ES EF

2 3 5
2 3 5
LS LF ES EF
4 5 8
3 5 8
LS LF

ES EF
1 0 3
3 0 3 ES EF
LS LF 6 6 7
ES EF 1 7 8
5 5 6 LS LF
1 6 7
ES EF LS LF
3 3 4
1 4 5
LS LF

Critical Path where slack is zero

Activity ES EF LS LF Slack
1 0 3 0 3 0 1----2----4----7
2 3 5 3 5 0
3 3 4 4 5 1
4 5 8 5 8 0
5 5 6 6 7 1
6 6 7 7 8 1
7 8 9 8 9 0
ES EF
7 8 9
1 8 9
LS LF
Previous network with time in weeks
8 ES EF
2 12 20
8 12 20
LS LF 12 ES EF
Crash : 0 4 20 32
500 12 20 32
LS LF
Crash : 0
12 ES EF 7000
1 0 12
12 0 12 ES EF
LS LF 6 24 28
Crash : 0 ES EF 4 28 32
400 5 20 24 LS LF
4 24 28 200
ES EF LS LF
3 12 16 200
4 16 20 Crashing Cost :
LS LF
3000
Critical Path where slack is zero

Activity ES EF LS LF Slack
1 0 12 0 12 0 Critical Path
2 12 20 12 20 0
3 12 16 16 20 4 1 2 ---> 4 ---> --->
4 20 32 20 32 0
5 20 24 24 28 4
6 24 28 28 32 4
7 32 36 32 36 0

Activity Normal Crash Normal Crash Crash cost Allowable


Time(W) Time(W) Cost Cost per week Crash time
1 12 7 3000 5000 400 5
2 8 5 2000 3500 500 3
3 4 3 4000 7000 3000 1
4 12 9 50000 71000 7000 3
5 4 1 500 1100 200 3
6 4 1 500 1100 200 3
7 4 3 15000 22000 7000 1
me in weeks

4 ES EF
7 32 36
4 32 36
LS LF
Crash : 0
7000

7
ES EF ES EF
1 0 8 4 8 13
8 1 9 5 16 21
LS LF LS LF ES EF
8 9 16
7 9 16
LS LF
ES EF ES EF ES EF
Start 2 0 6 5 6 9 9 9 13
6 0 6 3 6 9 4 12 16
LS LF LS LF LS LF
ES EF
6 3 7
4 5 9
ES EF LS LF
3 0 3
3 2 5
LS LF ES EF
7 3 5
2 14 16
LS LF

Critical Path where slack is zero

Activity ES EF LS LF Slack
1 0 8 1 9 1
2 0 6 0 6 0 Critical Path
3 0 3 2 5 2 ---> 2 ---> ---> 5
4 8 13 16 21 8
5 6 9 6 9 0
6 3 7 5 9 2
7 3 5 14 16 11
8 9 16 9 16 0
9 9 13 12 16 3
10 13 17 21 25 8
11 16 25 16 25 0

Activity a m b t б2
1 6 8 10 8 0.44 tp = 25
2 3 6 9 6 1.00 б 2
=
3 1 3 5 3 0.44
4 2 4 12 5 2.78
5 2 3 4 3 0.11
6 3 4 5 4 0.11
7 2 2 2 2 0.00
8 3 7 11 7 1.78
9 2 4 6 4 0.44
10 1 4 7 4 1.00
11 1 10 13 9 4.00
ES EF
10 13 17
4 21 25
LS LF
ES EF
11 16 25 Finish
9 16 25
LS LF

Critical Path
---> ---> 8 ---> ---> 11