DAFTAR HARGA SATUAN UPAH DAN BAHAN

SATUAN HARGA KET.


NO. URAIAN SATUAN
(RP.)
A UPAH:
1 Tukang hari 50,000
2 Kepala Tukang hari 60,000
3 Pekerja hari 40,000
4 Mandor hari 55,000
B BAHAN/MATERIAL:
1 Amplas Biasa lbr. 5,000
2 Amplas Niken lbr. 6,000
3 Batu Bata bh. 400
4 Batu Kali m3 225,000
5 Besi Beton kg. 11,000
6 Bubungan Genteng Beton bh. 6,500
7 Cat Dasar kg. 15,000
8 Cat Kilat kg. 30,000
9 Cat Meni Nippon kg. 27,000
10 Cat Tembok kg. 10,000
11 Genteng Beton Lokal bh. 3,000
12 Grendel bh. 18,000
13 Kawat Pengikat kg. 7,800
14 Kayu Balok btg 60,000
16 Kayu Klas III m3 1,700,000
17 Kayu Klas IV m3 1,200,000
18 Keramik 30 x 30 cm m2 30,000
19 Koral Beton m3 130,000
20 List Profil N/K 1 m' 3,000
21 Minyak Cat ltr. 5,000
22 Paku Asbes bh. 950
23 Paku bermacam-macam ukuran kg 7,000
24 Paku Beton bh. 700
25 Paku Biasa kg. 7,000
26 Paku Plywood kg. 16,750
27 Paku Seng kg. 17,400
28 Pasir Pasang m3 175,000
30 Perekat/Adukan/Spesi m3 48,700
31 Pipa PVC f 3" m' 165,000
32 Pipa PVC f 4" m' 180,000
33 Plamir Kayu kg. 10,000
34 Plamir Tembok kg. 8,000
35 Plywood 3 mm m2 35,000
36 Plywood 4 mm m2 50,000
37 Split m3 205,000
38 Semen Portland (PC) 50 kg zak 48,000
39 Semen Putih zak 72,000
40 Seng Gelombang m2 35,000
41 Seng Plat m2 85,000
42 Tanah Urug m3 60,000
43 Ter / Residu ltr. 4,500
44 Thinner ltr. 12,000
45 Alat Bantu / Steiger Ls 26,000
46 Kayu Kasau 5/7 btg 11,500
47 Seng 7 Kaki kpg 54,500
48 Tanah Puru m3 66,000
49 Kusen Type PJ2a unit 350,000
50 Kusen Type PJ2b unit 350,000
51 Kusen Type P1 unit 300,000
53 Kusen jendela kamper singkil unit 200,000
56 Pintu Panil 85x210 cm bh. 750,000
57 Pintu Double Plywood 80x210 cm bh. 250,000
58 Pintu Double Plywood lapis Seng 70x210 cm bh. 350,000
59 Jendela 70x162 cm bh. 200,000
62 Kunci pintu bh. 70,000
63 Engsel pintu bh. 17,000
64 Engsel Jendea+Slot bh. 15,000
65 Railing Tangga besi bh. 1,500,000
66 Torrren Air 1000 ml bh. 1,800,000
DAFTAR ANALISA PEKERJAAN

I. PEKERJAAN PERSIAPAN
1. Analisa 10 m2 Pembersihan Lapangan
0.7500 Pekerja @Rp. 40,000.00 Rp. 30,000.00
0.0375 Mandor @Rp. 55,000.00 Rp. 2,062.50
Rp. 32,062.50
Untuk 1 M2 = 1/10 Rp. 3,206.25

2. Analisa 10 M' Pasangan Bouwplank


0.0500 M3 Kayu Klas IV @Rp. 1,200,000.00 Rp. 60,000.00
0.1000 Kg Paku Biasa @Rp. 7,000.00 Rp. 700.00
0.8000 Tukang @Rp. 50,000.00 Rp. 40,000.00
0.0800 Kepala Tukang @Rp. 60,000.00 Rp. 4,800.00
0.2800 Pekerja @Rp. 40,000.00 Rp. 11,200.00
0.0140 Mandor @Rp. 55,000.00 Rp. 770.00
Rp. 117,470.00
Untuk 1 M' = 1/10 Rp. 11,747.00

II. PEKERJAAN PONDASI.


1. Analisa 1 M3 Galian Tanah Pondasi
0.7500 Pekerja @Rp. 40,000.00 Rp. 30,000.00
0.0250 Mandor @Rp. 55,000.00 Rp. 1,375.00
Rp. 31,375.00

2. Analisa 1 M3 Urugan Pasir Bawah Pondasi


1.0000 m3 Pasir Urug @Rp. #REF! Rp. #REF!
0.3000 Pekerja @Rp. 40,000.00 Rp. 12,000.00
0.0100 Mandor @Rp. 55,000.00 Rp. 550.00
Rp. #REF!

3. Analisa 1 M3 Pasangan Pondasi Batu Kali


1.0000 M3 Batu kali @Rp. 225,000.00 Rp. 225,000.00
2.0240 Zak Semen Portland (PC) @Rp. 48,000.00 Rp. 97,152.00
0.4060 M3 Pasir Pasang @Rp. 175,000.00 Rp. 71,050.00
1.2000 Tukang @Rp. 50,000.00 Rp. 60,000.00
0.1200 Kepala Tukang @Rp. 60,000.00 Rp. 7,200.00
3.6000 Pekerja @Rp. 40,000.00 Rp. 144,000.00
0.1800 Mandor @Rp. 55,000.00 Rp. 9,900.00
Rp. 614,302.00

4. Analisa 1 M3 Urugan Tanah Urug biasa


1.2000 M3 Tanah Urug @Rp. 60,000.00 Rp. 72,000.00
0.3000 Pekerja @Rp. 40,000.00 Rp. 12,000.00
0.0330 Mandor @Rp. 55,000.00 Rp. 1,815.00
Rp. 85,815.00

III. PEK. BETON BERTULANG Ad. 1:2:3


a. Analisa 1 M Beton ad. 1 : 2 : 3
3

6.4000 Zak Semen Portland (PC) @Rp. 48,000.00 Rp. 307,200.00


0.5400 M3 Pasir Pasang @Rp. 175,000.00 Rp. 94,500.00
0.8200 M3 Koral Beton @Rp. 130,000.00 Rp. 106,600.00
1.0000 Tukang @Rp. 50,000.00 Rp. 50,000.00
0.1000 Kepala Tukang @Rp. 60,000.00 Rp. 6,000.00
6.0000 Pekerja @Rp. 40,000.00 Rp. 240,000.00
0.3000 Mandor @Rp. 55,000.00 Rp. 16,500.00
Rp. 820,800.00

b. Analisa Tulang Besi (Upah/100 kg/M 3)


110.0000 Kg Besi Beton @Rp. 11,000.00 Rp. 1,210,000.00
2.0000 Kg Kawat Pengikat @Rp. 7,800.00 Rp. 15,600.00
6.7500 Tukang @Rp. 50,000.00 Rp. 337,500.00
2.2500 Kepala Tukang @Rp. 60,000.00 Rp. 135,000.00
6.7500 Pekerja @Rp. 40,000.00 Rp. 270,000.00
Rp. 1,968,100.00

c. Analisa Upah Bekisting (Kayu Cetakan) / M3 Balok dan Kolom


0.4000 M3 Kayu Klas IV @Rp. 1,200,000.00 Rp. 480,000.00
4.0000 Kg Paku Biasa @Rp. 7,000.00 Rp. 28,000.00
5.0000 Tukang @Rp. 50,000.00 Rp. 250,000.00
0.5000 Kepala Tukang @Rp. 60,000.00 Rp. 30,000.00
2.0000 Pekerja @Rp. 40,000.00 Rp. 80,000.00
0.1000 Mandor @Rp. 55,000.00 Rp. 5,500.00
Rp. 873,500.00

d. Upah Pembongkaran Bekisting


4.0000 Pekerja @Rp. 40,000.00 Rp. 160,000.00
Rp. 160,000.00

Harga 1 M3 Beton Bertulang 1 : 2 : 3 (Praktis)


1.0000 Kl a @Rp. 820,800.00 Rp. 820,800.00
1.0000 Kl b @Rp. 1,968,100.00 Rp. 1,968,100.00
0.4000 Kl c @Rp. 873,500.00 Rp. 349,400.00
0.4000 Kl d @Rp. 160,000.00 Rp. 64,000.00
Rp. 3,202,300.00

VI. PEKERJAAN DINDING DAN PLESTERAN.


1. Analisa 1 M2 Pasangan Dinding Batu Bata ad. 1 : 4
45.0000 Bh Batu Bata Lubang @Rp. 400.00 Rp. 18,000.00
0.0920 Zak Semen Portland (PC) @Rp. 48,000.00 Rp. 4,416.00
0.0130 M 3
Pasir Pasang @Rp. 175,000.00 Rp. 2,275.00
0.1500 Tukang @Rp. 50,000.00 Rp. 7,500.00
0.0150 Kepala Tukang @Rp. 60,000.00 Rp. 900.00
0.4500 Pekerja @Rp. 40,000.00 Rp. 18,000.00
0.0225 Mandor @Rp. 55,000.00 Rp. 1,237.50
Rp. 52,328.50

2. Analisa 1 M2 Plesteran Kolom ad. 1 : 2


0.1120 Zak Semen Portland (PC) @Rp. 48,000.00 Rp. 5,376.00
0.0140 M3 Pasir Pasang @Rp. 175,000.00 Rp. 2,450.00
0.2000 Tukang @Rp. 50,000.00 Rp. 10,000.00
0.0200 Kepala Tukang @Rp. 60,000.00 Rp. 1,200.00
0.4000 Pekerja @Rp. 40,000.00 Rp. 16,000.00
0.0200 Mandor @Rp. 55,000.00 Rp. 1,100.00
Rp. 36,126.00
3. Analisa 1 M2 Plesteran ad. 1 : 4
0.0864 Zak Semen Portland (PC) @Rp. 48,000.00 Rp. 4,147.20
0.0139 M3 Pasir Pasang @Rp. 175,000.00 Rp. 2,432.50
0.1500 Tukang @Rp. 50,000.00 Rp. 7,500.00
0.0150 Kepala Tukang @Rp. 60,000.00 Rp. 900.00
0.4000 Pekerja @Rp. 40,000.00 Rp. 16,000.00
0.0200 Mandor @Rp. 55,000.00 Rp. 1,100.00
Rp. 32,079.70

VI. PEKERJAAN ATAP


1. Analisa 1 M3 Kuda-kuda / Gording
1.1000 M3 Kayu Klas III @Rp. 1,700,000.00 Rp. 1,870,000.00
24.0000 Tukang @Rp. 50,000.00 Rp. 1,200,000.00
2.4000 Kepala Tukang @Rp. 60,000.00 Rp. 144,000.00
8.0000 Pekerja @Rp. 40,000.00 Rp. 320,000.00
0.4000 Mandor @Rp. 55,000.00 Rp. 22,000.00
Untuk kuda-kuda bentangan diatas 9.00 m' Rp. 3,556,000.00
Untuk kuda-kuda bentangan s/d max = 9.00 m' upah x 75% Rp. 2,667,000.00

2. Analisa 1 M2 Rangka Atap kayu


0.0167 M3 Kayu Klas III @Rp. 1,700,000.00 Rp. 28,390.00
0.2500 Kg Paku Biasa @Rp. 7,000.00 Rp. 1,750.00
0.1000 Tukang @Rp. 50,000.00 Rp. 5,000.00
0.0100 Kepala Tukang @Rp. 60,000.00 Rp. 600.00
0.1000 Pekerja @Rp. 40,000.00 Rp. 4,000.00
0.0050 Mandor @Rp. 55,000.00 Rp. 275.00
Rp. 40,015.00

3. Analisa 1 M2 Atap Genteng Beton


10.0000 Bh Genteng Beton Lokal @Rp. 3,000.00 Rp. 30,000.00
0.2200 Tukang @Rp. 50,000.00 Rp. 11,000.00
0.0220 Kepala Tukang @Rp. 60,000.00 Rp. 1,320.00
0.3200 Pekerja @Rp. 40,000.00 Rp. 12,800.00
0.0160 Mandor @Rp. 55,000.00 Rp. 880.00
Rp. 56,000.00

4. Analisa 1 M' Nok Genteng Beton


4.5000 Bh Bubungan Genteng Beto @Rp. 6,500.00 Rp. 29,250.00
0.0880 Zak Semen Portland (PC) @Rp. 48,000.00 Rp. 4,224.00
0.0300 M3 Pasir Pasang @Rp. 175,000.00 Rp. 5,250.00
0.4000 Tukang @Rp. 50,000.00 Rp. 20,000.00
0.0400 Kepala Tukang @Rp. 60,000.00 Rp. 2,400.00
0.8000 Pekerja @Rp. 40,000.00 Rp. 32,000.00
0.0400 Mandor @Rp. 55,000.00 Rp. 2,200.00
Rp. 95,324.00

5. Analisa Baut Konstruksi


1.0000 Bh Baut 12 m pendek @Rp. 2,500.00 Rp. 2,500.00
1.0000 Bh Baut 12 m panjang @Rp. 4,000.00 Rp. 4,000.00
1.0000 Unit Plat Strip @Rp. 10,000.00 Rp. 10,000.00
1.0000 Unit Begel (type 1) @Rp. 25,000.00 Rp. 25,000.00
1.0000 Unit Begel (type 2) @Rp. 25,000.00 Rp. 25,000.00
1.0000 Unit Baut Angkur @Rp. 15,000.00 Rp. 15,000.00

Harga 42 bh Baut f 12 mm pendek adalah 42 Rp. 2,500.00


Rp. 105,000.00
Harga 12 bh Baut f 12 mm panjang adalah 12 Rp. 4,000.00
Rp. 48,000.00
Harga 31 bh Plat strip (dua sisi) adalah 31 Rp. 10,000.00
Rp. 310,000.00
Harga 1 bh Plat 50x50 mm adalah 1 Rp. 25,000.00
Rp. 25,000.00
Harga 13 bh Begel (type 1) adalah 13 Rp. 25,000.00
Rp. 325,000.00
Harga 3 bh Begel (type 2) adalah 3 Rp. 25,000.00
Rp. 75,000.00
Harga 4 bh Plat Strip U adalah 4 Rp. 30,000.00
Rp. 120,000.00
Harga 31 bh Baut angkur adalah 31 Rp. 15,000.00
Rp. 465,000.00
Harga 1 Pekerjaan baut konstruksi adalah Rp. 1,609,500.00

6. Analisa 1 M2 Listplank Kayu


0.0220 M3 Kayu Klas II @Rp. 1,700,000.00 Rp. 37,400.00
0.1000 Kg Paku Biasa @Rp. 7,000.00 Rp. 700.00
0.8000 Tukang @Rp. 50,000.00 Rp. 40,000.00
0.0800 Kepala Tukang @Rp. 60,000.00 Rp. 4,800.00
0.2800 Pekerja @Rp. 40,000.00 Rp. 11,200.00
0.0140 Mandor @Rp. 55,000.00 Rp. 770.00
Rp. 94,870.00

VI. PEKERJAAN LANTAI


1. Analisa 1 M2 Pasangan Lantai Keramik 30 x 30 cm
11.0000 Bh Keramik 30 x 30 @Rp. 30,000.00 Rp. 330,000.00
0.0960 Zak Semen Portland (PC) @Rp. 48,000.00 Rp. 4,608.00
0.0500 M3 Perekat @Rp. 48,700.00 Rp. 2,435.00
0.2500 Tukang @Rp. 50,000.00 Rp. 12,500.00
0.0250 Kepala Tukang @Rp. 60,000.00 Rp. 1,500.00
0.5000 Pekerja @Rp. 40,000.00 Rp. 20,000.00
0.0250 Mandor @Rp. 55,000.00 Rp. 1,375.00
Rp. 372,418.00

2. Analisa 1 M3 Beton ad. 1 : 2 : 3


6.4000 Zak Semen Portland (PC) @Rp. 48,000.00 Rp. 307,200.00
0.5400 M3 Pasir Pasang @Rp. 175,000.00 Rp. 94,500.00
0.8200 M 3
Koral Beton @Rp. 130,000.00 Rp. 106,600.00
1.0000 Tukang @Rp. 50,000.00 Rp. 50,000.00
0.1000 Kepala Tukang @Rp. 60,000.00 Rp. 6,000.00
6.0000 Pekerja @Rp. 40,000.00 Rp. 240,000.00
0.3000 Mandor @Rp. 55,000.00 Rp. 16,500.00
Rp. 820,800.00

VII. PEKERJAAN SALURAN


1. Analisa 1 M2 Pasangan Batu Bata ad. 1 : 4
45.0000 Bh Batu Bata Lubang @Rp. 400.00 Rp. 18,000.00
0.0920 Zak Semen Portland (PC) @Rp. 48,000.00 Rp. 4,416.00
0.0130 M3 Pasir Pasang @Rp. 175,000.00 Rp. 2,275.00
0.1500 Tukang @Rp. 50,000.00 Rp. 7,500.00
0.0150 Kepala Tukang @Rp. 60,000.00 Rp. 900.00
0.4500 Pekerja @Rp. 40,000.00 Rp. 18,000.00
0.0225 Mandor @Rp. 55,000.00 Rp. 1,237.50
Rp. 52,328.50

VIII. PEKERJAAN PINTU


1. Analisa Pintu
1 Unit Pintu @Rp. 50,000.00 Rp. 50,000.00

IX. PEKERJAAN PLAFOND DAN RANGKA


1. Analisa 1 M2 Plafond Plywood 4 mm
1.0000 m2 Plywood 4 mm @Rp. 50,000.00 Rp. 50,000.00
0.0100 m3 Kayu Klas III @Rp. 1,700,000.00 Rp. 17,000.00
0.2000 Kg Paku Biasa @Rp. 7,000.00 Rp. 1,400.00
0.0500 Kg Paku Plywood @Rp. 16,750.00 Rp. 837.50
0.8000 Tukang @Rp. 50,000.00 Rp. 40,000.00
0.0800 Kepala Tukang @Rp. 60,000.00 Rp. 4,800.00
0.2800 Pekerja @Rp. 40,000.00 Rp. 11,200.00
0.0140 Mandor @Rp. 55,000.00 Rp. 770.00
Rp. 126,007.50

2. Analisa 10 M' List Profil Kayu N/K 1


10.0000 m' List Profil N/K 1 @Rp. 3,000.00 Rp. 30,000.00
0.1000 Kg Paku Biasa @Rp. 7,000.00 Rp. 700.00
0.8000 Tukang @Rp. 50,000.00 Rp. 40,000.00
0.0800 Kepala Tukang @Rp. 60,000.00 Rp. 4,800.00
0.2800 Pekerja @Rp. 40,000.00 Rp. 11,200.00
0.0140 Mandor @Rp. 55,000.00 Rp. 770.00
Rp. 87,470.00
Untuk 1 M' = 1/10 Rp. 8,747.00

X. PEKERJAAN PENGECATAN
1. Analisa 10 M2 Pengecatan Tembok 3x sapu
3.5000 Kg Cat Tembok @Rp. 10,000.00 Rp. 35,000.00
2.0000 Kg Plamir Tembok @Rp. 8,000.00 Rp. 16,000.00
2.0000 Lbr Amplas Biasa @Rp. 5,000.00 Rp. 10,000.00
2.0000 Tukang @Rp. 50,000.00 Rp. 100,000.00
0.2000 Kepala Tukang @Rp. 60,000.00 Rp. 12,000.00
1.5000 Pekerja @Rp. 40,000.00 Rp. 60,000.00
0.0750 Mandor @Rp. 55,000.00 Rp. 4,125.00
Rp. 237,125.00
Untuk 1 M2 Rp. 23,712.50

2. Analisa 10 M2 Pengecatan Kayu Mengkilat 3x sapu


2.8400 Kg Cat Kilat @Rp. 30,000.00 Rp. 85,200.00
1.4200 Kg Cat Dasar @Rp. 15,000.00 Rp. 21,300.00
2.0000 Ltr Minyak Cat @Rp. 5,000.00 Rp. 10,000.00
1.2000 Kg Cat Meni Nippon @Rp. 27,000.00 Rp. 32,400.00
0.8000 Kg Plamir kayu @Rp. 10,000.00 Rp. 8,000.00
3.0000 Lbr Amplas Niken @Rp. 6,000.00 Rp. 18,000.00
2.2500 Tukang @Rp. 50,000.00 Rp. 112,500.00
0.2250 Kepala Tukang @Rp. 60,000.00 Rp. 13,500.00
1.5000 Pekerja @Rp. 40,000.00 Rp. 60,000.00
0.0750 Mandor @Rp. 55,000.00 Rp. 4,125.00
Rp. 365,025.00
Untuk 1 M2 Rp. 36,502.50

3. Analisa 10 M2 Cat Plafond 3x sapu


2.8000 Kg Cat Tembok @Rp. 10,000.00 Rp. 28,000.00
1.0000 Ls Alat Bantu / Steiger @Rp. 26,000.00 Rp. 26,000.00
1.5000 Tukang @Rp. 50,000.00 Rp. 75,000.00
0.1500 Kepala Tukang @Rp. 60,000.00 Rp. 9,000.00
1.0000 Pekerja @Rp. 40,000.00 Rp. 40,000.00
0.0500 Mandor @Rp. 55,000.00 Rp. 2,750.00
Rp. 180,750.00
Untuk 1 M2 Rp. 18,075.00

XI. PEKERJAAN LAIN-LAIN


1. Pas. Railing tangga
1 bh Railing Tangga @Rp. 1,500,000.00 Rp. 1,500,000.00
1. Pek. Sumur resapan
1 bh Sumur Resapan @Rp. 1,000,000.00 Rp. 1,000,000.00
2. Pas. Torren
2 bh Pas. Torren @Rp. 1,800,000.00 Rp. 3,600,000.00

25.00 titik Instalasi Listrik @Rp. 130,000.00 Rp. 3,250,000.00


Rp. 9,350,000.00

Untuk 1 M2 = 1/10 935,000.00


DAFTAR BOBOT
PEMBANGUNAN RUMAH TINGGAL

I. PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan 140 M2
2 Pasangan Bouwplank / Pengukuran 140 M'
3 Biaya Air Kerja 1 Ls

II. PEKERJAAN PONDASI.


1 Galian Tanah Pondasi 20 M3
2 Urugan Pasir Bawah Pondasi 4 M3
3 Pasangan Pondasi Batu kali T 1.20 21 M3
4 Urugan Tanah Kembali bekas Galian 10 M3

III. PEK. BETON BERTULANG Ad. 1:2:3


1 Sloof Beton Bangunan 20/25 6.5 M3
2 Sloof Beton Pagar 1.62 M3
3 Kolom Beton Bangunan u 15/15 4.5 M3
4 Kolom Beton Pagar 1500 M3
5 Ring Balok Beton Bangunan u 15/20 cm 5 M3
6 Ring Balok Beton Pagar 1.62 M3

VI. PEKERJAAN DINDING DAN PLESTERAN.


1 Pas. Dinding Batu Bata Bangunan adukan 1 : 250 M2
2 Pas. Dinding Batu Bata Pagar adukan 1 : 4 34 M2
3 Plesteran Kolom Pagar adukan 1 : 2 31.04 M2
4 Plesteran Dind. Batu Bata Banguann ad. 1 : 300 M2
5 Plesteran Dinding Batu Bata Pagar ad. 1 : 4 34 M2

VI. PEKERJAAN ATAP


1 Balok Dinding 8/12 Kayu Klas III 0.2196 M3
2 Kuda-kuda Kayu Klas III 4 M3
4 Bubungan dan Jurai 8/12 Kayu Klas III 5 M3
5 Rangka Atap Kayu Klas III 3 M2
6 Atap Genteng Beton 3 bh
7 Nok Genteng Beton 31.39 M'
8 Baut Konstruksi f12 mm 1 Pek
9 Listplank 3/30 Kayu Klas III 70 M2

VI. PEKERJAAN LANTAI.


1 Beton Lantai adukan 1:2:3 65,2 M3
2 Pasangan Lantai Keramik 30/30 60 M2
3 Beton/cor lantai atas ad. 1 : 2 : 3 0 M2

VII. PEKERJAAN SALURAN


Pekerjaan Saluran Keliling 60 M2

VIII. PEKERJAAN PINTU


1 Kusen jendela dan pintu kamper singkil 8 Unit
2 Pintu Panil 2 Unit
3 Pintu Double Plywood 2 Unit
4 Pintu Double Plywood lapis Seng 2 Unit
5 Jendela 4 Unit

IX. PEKERJAAN PLAFOND DAN RANGKA.


1 Pas. Plafond Triplek 4 mm 65,2 M2
2 List Plafond 65,2 M2
X. PEKERJAAN PENGECATAN
1 Pengecatan Dinding dan Kolom 200 M2
2 Pengecatan Listplank 45 M2
3 Pengecatan Plafond Luar dan Dalam 65,2 M2

XI. PEKERJAAN PAGAR


1 Luas Pagar Besi 10 M2
2 Luas Pintu Pagar Besi 6.5 M2

XII. PEKERJAAN LAIN-LAIN


pas. Railing tangga 1 bh
Pas Torren air 1 bh
Pek. Instalasi listrik 1 pek
Pek. Instalasi Plambing 1 pek
RENCANA ANGGARAN BIAYA (RAB)
PEMBANGUNAN RUMAH TINGGAL

hrga satuan JUMLAH


NO URAIAN PEKERJAAN Bobot SAT (Rp) (Rp)

I. PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan 140.00 M2 3,206.25 448,875.00
2 Pas. Bouwplank / Pengukuran 140.00 M' 11,747.00 1,644,580.00

2,093,455.00

II. PEKERJAAN PONDASI.


1 Galian Tanah Pondasi 20.00 M3 31,375.00 627,500.00
3 Pas. Pondasi Batu kali 21.00 M3 614,302.00 12,900,342.00
4 Urugan Tnh. Kembali bks. Galian 10.00 M3 85,815.00 858,150.00
14,385,992.00

III. PEKERJAAN BETON BERTULANG


1 Sloof Beton Bangunan 15/20 6.50 M3 3,202,300.00 20,814,950.00
2 Sloof Beton Pagar15/20 1.62 M3 3,202,300.00 5,187,726.00
3 Kolom Beton Bangunan 20/20 4.50 M3 3,202,300.00 14,410,350.00
4 Kolom Beton Pagar 20/20 2.38 M3 3,202,300.00 7,634,283.20
5 R. Balok Beton Bangunan 10/15 5.00 M3 3,202,300.00 16,011,500.00
6 Ring Balok Beton Pagar 10/15 1.62 M3 3,202,300.00 5,187,726.00
64,058,809.20

IV. PEKERJAAN DINDING & PLESTERAN.


1 Pas. Dind. Bata Bang. ad. 1 : 4 550.00 M2 52,328.50 28,780,675.00
2 Pas. Dinding Bata Pagar ad. 1 : 4 250.00 M2 52,328.50 13,082,125.00
3 Plesteran Kolom Pagar ad. 1 : 2 31.04 M2 36,126.00 1,121,351.04
4 Plest. Dind. Bata Bang. ad. 1 : 4 300.00 M2 32,079.70 9,623,910.00
5 Plest. Dind. Bata Pagar ad. 1 : 4 250.00 M2 32,079.70 8,019,925.00
52,608,061.04

V. PEKERJAAN ATAP
1 Balok Dinding 8/12 Kayu Klas III 0.22 M3 2,667,000.00 585,673.20
2 Kuda-kuda Kayu Klas III 4.00 M3 2,667,000.00 10,668,000.00
4 Bubungan 8/12 Kayu Klas III 5.00 M3 2,667,000.00 13,335,000.00
5 Rangka Atap Kayu Klas III 3.00 M2 40,015.00 120,045.00
6 Atap Genteng Beton 3.00 M2 56,000.00 168,000.00
7 Nok Genteng Beton 31.39 M' 95,324.00 2,992,220.36
8 Baut Konstruksi f12 mm 1.00 Pek 1,609,500.00 1,609,500.00
9 Listplank 3/30 Kayu Klas III 60.00 M2 94,870.00 5,692,200.00
35,170,638.56

VI. PEKERJAAN LANTAI.


1 Beton Lantai adukan 1:2:3 65,2 M3 820,800.00 53,516,160.00
2 Pasangan Lantai Keramik 30/30 60.00 M3 372,418.00 22,345,080.00
75,861,240.00

VII. PEKERJAAN SALURAN


Pekerjaan Saluran Keliling 60.00 M' 52,328.50 3,139,710.00

VIII. PEKERJAAN KUSEN DAN PINTU


1 Kusen Jendela dan pintu 33.00 Unit 200,000.00 6,600,000.00
2 Pintu Panil 8.00 Unit 750,000.00 6,000,000.00
3 P. Double Plywood 8.00 Unit 250,000.00 2,000,000.00
4 P. Double Ply. Lapis Seng 4.00 Unit 350,000.00 1,400,000.00
5 Jendela 13.00 Unit 200,000.00 2,600,000.00
18,600,000.00

IX. PEKERJAAN PLAFOND & RANGKA.


1 Pas. Plafond Triplek 4 mm 65,2 M2 126,007.50 #VALUE!
2 List Plafond 65,2 M' 8,747.00 #VALUE!
#VALUE!

X. PEKERJAAN PENGECATAN
1 Pengecatan Dinding dan Kolom 200.00 M2 23,712.50 4,742,500.00
2 Pengecatan Listplank 60.00 M2 36,502.50 2,190,150.00
3 Pengec. Plafond Luar dan Dalam 189.90 M2 18,075.00 3,432,442.50
10,365,092.50

X. PEKERJAAN PAGAR
1 Luas Pagar Besi 10.00 M2 23,712.50 237,125.00
2 Luas Pintu Pagar Besi 6.50 M2 18,075.00 117,487.50
354,612.50

XI. PEKERJAAN LAIN-LAIN


1 Pas. Railing Tangga 1.00 bh 1,500,000.00 1,500,000.00
2 Sumur Reapan 1.00 bh 1,000,000.00 1,000,000.00
3 Pas. Torren 2.00 bh 1,800,000.00 3,600,000.00
4 Instalasi Plambing 1.00 Pek 6,500,000.00 6,500,000.00
5 Instalasi Listrik 25.00 titik 130,000.00 3,250,000.00
15,850,000.00
###
###
###
###
###
REKAPITULASI
PEMBANGUNAN RUMAH

I. PEKERJAAN PERSIAPAN Rp. 2,093,455.00

II. PEKERJAAN PONDASI. Rp. 14,385,992.00

III. PEK. BETON BERTULANG Ad. 1:2:3 Rp. 64,058,809.20

IV. PEKERJAAN DINDING DAN PLESTERAN. Rp. 52,608,061.04

V. PEKERJAAN ATAP Rp. 35,170,638.56

VI. PEKERJAAN LANTAI Rp. 75,861,240.00

VII. PEKERJAAN SALURAN Rp. 3,139,710.00

VIII. PEKERJAAN KUSEN DAN PINTU Rp. 18,600,000.00

IX. PEKERJAAN PLAFOND DAN RANGKA. Rp. #VALUE!

X. PEKERJAAN PENGECATAN Rp. 10,365,092.50

XI. PEKERJAAN PAGAR Rp. 10,365,092.50

XII. PEKERJAAN LAIN-LAIN Rp. 15,850,000.00

JUMLAH Rp. #VALUE!

TOTAL BIAYA Rp. #VALUE!