Section 2.7
Contracts, Specifications,
Quality Assurance and
As-Built Documentation
Contents
The Contents of this Section are as follows:
page
2.7.1
Introduction
2.7.2
2.7.3
2.7.4
Survey Standards
2.7.5
2.7.6
Hastings District Council - Code of Practice for Subdivision and Land Development
Part 2 Section 2.7
November 1997
2.7
2.7.1
Introduction
The previous sections of Part 2 of this Code of Practice have discussed the engineering
standards that Council believes will provide acceptable solutions, but not necessarily the
only solutions, for the engineering works associated with subdivision or land use
projects. Council will require in the Consent Conditions that these projects are properly
documented and certified by an appropriate professional (refer Part 1 of the Code of
Practice).
This section of the Code of Practice will outline Councils requirements in relation to
Construction Conditions of Contract and Specifications, Engineering Drawing
Presentation, Quality Assurance and Inspection, As-Built Documentation and Quality
Assurance Record.
2.7.2
Conditions of Tendering
Type of Contract (e.g., Lump Sum or Measure and Value)
Bonds
Nomination of Engineer to the Contract
Time Extensions
Contract Period
Liquidated Damages
Insurance
Health and Safety
Traffic Management
Quality Plans
Programming of Work
Hastings District Council - Code of Practice for Subdivision and Land Development
Part 2 Section 2.7
November 1997
2.7.3
1:500, 1:250
1:500, 1:250
Detail drawings shall utilise appropriate scales selected from any of the above or at
1:100, 1:50, 1:20 or 1:10.
Draughting standards will comply with
NZS/AS 1100.401 (1984) Technical drawing, Supplement No.3 (Jan 1984) Engineering
Survey and Engineering Survey Design-Sewerage and Water Supply
NZS/AS 1100.401 (1984) Technical drawing, Supplement No.4 (Jan 1984) Engineering
Survey and Engineering Survey Design-Roads
2.7.4
Survey Standards
The following survey standards should be followed during the construction phase of a
roading development.
Hastings District Council - Code of Practice for Subdivision and Land Development
Part 2 Section 2.7
November 1997
(a)
Horizontal
10mm
(b)
Vertical
5mm
Roading Construction
Tolerances from lift pegs or other setting out points, which may include concrete
kerb and channel or a fixed point of concrete kerbing, shall be as shown below.
Reference shall also be made to the Transit New Zealand Specification TNZ B/2
: 1991.
(a)
Width Tolerances
Unconstrained (i.e., no K & C)
Constrained by K & C
(b)
-20mm to + 100mm
0mm to + 20mm
Vertical Tolerances
Kerb and Channel and footpaths
Pavement Layers
Sub-base course
- 5mm to + 5mm
Basecourse
- 5 mm + 15 mm
varies see note 1
Note 1 : Tolerance (i) at or close to the lip of channel - 5mm + 0mm
(ii) at other locations on pavement - 5mm + 15mm
Horizontal
50mm
(b)
Vertical
5mm
Hastings District Council - Code of Practice for Subdivision and Land Development
Part 2 Section 2.7
November 1997
2.7.5
The developer and his/her advisors are responsible for providing Council with
Certifications of:
These must be provided for all engineering works associated with subdivision and land
development, in accordance with Part 2 of this Code of Practice, and Section 4.0 of the
District Plan. The Certification must be prepared by an appropriately qualified
professional.
If Council inspection of the facilities involved is required (in accordance with Sections
2.3, 2.4, 2.5 and 2.6 of this Code of Practice) the Construction documentation shall
ensure that further to Clause 6.4.4 of NZS 3910, the notification of readiness for
inspection, recording, measuring and testing shall not be less than a minimum of 24
hours. Council will undertake any inspections and will advise the developer whether it is
prepared to take responsibility for the development on behalf of the ratepayers of the
Hastings District. Any areas where in the Councils view standards have not been met,
will be notified to the developer for his action before compliance is recommended.
2.7.6
Council will require that the following documents are submitted by the developer with the
required Certification by an appropriate professional (refer Part 1 of this Code of
Practice) when applying for Subdivision Compliance or Code Compliance.
As built drawings of all engineering works including earthworks, stormwater,
sanitary sewer, water supply, and roading and traffic engineering (including subsoil
drainage) to the standards required in Section 2.7.3.
For earthworks the As-builts will record the depth and location of fill, the position,
type and size of any subsoil drains or structures including retaining walls, and the
extent and location of cut batters.
For stormwater and sanitary sewer the As-builts will detail the location of all property
boundaries, pipe diameters and materials used, depths and date of completion,
pumps, valves and control equipment (including manufacturers and date of
manufacture), structures including manholes (giving levels of invert and lid), kerbs
and sumps, and discharge points.
The As-built plans for water supply will detail the location of all property boundaries,
pipes, valves, hydrants and connections (including manufacturers and date of
manufacture), pipe diameters and materials used, depths and date of completion. All
specials made up shall be detailed on these plans. As-built plans of any rural water
supply system and operating instructions shall be lodged with the Hastings District
Council, who in this respect will act as librarian.
Hastings District Council - Code of Practice for Subdivision and Land Development
Part 2 Section 2.7
November 1997
Horizontal
50mm
(b)
Vertical
5mm
A summary of the Quality Assurance records obtained throughout the works will also
be submitted when applying for Subdivision Compliance or Code Compliance. This
will take the form of a report prepared by an appropriately qualified professional. The
report will summarise the Quality Assurance Records and Standards achieved in all
aspects of the project, in particular;
-
Water Supply (refer to Sections 2.5.5 and 2.5.6 of the Code of Practice, in
particular 2.5.5.9 Testing, 2.5.5.10 Cleaning and Disinfection, and 2.5.6
Inspection During Construction)
Roading and Traffic Engineering (refer to Section 2.6.16 of the Code of Practice,
in particular 2.6.16.4, Inspection During Construction).
In addition, if Council is not satisfied with the standard of information provided, any or
all Quality Assurance records must be provided to Council with 24 hours upon
receiving a written request to do so by Council.
Hastings District Council - Code of Practice for Subdivision and Land Development
Part 2 Section 2.7
November 1997