overpressure of 100 mbar and 30 mbar respectively.
The explosion risk to the workers is dependent on the protection afforded by various building as is
thus dependent on building types. Figure 22 and Figure 23, Figure 24 and Figure 25, Figure 26 and
Figure 27 show the explosion risks to building types B2, B4 and B5 respectively.
All the occupied buildings at this site are shown to have very low explosion risk. Table 14
summarizes the over-pressure and anticipated damage from a 10-4 per year explosion scenario.
Table 14- Summary Explosion Damage for the 10-4/yr Hazard
Building
Number

Building Name

Building

10-4 Peak

classification

Overpressure

(B1-B7)

(psi)

Explosion
Damage (10-4)

Administration Building

B4

0.2

Minor, Level 1

Canteen No1

B4

0.2

Minor, Level 1

Medical Center

B4

0.2

Minor, Level 1

Main Guard House

B4

0.2

Minor, Level 1

Central Control Room

B5

0.3

Minor, Level 1

Laboratory

B4

0.2

Minor, Level 1

Maintenance Workshop

B2

0.3

Minor, Level 1

Warehouse

B2

0.2

Minor, Level 1

12

Canteen No2

B4

0.2

Minor, Level 1

Page 55 of 96

Report N . 2514054 R01


Issue 4

Building

Building Name

Number

Building

10-4 Peak

classification

Overpressure

(B1-B7)

(psi)

Explosion
Damage (10-4)

13

Fire Station

B4

0.2

Minor, Level 1

14

Main Substation

B5

0.4

Minor, Level 1

15

Emergency Generator

B5

0.4

Minor, Level 1

18

SS- U04

B4

0.3

Minor, Level 1

19

SS-O04

B4

0.2

Minor, Level 1

20

SS- U01

B4

0.4

Minor, Level 1

21

SS- P09

B4

1.0

Minor, Level 1

22

SS- P07

B4

1.1

Minor, Level 1

23

SS-P02

B4

1.1

Minor, Level 1

24

SS-P06

B4

0.7

Minor, Level 1

25

SS- P03

B4

0.9

Minor, Level 1

26

SS- P04

B4

3.5

Minor, Level 1

27

SS- P01

B4

0.5

Minor, Level 1

28

SS- P08

B4

0.5

Minor, Level 1

30

SS-P05

B4

0.8

Minor, Level 1

31

SS-U03

B4

0.6

Minor, Level 1

32

SS-O03

B4

0.3

Minor, Level 1

33

SS-U02

B4

0.0

Minor, Level 1

34

SS-O01

B4

0.1

Minor, Level 1

36

ISB-014

B5

0.3

Minor, Level 1

37

ISB-013

B5

0.4

Minor, Level 1

Page 56 of 96

Report N . 2514054 R01


Issue 4

Building

Building Name

Number

Building

10-4 Peak

classification

Overpressure

(B1-B7)

(psi)

Explosion
Damage (10-4)

38

ISB-03

B5

0.9

Minor, Level 1

39

ISB-011

B5

0.9

Minor, Level 1

40

ISB-06

B5

1.5

Minor, Level 1

41

ISB-05

B5

0.8

Minor, Level 1

42

ISB-04

B5

0.8

Minor, Level 1

43

ISB-02

B5

1.7

Minor, Level 1

44

ISB-12

B5

0.5

Minor, Level 1

45

ISB-01

B5

0.5

Minor, Level 1

46

ISB-10

B5

0.5

Minor, Level 1

48

ISB-08

B5

0.6

Minor, Level 1

49

ISB-07

B5

0.8

Minor, Level 1

50

ISB-18

B5

0.6

Minor, Level 1

51

ISB-17

B5

0.2

Minor, Level 1

52

ISB-15

B5

0.1

Minor, Level 1

53

ISB-16

B5

0.3

Minor, Level 1

54

ISB-19

B5

0.0

Minor, Level 1

56

Jetty Area Guard House

B4

0.0

Minor, Level 1

60

Jetty Area Admin/Control Building

B5

0.0

Minor, Level 1

Page 57 of 96

Report N . 2514054 R01


Issue 4

Figure 16 Flammable Gas Frequency across the Main Plant

Page 58 of 96

Report N . 2514054 R01


Issue 4

Figure 17 Flammable Gas Frequency across the Jetty Area

Page 59 of 96

Report N . 2514054 R01


Issue 4

Figure 18 - Frequency of Overpressure Exceeding 100 mbar Main Plant

Page 60 of 96

Report N . 2514054 R01


Issue 4

Figure 19 - Frequency of Overpressure Exceeding 100 mbar Jetty Area

Page 61 of 96

Report N . 2514054 R01


Issue 4

Figure 20 - Frequency of Overpressure Exceeding 30 mbar Main Plant

Page 62 of 96

Report N . 2514054 R01


Issue 4

Figure 21 - Frequency of Overpressure Exceeding 30 mbar Jetty Area

Page 63 of 96

Report N . 2514054 R01


Issue 4

Figure 22 - Explosion Risk Plot for Building Type B2 Main Plant

Page 64 of 96

Report N . 2514054 R01


Issue 4

Figure 23 - Explosion Risk Plot for Building Type B2 Jetty Area

Page 65 of 96

Report N . 2514054 R01


Issue 4

Figure 24 - Explosion Risk Plot for Building Type B4 Main Plant

Page 66 of 96

Report N . 2514054 R01


Issue 4

Figure 25 - Explosion Risk Plot for Building Type B4 Jetty Area

Page 67 of 96

Report N . 2514054 R01


Issue 4

Figure 26 - Explosion Risk Plot for Building Type B5 Main Plant

Page 68 of 96

Report N . 2514054 R01


Issue 4

Figure 27 - Explosion Risk Plot for Building Type B5 Jetty Area

Page 69 of 96

Report N . 2514054 R01


Issue 4

6.5.2

Fire Risk

The frequency of cloud fire, frequency contour plots for heat flux exceeding 15kW/m2 and BLEVE
frequency plots are shown in Figure 28, Figure 29, Figure 30, Figure 31 and Figure 32 respectively.

Page 70 of 96

Report N . 2514054 R01


Issue 4

Figure 28 - Cloud Fire Frequency Contour Plot Main Plant

Page 71 of 96

Report N . 2514054 R01


Issue 4

Figure 29 - Cloud Fire Frequency Contour Plot Jetty Area

Page 72 of 96

Report N . 2514054 R01


Issue 4

Figure 30 - Frequency Contour Plot for Heat Flux above 15kW/m2 Main Plant
Page 73 of 96

Report N . 2514054 R01


Issue 4

Figure 31 - Frequency Contour Plot for Heat Flux above 15kW/m2 Jetty Area

Page 74 of 96

Report N . 2514054 R01


Issue 4

Figure 32 BLEVE Risk Plot

Page 75 of 96

Report No. 2514054 R01


Issue 4

The Individual Risk (IR) from fire for the most exposed person within the occupied buildings was
found to be negligible. This is based on the building being type B2.
Table 15 summarises the frequency of exceeding heat flux of 15kW/m2 at various buildings.
Table 15 Frequency of 15kW/m2 at buildings
Building

Building Name

Number

Freq of 15
kW/m

Administration Building

Negligible

Canteen No1

Negligible

Medical Center

Negligible

Main Guard House

Negligible

Central Control Room

Negligible

Laboratory

Negligible

Maintenance Workshop

Negligible

Warehouse

Negligible

12

Canteen No2

Negligible

13

Fire Station

Negligible

14

Main Substation SS-M01

Negligible

15

Emergency Generator

Negligible

18

SS- U04

Negligible

19

SS - O04

Negligible

20

SS- U01

Negligible

21

SS- P09

3.27E-03

22

SS- P07

2.92E-03

23

SS-P02

1.45E-04

24

SS-P06

2.67E-03

Page 76 of 96

Report No. 2514054 R01


Issue 4

Building

Building Name

Number

Freq of 15
kW/m

25

SS- P03

2.83E-03

26

SS- P04

2.65E-02

27

SS- P01

1.01E-02

28

SS- P08

5.73E-03

30

SS-P05

1.52E-02

31

SS-U03

1.92E-06

32

SS-O03

5.42E-04

33

SS-U02

1.08E-03

34

SS-O01

Negligible

36

ISB-014

Negligible

37

ISB-013

1.72E-06

38

ISB-03

3.38E-03

39

ISB-011

9.62E-04

40

ISB-06

3.47E-03

41

ISB-05

1.99E-04

42

ISB-04

1.99E-04

43

ISB-02

8.23E-03

44

ISB-12

3.62E-06

45

ISB-01

1.01E-02

46

ISB-10

1.10E-03

48

ISB-08

2.98E-03

49

ISB-07

8.27E-03

Page 77 of 96

Report No. 2514054 R01


Issue 4

Building

Building Name

Number

Freq of 15
kW/m

50

ISB-18

3.26E-05

51

ISB-17

1.31E-05

52

ISB-15

Negligible

53

ISB-16

Negligible

54

ISB-19

1.45E-06

56

60

Local Guardhouse No2 (Jetty


Area)
Jetty Area Admin/Control Building

Page 78 of 96

Negligible

Negligible

Report No. 2514054 R01


Issue 4

7
7.1

RISK ASSESSMENT
On Site Risk

This section compares the risks calculated in Section 6 with the acceptance criteria.
Table 16 summarises the occupancy risk for each building on the site and compares it against the
acceptance criteria defined in Section 6.4. It is highlighted that Table 16 includes the risk
contributions for explosion and fire scenarios in order to provide the total risk to particular building
occupants. It is noted that toxic risks for the building occupants at the site are not included in
accordance with the scope of this work.
All the occupied buildings are considered to be exposed to negligible risk from fire and explosion
events. Detailed recommendations for mitigations for each building considered within the assessment
are provided in Section 8 of this report.
Table 16 - Summary Occupancy Risk Values
Building
Number

Building
Building Name

classification

Tolerability

(B1-B7)

Administration Building

B4

Acceptable

Canteen No1

B4

Acceptable

Medical Center

B4

Acceptable

Main Guard House

B4

Acceptable

Central Control Room

B5

Acceptable

Laboratory

B4

Acceptable

Maintenance Workshop

B2

Acceptable

Warehouse

B2

Acceptable

10

Central Chemical Store

B2

Acceptable

11

Central Catalyst Store

B2

Acceptable

12

Canteen No2

B4

Acceptable

13

Fire Station

B4

Acceptable

55

Local Guardhouse No1

B4

Acceptable

Page 79 of 96

Report No. 2514054 R01


Issue 4

Building

Building

Building Name

Number

56

Tolerability

(B1-B7)
Jetty Area Guard House
Jetty Area Admin/Control

60

classification

Building

Page 80 of 96

B4

B5

Acceptable

Acceptable

Report N . 2514054 R01


Issue 4

Table 17 Overall Risk to Functionally Significant Buildings


Building

Building Name

Number

Type

Frequency For

Cloud Fire

Damage > 2B

Frequency

Frequency of flux

Overall

greater than 15

Frequency of

kW/m2

Damage

Overall Risk

26

SS- P04

B4

Negligible

2.06E-03

2.65E-02

2.86E-02

Mitigate

30

SS-P05

B4

Negligible

2.72E-03

1.52E-02

1.79E-02

Mitigate

47

ISB-09

B5

2.90E-06

8.84E-03

8.84E-03

1.77E-02

Mitigate

45

ISB-01

B5

1.00E-06

5.38E-03

1.01E-02

1.55E-02

Mitigate

27

SS- P01

B4

Negligible

5.38E-03

1.01E-02

1.55E-02

Mitigate

49

ISB-07

B5

Negligible

2.57E-03

8.27E-03

1.08E-02

Mitigate

43

ISB-02

B5

Negligible

2.06E-03

8.23E-03

1.03E-02

Mitigate

28

SS- P08

B4

2.00E-05

1.12E-04

5.73E-03

5.86E-03

Mitigate

40

ISB-06

B5

Negligible

2.36E-03

3.47E-03

5.83E-03

Mitigate

21

SS- P09

B4

5.00E-06

1.22E-03

3.27E-03

4.50E-03

Mitigate

24

SS-P06

B4

Negligible

1.54E-03

2.67E-03

4.21E-03

Mitigate

48

ISB-08

B5

Negligible

1.03E-03

2.98E-03

4.01E-03

Mitigate

Page 81 of 96

Report N . 2514054 R01


Issue 4

Building

Building Name

Number

Type

Frequency For

Cloud Fire

Damage > 2B

Frequency

Frequency of flux

Overall

greater than 15

Frequency of

kW/m

Overall Risk

Damage

38

ISB-03

B5

Negligible

5.15E-04

3.38E-03

3.90E-03

Mitigate

22

SS- P07

B4

2.50E-06

5.15E-04

2.92E-03

3.44E-03

Mitigate

25

SS- P03

B4

Negligible

8.40E-05

2.83E-03

2.91E-03

Mitigate

39

ISB-011

B5

Negligible

1.76E-03

9.62E-04

2.72E-03

Mitigate

33

SS-U02

B4

Negligible

8.22E-04

1.08E-03

1.90E-03

Mitigate

46

ISB-10

B5

1.80E-05

1.03E-04

1.10E-03

1.22E-03

Mitigate

32

SS-O03

B4

Negligible

2.84E-07

5.42E-04

5.42E-04

ALARP

41

ISB-05

B5

Negligible

1.52E-04

1.99E-04

3.51E-04

ALARP

42

ISB-04

B5

Negligible

1.52E-04

1.99E-04

3.51E-04

ALARP

23

SS-P02

B4

2.00E-05

8.66E-05

1.45E-04

2.52E-04

ALARP

44

ISB-12

B5

Negligible

1.31E-04

3.62E-06

1.35E-04

ALARP

50

ISB-18

B5

Negligible

2.68E-05

3.26E-05

5.94E-05

ALARP

51

ISB-17

B5

Negligible

2.31E-05

1.31E-05

3.62E-05

ALARP

Page 82 of 96

Report N . 2514054 R01


Issue 4

Building

Building Name

Number

Type

Frequency For

Cloud Fire

Damage > 2B

Frequency

Frequency of flux

Overall

greater than 15

Frequency of

kW/m

Overall Risk

Damage

54

ISB-19

B5

Negligible

1.46E-05

1.45E-06

1.61E-05

ALARP

20

SS- U01

B4

1.30E-05

1.27E-06

3.60E-07

1.46E-05

ALARP

37

ISB-013

B5

Negligible

5.04E-06

1.72E-06

6.76E-06

Acceptable

31

SS-U03

B4

Negligible

3.49E-06

1.92E-06

5.41E-06

Acceptable

19

SS-O04

B4

2.50E-06

Negligible

Negligible

2.50E-06

Acceptable

14

Main Substation SS-M01

B5

Negligible

1.27E-06

Negligible

1.27E-06

Acceptable

15

Emergency Generator

B5

Negligible

1.27E-06

Negligible

1.27E-06

Acceptable

36

ISB-014

B5

1.00E-06

Negligible

Negligible

1.00E-06

Acceptable

53

ISB-16

B5

Negligible

1.54E-08

1.87E-07

2.02E-07

Acceptable

Administration Building

B4

Negligible

Negligible

Negligible

Negligible

Acceptable

Canteen No1

B4

Negligible

Negligible

Negligible

Negligible

Acceptable

Medical Center

B4

Negligible

Negligible

Negligible

Negligible

Acceptable

Main Guard House

B4

Negligible

Negligible

Negligible

Negligible

Acceptable

Page 83 of 96

Report N . 2514054 R01


Issue 4

Building

Building Name

Number

Type

Frequency For

Cloud Fire

Damage > 2B

Frequency

Frequency of flux

Overall

greater than 15

Frequency of

kW/m

Overall Risk

Damage

Central Control Room

B5

Negligible

Negligible

Negligible

Negligible

Acceptable

12

Canteen No2

B4

Negligible

Negligible

Negligible

Negligible

Acceptable

13

Fire Station

B4

Negligible

Negligible

Negligible

Negligible

Acceptable

18

SS- U04

B4

Negligible

Negligible

Negligible

Negligible

Acceptable

34

SS-O01

B4

Negligible

Negligible

Negligible

Negligible

Acceptable

52

ISB-15

B5

Negligible

Negligible

Negligible

Negligible

Acceptable

56

Jetty Area Guard House

B4

Negligible

Negligible

Negligible

Negligible

Acceptable

60

Jetty Area Admin/Control Building

B5

Negligible

Negligible

Negligible

Negligible

Acceptable

Page 84 of 96

Report No. 2514054 R01


Issue 4

7.2

Off-site Risk

7.2.1

Villages to the East of the site

7.2.1.1 Societal Risk


The societal risks are presented in the form of an F-N Curve in Figure 33. The villages are
considered to have approximately 320 dwellings with 5 people each on average. The construction of
the dwellings is assumed to be basic, affording little protection from fire or toxic gas ingress. The FN curve shows that the societal risks to the villages from the NSRP are unacceptable.

Figure 33 F-N Curve (Villagers only)


Note:
The risk levels in the F-N curve are represented as follow (See Section 6.4.2)

Red Region: Unacceptable;

Yellow & Green Region: Acceptable according to UK HSE document R2P2 definition [12];

Green Region: A conservative acceptability criteria used by some companies.

R2P2 states that death of more than 50 people in any incident should be less than 1 in 5000 years.
The F-N curve is constructed by using a slope of -1 from FN pair of 2x10-4, 50 and Nmax of 1000
[12]. The line is represented by the interface between the RED and YELLOW regions of Figure 33,
implying that values within the RED region are unacceptable.
7.2.1.2 Individual Risk
The Location Specific Individual Risk (LSIR) is shown in Figure 34 and Figure 35. The maximum
location specific individual risk (LSIR) at the villages is 5.42x10-3/year. LSIR represents an
individual risk (IR) to an individual who remains at the location at all the time. Considering that the
individual could move to different location from high risk to low risk, an occupancy ratio of 0.5 is
appropriate thus giving an individual risk (IR) of 2.71E-3 per year. This level of risk is considered
unacceptable (>1E-4 is unacceptable for general public). Even if the occupancy ratio is taken as 0.1,
i.e. an individual is only in the high risk area for less than 2.5 hours per day, the risks are still
unacceptable.
Page 85 of 96

Report No. 2514054 R01


Issue 4

It may therefore be concluded that the risk to the villages is unacceptable both from individual risk
and societal risk perspectives.
7.2.2

Road to the South of the site

7.2.2.1 Individual Risk


The Location Specific Individual Risk (LSIR) for the road is shown in Figure 34. The results show
that the maximum LSIR at the road area is 1.88x10-3/year. The occupancy ratio considered for the
road is 0.006 based on the traffic moving at 60 km/hour and any one individual travelling twice a
day, six days per week across the site on this road. Therefore, the maximum individual risk at the
road is 1.13x10-5/year which corresponds to the ALARP region based on the risk tolerability criteria
in Section 6.4. This implies that mitigation measures should be considered to reduce risks as long as
the cost of such measures is not disproportionate to the benefit.

Page 86 of 96

Report N . 2514054 R01


Issue 4

Figure 34 Total Fire and Explosion Risk Contour Level Main Plant

Page 87 of 96

Report N . 2514054 R01


Issue 4

Figure 35 Total Fire and Explosion Risk Contour Level Jetty Area

Page 88 of 96

Report No. 2514054 R01


Issue 4

CONCLUSIONS & RECOMMENDATIONS

8.1

Buildings at the site

The results from this coarse QRA indicate that there are a number of buildings at the site that require
risk reduction measures. This includes 18 buildings where risk mitigation must be undertaken and
10 buildings where risk mitigation should be considered, and implemented as necessary, in order to
demonstrate that the buildings risk status is ALARP. Total fire and explosion risk contour level
The focus of the Risk mitigation is to reduce the likelihood and/or consequences of explosions/Fire
on the site.
Based on this analysis, the following Table 18 provides a summary of recommendations for
refinement of the risk predicted for an area/building or for mitigation of its risk. The
recommendations are presented as General, Explosion and Fire.
Even though the explosion risk at NSRP is low, it is recommended that best industrial practice
should be used and building classification not be downgraded based on the results of this risk
assessment.
Furthermore, a detailed QRA must be undertaken once detailed plant design is in place to confirm or
update the explosion risks in particular which are sensitive to plant congestion but also other risks
which are based on the early plant information. At the detailed QRA stage, it may be possible to take
account of various mitigations in place such as the water deluge, shutdown and blowdown and risk
based inspection and maintenance and regular fugitive emission testing.
Table 18 Recommendations
Ref. No.

Description of Recommendations Options

General Recommendations
Reduce Event Likelihood
L1

Ensure that the design specifications for all plant include performance standards such that plant
failure, and thus hydrocarbon release scenarios, will be minimized through design.

L2

Reduce the hazard magnitude through the installation of gas (toxic and flammable) detectors
with emergency shutdown (ESD) systems within the critical hazard locations. Emergency
shutdown valves to be located outside fire impact zone. If the valve is located inside a
fire/explosion zone then fire proofing is necessary to provide protection for a specified period of
time in line with API 2001.

L3

Minimize the presence of ignition sources around the process units

L4

Where possible, consider leak point minimization for all equipment (e.g. welded, rather than
flanged pipe connections, fail safe valves, spring loaded manual valves, flange covers)

L5

Implement a risk-based inspection (RBI) and maintenance process such that the plant items
that pose the greatest risk to the plant receive the greatest levels of inspection and maintenance

L6

Since there is a risk of an event moving onto the public highway, provisions will need to be in
place to prevent traffic movement on the highway in the event of a site incident.

Page 89 of 96

Report No. 2514054 R01


Issue 4

Ref. No.

Description of Recommendations Options

L7

Toxic and vapour cloud events, generally leave the site periphery it is suggested that a plan will
need to be in place to alert the populations to either end of the plant limit in the event of a site
incident. Such measures will form part of the Site Emergency Response Plan which is to be
detailed during the Detailed design.
Emergency procedures should be put in place and followed if a leak is detected. Good
procedures and training for emergency response are essential.

Reduce Vulnerability
V1

Reduce the vulnerability of the building occupants through the avoidance of windows within
buildings located within the process areas.

V2

Reduce the vulnerability of the building occupants to toxic ingress through the implementation of
toxic gas detection and dampers on the HVAC inlet ducts for putting into recycle as well as
manual shutdown.

Explosion Recommendations

V3

Reduce the vulnerability through relocation of road, provide a barrier between road and plant
(not always effective for blast but prevents missiles) and reduce congestion near the site
boundary.

V4

For buildings with cloud fire frequency >1E-4 p.a., positive pressurisation and double doors
should be provided in the building. LEL detection should also be incorporated into the ventilation
inlets & automatically shutdown the ventilation system providing alarms on LEL detection

V5

For buildings with cloud fire frequency between 1E-4 & 1E-5 p.a. self-closing doors with gas
tight seals should be provided in addition to LEL detection in the ventilation inlets providing
automatic shutdown of the ventilation system and alarms on LEL detection (See Table 28 and
Table 29).

V6

For Buildings with cloud fire frequency between 1E-5 & 1E-6 p.a., self-closing doors with gas
tight seals and LEL monitors alarms and manual HVAC shutdown should be provided.

V7

Buildings should be designed to withstand the 10-4/yr explosion overpressure as a minimum

Fire Recommendations

V8

Reduce the vulnerability of the buildings to flammable gas ingress through the implementation
of flammable gas detection and dampers on the HVAC inlet ducts, self-closing doors with gas
tight seals and LEL monitors, alarms and manual HVAC shutdown should be provided. As given
for explosion

V9

Reduce risk to building occupants from fire by ensuring building has safe refuge areas in case
of fire and /or the building has adequate fire proofing.

V10

Reduce BLEVE risk by insulating vessels, improve depressurisation and vessel deluge.
Depressurized the leaking section using blowdown system.

Toxic Recommendations

Page 90 of 96

Report No. 2514054 R01


Issue 4

Ref. No.

Description of Recommendations Options

T1

The ERPG contours are based on gas dispersion modeling for free field flat terrain. Simple
consequence assessment models used in QRA are not appropriate for dealing with complex
terrain especially for near field effects. It is recommended that a Computational Fluid Dynamics
based H2S dispersion study should be undertaken in the detailed phase of the design to
ascertain the toxic risks and if there are any specific areas where high H2S concentrations
might develop due to the presence of the mountain to the west of the site.

Based on the mitigation options detailed in Table 18, recommendations in respect of explosion risk
for each functional but considered unoccupied building were assessed are provided in Table 19.
Table 19 Recommendations Functional Significant Buildings

Building

Cloud

LEL

Fire Risk

Detection

Manual

Automatic

HVAC

HVAC

Shutdown

Shutdown

Positive
Pressurisation
in building and
double doors

Self Closing
Doors with gas
tight seals

ISB-09

8.84E-03

Yes

No

Yes

Yes

No

SS- P01

5.38E-03

Yes

No

Yes

Yes

No

ISB-01

5.38E-03

Yes

No

Yes

Yes

No

SS-P05

2.72E-03

Yes

No

Yes

Yes

No

ISB-07

2.57E-03

Yes

No

Yes

Yes

No

ISB-06

2.36E-03

Yes

No

Yes

Yes

No

SS- P04

2.06E-03

Yes

No

Yes

Yes

No

ISB-02

2.06E-03

Yes

No

Yes

Yes

No

ISB-011

1.76E-03

Yes

No

Yes

Yes

No

SS-P06

1.54E-03

Yes

No

Yes

Yes

No

SS- P09

1.22E-03

Yes

No

Yes

Yes

No

ISB-08

1.03E-03

Yes

No

Yes

Yes

No

SS-U02

8.22E-04

Yes

No

Yes

Yes

No

SS- P07

5.15E-04

Yes

No

Yes

Yes

No

ISB-03

5.15E-04

Yes

No

Yes

Yes

No

Page 91 of 96

Report No. 2514054 R01


Issue 4

Building

Cloud

LEL

Fire Risk

Detection

Manual

Automatic

HVAC

HVAC

Shutdown

Shutdown

Positive
Pressurisation
in building and
double doors

Self Closing
Doors with gas
tight seals

ISB-05

1.52E-04

Yes

No

Yes

Yes

No

ISB-04

1.52E-04

Yes

No

Yes

Yes

No

ISB-12

1.31E-04

Yes

No

Yes

Yes

No

SS- P08

1.12E-04

Yes

No

Yes

Yes

No

ISB-10

1.03E-04

Yes

No

Yes

Yes

No

SS-P02

8.66E-05

Yes

No

Yes

No

Yes

SS- P03

8.40E-05

Yes

No

Yes

No

Yes

ISB-18

2.68E-05

Yes

No

Yes

No

Yes

ISB-17

2.31E-05

Yes

No

Yes

No

Yes

ISB-19

1.46E-05

Yes

No

Yes

No

Yes

ISB-013

5.04E-06

Yes

No

Yes

No

Yes

SS-U03

3.49E-06

Yes

No

Yes

No

Yes

1.27E-06

Yes

No

Yes

No

Yes

Generator

1.27E-06

Yes

No

Yes

No

Yes

SS- U01

1.27E-06

Yes

No

Yes

No

Yes

SS-O03

2.84E-07

No

Yes

No

No

Yes

ISB-16

1.54E-08

No

Yes

No

No

Yes

No

No

No

No

No

No

No

No

No

No

Main Substation
SS-M01
Emergency

Administration
Building
Canteen No1

Negligible
Negligible

Page 92 of 96

Report No. 2514054 R01


Issue 4

Building

Medical Center

Automatic

HVAC

HVAC

Shutdown

Shutdown

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

No

Cloud

LEL

Fire Risk

Detection

Negligible

Positive

Manual

Pressurisation
in building and
double doors

Self Closing
Doors with gas
tight seals

Main Guard
House

Negligible

Central Control
Room

Negligible

Canteen No2
Fire Station
SS- U04
SS-O04

Negligible
Negligible
Negligible
Negligible

SS-O01

Negligible

ISB-014
ISB-15

Negligible
Negligible

Jetty Area
Guard House

Negligible

Jetty Area
Admin/Control
Building

8.2
8.2.1

Negligible

Off-site Population
Villages to the East of the site

The risk to the villages, both in terms of individual and societal are unacceptable. Assuming that the
site location has been decided, the risk from the NSRP site to the villages are such that reasonable
measures of reducing risks to an acceptable level could be impractical. The Societal risks can be
reduced by reducing the population and reducing the frequency and magnitude of hazards from the
site. However, the risk assessment here does not take account of the fact that the villages are in
wooded area which is susceptible to fire escalation. In light of this, re-location of the villages to a
safer place should be given serious consideration.
Page 93 of 96

Report No. 2514054 R01


Issue 4

8.2.2

Road to the South of the plant

Although the risks to the road users for Bidder 1 option are lower than the FEED study case, the
road is nonetheless too close to the Plant boundary. It is prudent to keep the option of a barrier
between the Plant and the road as well as traffic control measures. The recommendations to reduce
risks to the road users are as follows in Table 20.
Table 20 Recommendations vulnerability
Ref. No.

Description of Recommendations Options

Reduce Vulnerability to Offsite Road to the South

VR1

Reduce the vulnerability by adding a barrier along the high risk part of the plant boundary
between the plant and the road to the south to prevent direct fire impingement and to reduce
heat flux.

VR2

Reduce risk to road users by early warning on leak and closure of access.

It is proposed that a 500m long, 6m high concrete wall designed to withstand 30 mbar side-on
overpressure as shown on Figure 36, together with the traffic control measures should provide
practical mitigation solution.

Control barriers/stop
lights

Concrete Wall 500m (6m high to


withstand 30 mbar overpressure)

Figure 36 Proposed concrete wall and traffic warning/control

Page 94 of 96

Control barriers/stop
lights

Report N . 2514054 R01


Issue 4

UNCERTAINTY IN QRA

There will always be uncertainty as to whether certain events will occur or not, what the immediate
effects will be, and what the consequences for people, environment, or assets may be. This
uncertainty reflects the insufficient information and knowledge available for the analysis, in relation
to technical solutions, operations, and maintenance philosophies, logistic premises etc [13].
Uncertainties in the QRA will derive from the following examples:

Since the design is at FEED stage, the level of detail in the system drawings necessitates the
use of assumptions in terms of the equipment types and volumes.

The distribution of flanges, valves, connections, instruments and pipe sizes are assumed
based on work undertaken by Shell (default values in Shepherd) and are taken to be an
average reflection of the distribution that is to be expected. However, the actual distributions
may vary in the final design.

The consequence modelling of the release scenarios has made some simplifications in terms
of modelling the release of mixed fluids (e.g predominantly liquid material containing gases
that may flash). The analysis of this phenomenon is very complex and as such, the
consequence results for some scenarios are a best representation of the actual scenario.

The flow rates are taken conservatively as the instantaneous release rates. These rates could
be far in excess of the actual mass flow rates of materials through the process segments. This
is considered to be accepted methods of undertaking such studies since the results are on the
side of conservatism. However, if required, such conservatisms could be explored in detail if
considered necessary.

The explosion overpressures are derived from assumed congestion levels based on a simple
2D plant layout drawing and at the time of this assessment only were available for the RFCC,
ARC and HMU units. It is usual to visit the actual site to undertake such assessments of site
congestion. Clearly, this is not possible with a proposed plant; therefore, as the plant design
progresses, the explosion parameters should be re-visited.

A moderate damage to site buildings is assumed if thermal flux exceeds 15kW/m2. For
concrete or masonry infill buildings this is a conservative assumption. However this gives an
estimate as to which buildings should be considered to be at risk from fire and appropriate
insulation measures.

Page 95 of 96

Report N . 2514054 R01


Issue 4

10 REFERENCES
1. Management of hazards associated with location of process plant buildings, API
recommended practice 752, Second Edition, Nov. 2003.
2. HAZID-ENVID Review Report, 3550-8150-RP-0002 Rev.01, 01.05.2009, FWEL
3. FRED v 5.1 Technical manual, 2009.
4. SHEPHERD v2.1 Technical manual, 2009.
5. Refinery Design basis overall 3550-8110-PD-0005 Rev. 01, FWEL.
6. NSRP Refinery and Petrochemical Complex Plot plant, H-000-1225-501_5 REV 5,
FWEL.
7. NRSP Marine Facility Plot plant, 3550-8230-01-0002, FWEL.
8. Hydrocarbon Leak and Ignition Database, EP Forum Risk Assessment Data Directory, EP
Forum Report No. 11.8/250, E&P Forum, 1996.
9. Cox, A. W., Lees, F.W. and Ang M. Lm, Classification of Hazardous Locations,
IChemE, Rugby, England, 1990.
10. American Industrial Hygiene Association ERPG Table, 2008.
11. Frank P Lees, Loss Prevention in Process Industries, 2nd Edition, BH, 1996.
12. HSE, Reducing risks, protecting people - R2P2, 2001.
13. Nicolet-Monnier M. Gheorghe V. Andrian , Topics in Safety, Risk, Reliability and Quality
Quantitative Risk Assessment of Hazardous Material Transport Systems,. Kluwer
Academic Publishers, 1996.
14. NSRP Refinery and Petrochemical Complex Project Coarse QRA, Issue 4 FINAL, Report
No.2204898 R01, ABSC, Sep 2009

Page 96 of 96

Anda mungkin juga menyukai