CUT AND FILL

a. Pekerjaan Galian
Komponen Luas Jarak S Jarak Volume
I. BAGIAN I (Lahan alur barat)
Potongan A1
Potongan A1'
Potongan A2
II. BAGIAN II
Potongan A2 - - -
Potongan A3 1,289.29 29.16 29.16 18,797.88
Potongan A4 1,202.83 17.53 46.69 21,843.47
Potongan A5 837.62 17.47 64.16 17,823.38
Potongan A6 770.53 17.53 81.69 14,095.49
Potongan A7 683.57 17.53 99.22 12,745.19
Potongan A8 598.69 17.53 116.75 11,239.01
Potongan A9 582.97 17.53 134.28 10,357.28
Potongan A10 734.05 17.53 151.81 11,543.72
III. BAGIAN III
Potongan A10 734.05 - - -
Potongan A11 827.46 26.36 26.36 20,580.73
Potongan A12 396.54 57.03 83.39 34,902.36
Potongan A13 1,366.98 40.30 123.69 35,534.93
IV. BAGIAN IV
Potongan A13 1,367.00 - - -
Potongan A14 1,010.92 17.75 17.75 21,104.00
Potongan A15 1,802.20 17.50 35.25 24,614.73
Potongan A16 1,305.12 17.50 52.75 27,189.02
V. BAGIAN V (Cluster utama)
Potongan A16 1,305.12 - - -
Potongan 17 24.59 24.59 16,046.45
Potongan 18 42.11 66.70 -
VI. BAGIAN VI (Pintu masuk utama)
Potongan A19
Potongan A20
Volume galian
Jumlah jam kerja
Sewa alat + tmsk bahan bakar dll
Total biaya pekerjaan galian
Penambahan biaya

b. Pekerjaan Timbunan
I. BAGIAN I (Lahan alur barat)

KOMPONEN Luas Jarak S Jarak Volume


Potongan A1 1,506.73 - - -
Potongan A1' 1,506.73 25.40 25.40 38,270.99
Potongan A2 1,506.73 37.54 62.94 56,562.72
II. BAGIAN II
Potongan A2 1,506.73 - - -
Potongan A3 39.72 29.16 29.16 22,547.27
Potongan A4 48.43 17.53 46.69 772.65
Potongan A5 80.17 17.47 64.16 1,123.36
Potongan A6 62.63 17.53 81.69 1,251.64
Potongan A7 94.90 17.53 99.22 1,380.70
Potongan A8 145.39 17.53 116.75 2,106.12
Potongan A9 123.94 17.53 134.28 2,360.66
Potongan A10 90.42 17.53 151.81 1,878.83
III. BAGIAN III
Potongan A10 90.42 - - -
Potongan A11 125.68 26.36 26.36 2,848.15
Potongan A12
Potongan A13
IV. BAGIAN IV
Potongan A13
Potongan A14
Potongan A15
Potongan A16
V. BAGIAN V (Cluster utama)
Potongan A16 - - - -
Potongan 17 990.74 24.59 24.59 20,302.00
Potongan 18 473.18 42.11 66.70 25,685.84
VI. BAGIAN VI (Pintu masuk utama)
Potongan A19 636.59 - - -
Potongan A20 636.59 51.86 51.86 33,013.53
Volume timbunan rencana :
Jumlah jam kerja :
Sewa alat + tmsk bahan bakar dll :
Total biaya pekerjaan galian :
Penambahan biaya :

ESTIMASI PENAMBAHAN VOLUME TANAH UNTUK PEMADATAN

A. Data Cut & Fill Awal


Volume galian rencana 198,945.08 m3
Sisa timbunan layak pakai 50% 69,876.59 m3
(Tanah non homogen)

B. Estimasi kebutuhan untuk pemadatan


Volume timbunan rencana 130% 181,679.13 m3
Sisa timbunan tersedia 69,876.59
Kebutuhan tambahan tanah timbunan 111,802.54 m3

C. Kapasitas alat rencana


Kapasitas alat 161.22 m3/jam
Jam kerja alat 693.48 Jam
Sewa alat + tmsk bahan bakar dll 310,000 / Jam
Biaya pekerjaan 214,978,210
S Volume

-
18,797.88
40,641.34
58,464.73
72,560.21
85,305.40
96,544.41
106,901.70
118,445.41

-
20,580.73
55,483.09
91,018.02

-
21,104.00
45,718.73
72,907.75

-
16,046.45
16,046.45

198,945.08 m3
2,968.00 jam
310,000.00 / Jam
920,080,205
17,360.00 / m2

c. Pekerjaan Pemadatan
Bobot Eskalasi
Pemadatan Pemadatan

S Volume (%) (m3)


- - -
38,270.99 0.21 49,752.29
94,833.71 0.52 123,283.83

- - -
22,547.27 0.12 29,311.45
23,319.92 0.13 30,315.90
24,443.28 0.13 31,776.26
25,694.92 0.14 33,403.40
27,075.62 0.15 35,198.30
29,181.74 0.16 37,936.27
31,542.40 0.17 41,005.12
33,421.23 0.18 43,447.60

- - -
2,373.45 0.01 3,085.49

- - -
20,302.00 0.11 26,392.59
45,987.83 0.25 59,784.18

- - -
33,013.53 0.18 42,917.59

139,753.17 Volume pemadatan rencana :


866.85 jam Jumlah jam kerja total :
310,000.00 / Jam Sewa alat + tmsk bahan bakar dll :
268,722,762 Total biaya pekerjaan galian :
5,070.24 /m2 Penambahan biaya :

Volume timbunana rencana :


Bobot timbunan awal :
Faktor penambahan :
Luas
Volume
Penampang Jarak komulatif
Pemadatan
Timbunan
(m2) (m1) (m3)
- - -
3,465.48 25.40 88,023.28
3,465.48 62.94 218,117.54

- - -
1,778.42 29.16 51,858.72
1,148.76 46.69 53,635.82
876.24 64.16 56,219.54
723.45 81.69 59,098.32
627.63 99.22 62,273.92
574.89 116.75 67,118.01
540.27 134.28 72,547.53
506.35 151.81 76,868.84

- - -
207.09 26.36 5,458.95

- - -
1,898.93 24.59 46,694.59
1,585.79 66.70 105,772.01

- - -
1,464.16 51.86 75,931.12

251,555.71
1,560.33 jam
310,000.00 / Jam
483,700,972
9,126.43 /m2

181,679.13
0.77
1.30
b. Pekerjaan Timbunan Padat (Sebelum dikurangi Volume Sisa Galian)
I. BAGIAN I (Lahan alur barat)
KOMPONEN Luas Jarak Σ Jarak Σ Volume

Potongan A1 - - - -
Potongan A1' 3,465.48 25.40 25.40 88,023.28
Potongan A2 3,465.48 37.54 62.94 218,117.54

II. BAGIAN II
Potongan A2 - - - -
Potongan A3 1,778.42 29.16 29.16 51,858.72
Potongan A4 1,148.76 17.53 46.69 53,635.82
Potongan A5 876.24 17.47 64.16 56,219.54
Potongan A6 723.45 17.53 81.69 59,098.32
Potongan A7 627.63 17.53 99.22 62,273.92
Potongan A8 574.89 17.53 116.75 67,118.01
Potongan A9 540.27 17.53 134.28 72,547.53
Potongan A10 506.35 17.53 151.81 76,868.84

III. BAGIAN III


Potongan A10 - - - -
Potongan A11 207.09 26.36 26.36 5,458.95
Potongan A12
Potongan A13

IV. BAGIAN IV
Potongan A13
Potongan A14
Potongan A15
Potongan A16

V. BAGIAN V (Cluster utama)


Potongan A16 - - - -
Potongan 17 1,898.93 24.59 24.59 46,694.59
Potongan 18 1,585.79 42.11 66.70 105,772.01

VI. BAGIAN VI (Pintu masuk utama)


Potongan A19 - - - -
Potongan A20 1,464.16 51.86 51.86 75,931.12

Volume timbunan rencana : 321,432.30


Jumlah jam kerja : 1,993.75
Sewa alat + tmsk bahan bakar dll : 310000
Total biaya pekerjaan galian : 618,062,354
Penambahan biaya : 11,661.55

Luas Total Penampang 18,862.94


Volume pengurangan luas penampang 69876.59
Bobot pengurangan
Sisa Galian) b. Pekerjaan Timbunan Padat
I. BAGIAN I (Lahan alur barat)
KOMPONEN Luas
0 - Potongan A1 #DIV/0!
0.27 19,135.50 Potongan A1' 2712.12
0.68 47,416.86 Potongan A2 2712.12

II. BAGIAN II
0 - Potongan A2 #DIV/0!
0.16 11,273.64 Potongan A3 1391.81
0.17 11,659.96 Potongan A4 899.03
0.17 12,221.64 Potongan A5 685.75
0.18 12,847.46 Potongan A6 566.18
0.19 13,537.81 Potongan A7 491.19
0.21 14,590.87 Potongan A8 449.91
0.23 15,771.20 Potongan A9 422.82
0.24 16,710.62 Potongan A10 396.27

III. BAGIAN III


0 - Potongan A10 #DIV/0!
0.02 1,186.73 Potongan A11 162.07
Potongan A12
Potongan A13

IV. BAGIAN IV
Potongan A13
Potongan A14
Potongan A15
Potongan A16

V. BAGIAN V (Cluster utama)


0 - Potongan A16 #DIV/0!
0.15 10,151.00 Potongan 17 1486.12
0.33 22,993.92 Potongan 18 1241.05

VI. BAGIAN VI (Pintu masuk utama)


0 - Potongan A19 #DIV/0!
0.24 16,506.76 Potongan A20 1145.86

jam
/ Jam Sewa alat + tmsk bah

/m2
Jarak Σ Jarak Σ Volume

- - -
25.40 25.40 68,887.79
37.54 62.94 170,700.68

- - -
29.16 29.16 40,585.09
17.53 46.69 41,975.86
17.47 64.16 43,997.90
17.53 81.69 46,250.86
17.53 99.22 48,736.11
17.53 116.75 52,527.14
17.53 134.28 56,776.32
17.53 151.81 60,158.22

- - -
26.36 26.36 4,272.22

- - -
24.59 24.59 36,543.59
42.11 66.70 82,778.10

- - -
51.86 51.86 59,424.35

Volume timbunan rencana : 251,555.71


Jumlah jam kerja : 1,560.33
Sewa alat + tmsk bahan bakar dll : 310000
Total biaya pekerjaan galian : 483,700,972
Penambahan biaya : 9,126.43
b. Pekerjaan Timbunan Padat

I. BAGIAN I (Lahan alur barat)


KOMPONEN Luas Jarak Σ Jarak Σ Volume
Potongan A1 - - - -
Potongan A1' 2,712.12 25.40 25.40 68,887.79
Potongan A2 2,712.12 37.54 62.94 170,700.68

II. BAGIAN II
Potongan A2 1,320.31 - - -
Potongan A3 1,391.81 29.16 29.16 40,585.09
Potongan A4 899.03 17.53 46.69 41,975.86
Potongan A5 685.75 17.47 64.16 43,997.90
Potongan A6 566.18 17.53 81.69 46,250.86
Potongan A7 491.19 17.53 99.22 48,736.11
Potongan A8 449.91 17.53 116.75 52,527.14
Potongan A9 422.82 17.53 134.28 56,776.32
Potongan A10 396.27 17.53 151.81 60,158.22

III. BAGIAN III


Potongan A10 - - - -
Potongan A11 162.07 26.36 26.36 4,272.22
Potongan A12
Potongan A13

IV. BAGIAN IV
Potongan A13
Potongan A14
Potongan A15
Potongan A16

V. BAGIAN V (Cluster utama)


Potongan A16 - - - -
Potongan 17 1,486.12 24.59 24.59 36,543.59
Potongan 18 1,241.05 42.11 66.70 82,778.10

VI. BAGIAN VI (Pintu masuk utama)


Potongan A19 - - - -
Potongan A20 1,145.86 51.86 51.86 59,424.35

Volume timbunan rencana : 251,556


Jumlah jam kerja : 1,560
Sewa alat + tmsk bahan bakar dll : 310,000
Total biaya pekerjaan galian : 483,700,972
Penambahan biaya : 9,126
m3
jam
/ jam
/ m2
No.
Jenis Alat Berat EXCAVATOR
Merk KOMATSU
Type PC 400 6
Opr. Weight 41400 kg
Track Shoe 600 mm
Ground Pressure 0.79 mm
Boom 7.06
Arm 4.8

Data BUCKET
q1 volume Bucket
k bucket Factor

Data Lapangan
Kk kondisi lahan kerja
Ts jenis tanah

Data kondisi kerja


Ewo effisiensi kerja 50mnt/jam
Eop effisiensi operator sedang
Emt effisiensi material lunak
Etotal effisiensi total

Siklus & produksi Excavator


Wgali waktu gali
Wputar isi waktu putar isi
Wputar kembali waktu putar kembali
Wbuang waktu buang

Cm waktu siklus Cm = √ (Wgali + Wputar isi + Wputar kembali + Wbuang)

q produksi per siklus q = q1 x k

Q produksi per jam Q = (q x 3600 x E) / Cm

No.
Jenis Alat Berat BULLDOZER
Merk KOMATSU
Type D 65 E - 8
Opr. Weight 17515 kg
Flywheel HP 165 HP
L Lebar Blade 3.97 m
H Tinggi Blade 1.05 m

Data Lapangan
Ve Volume excavation total
Ts Jenis tanah
Tc Jenis galian

Kondisi lapangan
Kk Kondisi kerja / operating (sedang)
Mk Material keras
Eff Effisiensi kerja
A Blade factor
Eff_buck Bucket effisiensi

Siklus BULLDOZER
E Effisiensi E = Kk x Mk

D Jarak angkut
F Kecepatan maju 5 kpj 83.33 m/menit
R Kecepatan mundur 8 kpj 133.33 m/menit
Z Waktu ganti persnelling
Cm Waktu siklus Cm = (D/F) + (D/R) + Z

Produksi per siklus


q produksi per siklus q = L x H2 x A
Q produksi per jam Q = (q x 60 x E) / Cm
1
0.8

0.83
0.90
0.90
0.68

15 dt
5 dt
3 dt
6 dt

29 dt
0.8 m3
67.03 m3 / jam

111,235.05 m3
padas
padas

0.9
0.9
0.84
1.2
0.8

0.81
50 m
75 m/menit
120 m/menit
0.5 menit
1.58 menit

5.25 m3
161.22 m3 / jam