RENCANA ANGGARAN BIAYA ( RAB )

RENOVASI KANTOR DI JL. PARANG KESIT RAYA TLOGOSARI SEMARANG

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

A. PEK. PERSIAPAN & TANAH


1 Pasang Bouwplank 1.00 ls 750,000.00 750,000.00
2 Galian Tanah 10.08 m3 16,000.00 161,280.00
3 Urugan Kembali 5.04 m3 8,000.00 40,320.00
4 Urugan Tanah 18.00 m3 60,500.00 1,089,000.00
5 Urugan Pasir Bawah Lantai 4.50 m3 87,500.00 393,750.00
2,434,350.00

PEK. BONGKARAN, DLL


1 Bongkaran & Perbaikan 1.00 ls 10,000,000.00 10,000,000.00
2 Tutup Beton Saluran 15.00 m' 400,000.00 6,000,000.00
3 Pagar Tralis 8.00 m' 400,000.00 3,200,000.00
19,200,000.00

B. PEK. PONDASI & BETON


1 Pasang Pondasi 5.60 m3 401,500.00 2,248,400.00
2 Beton Plat Lajur 2.40 m3 3,680,000.00 8,832,000.00
3 Kolom Konstruksi 40 x 40 5.44 m3 4,375,000.00 23,800,000.00
4 Balok 25 x 50 5.00 m3 4,725,000.00 23,625,000.00
5 Plat Dag + Plat Atap 12 cm 14.40 m3 3,390,000.00 48,816,000.00
6 Beton Sayap + Tepi 3.60 m3 3,390,000.00 12,204,000.00
7 Balok Lantai 15 x 20 0.48 m3 3,680,000.00 1,766,400.00
121,291,800.00

C. PEK. PASANGAN, PLESTERAN


1 Pasang Batu Merah 86.00 m2 60,500.00 5,203,000.00
2 Plesteran Dinding 172.00 m2 22,500.00 3,870,000.00
3 Acian 261.00 m2 12,500.00 3,262,500.00
4 Sponengan Sudut 315.00 m' 6,000.00 1,890,000.00
14,225,500.00

D. PEK. LANTAI KERAMIK


1 Lantai Keramik 40 x 40 120.00 m2 112,500.00 13,500,000.00
13,500,000.00

E. PEK. KOSEN, PINTU, KACA


1 Kosen Aluminium 95.60 m' 75,000.00 7,170,000.00
2 Pintu Kaca Rangka Aluminium 2.00 Dn 1,250,000.00 2,500,000.00
3 Kaca Rayban 27.20 m2 90,000.00 2,448,000.00
4 Pintu Folding Gate 39.00 m2 425,000.00 16,575,000.00
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA
28,693,000.00

F. PEKERJAAN PLAFON & CAT


1 Plafon Gypsum 90.00 m2 140,000.00 12,600,000.00
2 Cat Plafon + Tembok 351.00 m2 17,500.00 6,142,500.00
18,742,500.00

G. PEK. INSTALASI LISTRIK


1 Instalasi Titik Lampu 13 titik 140,000.00 1,820,000.00
2 Instalasi Titik Stop Kontak 5 titik 140,000.00 700,000.00
3 Instalasi Titik Stop Kontak AC 2 titik 250,000.00 500,000.00
4 Pemasangan Lampu SL 18 Watt 13 bh 35,000.00 455,000.00
5 Pemasangan Box MCB 4 Group 1 unit 450,000.00 450,000.00
6 Pindah KWH Meter 1 unit 300,000.00 300,000.00
7 Grounding Arde 1 unit 200,000.00 200,000.00
4,425,000.00

Jumlah 222,512,150.00
Jasa 10% 22,251,215.00
Jumlah Total 244,763,365.00

Dibulatkan 244,763,000.00

Terbilang : Dua Ratus Empat Puluh Empat Ribu Tujuh Ratus Enam Puluh Tiga Ribu Rupiah.