Anda di halaman 1dari 13

NJCC January 1996

Code of Procedurefor
Single Stage
Selective Tendering

National Joint Consultative Committee for Building


in collaboration with:

The Scottish Joint Consultative Committee and


The Joint Consultative Committee for Building,
Northern Ireland
NJCC Publications

CODESOFPROCEDURE

SingleStageSelectiveTendering(1996) SelectiveTenderingfor Designand Build Selectionof a Management Contractor


(1995) and Works Contractors (1991)
Two StageSelectiveTendering(1996)
Lettingand Management of Domestic
Sub-contractWorks (1989)

GUIDANCE NOTES

1 Joint VentureTenderingfor 4 Pre-TenderMeetings(1988) 8 ConstructionManagement:


Contractsin the United Kingdom Selection and Appointmentof
(1996) 5 Reproductionof Drawingsfor ConstructionManager and Trade
Tender Purposes (1996) Contractors(1994)
2 Performance Bonds(1995)
6 CollateralWarranties (1992) 9 ChargesforAdmission to Approved
(3) (FireOfficersRecommendations) and Select Lists and for Tender
Withdrawn August 1993 7 Alternative Dispute Resolution Documents (1994)
(1993)

PROCEDURENOTES

1 Variationson Construction 9 TenderingPeriods 16 'Record' (or'As Fitted') Drawings


Contracts (RevisedJanuary 1996) and Operating and Maintenance
(RevisedJanuary 1996) Instructions
( 1 O ) (AdvicetoTenderers: UseofPostal (Underreview)
2 Alterationsto Standard Formsof Services)
Contract Withdrawn March1989 17 Set-off and Adjudication Procedures
(RevisedJanuary 1996) under Sub-contract
11 FinancialControland Cash Flow (RevisedJuly 1991)
3 Additional Informationfor (RevisedJanuary 1996)
Tenderers 18 UseandCompletionofNSC/1
(RevisedJanuary 1996) 12 Tenderingfor Building Works (Issued July1991)
without Bills of Quantities
4 Placingof Contractswith a (RevisedJune 1992) 19 The PublicWorks Contracts
Substantial BuildingServices Regulations1991-ContractAward
Engineering Content 13 Naming of Officials by Public Proceduresof theEC'Works
(RevisedSeptember 1989) Authorities in the Articles of Directive'
Agreement inStandard Formsof (IssuedJune 1994)
(5) (SelectiveTendering) Building Contract
Withdrawn March1978 (RevisedJanuary1996) 20 The construction (Designand
Management)Regulations1994
(6) (NEDOPriceAdjustment Formula) 14 Placing of Sub-contractsinvolving (SI 1994No.3140)
Withdrawn March1978 design, preparationof drawings (IssuedFebruary 1995)
and/oroff-site fabrication workby
7 Standard Form of Building Contract Sub-Contractors
1980Edition-Clauses38.7 and 39.8 (RevisedJanuary 1996)
(RevisedSeptember 1989)
15 CommissioningandTesting
(8) (NEDOPriceFluctuationFormula- (Underreview)
Clause31F)
Withdrawn March 1978

TENDERINGQUESTIONNAIRES

Applicationfor admissionto Applicationfor admissionto


Approved Listsof Contractors SelectListsof Contractorsfor one
particularcontract

Available from:
RlBA Publications
Surveyors Publications
CIPLtd
CONTENTS Page clear to all potential tenderers at the outset; the
principles set out hereafter should still be
1.0 Foreword 1 observed.

2.0 Introduction 1 The objective is to achieve value for money for


the employer; good tendering procedures are
3.0 The list of Tenderers 2 part of a range of issues an employer must
consider to achieve that.
4.0 Tendering Procedure 2
1.2 The Construction (Design and Management)
5.0 Assessing Tenders and Notifying Results 4 Regulations 1994 [1] (CDM) place duties upon
employers, architects, designers and
6.0 Examination and Adjustment of the contractors with regard to health and safety. It
Priced Bill(s) 4 must be taken into account, co-ordinated and
managed effectively throughout all stages of a
7.0 Negotiated Reduction of Tender 5 construction project, from conception, design
and planning through to the execution of works
on site and subsequent maintenance and
Appendices repair.

A Preliminary Enquiry for Invitation to Tender This Code assumes that a planning supervisor
for use with: has been appointed under CDM.

.1 Standard Form of Building Contract 7 1.3 Consequent upon entry into the European
Intermediate Form of Building Contract Union tenders for public sector construction
Agreement for Minor Building Works contracts above a specified value must be
invited and contracts awarded in accordance
.2(S) Scottish Minor Works Contract 8 with Directive 71/305/EEC (as amended by
Directive 89/440/EEC), implemented in the UK
B Formal Invitation to Tender 9 by The Public Works Contracts Regulations
1991 (SI) 1991/2680. In these instances, the
C Form of Tender 10 provisions of the Code will be qualified by the
supplementary tendering procedures specified
in the Regulations. Public contracting
authorities within the meaning of the
Regulations are responsible for ensuring that
their tender and award procedures for works
Note: The Code applies in the whole of the contracts comply with the provisions of the
United Kingdom, but where Scottish practice Regulations or subsequent legislation. (See
differs, suitable recommendations are printed NJCC Procedure Note 19.)
in italics.
1.4 This Code is complementary to other NJCC
publications (listed opposite).

1.0 FOREWORD 1.5 Throughout the Code the word 'architect' is


used to mean architect [2] or contract
1.1 This Code has been prepared for use by all who administrator and the word 'employer', to mean
commission construction work, whether in the building owner or employing body in the sense
private or public sectors. It envisages the use of that the terms are used in the standard forms of
single stage tendering by a selected list of building contract.
tenderers which is currently the most common
method of obtaining tenders for the majority of
construction contracts. 2.0 INTRODUCTION

On contracts where it is desired to secure the 2.1 The general principles of the Code are fully
early involvement of the contractor before the supported by the Department of the
development of the design is completed two Environment and take into account the relevant
stage tendering procedures may be adopted. recommendations of the National Economic
These procedures are detailed in a companion Development Office (NEDO) report 'The Public
NJCC Code of Procedure for Two Stage Client and the Construction Industries', the
Selective Tendering. report 'The Placing and Management of
Contracts for Building and Civil Engineering
Nothing in this Code should be taken to suggest
that the employer is obliged to accept the [1] See also the Approved Code of Practice issued in
lowest or any tender, although if the procedure February 1995 by the Health and Safety Commission
advocated in the Code is followed, the 'Managing construction for health and safety'.
successful tenderer will normally be the one
[2] The term 'architect' applies only to any person
offering the lowest price, on a lump sum basis. entitled to use the name 'architect' under and in
If it is the employer's intention to allow bids accordance with the Architects Registration Acts 1931
based on alternative criteria, this must be made to 1969.

Code: Single Stage 1


2.1 continued number of tenderers should be not more than
four.
Work' (The Banwell Report), 'Action on the
Banwell Report' and 'Constructing the Team' When the list has been settled, one or two
(The Latham Report 1994). further names should be appended in order that
they may replace any firms on the list that do
2.2 In order that its detailed recommendations may not accept the preliminary invitation.
be most widely applicable, this Code assumes
that a standard form of contract would be The actual number invited should be notified to
entered into following the acceptance of a all tenderers.
tender. This assumption in no way precludes
the use of the Code where other forms of 3.2 When selecting the short list the following are
contract are employed, though certain details among the points which should be considered:
may require modification.
.1 the firm's financial standing and record;
2.3 The contractor's tender is the price for which he
offers to carry out and complete, in accordance .2 whether the firm has had recent experience
with the conditions of the contract and statutory of building at the required rate of completion
requirements, the works shown on the over a comparable contract period;
drawings and described in the bill(s) of
quantities and/or specifications and schedules. .3 the firm's general experience, skill and
reputation in the area in question;
2.4 Good tendering procedure demands that the
contractor's tendered price should not be .4 whether the technical and management
altered without justification. Difficulties have structure of the firm including the
arisen when an examination of the priced bill(s) management of sub-contractors is adequate
revealed errors or a discrepancy between these for the type of contract envisaged;
prices and the tender figure. The Code lays
down, in Section 6, alternative methods of .5 the firm's competence and resources in
dealing with this situation before the respect of statutory health and safety
contractor's offer is accepted. The first requirements;
alternative does not permit the correction of
errors in priced bill(s) of quantities, the second .6 the firm's approach to quality assurance
does. systems; and

The choice must be made before contractors .7 whether the firm will have adequate capacity
are invited to tender. at the relevant time.

2.5 It should be a condition of tender that obvious 3.3 Approved lists should be reviewed periodically
errors in pricing or significant errors in to exclude firms whose performance has been
arithmetic discovered before the acceptance of unsatisfactory, and to allow the introduction of
the contractor's tender should be dealt with in suitable additional firms.
accordance with one of the alternatives in
Section 6 of this Code. 3.4 The object of selection is to make a list of firms,
any one of which could be entrusted with the
job [3]. If this is achieved, then the final choice
3.0 THE LIST OF TENDERERS of contractor will be simple - the firm offering
the lowest tender. Only the most exceptional
3.1 Once it has been decided that a contractor is to cases justify departure from this general
be selected under a competitive tendering recommendation.
procedure, a short list of suitable tenderers
should be drawn up either from the employer's
approved list of contractors or from an ad hoc 4.0 TENDERING PROCEDURE
list of contractors.
4.1 Preliminary Enquiry
It should be appreciated that, because of the
cost of preparing tenders, the larger the tender .1 In order that contractors may be able to
lists become the greater will be the cost of decide whether they will tender, and to
abortive tendering, and this will be reflected in anticipate demands on their tendering staff,
higher building prices. each firm should be sent, and should reply
promptly to, a preliminary invitation to
This list, irrespective of the size of the contract, tender as illustrated in Appendix A -
should contain not more than six names. 'Preliminary Enquiry for Invitation to Tender'.

Regard should also be paid to the amount of It is essential that all the details itemised in
work demanded of tenderers in order to Appendix A are stated in the preliminary
formulate their bids and where this involves
extensive quantification,specification, [3] Arrangements for pre-tender interviews may
specialisation and/or calculation the maximum facilitate this objective. (See NJCC Procedure Note 4-
Pre-Tender Meetings.)

2 Code: Single Stage


4.1 .1 continued prior consideration and should then be
drafted by a person competent to ensure that
enquiry. The omission of relevant all consequential alterations to other clauses
information may seriously impede are made (see NJCC Procedure Note 2).
contractors in deciding whether or not to
tender. The tenderer's attention should be
specifically drawn in the Preliminary
.2 It is suggested that an appropriate period of Invitation to Tender (see Appendix A) to any
time between the preliminary enquiry and alterations to be made to the standard form
the despatch of tender documents is 4 to 6 of contract and, where appropriate, reasons
weeks, although in some instances a period should be given, so that the implications of
of 3 months would not be unreasonable. In such amendments may be considered by the
cases beyond 3 months the preliminary tenderers prior to acceptance of the
invitation should be confirmed a month invitation to tender; and so minimise the risk
before tenders are invited. of subsequent queries at tender stage which
may result in an extension of the tender
.3 Once a contractor has signified initial period (see clause 4.4).
agreement to tender it is in the best interests
of all parties that such acceptance should be 4.3 Time for Tendering
honoured. If in exceptional circumstances a
contractor has to withdraw his acceptance he .1 The time allowed for the preparation of
should give notice of this intention before tenders should be determined in relation to
the issue of tender documents. If for any the size and complexity of the job.
reason this is not possible, notice should be Inadequate tendering time can lead to
given not later than two working days after mistakes and the client may not obtain the
receipt of the tender documents. most competitive prices. A minimum of four
working weeks (20 working days) should
.4 After the latest date for the acceptance of the normally be allowed. Major projects, plan
preliminary invitation the final short list of and specification tenders [4], works having a
tenderers will be selected. All firms should significant non-nominated specialist content
be notified promptly whether or not they or other special circumstances may well
have been included in the tender list. require a longer period. The tender period
must be sufficient to enable the tenderer to
4.2 The Tender Documents obtain competitive quotations for the supply
of materials and for the execution of works
.1 On the day stated in the preliminary to be sub-let. The latest time for submission
invitation all tender documents should be should be specified as an hour of a day and
available for collection or despatched to the should be chosen to allow as short a time as
tenderers by first class post. See Appendix B possible to elapse before opening the
for suggested 'Formal Invitation to Tender' tenders. Tenders received after time should
and Appendix C for suggested 'Form of not be admitted to the competition.
Tender'.
.2 If bills of quantities are issued to tenderers in
.2 The conditions of tendering should be sections, or any supporting or relevant
absolutely clear so that all tenders are documentation issued at a later stage in the
submitted on the same basis. The contract tendering period, the date for the return of
period should be specified in the tender tenders should be extended with the full
documents and tenderers should be required tendering period calculated from the date of
to make offers based on the same period of issue of the final information.
completion in order to limit competition to
price only. Sufficient time must be given to allow
tenderers to comply with the requirements
.3 The NJCC strongly recommends the use of of the Construction (Design and
the standard forms of building contract in Management) Regulations 1994.
unamended form.
4.4 Tender Compliance
Although it is recognised that the terms of
the standard forms are not mandatory and .1 If a tenderer considers that any of the tender
that the employer and his professional documents are deficient in any respect and
advisers may alter them at their discretion, require clarification, or contain unacceptable
the NJCC believes that alterations to the alterations to the standard form of building
standard forms impede the efforts being contract not previously set out in the
made towards achieving greater Preliminary Invitation to Tender (see
standardisation of building procedures. The Appendix A) he should inform the issuing
NJCC is firmly of the opinion that if authority or the architect (with a copy to the
alterations to the standard forms have to be quantity surveyor) as soon as possible and
made it is essential in the interests of good preferably not less than ten working days
practice and of economic building that they
be kept to an absolute minimum. They [4] See NJCC Procedure Note 12 -Tendering for
should not be undertaken without serious Building Works without Bills of Quantities.

Code: Single Stage 3


4.4 .1 continued 5.2 * The priced bill(s) of quantities, contained in a
sealed, separate envelope, endorsed with the
before the tenders are due. If it is decided to tenderer’s name, should be submitted at the
amend the documents the issuing authority same time as the tender.
or architect should inform all tenderers and
extend the time for tendering if necessary. 5.3 The NJCC does not recommend that all
tenderers be required to submit a response to
.2 For fair competitive tendering it is essential the health and safety plan with their tenders.
that the tenders submitted by each tenderer The lowest tenderer should be required to
be based on identical tender documents (a submit its response as soon as possible.
compliant tender) and that the tenderers
should not attempt to vary the basis by 5.4 It is important that all but the lowest three
qualifying their tenders. tenderers should be informed immediately that
their tenders have been unsuccessful, as this
If, in addition, the employer is prepared to information is critical in relation to a
receive alternative offers varying any aspect contractor‘s strategic tender planning. In order
of the project specifications including an to serve the employer’s interests in the event of
alternative contract period all tenderers the lowest tenderer withdrawing his offer, the
should be notified accordingly. The second and third lowest tenderers should be
alternative offer, which the employer may informed that their tenders were not the most
reject, should be supported by a fully favourable received but that they will be
specified and priced build-up. approached again if it is decided to give further
consideration to their offers. They should
An alternative offer should only be subsequently be notified at once when a
considered if accompanied by a compliant decision to accept a tender has been taken.
tender.
5.4 * The envelope containing the bill(s) of the lowest
.3 A tenderer who otherwise submits a tenderer should be opened and the bill(s)
qualified tender should be given the examined. Alternatively the lowest three
opportunity to withdraw the qualifications to tenderers should be advised that their offers are
produce a compliant tender; if he fails to do under consideration and the envelopes
so his whole tender should be rejected if it is containing the bill(s) of the lowest three
considered that such qualifications afford the tenderers should be opened and the bill(sl
tenderer an unfair advantage over other examined. Tenderers whose offers are being
tenderers. rejected should be informed immediately or as
early as possible.
4.5 Withdrawal of Tender before Acceptance
5.5 A contract must not be entered into nor works
.1 Under English law a tender may be started on site until satisfaction has been
withdrawn at any time before its acceptance. obtained on the firm’s competence and
resources in respect of statutory health and
*. 1 Under Scots law, if the provision for the safety requirements.
tender to be withdrawn at any time before its
acceptance is to be available, the words 5.6 Once the contract has been let every tenderer
‘unless previously withdrawn‘ should be should be supplied with a list of the firms who
inserted in the tender after the words ‘this tendered (in alphabetical order) and a list of the
tender remains open for consideration . . .’ tender prices (in ascending order of value).

(Note: this clause is nor, however, contained


in tenders issued in Scotland by the 6.0 EXAMINATION AND ADJUSTMENT OF THE
Department of the Environment; see PRICED BILL(S)
Appendix C for suggested ‘Form of Tender‘.)
6.1 The examination of the priced bill(s) of
quantities supporting the tender under
5.0 ASSESSING TENDERS AND NOTIFYING consideration should be made by the quantity
RESULTS surveyor who should treat the document as
confidential; on no account should any details
5.1 Tenders should be opened as soon as possible of the tenderer‘s pricing be disclosed to any
after the time for receipt of tenders. person, other than the architect or other
appropriate consultant, except with the express
5.2 The lowest tenderer should be required to permission of the tenderer.
submit priced bill(s) of quantities as soon as
possible and in any case within four working 6.2 The object of examining priced bills is to detect
days. errors in computation of the tender. If the
quantity surveyor finds such errors, he should
Tenderers should be informed that failure to report them to the architect who, in conjunction
comply with this requirement may render the with the employer, will determine the action to
tender liable to rejection. be taken under whichever is appropriate of the
alternatives set out below and referred to in the
* Applicable in Scotland only.

4 Code: Single Stage


6.2 continued NJCC strongly deplores any practice which
seeks to reduce any tender arbitrarily where the
Formal Invitation to Tender and the Form of tender has been submitted in free competition
Tender. (See Appendices B and C.) and no modifications to the specification,
quantity or conditions under which the work is
6.3 Alternative 1 to be executed are to be made, or to reduce
tenders other than the lowest to a figure below
.1 The tenderer should be given details of such the lowest tender.
errors and afforded an opportunity of
confirming or withdrawing his offer. If the 7.2 Should the tender under consideration exceed
tenderer withdraws, the priced bill(s) of the the employer’s budget the recommended
second lowest should be examined, and if procedure is for a reduced price to be
necessary this tenderer be given a similar negotiated with the tenderer, based on agreed
opportunity. changes to the specification or the quantity of
work. The basis of negotiations and any
.2 An endorsement should be added to the agreements made should be fully documented.
priced bill(s) indicating that all rates or prices
(excluding preliminary items, contingencies, 7.3 Only when these negotiations fail should
prime cost and provisional sums) inserted negotiations proceed with the next lowest
therein by the tenderer are to be considered tenderer. If these negotiations also fail, similar
as reduced or increased in the same action may be taken with the third lowest
proportion as the corrected total of priced tenderer.
items exceeds or falls short of such items.
This endorsement should be signed by both 7.4 If all these negotiations fail, new tenders may
parties to the contract. be called for.

6.4 Alternative 2

.1 The tenderer should be given an opportunity


of confirming his offer or of amending it to
correct genuine errors. Should he elect to
amend his offer and the revised tender is no
longer the lowest, the offer of the firm now
lowest in the competition should be
examined.

*.1 The lowest tenderer or each of the lowest


three renderers should be given an
opportunity of confirming his offer or
amending it to correct genuine error.

.2 If the tenderer elects not to amend his offer,


an endorsement will be required as in clause
6.3.2. If the tenderer does amend his tender
figure, and possibly certain of the rates in his
bill(s), he should either be allowed access to
his original tender to insert the correct
details and to initial them or be required to
confirm all the alterations in a letter. If in the
latter case his revised tender is eventually
accepted, the letter should be conjoined with
the acceptance and the amended tender
figure and the rates in it substituted for those
in the original tender.

6.5 When a tender is found to be free of error, or


the tenderer is prepared to stand by his tender
in spite of error, or a tender on amendment is
still the lowest, this should be recommended to
the employer for acceptance.

7.0 NEGOTIATED REDUCTION OF TENDER

7.1 As previously stated in clause 2.4, good


tendering procedure demands that a
contractor’s tendered price should not be
altered without justification. In particular, the

* Applicable in Scotland only.

Code: Single Stage 5


Appendix A.1 PRELIMINARY ENQUIRY FOR INVITATION TO TENDER

Applicable where the JCT Standard Form of Building Contract, Intermediate Form of
Building Contract or Agreement for Minor Building Works is to be used

Dear Sirs,

Heading

I am/We are authorised to prepare a preliminary list of tenderers for construction of the
works described below.

Please indicate whether or not you wish to be invited to submit a tender for these works.
Your acceptance will imply your agreement to submit: a wholly bona fide tender in
accordance with the principles laid down in the NJCC 'Code of Procedure for Single
Stage Selective Tendering' 1996, and not to divulge your tender price to any person or
body before the time for submission of tenders. Once the contract has been let, I/we
undertake to supply all tenderers with a list of the tender prices.

You are requested to reply by. . . Your inability to accept will in no way prejudice your
opportunities for tendering for further work under my/our direction; neither will your
inclusion in the preliminary list at this stage guarantee that you will subsequently receive
a formal invitation to tender for these works.

Yours faithfully. . .

a Project.. .
b Type and function of the building, e.g. commercial, industrial, housing, etc., with any
other details.. .
c General description of the project. . .
d Employer.. .
e Employer's professional team . . .
f Planning Supervisor.. .
g Location of site. . . (Site plan enclosed)
h Approximate cost range of project £ . . . to £ . . .
i Number of tenderers it is proposed to invite.. .
j Nominated sub-contractors for major items. . . [1]
k Form of Contract:
List here Form of Contract, e.g. JCT 80/IFC 84/MW 80,* together with
(i) Appendix items to the appropriate form completed †
(not applicable to MW 80)
(ii) The JCT Amendments proposed to the standard form ‡
[Note: Attention is drawn to the advice given in clause 4.2.3.1
I Examination and correction of priced bill(s) [Section 6 of Code1 121;
Alternative 1/Alternative 2 [3] will apply
m The contract is to be executed as a deed/a simple contract §
n Anticipated date for possession . . .
o Period for completion of works. . .
p Approximate date for despatch of all tender documents . . .
q Tender period.. . weeks
r Tender to remain open for. . . weeks [4]
s Details of guarantee requirements. . . (if any) [5]
t Particular conditions applying to the contract are. . .

References [1] Not appropriate for IFC 84 or MW 80.


[2] Only appropriate for JCT 80 With Quantities or IFC 84 if the priced document is to be contract
bills.
I3] Delete as appropriate before issuing.
[4] This period should be as short as possible.
[5] See NJCC Guidance Notes 2 and 6.
* In Scotland the appropriate SBCC Scottish Building Contract (SBC).
† In Scotland Appendix II.
‡ In Scotland the SBCC Amendment Sheet (number and date) to be used with the appropriate
SBC.
§ In Scotland as a formal/informal contract.
Previous page
Code: Single Stage 7
is blank
Appendix A.2(S) PRELIMINARY ENQUIRY FOR INVITATION TO TENDER

Applicable where the Scottish Minor Works Contract is to be used

Dear Sirs,

Heading

I am/We are authorised to prepare a preliminary list of tenderers for construction of the
works described below.

Your attention is drawn to the fact that apart from the alternative clauses to the Scottish
Minor Works Contract as detailed below under item i, further amendments to the
Scottish Minor Works Contract, if any are annexed hereto, will be incorporated in the
tender documents.

Will you please indicate whether you wish to be invited to submit a tender for these
works on this basis. Your acceptance will imply your agreement to submit a wholly bona
fide tender in accordance with the principles laid down in the NJCC 'Code of Procedure
for Single Stage Selective Tendering' 1996, and not to divulge your tender price to any
person or body before the time for submission of tenders. Once the contract has been
let, I/we undertake to supply all tenderers with a list of the tender prices.

Please state whether you would require any additional unbound copies of the bill(s) in
addition to the two copies you would receive; a charge may be made for extra copies. [I]

You are requested to reply by. . . Your inability to accept will in no way prejudice your
opportunities for tendering for further work under my/our direction; neither will your
inclusion in the preliminary list at this stage guarantee that you will subsequently receive
a formal invitation to tender for these works.

Yours faithfully. ..

a Job ...
b Employer.. .
c Architect/Contract Administrator . . .
d Quantity Surveyor. . .
e Consultants.. .
f Location of site.. , (Site plan enclosed)
g General description of work. . .
h Approximate cost range £ . . . to £.. . .
i Form of Contract: Scottish Minor Works Contract
Alternative A/Alternative B [1] will apply: the Planning Supervisor shall be . . .
Clause 2.0 will/will not [1] apply
Clause 6.5 will/will not [1] apply
Clause 7.2: Clause B1.1 of said Memorandum, Section B will/will not [I] apply
Clause 7.4 from 'or shall have given' to the end of clause 7.4 will/will not [1] apply
Clause 8.3A/8.3B will/will not [1] apply: the percentage to cover professional fees
is ... %
j Examination and correction of priced bill(s) [Section 6 of Code];
Alternative 1/Alternative 2 [1] will apply
k The contract is to be formally/informally [1] executed
I Anticipated date for commencement of works. . .
m Anticipated date for completion of works. . .
n Tender period.. .weeks
o Tender to remain open for.. . weeks [2]
p Liquidate damages (if any), anticipated value £ . . . per. . .
q Defects liability period under clause 3.5. . .
r Retention under clause 6.2. . . %
s Period specified in clause 6.4 shall be . . .
t Percentage specified in clause 6.5 (if applicable) is. . .
U Particular conditions applying to the contract are. . .

References [1] Delete as appropriate, before issuing.


[2] This period should be as short as possible.

8 Code: Single Stage


Appendix B FORMAL INVITATION TO TENDER

Dear Sirs,

Heading

Following your acceptance of the invitation to tender for the above, I/we now have
pleasure in enclosing the following:

a two copies of the bill(s) of quantities/specifications/schedules [1];


b (i) two copies of the location drawings, component drawings, dimension drawings
and information schedules (e.g. JCT 80 With Quantities ‡ or IFC 84 where
Contract Bills are provided) [1];
(ii) two copies of all drawings (for JCT 80 Without Quantities, IFC 84 with
Specification and Drawings or MW 80) § [1];
(iii) two copies of the planning supervisor‘s pre-tender health and safety plan;
c two copies of the form of tender;
d addressed envelope(s) for the return of the tender (and priced bill(s) †) and
instructions relating thereto.

Will you please also note:

1 drawings and details may be inspected at. . .


2 the site may be inspected by arrangement with the employer/architect [1];
3 tendering procedure will be in accordance with the principles of the NJCC ‘Code of
Procedure for Single Stage Selective Tendering’ 1996;
4 examination and adjustment of priced bill(s) [Section 6 of Code];
Alternative 1/Alternative 2 [1] will apply.

The completed form of tender is to be sealed in the endorsed envelope provided and
delivered or sent by post to reach ...
not later than.. . hours on ..
.the.. . day of.. 19.. . .
* The completed form of tender and the priced bill(s) of quantities sealed in separate
endorsed envelopes provided are to be lodged not later than. . . hours on, . . the . . .
day of. . . 19. . . The envelope containing the render should be endorsed with the
job title; that containing the bill(s) of quantities should be endorsed with the job title
and tenderer’s name.

Will you please acknowledge receipt of this letter and enclosures and confirm that you
are able to submit a tender in accordance with these instructions.

Yours faithfully.
Architect/Quantity Surveyor [1]

References [1] Delete as appropriate, before issuing.


* Applicable in Scotland only in which case the preceding sentence would not be used.
† Applicable in Scotland only.
‡ In Scotland SBCC With Quantities.
§ In Scotland SBCC Without Quantities or SMWC 86.

Code: Single Stage 9


Appendix C FORM OF TENDER

This form of tender is suitable for use only when a formal contract is entered into

Tender for. .. (description of Works)


To. .. (Employer)

Sir(s),

I/We having read the conditions of contract and bill(s) of quantities/specifications/


schedules [1] delivered to me/us and having examined the drawings and other
documents referred to therein do hereby offer to execute and complete in accordance
with the conditions of contract the whole of the works described for the sum of. .. £ ...
and within ... weeks [2] from the date of possession.

* //We undertake in the event of your acceptance to execute with you a formal contract
embodying all the conditions and terms contained in this offer.

I/We agree that should obvious errors in pricing or errors in arithmetic be discovered
before acceptance of this offer in the priced bill(s) of quantities submitted by me/us these
errors will be dealt with in accordance with Alternative 1/Alternative 2 [1] contained in
Section 6 of the NJCC 'Code of Procedure for Single Stage Selective Tendering' 1996.

This tender remains open for consideration for. .. days [3] from the date fixed for the
submission or lodgement of tenders,[4].

Dated this ............................................................... day of .............................................. 19 ...............

Name.. .............................................................................................................................

Address ........................................................................................................................................

Signature .................................................................. Witness* ................................................................

* The completed form of tender and the priced bill(s) of quantities sealed in separate
endorsed envelopes provided are to be lodged not later than. .. hours on ... the. ..
day of. .. 19. .. The envelope containing the tender should be endorsed with the
job title: that containing the bill(s) of quantities should be endorsed with the job title
and tenderer's name.

References [1] Delete as appropriate, before issuing.


I21] To be completed before Form of Tender is sent out.
[3] Any period quoted should not normally exceed 28 days and only in exceptional circumstances
should it extend beyond 56 days.
[41] Refer to clause 4.5 of this Code.
* Applicable in Scotland only.

10 Code: Single Stage


The National Joint Consultative
Committee for Building

The National Joint Consultative The original constituent bodies during the The NJCC keeps all its publications under
committee for Building was set up in first two decades of the NJCC were the review and up to date and ensures that
1954, after publicattention had been RIBA, RlCS and BEC (then NFBTE) but they reflect the principles of the Latham
focused on the importance of selective, as following the publication of the Banwell Report Constructing the Team.
opposed to indiscriminate, tendering. Report The Placing and Management of
Contracts for Building and Civil The Good Practice Panel is often
Engineering Work the Association of described as the 'powerhouse' of the
Consulting Engineers, the Federation of NJCC and 'the custodian of good practice'
Building Specialist Contractors and the in the industry. lts two main functions are:
Confederation of Associations of
Specialist Engineering Contractors joined 1. To review and revise existing Codes
in the early 1970s. and formulate new ones where
required.
Throughout its existence the principal 2. To receive reports on practice
pre-occupation of the NJCC has been best difficulties encountered throughout
described as the encouragement of 'good the industry and to advise on
practice'. By this is meant the appropriate courses of action.
identification of what is the good way of
doing things in the-often complex- The Panel's underlying function, which is
operation of building processes. In effect fundamental and which applies to all its
the NJCC sets out standards and it is the work, is to decide on what is, and what is
only fully representative body to do so, or not, good practice. It formulatesopinions
capableofdoing so, with the authority of on the information it is able to obtain and
its constituent bodies. offers informal advice, mostly in relation
totendering proceduresand contract
The NJCC's mostwidely known management. Although a voluntary body
publication is its Code of Procedure for which cannot enforce itsviewthe Panel
Single Stage SelectiveTendering, first nevertheless enjoys considerable
published in 1959. Tens of thousands of influence and authority. Its prestige is
copies have been sold in several editions such that its opinions are widely
and it isgenerally accepted thatthisone respected and usually accepted.
document transformed tendering
practices in the years following its The NJCC, through its Good Practice
publication. Panel, maintains continuous liaison as
required with such bodies as the DoE, the
For the first time recommended Local Authorities Associations, the
procedures which were easily Chartered lnstitute of Public Financeand
comprehensible, obviously ethical and Accountancy as well as the
clearly designed to prevent undesirable representatives of the private sector. The
practices were spelt out and positive function of the NJCC in actively
recommended by an authoritative body influencing ethical and procedural
representing the building industry. In the standards in the industry proves that it is
years since publication the code has not just a talking shop. In addition it
contributed greatly to the proper makes an important contribution to the
regulation of tendering procedures and improvement of building practice and,
has markedly improved the climate in indirectly, to increased productivity.
which the industry operates.
One of the NJCC's strengths is that its
The Code, like other NJCC documents, opinions and recommendations are
was endorsed by the Department of the reached after consultation and discussion
Environment and is widely used in the between practitioners in the building
public sector. Indeed, at one time 85% of industry-those who are actively
local authorities were believed to base involved at senior level with the day to
theirtendering procedureson it. In recent day problems of building. This
years the Code has also become consultation - involving all significant
increasingly used in the private sector. interests in the industry (professions,
main contractors and specialist sub-
The Single Stage Code was followed by a contractors)- leads to recommendations
Code of Procedure for Two Stage which are authoritative and, as
Selective Tendering, the Code of experience shows, continue to be
Procedure for Tendering for Design and effective for many years.
Build, the Code of Procedure for the
Letting and Management of Domestic
Sub-contract Works and the Code of
Procedure for the Selection of a
Management Contractor and Works
Contractors. From time to time the NJCC
has also published a series of Procedure
Notes. More recently the NJCC has
introduced a series of Guidance Notes,
which are listed inside the front cover
hereof.
NJCC
National Joint Consultative Committee for Building

Constituent bodies:
Royal Institute of British Architects
Royal Institution of Chartered Surveyors
Association of Consulting Engineers
Building Employers Confederation
Federation of Building Specialist Contractors
Specialist Engineering Contractors’ Group

Published for the NJCC by RIBA Publications,


Finsbury Mission, 39 Moreland Street, London EC1V 8BB
RlBA Publications is a division of RlBA Companies Ltd

© 1996 NJCC

Printed by The Broadwater Press Ltd,


Welwyn Garden City, Herts

1.96 C B A

Anda mungkin juga menyukai