28 C-C-ES-106 GROUND FLOOR PLAN POWER ROUTING LAYOUT TOWER C 4-Sep-10 4-Sep-10 14-Sep-10 C O FANAR DESIGN
31 C-A-ES-107 1st PODIUM PLAN POWER ROUTING LAYOUT TOWER A 1-Sep-10 1-Sep-10 14-Sep-10 C O FANAR DESIGN
33 C-C-ES-107 1st PODIUM PLAN POWER ROUTING LAYOUT TOWER C 4-Sep-10 4-Sep-10 14-Sep-10 C O FANAR DESIGN
36 C-A-ES-108 2nd PODIUM PLAN POWER ROUTING LAYOUT TOWER A 1-Sep-10 1-Sep-10 14-Sep-10 C O FANAR DESIGN
38 C-C-ES-108 2nd PODIUM PLAN POWER ROUTING LAYOUT TOWER C 4-Sep-10 4-Sep-10 14-Sep-10 C O FANAR DESIGN
41 C-A-ES-109 3rd LEVEL PLAN POWER ROUTING LAYOUT TOWER A 4-Sep-10 4-Sep-10 14-Sep-10 C O FANAR DESIGN
42 C-B-ES-109 3rd LEVEL PLAN POWER ROUTING LAYOUT TOWER B 7-Oct-10 5-Oct-10 6-Oct-10 C O FANAR DESIGN
43 C-C-ES-109 3rd LEVEL PLAN POWER ROUTING LAYOUT TOWER C 4-Sep-10 4-Sep-10 14-Sep-10 C O FANAR DESIGN
45 C-X-ES-109 3rd LEVEL PLAN POWER ROUTING LAYOUT MASTER 15-Dec-10 4-Nov-10 7-Nov-10 C O FANAR 11/20/2010 DESIGN
47 C-B-ES-110 4th LEVEL PLAN POWER ROUTING LAYOUT TOWER B 7-Oct-10 5-Oct-10 6-Oct-10 C O FANAR DESIGN
49 C-D-ES-110 4th LEVEL PLAN POWER ROUTING LAYOUT TOWER D 5-Oct-10 5-Oct-10 6-Oct-10 C O FANAR DESIGN
50 C-X-ES-110 4th LEVEL PLAN POWER ROUTING LAYOUT MASTER 15-Dec-10 4-Nov-10 7-Nov-10 C O FANAR 11/20/2010 DESIGN
52 C-B-ES-111 5th LEVEL PLAN POWER ROUTING LAYOUT TOWER B 7-Oct-10 5-Oct-10 6-Oct-10 C O FANAR DESIGN
54 C-X-ES-111 5th LEVEL PLAN POWER ROUTING LAYOUT MASTER 15-Dec-10 4-Nov-10 7-Nov-10 C O FANAR 11/20/2010 DESIGN
56 C-B-ES-112 6th LEVEL PLAN POWER ROUTING LAYOUT TOWER B 7-Oct-10 5-Oct-10 6-Oct-10 C O FANAR DESIGN
58 C-D-ES-112 6th LEVEL PLAN POWER ROUTING LAYOUT TOWER D 5-Oct-10 5-Oct-10 6-Oct-10 C O FANAR DESIGN
59 C-X-ES-112 6th LEVEL PLAN POWER ROUTING LAYOUT MASTER 15-Dec-10 4-Nov-10 7-Nov-10 C O FANAR 11/20/2010 DESIGN
61 C-B-ES-113 7th LEVEL PLAN POWER ROUTING LAYOUT TOWER B 7-Oct-10 5-Oct-10 6-Oct-10 C O FANAR DESIGN
63 C-X-ES-113 7th LEVEL PLAN POWER ROUTING LAYOUT MASTER 15-Dec-10 4-Nov-10 7-Nov-10 C O FANAR 11/20/2010 DESIGN
65 C-B-ES-114 8th LEVEL PLAN POWER ROUTING LAYOUT TOWER B 9-Oct-10 5-Oct-10 6-Oct-10 C O FANAR DESIGN
67 C-D-ES-114 8th LEVEL PLAN POWER ROUTING LAYOUT TOWER D 5-Oct-10 5-Oct-10 6-Oct-10 C O FANAR DESIGN
68 C-X-ES-114 8th LEVEL PLAN POWER ROUTING LAYOUT MASTER 15-Dec-10 4-Nov-10 8-Nov-10 C O FANAR 11/20/2010 DESIGN
72 C-X-ES-115 9th LEVEL PLAN POWER ROUTING LAYOUT MASTER 15-Dec-10 4-Nov-10 8-Nov-10 C O FANAR 11/20/2010 DESIGN
76 C-D-ES-116 10th LEVEL PLAN POWER ROUTING LAYOUT TOWER D 5-Oct-10 5-Oct-10 6-Oct-10 C O FANAR DESIGN
77 C-X-ES-116 10th LEVEL PLAN POWER ROUTING LAYOUT MASTER 15-Dec-10 4-Nov-10 8-Nov-10 C O FANAR 11/20/2010 DESIGN
81 C-X-ES-117 11th LEVEL PLAN POWER ROUTING LAYOUT MASTER 15-Dec-10 4-Nov-10 8-Nov-10 C O FANAR 11/20/2010 DESIGN
85 C-D-ES-118 12th LEVEL PLAN POWER ROUTING LAYOUT TOWER D 5-Oct-10 5-Oct-10 6-Oct-10 C O FANAR DESIGN
86 C-X-ES-118 12th LEVEL PLAN POWER ROUTING LAYOUT MASTER 15-Dec-10 4-Nov-10 8-Nov-10 C O FANAR 11/20/2010 DESIGN
90 C-X-ES-119 13th LEVEL PLAN POWER ROUTING LAYOUT MASTER 15-Dec-10 4-Nov-10 8-Nov-10 C O FANAR 11/20/2010 DESIGN
94 C-D-ES-120 14th LEVEL PLAN POWER ROUTING LAYOUT TOWER D 6-Oct-10 5-Oct-10 6-Oct-10 C O FANAR 11/20/2010 DESIGN
95 C-X-ES-121 15th LEVEL PLAN POWER ROUTING LAYOUT MASTER 15-Dec-10 6-Nov-10 8-Nov-10 C O FANAR 11/20/2010 DESIGN
98 C-D-ES-122 16th LEVEL PLAN POWER ROUTING LAYOUT TOWER D 6-Oct-10 5-Oct-10 6-Oct-10 C O FANAR DESIGN
99 C-X-ES-122 16th LEVEL PLAN POWER ROUTING LAYOUT MASTER 15-Dec-10 6-Nov-10 8-Nov-10 C O FANAR 11/20/2010 DESIGN
101 C-X-ES-123 17th LEVEL PLAN POWER ROUTING LAYOUT MASTER 15-Dec-10 4-Nov-10 8-Nov-10 C O FANAR 11/20/2010 DESIGN
104 C-D-ES-124 18th LEVEL PLAN POWER ROUTING LAYOUT TOWER D 6-Oct-10 5-Oct-10 6-Oct-10 C O FANAR DESIGN
105 C-X-ES-124 18th LEVEL PLAN POWER ROUTING LAYOUT MASTER 15-Dec-10 6-Nov-10 8-Nov-10 C O FANAR 11/20/2010 DESIGN
106 C-D-ES-125 19th LEVEL PLAN POWER ROUTING LAYOUT TOWER D 6-Oct-10 5-Oct-10 6-Oct-10 C O FANAR DESIGN
107 C-X-ES-125 19th LEVEL PLAN POWER ROUTING LAYOUT MASTER 15-Dec-10 4-Nov-10 8-Nov-10 C O FANAR 11/20/2010 DESIGN
108 C-D-ES-126 20th LEVEL PLAN POWER ROUTING LAYOUT TOWER D 6-Oct-10 5-Oct-10 6-Oct-10 C O FANAR DESIGN
109 C-X-ES-126 20th LEVEL PLAN POWER ROUTING LAYOUT TOWER D MASTER 15-Dec-10 4-Nov-10 8-Nov-10 C O FANAR 11/20/2010 DESIGN
44 C-D-EP-109 3rd LEVEL PLAN ELECTRICAL POWER LAYOUT TOWER D 25-Oct-10 17-Oct-10 23-Oct-10 C O FANAR INCOOPERATION (SITE+SD)
45 C-X-EP-109 3rd LEVEL PLAN ELECTRICAL POWER LAYOUT MASTER 15-Dec-10 2-Nov-10 7-Nov-10 C O FANAR 11/20/2010 INCOOPERATION (SITE+SD)
49 C-D-EP-110 4th LEVEL PLAN ELECTRICAL POWER LAYOUT TOWER D 19-Oct-10 11-Oct-10 30-Oct-10 C O FANAR INCOOPERATION (SITE+SD)
50 C-X-EP-110 4th LEVEL PLAN ELECTRICAL POWER LAYOUT MASTER 15-Dec-10 2-Nov-10 7-Nov-10 C O FANAR 11/20/2010 INCOOPERATION (SITE+SD)
55 C-X-EP-111 5th LEVEL PLAN ELECTRICAL POWER LAYOUT MASTER 15-Dec-10 2-Nov-10 7-Nov-10 C O FANAR 11/20/2010 INCOOPERATION (SITE+SD)
59 C-D-EP-112 6th LEVEL PLAN ELECTRICAL POWER LAYOUT TOWER D 19-Oct-10 11-Oct-10 30-Oct-10 C O FANAR INCOOPERATION (SITE+SD)
60 C-X-EP-112 6th LEVEL PLAN ELECTRICAL POWER LAYOUT MASTER 15-Dec-10 2-Nov-10 7-Nov-10 C O FANAR 11/20/2010 INCOOPERATION (SITE+SD)
64 C-D-EP-113 7th LEVEL PLAN ELECTRICAL POWER LAYOUT TOWER D 19-Oct-10 11-Oct-10 30-Oct-10 C O FANAR INCOOPERATION (SITE+SD)
65 C-X-EP-113 7th LEVEL PLAN ELECTRICAL POWER LAYOUT MASTER 15-Dec-10 2-Nov-10 7-Nov-10 C O FANAR 11/20/2010 INCOOPERATION (SITE+SD)
69 C-D-EP-114 8th LEVEL PLAN ELECTRICAL POWER LAYOUT TOWER D 20-Oct-10 11-Oct-10 30-Oct-10 C O FANAR INCOOPERATION (SITE+SD)
70 C-X-EP-114 8th LEVEL PLAN ELECTRICAL POWER LAYOUT MASTER 15-Dec-10 2-Nov-10 7-Nov-10 C O FANAR 11/20/2010 INCOOPERATION (SITE+SD)
74 C-D-EP-115 9th LEVEL PLAN ELECTRICAL POWER LAYOUT TOWER D 20-Oct-10 11-Oct-10 30-Oct-10 C O FANAR INCOOPERATION (SITE+SD)
75 C-X-EP-115 9th LEVEL PLAN ELECTRICAL POWER LAYOUT MASTER 15-Dec-10 2-Nov-10 7-Nov-10 C O FANAR 11/20/2010 INCOOPERATION (SITE+SD)
79 C-D-EP-116 10th LEVEL PLAN ELECTRICAL POWER LAYOUT TOWER D 20-Oct-10 11-Oct-10 30-Oct-10 C O FANAR INCOOPERATION (SITE+SD)
80 C-X-EP-116 10th LEVEL PLAN ELECTRICAL POWER LAYOUT MASTER 15-Dec-10 2-Nov-10 7-Nov-10 C O FANAR 11/20/2010 INCOOPERATION (SITE+SD)
84 C-D-EP-117 11th LEVEL PLAN ELECTRICAL POWER LAYOUT TOWER D 20-Oct-10 11-Oct-10 30-Oct-10 C O FANAR INCOOPERATION (SITE+SD)
85 C-X-EP-117 11th LEVEL PLAN ELECTRICAL POWER LAYOUT MASTER 15-Dec-10 2-Nov-10 7-Nov-10 C O FANAR 11/20/2010 INCOOPERATION (SITE+SD)
89 C-D-EP-118 12th LEVEL PLAN ELECTRICAL POWER LAYOUT TOWER D 20-Oct-10 11-Oct-10 30-Oct-10 C O FANAR INCOOPERATION (SITE+SD)
90 C-X-EP-118 12th LEVEL PLAN ELECTRICAL POWER LAYOUT MASTER 15-Dec-10 2-Nov-10 7-Nov-10 C O FANAR 11/20/2010 INCOOPERATION (SITE+SD)
94 C-D-EP-119 13th LEVEL PLAN ELECTRICAL POWER LAYOUT TOWER D 21-Oct-10 11-Oct-10 30-Oct-10 C O FANAR INCOOPERATION (SITE+SD)
95 C-X-EP-119 13th LEVEL PLAN ELECTRICAL POWER LAYOUT MASTER 15-Dec-10 2-Nov-10 7-Nov-10 C O FANAR 11/20/2010 INCOOPERATION (SITE+SD)
96 C-X-EP-120 14th LEVEL PLAN ELECTRICAL POWER LAYOUT MASTER 15-Dec-10 2-Nov-10 7-Nov-10 C O FANAR 11/20/2010 INCOOPERATION (SITE+SD)
99 C-D-EP-120 14th LEVEL PLAN ELECTRICAL POWER LAYOUT TOWER D 21-Oct-10 11-Oct-10 30-Oct-10 C O FANAR INCOOPERATION (SITE+SD)
100 C-X-EP-121 15th LEVEL PLAN ELECTRICAL POWER LAYOUT MASTER 15-Dec-10 2-Nov-10 7-Nov-10 C O FANAR 11/20/2010 INCOOPERATION (SITE+SD)
103 C-D-EP-121 15th LEVEL PLAN ELECTRICAL POWER LAYOUT TOWER D 21-Oct-10 11-Oct-10 30-Oct-10 C O FANAR INCOOPERATION (SITE+SD)
104 C-X-EP-122 16th LEVEL PLAN ELECTRICAL POWER LAYOUT MASTER 15-Dec-10 2-Nov-10 7-Nov-10 C O FANAR 11/20/2010 INCOOPERATION (SITE+SD)
106 C-D-EP-122 16th LEVEL PLAN ELECTRICAL POWER LAYOUT TOWER D 21-Oct-10 11-Oct-10 30-Oct-10 C O FANAR INCOOPERATION (SITE+SD)
CONTRACTOR's PREPARATION & SUBMITTAL STATUS LOG (E1)
KING ABDULLAH FINANCIAL DISCTRICT (5.07 & 5.08)
Contract : CONTRACTOR : ALFANAR MEP PROJECTS 12/20/2010 9:12 DATA DATE : 20-Dec-10 REVISION : 08 ( Based on New Design )
Type of Submittal
ACTION CODE :
" A " - APPROVED
" B " - APPROVED WITH COMMENTS
" C " - REVISED / RESUBMIT
" D " - REJECTED / NO NEED TO SUBMIT
109 C-D-EP-123 17th LEVEL PLAN ELECTRICAL POWER LAYOUT TOWER D 8-Nov-10 11-Oct-10 30-Oct-10 C O FANAR INCOOPERATION (SITE+SD)
111 C-X-EP-124 18th LEVEL PLAN ELECTRICAL POWER LAYOUT MASTER 15-Dec-10 2-Nov-10 7-Nov-10 C O FANAR 11/20/2010 INCOOPERATION (SITE+SD)
113 C-D-EP-125 19th LEVEL PLAN ELECTRICAL POWER LAYOUT TOWER D 23-Oct-10 12-Oct-10 23-Oct-10 C O FANAR INCOOPERATION (SITE+SD)
114 C-X-EP-125 19th LEVEL PLAN ELECTRICAL POWER LAYOUT MASTER 15-Dec-10 2-Nov-10 7-Nov-10 C O FANAR 11/20/2010 INCOOPERATION (SITE+SD)
116 C-D-EP-126 20th LEVEL PLAN ELECTRICAL POWER LAYOUT TOWER D 23-Oct-10 12-Oct-10 23-Oct-10 C O FANAR INCOOPERATION (SITE+SD)
TELEPHONE SYSTEM LAYOUT DRAWINGS__START = 18 APR 2010 ,,, FINISH= 16 DEC 2010 _ _ _ _ _ _ _ _ _ _ _
FIRE ALARM LAYOUT DRAWINGS__START = 18 APR 2010 ,,, FINISH= 15 DEC 2010 _ _ _ _ _ _ _ _ _ _ _
LOW CURRENT SYSTEM LAYOUT__START = 1 SEP 2010 ,,, FINISH= 18 DEC 2010 _ _ _ _ _ _ _ _ _ _ _
IRRIGATION SYSTEM__START = 17 OCT 2010 ,,, FINISH= 18 OCT 2010 _ _ _ _ _ _ _ _ _ _ _
BMS SHOP DRAWINGS__START = 23 OCT 2010 ,,, FINISH= 14 FEB 2011 _ _ _ _ _ _ _ _ _ _ _
1 BMS Riser PLOT 5.07 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
2 TYPICAL FAHU 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
3 AHU W/O E.Heater 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
5 TYPICAL FCU W/O E.Heater(Non occupied spaces) 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
6 TYPICAL FCU W/ E.Heater(Occupied spaces) 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
7 STAIRCASE PRESSURIZATION FAN 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
8 LIFT LOBBY PRESSURIZATION FAN 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
9 SMOKE EXHAUST FAN 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
10 JET FAN 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
11 CYCLONE FANS 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
12 FRESH AIR FANS 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
13 EXHAUST FANS 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
14 KITCHEN EXHAUST FAN 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
15 POTABLE WATER TANK 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
16 MAIN DOMESTIC BOOSTER PUMPS 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
17 W.C FLUSH WATER TANK 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
18 W.C FLUSH WATER BOOSTER 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
19 CREATION TREATMENT WATER SYSTEM 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
20 CHILLED WATER & HEAT EXCHANGE SYSTEM 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
21 BMS Riser PLOT 5.08 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
22 BMS MONITORING OF LOW CURRENT SYSTEMS 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
23 TRANSFORMERS MONITORING BY BMS 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
24 GENERATOR & ATS MONITORING BY BMS 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
25 ELEVATOR GENERATOR MONITORING BY BMS 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
26 ELECTRICAL MAIN DISTRIBUTION PANEL MONITORING BY BMS 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
27 FIRE PUMP SET MONITORING BY BMS 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
28 SUMP PITS MONITORING BY BMS 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
29 LIFT SUMP PITS MONITORING BY BMS 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
30 DEWATERING SUMP PIT 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
31 LIGHTING CONTROL PANEL FOR EXTERNAL LIGHTING 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
32 LIGHTING CONTROL PANEL FOR BASEMENT LIGHTING 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
33 LIGHTING CONTROL PANEL FOR GROUND FLOOR 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
34 LIGHTING CONTROL PANEL FOR TOWER UPPER FLOORS 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
35 LIGHTING CONTROL PANEL FOR TOWER ROOF 23-Oct-10 7-Nov-10 9-Nov-10 C O FANAR 12/1/2010
DRAINAGE LAYOUT SHOP DRAWING__START = 8 AUG 2010 ,,, FINISH= 9 FEB 2011 _ _ _ _ _ _ _ _ _ _ _
45 C-B-PD-109 3rd LEVEL PLAN DRAINAGE LAYOUT TOWER B 16-Dec-10 23-Sep-10 26-Sep-10 C O FANAR
WATER SUPPLY LAYOUT SHOP DRAWING__START = 10 AUG 2010 ,,, FINISH= 12 FEB 2011 _ _ _ _ _ _ _ _ _ _ _
Earthing & Lightning__START = 27 NOV 2010 ,,, FINISH= 22 DEC 2010 _ _ _ _ _ _ _ _ _ _ _
2 C-X-EE-202 Earthing Schematic Diagram - Parcel 5.08 27-Nov-10 25-Nov-10 28-Nov-10 C O FANAR 12/5/2010
3 C-X-EE-203 Lighting Protection Schematic Diagram 27-Nov-10 25-Nov-10 28-Nov-10 C O FANAR 12/5/2010
11 C-A-EE-106 GROUND FLOOR PLAN EARTHING & LIGHTNING PROTECTION LAYOUT PART A 22-Dec-10 7-Dec-10 7-Dec-10 C O FANAR 12/8/2010
12 C-B-EE-106 GROUND FLOOR PLAN EARTHING & LIGHTNING PROTECTION LAYOUT PART B 22-Dec-10 7-Dec-10 7-Dec-10 C O FANAR 12/8/2010
13 C-C-EE-106 GROUND FLOOR PLAN EARTHING & LIGHTNING PROTECTION LAYOUT PART C 22-Dec-10 7-Dec-10 7-Dec-10 C O FANAR 12/8/2010
14 C-D-EE-106 GROUND FLOOR PLAN EARTHING & LIGHTNING PROTECTION LAYOUT PART D 22-Dec-10 7-Dec-10 7-Dec-10 C O FANAR 12/8/2010
15 C-X-EE-106 GROUND FLOOR PLAN EARTHING & LIGHTNING PROTECTION LAYOUT MASTER PLAN 22-Dec-10 7-Dec-10 7-Dec-10 C O FANAR 12/8/2010
CO ORDINATION LAYOUT DRAWINGS__START = 16 OCT 2010 ,,, FINISH= 14 FEB 2011 _ _ _ _ _ _ _ _ _ _ _
1 C-X-CO-102 4th BASEMENT ELECTO MECH CO-ORDINATION LAYOUT Master Plan 24-Oct-10 24-Oct-10 27-Oct-10 C O FANAR
6 C-X-CO-103 3rd BASEMENT ELECTO MECH CO-ORDINATION LAYOUT Master Plan 16-Oct-10 16-Oct-10 23-Oct-10 C O FANAR
Mechanical Riser Drawings__START = 1 JAN 2011 ,,, FINISH= 25 JAN 2011 _ _ _ _ _ _ _ _ _ _
EXHAUST & FRESH AIR LAYOUT SHOP DRAWING__START = 1 SEP 2010 ,,, FINISH= 12 FEB 2011 _ _ _ _ _ _ _ _ _ _
2 C-A-MA-102-1-2 4th BASEMENT PLAN EX & FRESH AIR LAYOUT PART A 1-Sep-10 1-Sep-10 1-Sep-10 C O FANAR
3 C-B-MA-102-1-2 4th BASEMENT PLAN EX & FRESH AIR LAYOUT PART B 1-Sep-10 1-Sep-10 1-Sep-10 C O FANAR
4 C-C-MA-102-1-2 4th BASEMENT PLAN EX & FRESH AIR LAYOUT PART C 1-Sep-10 1-Sep-10 1-Sep-10 C O FANAR
5 C-D-MA-102-1-2 4th BASEMENT PLAN EX & FRESH AIR LAYOUT PART D 1-Sep-10 1-Sep-10 1-Sep-10 C O FANAR
6 C-X-MA-102-1-2 4th BASEMENT PLAN EX & FRESH AIR LAYOUT MASTER 1-Sep-10 1-Sep-10 1-Sep-10 C O FANAR
7 C-A-MA-103-1-2 3rd BASEMENT PLAN EX & FRESH AIR LAYOUT PART A 27-Sep-10 27-Sep-10 C O FANAR
8 C-B-MA-103-1-2 3rd BASEMENT PLAN EX & FRESH AIR LAYOUT PART B 27-Sep-10 27-Sep-10 C O FANAR
9 C-C-MA-103-1-2 3rd BASEMENT PLAN EX & FRESH AIR LAYOUT PART C 27-Sep-10 27-Sep-10 C O FANAR
10 C-D-MA-103-1-2 3rd BASEMENT PLAN EX & FRESH AIR LAYOUT PART D 27-Sep-10 27-Sep-10 C O FANAR
11 C-X-MA-103-1-2 3rd BASEMENT PLAN EX & FRESH AIR LAYOUT MASTER 27-Sep-10 27-Sep-10 C O FANAR
12 C-A-MA-104-1-2 2nd BASEMENT PLAN EX & FRESH AIR LAYOUT PART A 25-Sep-10 25-Sep-10 C O FANAR
13 C-B-MA-104-1-2 2nd BASEMENT PLAN EX & FRESH AIR LAYOUT PART B 25-Sep-10 25-Sep-10 C O FANAR
14 C-C-MA-104-1-2 2nd BASEMENT PLAN EX & FRESH AIR LAYOUT PART C 25-Sep-10 25-Sep-10 C O FANAR
15 C-D-MA-104-1-2 2nd BASEMENT PLAN EX & FRESH AIR LAYOUT PART D 25-Sep-10 25-Sep-10 C O FANAR
16 C-X-MA-104-1-2 2nd BASEMENT PLAN EX & FRESH AIR LAYOUT MASTER 25-Sep-10 25-Sep-10 C O FANAR
SUPPLY AIR & CHILLED WATER LAYOUT SHOP DRAWING__START = 1 SEP 2010 ,,, FINISH= 13 FEB 2011 _ _ _ _ _ _ _ _ _ _
1 C-A-MA-102-1-1 4th BASEMENT PLAN SUP AIR & CHW LAYOUT PART A 1-Sep-10 1-Sep-10 1-Sep-10 C O FANAR
2 C-B-MA-102-1-1 4th BASEMENT PLAN SUP AIR & CHW LAYOUT PART B 1-Sep-10 1-Sep-10 1-Sep-10 C O FANAR
3 C-C-MA-102-1-1 4th BASEMENT PLAN SUP AIR & CHW LAYOUT PART C 1-Sep-10 1-Sep-10 1-Sep-10 C O FANAR
4 C-D-MA-102-1-1 4th BASEMENT PLAN SUP AIR & CHW LAYOUT PART D 1-Sep-10 1-Sep-10 1-Sep-10 C O FANAR
5 C-X-MA-102-1-1 4th BASEMENT PLAN SUP AIR & CHW LAYOUT MASTER 1-Sep-10 1-Sep-10 1-Sep-10 C O FANAR
6 C-A-MA-103-1-1 3rd BASEMENT PLAN SUP AIR & CHW LAYOUT PART A 27-Sep-10 27-Sep-10 C O FANAR
7 C-B-MA-103-1-1 3rd BASEMENT PLAN SUP AIR & CHW LAYOUT PART B 27-Sep-10 27-Sep-10 C O FANAR
8 C-C-MA-103-1-1 3rd BASEMENT PLAN SUP AIR & CHW LAYOUT PART C 27-Sep-10 27-Sep-10 C O FANAR
9 C-D-MA-103-1-1 3rd BASEMENT PLAN SUP AIR & CHW LAYOUT PART D 27-Sep-10 27-Sep-10 C O FANAR
10 C-X-MA-103-1-1 3rd BASEMENT PLAN SUP AIR & CHW LAYOUT MASTER 27-Sep-10 27-Sep-10 C O FANAR
11 C-A-MA-104-1-1 2nd BASEMENT PLAN SUP AIR & CHW LAYOUT PART A 25-Sep-10 25-Sep-10 C O FANAR
12 C-B-MA-104-1-1 2nd BASEMENT PLAN SUP AIR & CHW LAYOUT PART B 25-Sep-10 25-Sep-10 C O FANAR
13 C-C-MA-104-1-1 2nd BASEMENT PLAN SUP AIR & CHW LAYOUT PART C 25-Sep-10 25-Sep-10 C O FANAR
14 C-D-MA-104-1-1 2nd BASEMENT PLAN SUP AIR & CHW LAYOUT PART D 25-Sep-10 25-Sep-10 C O FANAR
15 C-X-MA-104-1-1 2nd BASEMENT PLAN SUP AIR & CHW LAYOUT MASTER 25-Sep-10 25-Sep-10 C O FANAR
ELECTRICAL GENERAL DRAWINGS__START = 15 DEC 2010 ,,, FINISH= 15 DEC 2010 _ _ _ _ _ _ _ _ _ _
ELECTRICAL LIGHTING SYSTEM LAYOUT__START = 19 AUG 2010 ,,, FINISH= 1 FEB 2011 _ _ _ _ _ _ _ _ _ _