HARGA SATUAN

NO URAIAN SAT
( Rp. )
1 2 3 4
A BAHAN AGREGAT KASAR DAN BAHAN PEREKAT
1 Tanah urug m3 12,000.00
2 Pasir urug m3 40,000.00
3 Pasir pasang m3 65,000.00
4 Pasir beton Cimalaka m3 120,000.00
5 Batu belah pondasi m3 70,000.00
6 Batu pecah mesin 1/2 m3 140,000.00
7 Batu pecah mesin 2/3 m3 130,000.00
8 Batu pecah 3/5 m3 100,000.00
9 Batu apung Kg 11,000.00
10 semen tiga roda Kg 750.00
11 Semen putih Kg 2,000.00
12 Semen warna muda Kg 2,000.00
13 Semen warna tua Kg 2,000.00
14 Lem putih Fox Kg 12,000.00

B BAHAN PENUTUP DINDING


1 Bata merah bh 250.00
2 Bata terawang/loster bh 2,500.00

C BAHAN LOGAM DLL


1 Besi U-24 rata-rata uk. Dia 8 - 16 mm Kg 7,000.00
2 Seng plat BJLS 28 (90 x 180 cm) Lbr 45,000.00
3 Besi strip uk. 3 x 30 mm x 6 m (4,21 kg) Kg 5,000.00
4 Kawat beton Kg 10,000.00
5 Paku 1/2" - 3" Kg 10,000.00
6 Paku 3" - 5" Kg 10,000.00
7 Paku 5" - 12" Kg 8,000.00
8 Paku seng Kg 13,000.00
9 Paku asbes Kg 15,000.00
10 Allumunium Sheet m2 6,000.00
11 Gravel Beton 1/2 Dia 20 - 40 cm m' 22,500.00

D BAHAN PENGUNCI/PENGGANTUNG, KACA DLL


1 Engsel pintu nylon besar psg 10,000.00
2 Engsel pintu nylon kecil psg 8,000.00
3 Engsel jendela biasa psg 7,500.00
4 Engsel angin psg 3,500.00
5 Grendel jendela (spring knip) bh 10,000.00
6 Grendel jendela biasa (slot) bh 5,000.00
7 Grendel tanam pintu ganda (espagnolet) bh 15,000.00
8 Hak angin stainles bh 6,000.00
9 Hak angin kait biasa bh 2,500.00
10 Slot pintu dan jendela bh 4,500.00
11 Kunci pintu cap kuda terbang type besar bh 90,000.00
12 Kunci pintu cap kuda terbang type kecil bh 75,000.00
13 Kunci pintu kamar mandi, ALPA bh 65,000.00
14 Kaca polos 3 mm m2 42,500.00
15 Kaca polos 5 mm m2 55,000.00
16 Kertas ampelas kayu tembok lbr 2,000.00
17 Kape kayu 2" bh 2,000.00
18 Kape tembok bh 1,500.00
19 Kuas cat 3 - 4" bh 3,500.00
20 Rol cat bh 6,000.00
21 Bak mandi Fiber bh 75,000.00
22 Kloset jongkok, sek INA bh 500,000.00

E BAHAN KAYU/KAYU LAPIS DAN PLAFON


1 Kayu balok albasiah m3 300,000.00
2 Kayu papan albasiah m3 410,000.00
3 Kayu balok borneo m3 2,000,000.00
4 Kayu kaso borneo m3 2,000,000.00
5 Kayu papan borneo uk. 3/20 m3 2,100,000.00
6 Kayu balok borneo super (maranti) m3 2,800,000.00
HARGA SATUAN
NO URAIAN SAT
( Rp. )
1 2 3 4
7 Kayu papan borneo super (maranti) uk. 3/20 m3 2,500,000.00
8 Kayu papan borneo super (maranti) uk. 3/30 m3 2,500,000.00
9 Kayu balok kamper banjar m3 4,500,000.00
10 Kayu papan kamper banjar uk. 3/20 m3 4,500,000.00
11 Kayu papan kamper banjar uk. 3/30 m3 4,600,000.00
12 Kayu balok kamper samarinda m3 4,000,000.00
13 Kayu papan kamper samarinda 3/20 m3 4,000,000.00
14 Reng 2/3 kayu borneo super maranti btg 6,750.00
15 Reng 3/4 kayu borneo super maranti btg 13,500.00
16 Kayu dolken dia 8 - 10 cm btg 17,500.00
17 Bambu dia 5 - 7 cm btg 10,000.00
18 Bambu dia 7 - 10 cm btg 15,000.00
19 Triplek 3 mm 1,20 x 2,40 m lbr 42,500.00
20 Triplek 4 mm lbr 60,000.00
21 Multiplek 9 mm 1,20 x 2,40 m lbr 120,000.00
22 Multiplek 12 mm 1,20 x 2,40 m lbr 135,000.00
23 Multiplek 15 mm 1,20 x 2,40 m lbr 150,000.00
24 Multiplek 18 mm 1,20 x 2,40 m lbr 180,000.00
25 Teakwood 4 mm 1,20 x 2,40 m lbr 120,000.00
26 Milamin 4 mm 1,20 x 2,40 m lbr 62,500.00
27 Eternit biasa lbr 2,500.00
28 Eternit cap bola dunia lbr 5,000.00
29 Eternit cap dua gajah lbr 7,500.00
30 Eternit cap Hardflek 5 mm uk 1,05 x 1,80 m lbr 75,000.00
31 Eternit cap Hardflek 5 mm uk 1,05 x 2,40 m lbr 150,000.00
32 Eternit Triplek 4 mm, 1,00 x 1,00 x 4,0 mm lbr 11,500.00
33 List profil 2x2 cm m' 3,500.00
34 List profil 1x3 cm m' 2,000.00
35 List kayu 1x4 cm m' 2,500.00
36 List kayu 1x5 cm m' 3,000.00
37 List kayu 2x4 cm m' 3,500.00

F BAHAN PENUTUP ATAP


1 Genteng kodok natural ek. Jati wangi bh 1,000.00
2 Genteng palentong natural ek. Jati wangi bh 850.00
3 Genteng bubung segitiga/bulat natural bh 2,000.00
4 Genteng bubung palentong besar natural bh 2,000.00
5 Asbes Gelombang lbr 37,500.00
6 Bubung Asbes gelombang bh 7,500.00

G BAHAN PENUTUP LANTAI


1 Keramik lantai wc 20/20 polos, sek Mulia m2 37,500.00
2 Keramik lantai wc 20/20 corak warna, sek Mulia m2 42,500.00
3 Keramik dinding 20/25 polos, sek Mulia m2 35,000.00
4 Keramik dinding 20/25 corak warna, sek Mulia m2 37,500.00
5 Kramik lantai 30/30 putih polos sek Mulia m2 31,000.00
6 Kramik lantai 30/30 Warna sek Mulia m2 34,000.00
7 Paving block natural tinggi 6 cm m2 23,000.00
8 Paving block warna tinggi 6 cm m2 25,000.00
9 Paving block natural tinggi 8 cm m2 27,500.00
10 Paving block warna tinggi 8 cm m2 30,000.00
11 Marmer m2 250,000.00

H BAHAN ALAT-ALAT LISTRIK


1 Kabel NYM 3 x 2,5, sek Prima m' 4,500.00
2 Solatif kabel roll 2,500.00
3 Pipa listrik lt 3,000.00
4 T-Dus bh 500.00
5 Inbow Dus bh 1,000.00
6 Lampu TL Phillips 5 - 25 Watt bh 25,000.00
7 Lampu pijar Phillip 5 - 25 Watt bh 5,000.00
8 Lampu pijar Phillip 40 - 80 Watt bh 7,500.00
9 Stop kontak, sek Broco bh 7,500.00
10 Saklar tunggal, sek Broco bh 7,500.00
11 Saklar ganda, sek Broco bh 10,000.00
12 Pitting ;ampu, sek Broco bh 5,000.00
HARGA SATUAN
NO URAIAN SAT
( Rp. )
1 2 3 4
I ALAT-ALAT SANITASI AIR
1 Pipa PVC 1/2" m' 3,000.00
2 Pipa PVC 1,5" m' 2,000.00
3 PIPA PVC 3" m' 15,000.00
4 Pipa PVC 4" m' 20,000.00
5 Soket 4" bh 4,000.00
6 Injuk kg 3,000.00

J BAHAN FINISHING
1 Cat dasar tembok, indo 9000 sealer water base Kg 7,000.00
2 Cat kayu sek SEIV Kg 28,000.00
3 Cat dasr kayu ltr 5,000.00
4 Meni kayu besi Bola Mas Kg 12,500.00
5 Plincoat ltr 10,000.00
6 Cat tembok, sek SANLEK kg 10,000.00
7 Dempul tembok (plamur Sanlek) Kg 17,500.00
8 Dempul kayu cap Kucing Kg 12,000.00
9 Thiner (minyak cat) ltr 12,500.00
10 Solignem (a blek 10 ltr) ltr 2,500.00
11 Spirtus ltr 3,500.00
12 Minyak tanah/solar ltr 4,500.00
13 Politur ltr 8,500.00
14 Plitur jadi Ultran ltr 22,000.00
15 Kertas ampelas kayu-tembok lbr 2,000.00
16 Kape kayu 2" bh 2,500.00
17 Kape tembok bh 2,500.00
18 Kuas 3-4" bh 3,500.00
19 Roll cat bh 6,000.00
DAFTAR HARGA SATUAN UPAH
0
0
0

HARGA DASAR
NO. URAIAN SAT
( Rp. )
1 2 3 4
1 Pekerja Org/hr 25,000.00
2 Tukang batu / tukang kayu Org/hr 30,000.00
3 Tukang besi profil / tukang las Org/hr 30,000.00
4 Tukang besi beton Org/hr 30,000.00
5 Tukang cat Org/hr 30,000.00
6 Tukang gali Org/hr 30,000.00
7 Kepala tukang batu / kayu Org/hr 35,000.00
8 Kepala tukang besi profil / las Org/hr 35,000.00
9 Kepala tukang besi beton Org/hr 35,000.00
10 Kepala tukang cat Org/hr 35,000.00
11 Kepala tukang gali Org/hr 35,000.00
12 Mandor Org/hr 40,000.00
ANALISA HARGA SATUAN PEKERJAAN
PEMBANGUNAN RUMAH SATU LANTAI TYPE II

HARGA
JUMLAH HARGA JUMLAH HARGA
SATUAN
NO. URAIAN SAT. KOEF.
BAHAN /
UPAH BAHAN UPAH BAHAN + UPAH
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
1 2 3 4 5 6 7 8
1 1M2 PEKERJAAN PENGUKURAN SITE
Bahan :
Peralatan lot 0.5000 1,000.00 500.00
Tenaga :
Pekerja Oh 0.0200 25,000.00 500.00
Tukang Oh 0.0100 30,000.00 300.00
Jumlah 500.00 800.00 1,300.00
Keuntungan Maksimal 10 % 130.00
Jumlah 1,430.00
Dibuilatkan 1,430.00
2 1M3 PEKERJAAN STRIPPING SEDALAM 0,1 M
Tenaga
Pekerja Oh 0.0500 25,000.00 1,250.00
Mandor Oh 0.0050 40,000.00 200.00
Jumlah 1,450.00 1,450.00
Keuntungan Maksimal 10 % 145.00
Jumlah 1,595.00
Dibuilatkan 1,590.00
4 1M2 PEMBERSIHAN LAPANGAN DAN PERATAAN
Tenaga :
Pekerja Oh 0.1000 25,000.00 2,500.00
Mandor Oh 0.0500 40,000.00 2,000.00
Jumlah 4,500.00 4,500.00
Keuntungan Maksimal 10 % 450.00
Jumlah 4,950.00
Dibuilatkan 4,950.00
5 1M' PASANGAN BOUWPLANK
Bahan :
Kayu papan 3/20 m3 0.0070 410,000.00 2,870.00
Kayu kaso albasiah m3 0.0120 300,000.00 3,600.00
Paku 2" - 5" kg 0.0200 8,000.00 160.00
Tenaga :
Tukang kayu oh 0.1000 30,000.00 3,000.00
Pekerja oh 0.1000 25,000.00 2,500.00
Kepala tukang kayu oh 0.0100 35,000.00 350.00
Mandor oh 0.0050 40,000.00 200.00
Jumlah 6,630.00 6,050.00 12,680.00
Keuntungan Maksimal 10 % 1,268.00
Jumlah 13,948.00
Dibuilatkan 13,940.00
HARGA
JUMLAH HARGA JUMLAH HARGA
SATUAN
NO. URAIAN SAT. KOEF.
BAHAN /
UPAH BAHAN UPAH BAHAN + UPAH
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
1 2 3 4 5 6 7 8
6 1M3 GALIAN TANAH BIASA KEDALAMAN 1 M
Tenaga :
Pekerja oh 0.4000 25,000.00 10,000.00
Mandor oh 0.0400 40,000.00 1,600.00
Alat Bantu ls 1.0000 2,500.00 2,500.00
Jumlah 14,100.00 14,100.00
Keuntungan Maksimal 10 % 1,410.00
Jumlah 15,510.00
Dibuilatkan 15,510.00
7 1M3 GALIAN TANAH BIASA KEDALAMAN 2 M
Tenaga :
Pekerja oh 0.5260 25,000.00 13,150.00
Mandor oh 0.0520 40,000.00 2,080.00
Alat Bantu ls 1.0000 2,500.00 2,500.00
Jumlah 17,730.00 17,730.00
Keuntungan Maksimal 10 % 1,773.00
Jumlah 19,503.00
Dibuilatkan 19,500.00
10 1M3 URUGAN TANAH KEMBALI
Tenaga :
Pekerja oh 0.1900 25,000.00 4,750.00
Mandor oh 0.0200 40,000.00 800.00
Alat Bantu[ ls 1.0000 500.00 500.00
Jumlah 6,050.00 6,050.00
Keuntungan Maksimal 10 % 605.00
Jumlah 6,655.00
Dibuilatkan 6,650.00
11 1M3 URUGAN PASIR
Bahan :
Pasir urug m3 1.2000 40,000.00 48,000.00
Tenaga :
Pekerja oh 0.1500 25,000.00 3,750.00
Mandor oh 0.0100 40,000.00 400.00
Alat Bantu ls 1.0000 2,000.00
Jumlah 48,000.00 4,150.00 52,150.00
Keuntungan Maksimal 10 % 5,215.00
Jumlah 57,365.00
Dibuilatkan 57,360.00
12 1M3 PASANGAN PONDASI BATU KOSONG AANSTAMPING
Bahan :
Batu belah 15 - 20 cm m3 1.2000 70,000.00 84,000.00
Pasir urug m3 0.4000 40,000.00 16,000.00
Tenaga :
Pekerja oh 0.5000 25,000.00 12,500.00
Tukang batu oh 0.5620 30,000.00 16,860.00
Kepala tukang batu oh 0.0750 35,000.00 2,625.00
Mandor oh 0.0560 40,000.00 2,240.00
Jumlah 100,000.00 34,225.00 134,225.00
Keuntungan Maksimal 10 % 13,422.50
Jumlah 147,647.50
Dibuilatkan 147,640.00

13 1M3 PASANGAN PONDASI BATU KALI 1 PC : 5 PS


Bahan :
Batu belah 15 - 20 cm m3 1.2000 70,000.00 84,000.00
Semen portland kg 136.0000 750.00 102,000.00
Pasir pasang m3 0.5440 65,000.00 35,360.00
Tenaga :
Pekerja oh 1.5000 25,000.00 37,500.00
Tukang batu oh 0.6000 30,000.00 18,000.00
Kepala tukang batu oh 0.0600 35,000.00 2,100.00
Mandor oh 0.0750 40,000.00 3,000.00
Jumlah 221,360.00 60,600.00 281,960.00
Keuntungan Maksimal 10 % 28,196.00
Jumlah 310,156.00
Dibuilatkan 310,150.00
14 1M2 PASANGAN BATA TRASRAAM 1 PS : 3 PS
Bahan :
Bata merah KW II bh 80.0000 250.00 20,000.00
PC kg 26.5000 750.00 19,875.00
Pasir pasang m3 0.0465 65,000.00 3,022.50
Tenaga :
Pekerja org 0.4800 25,000.00 12,000.00
Tukang batu org 0.1600 30,000.00 4,800.00
Kepala tukang batu org 0.0160 35,000.00 560.00
Mandor org 0.0480 40,000.00 1,920.00
Jumlah 42,897.50 19,280.00 62,177.50
Keuntungan Maksimal 10 % 6,217.75
Jumlah 68,395.25
Dibuilatkan 68,390.00
15 1M2 PASANGAN BATA MERAH TEBAL 1/2 BATA 1PC : 3 PS
Bahan :
Bata merah m3 70.0000 250.00 17,500.00
Semen portland kg 21.0000 750.00 15,750.00
Pasir pasang m3 0.0500 65,000.00 3,250.00
Tenaga :
Pekerja oh 0.4300 25,000.00 10,750.00
Tukang batu oh 0.2100 30,000.00 6,300.00
Kepala tukang batu oh 0.0200 35,000.00 700.00
Mandor oh 0.0100 40,000.00 400.00
Jumlah 36,500.00 18,150.00 54,650.00
Keuntungan Maksimal 10 % 5,465.00
Jumlah 60,115.00
Dibuilatkan 60,110.00
16 1M2 PASANGAN BATA MERAH TEBAL 1/2 BATA 1PC : 5 PS
Bahan :
Bata merah m3 70.0000 250.00 17,500.00
Semen portland kg 10.5000 750.00 7,875.00
Pasir pasang m3 0.0600 65,000.00 3,900.00
Tenaga :
Pekerja oh 0.3200 25,000.00 8,000.00
Tukang batu oh 0.1800 30,000.00 5,400.00
Kepala tukang batu oh 0.0200 35,000.00 700.00
Mandor oh 0.0100 40,000.00 400.00
Jumlah 29,275.00 14,500.00 43,775.00
Keuntungan Maksimal 10 % s 4,377.50
Jumlah 48,152.50
Dibuilatkan 48,150.00
17 1M2 PLESTERAN DINDING + ACIAN 1 : 2
Bahan :
PC kg 15.0000 750.00 11,250.00
Pasir pasang m3 0.0200 65,000.00 1,300.00
Tenaga :
Pekerja org 0.2900 25,000.00 7,250.00
Tukang batu org 0.2100 30,000.00 6,300.00
Kepala tukang batu org 0.0200 35,000.00 700.00
Mandor org 0.0200 40,000.00 800.00
Jumlah 12,550.00 15,050.00 27,600.00
Keuntungan Maksimal 10 % 2,760.00
Jumlah 30,360.00
Dibuilatkan 30,360.00
HARGA
JUMLAH HARGA JUMLAH HARGA
SATUAN
NO. URAIAN SAT. KOEF.
BAHAN /
UPAH BAHAN UPAH BAHAN + UPAH
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
1 2 3 4 5 6 7 8
18 1M2 PLESTERAN DINDING + ACIAN 1 : 3
Bahan :
Semen portland kg 8.0000 750.00 6,000.00
Pasir pasang m3 0.0200 65,000.00 1,300.00
Tenaga :
Pekerja oh 0.2900 25,000.00 25,000.00 7,250.00
Tukang batu oh 0.2100 30,000.00 30,000.00 6,300.00
Kepala tukang batu oh 0.0200 35,000.00 35,000.00 700.00
Mandor oh 0.0200 40,000.00 40,000.00 800.00
Jumlah 137,300.00 15,050.00 152,350.00
Keuntungan Maksimal 10 % 15,235.00
Jumlah 167,585.00
Dibuilatkan 167,580.00
19 1M2 PLESTERAN DINDING + ACIAN 1 : 5
Bahan :
Semen portland kg 5.0000 750.00 3,750.00
Pasir pasang m3 0.0200 65,000.00 1,300.00
Tenaga :
Pekerja oh 0.2900 25,000.00 7,250.00
Tukang batu oh 0.2100 30,000.00 6,300.00
Kepala tukang batu oh 0.0200 35,000.00 700.00
Mandor oh 0.0200 40,000.00 800.00
Jumlah 5,050.00 15,050.00 20,100.00
Keuntungan Maksimal 10 % 2,010.00
Jumlah 22,110.00
Dibuilatkan 22,110.00
20 1M2 FINISHING ACIAN
Bahan :
Semen portland kg 4.0000 750.00 3,000.00
Tenaga :
Pekerja oh 0.1400 25,000.00 3,500.00
Tukang batu oh 0.1100 30,000.00 3,300.00
Kepala tukang batu oh 0.0100 35,000.00 350.00
Mandor oh 0.0100 40,000.00 400.00
Jumlah 3,000.00 7,550.00 10,550.00
Keuntungan Maksimal 10 % 1,055.00
Jumlah 11,605.00
Dibuilatkan 11,600.00
21 1M2 PLESTERAN BETON 1PC : 3 PS T = 15 MM
Bahan :
Semen portland kg 7.0700 750.00 5,302.50
Pasir pasang m3 0.0210 65,000.00 1,365.00
Tenaga :
Pekerja oh 0.2600 25,000.00 6,500.00
Tukang batu oh 0.2000 30,000.00 6,000.00
Kepala tukang batu oh 0.0200 35,000.00 700.00
Mandor oh 0.0130 40,000.00 520.00
Jumlah 6,667.50 13,720.00 20,387.50
Keuntungan Maksimal 10 % 2,038.75
Jumlah 22,426.25
Dibuilatkan 22,420.00
22 1M3 PASANGAN KUSEN PINTU / JENDELA KAYU SAMARINDA
Bahan :
Kayu balok kamper samarinda m3 1.1000 4,000,000.00 4,400,000.00
Paku kg 1.2500 8,000.00 10,000.00
Lem Fox kg 1.0000 12,000.00 12,000.00
Tenaga :
Pekerja oh 4.0000 25,000.00 100,000.00
Tukang kayu oh 15.5000 30,000.00 465,000.00
Kepala tukang kayu oh 2.7000 35,000.00 94,500.00
Mandor oh 0.5000 40,000.00 20,000.00
Jumlah 4,422,000.00 679,500.00 5,101,500.00
Keuntungan Maksimal 10 % 510,150.00
Jumlah 5,611,650.00
Dibuilatkan 5,611,650.00
23 1M3 PASANGAN KUSEN PINTU / JENDELA KAYU KAMPER SAMARINDA
Bahan :
Kayu balok kamper samarinda m3 1.1000 4,000,000.00 4,400,000.00
Paku kg 1.2500 8,000.00 10,000.00
Lem Fox kg 1.0000 12,000.00 12,000.00
Tenaga :
Pekerja oh 4.0000 25,000.00 100,000.00
Tukang kayu oh 15.5000 30,000.00 465,000.00
Kepala tukang kayu oh 2.7000 35,000.00 94,500.00
Mandor oh 0.5000 40,000.00 20,000.00
Jumlah 4,422,000.00 679,500.00 5,101,500.00
Keuntungan Maksimal 10 % 510,150.00
Jumlah 5,611,650.00
Dibuilatkan 5,611,650.00
24 1M2 PASANGAN PINTU PANEL KAYU SAMARINDA
Bahan :
Kayu Borneo, papan m3 0.0400 4,000,000.00 160,000.00
Tenaga :
Pekerja oh 1.0000 25,000.00 25,000.00
Tukang kayu oh 2.5000 30,000.00 75,000.00
Kepala tukang kayu oh 0.2500 35,000.00 8,750.00
Mandor oh 0.0500 40,000.00 2,000.00
Jumlah 160,000.00 110,750.00 270,750.00
Keuntungan Maksimal 10 % 27,075.00
Jumlah 297,825.00
Dibuilatkan 297,820.00
25 1M2 PASANGAN DAUN PINTU TEAK WOOD 4 MM RANGKA KY. SAMARINDA
Bahan :
Rangka kayu SAMARINDA m3 0.0500 4,000,000.00 200,000.00
Teak Wood 4 mm lbr 0.6940 120,000.00 83,280.00
Lem Putih Fox kg 0.7500 12,000.00 9,000.00
Paku kg 0.1000 8,000.00 800.00
Tenaga :
Pekerja oh 0.6000 25,000.00 15,000.00
Tukang kayu oh 2.6000 30,000.00 78,000.00
Kepala tukang kayu oh 0.2600 35,000.00 9,100.00
Mandor oh 0.0260 40,000.00 1,040.00
Jumlah 293,080.00 103,140.00 396,220.00
Keuntungan Maksimal 10 % 39,622.00
Jumlah 435,842.00
Dibuilatkan 435,840.00
26 1M2 PASANGAN DAUN JENDELA KACA KAYU SAMARINDA
Bahan :
Kayu Borneo, papan m3 0.0200 4,000,000.00 80,000.00
Lem Putih Fox kg 0.3000 12,000.00 3,600.00
Tenaga :
Pekerja oh 0.3000 25,000.00 7,500.00
Tukang kayu oh 1.2000 30,000.00 36,000.00
Kepala tukang kayu oh 0.1200 35,000.00 4,200.00
Mandor oh 0.0200 40,000.00 800.00
Jumlah 83,600.00 48,500.00 132,100.00
Keuntungan Maksimal 10 % 13,210.00
Jumlah 145,310.00
Dibuilatkan 145,310.00
27 1M' PASANGAN PAPAN JALUSI KAYU BORNEO SUPER 1,5/12
Bahan :
Kayu Borneo Super, papan m3 0.0023 2,500,000.00 5,775.00
Paku kg 0.0100 8,000.00 80.00
Tenaga :
Pekerja oh 0.0500 25,000.00 1,250.00
Tukang kayu oh 0.1500 30,000.00 4,500.00
Kepala tukang kayu oh 0.0150 35,000.00 525.00
Mandor oh 0.0040 40,000.00 160.00
Jumlah 5,855.00 6,435.00 12,290.00
Keuntungan Maksimal 10 % 1,229.00
Jumlah 13,519.00
Dibuilatkan 13,510.00

28 1M2 PASANGAN KACA TEBAL 3 MM + List


Bahan :
Kaca tebal 3 mm m2 1.0000 42,500.00 42,500.00
List Kayu 1 cm m1 3.9000 2,000.00 7,800.00
Paku kaca kg 0.0200 10,000.00 200.00
Tenaga :
Pekerja oh 0.1500 25,000.00 3,750.00
Tukang kayu oh 0.1500 30,000.00 4,500.00
Jumlah 50,500.00 8,250.00 58,750.00
Keuntungan Maksimal 10 % 5,875.00
Jumlah 64,625.00
Dibuilatkan 64,620.00
29 1M2 PASANGAN KACA TEBAL 5 MM + List
Bahan :
Kaca tebal 5 mm m2 1.0000 55,000.00 55,000.00
List Kayu 1 cm m1 3.9000 2,000.00 7,800.00
Paku kaca kg 0.0200 10,000.00 200.00
Tenaga :
Pekerja oh 0.1500 25,000.00 3,750.00
Tukang kayu oh 0.1500 30,000.00 4,500.00
Jumlah 63,000.00 8,250.00 71,250.00
Keuntungan Maksimal 10 % 7,125.00
Jumlah 78,375.00
Dibuilatkan 78,370.00

30 1M1 PASANGAN BUBUNG GENTENG PALENTONG


Bahan :
Genteng bubung palentong bh 4.0000 2,000.00 8,000.00
Semen portland kg 6.5000 750.00 4,875.00
Pasir pasang m3 0.2100 65,000.00 13,650.00
Peralatan ls 1.0000 500.00 500.00
Tenaga :
Pekerja oh 0.1500 25,000.00 3,750.00
Tukang batu oh 0.2000 30,000.00 6,000.00
Kepala tukang batu oh 0.0100 35,000.00 350.00
Mandor oh 0.0100 40,000.00 400.00
Jumlah 27,025.00 10,500.00 37,525.00
Keuntungan Maksimal 10 % 3,752.50
Jumlah 41,277.50
Dibuilatkan 41,270.00
31 1M2 PASANGAN RANGKA LANGIT - LANGIT ( GRID 50 X 100 ) KAYU albasiah
Bahan :
Kayu kaso albasiah 5/7 m3 0.0270 300,000.00 8,100.00
Paku 5 - 10 cm kg 0.1800 8,000.00 1,440.00
Tenaga :
Pekerja org 0.2100 25,000.00 5,250.00
Tukang kayu org 0.3500 30,000.00 10,500.00
Kepala Tukang kayu org 0.0350 35,000.00 1,225.00
Mandor org 0.0110 40,000.00 440.00
Jumlah 9,540.00 17,415.00 26,955.00
Keuntungan Maksimal 10 % 2,695.50
Jumlah 29,650.50
Dibuilatkan 29,650.00
32 1M2 PASANGAN PLAFOND GYPSUM ( PABRIKASI )
Bahan + Upah
GYPSUM m2 1.0000 21,500.00 21,500.00
Jumlah 21,500.00 21,500.00
Keuntungan Maksimal 10 % 2,150.00
Jumlah 23,650.00
Dibuilatkan 23,650.00
33 1M1 PASANGAN LIST PLANK (3X30 CM), KAYU BORNEO
Bahan :
Kayu papan borneo m3 0.0100 410,000.00 4,100.00
Paku biasa 2-5" kg 0.0500 10,000.00 500.00
Tenaga :
Pekerja oh 0.0700 25,000.00 1,750.00
Tukang kayu oh 0.2000 30,000.00 6,000.00
Kepala tukang kayu oh 0.0200 35,000.00 700.00
Mandor oh 0.0040 40,000.00 160.00
Jumlah 4,600.00 8,610.00 13,210.00
Keuntungan Maksimal 10 % 1,321.00
Jumlah 14,531.00
Dibuilatkan 14,530.00
34 1M1 PEKERJAAN PAPAN RUITER 2/20, KAYU BORNEO
Bahan :
Kayu borneo, papan m3 0.0040 410,000.00 1,640.00
Paku biasa 2-5" kg 0.0600 10,000.00 600.00
Tenaga :
Pekerja oh 0.1000 25,000.00 2,500.00
Tukang kayu oh 0.1000 30,000.00 3,000.00
Kepala tukang kayu oh 0.0100 35,000.00 350.00
Mandor oh 0.0500 40,000.00 2,000.00
Jumlah 2,240.00 7,850.00 10,090.00
Keuntungan Maksimal 10 % 1,009.00
Jumlah 11,099.00
Dibuilatkan 11,090.00
HARGA
JUMLAH HARGA JUMLAH HARGA
SATUAN
NO. URAIAN SAT. KOEF.
BAHAN /
UPAH BAHAN UPAH BAHAN + UPAH
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
1 2 3 4 5 6 7 8
35 1M1 PEKERJAAN PAPAN RUITER 2/20, KAYU BORNEO SUPER
Bahan :
Kayu borneo super, papan m3 0.0040 2,500,000.00 10,000.00
Paku biasa 2-5" kg 0.0600 10,000.00 600.00
Tenaga :
Pekerja oh 0.1000 25,000.00 2,500.00
Tukang kayu oh 0.1000 30,000.00 3,000.00
Kepala tukang kayu oh 0.0100 35,000.00 350.00
Mandor oh 0.0500 40,000.00 2,000.00
Jumlah 10,600.00 7,850.00 18,450.00
Keuntungan Maksimal 10 % 1,845.00
Jumlah 20,295.00
Dibuilatkan 20,290.00
36 1M1 PEKERJAAN TALANG DATAR BJLS 28
Bahan :
Seng plat 3 x 6 BJLS 28 lbr 0.5000 45,000.00 22,500.00
Paku biasa 1/2-1" kg 0.0150 10,000.00 150.00
Kayu Borneo, papan m3 0.0096 2,100,000.00 20,160.00
Tenaga :
Pekerja oh 0.1500 25,000.00 3,750.00
Tukang kayu oh 0.4000 30,000.00 12,000.00
Kepala tukang kayu oh 0.0250 35,000.00 875.00
Mandor oh 0.0070 40,000.00 280.00
Jumlah 42,810.00 16,905.00 59,715.00
Keuntungan Maksimal 10 % 5,971.50
Jumlah 65,686.50
Dibuilatkan 65,680.00
37 1BH PASANG BAK FIBER GLASS
Bahan :
Bata merah bh 1.0000 250.00 250.00
Bak Fiber glass bh 1.0000 75,000.00 75,000.00
Semen PC kg 8.0000 750.00 6,000.00
Pasir pasang m3 0.2500 65,000.00 16,250.00
Keramik 20/20 m2 1.1000 42,500.00 46,750.00
Tenaga :
Pekerja org 0.2500 25,000.00 6,250.00
Tukang batu org 0.0130 30,000.00 390.00
Kepala tukang batu org 0.0250 35,000.00 875.00
Mandor org 0.0030 40,000.00 120.00
Jumlah 144,250.00 7,635.00 151,885.00
Keuntungan Maksimal 10 % 15,188.50
Jumlah 167,073.50
Dibuilatkan 167,070.00
38 1BH PASANG KLOSET JONGKOK
Bahan :
Kloset jongkok sek. INA bh 1.0000 600,000.00 600,000.00
Semen PC kg 5.5000 750.00 4,125.00
Pasir pasang m2 0.0900 65,000.00 5,850.00
Tenaga :
Pekerja org 0.0130 25,000.00 325.00
Tukang batu org 0.2500 30,000.00 7,500.00
Kepala tukang org 0.0250 35,000.00 875.00
Mandor org 0.0030 40,000.00 120.00
Jumlah 609,975.00 8,820.00 618,795.00
Keuntungan Maksimal 10 % 61,879.50
Jumlah 680,674.50
Dibuilatkan 680,670.00
39 1BH PASANG ENGSEL PINTU
Bahan :
Engsel pintu bh 1.0000 8,000.00 8,000.00
Tenaga :
Tukang kayu oh 0.1500 30,000.00 4,500.00
Jumlah 8,000.00 4,500.00 12,500.00
Keuntungan Maksimal 10 % 1,250.00
Jumlah 13,750.00
Dibuilatkan 13,750.00
HARGA
JUMLAH HARGA JUMLAH HARGA
SATUAN
NO. URAIAN SAT. KOEF.
BAHAN /
UPAH BAHAN UPAH BAHAN + UPAH
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
1 2 3 4 5 6 7 8
40 1BH PASANG ENGSEL JENDELA KUPU - KUPU
Bahan :
Engsel jendela bh 1.0000 7,500.00 7,500.00
Tenaga :
Tukang kayu oh 0.1500 30,000.00 4,500.00
Jumlah 7,500.00 4,500.00 12,000.00
Keuntungan Maksimal 10 % 1,200.00
Jumlah 13,200.00
Dibuilatkan 13,200.00
41 1BH PASANG KUNCI TANAM BIASA
Bahan :
Kunci tanam biasa type besar bh 1.0000 90,000.00 90,000.00
Tenaga :
Tukang kayu oh 0.5000 30,000.00 15,000.00
Jumlah 90,000.00 15,000.00 105,000.00
Keuntungan Maksimal 10 % 10,500.00
Jumlah 115,500.00
Dibuilatkan 115,500.00
42 1BH PASANG SLOT PINTU
Bahan :
Slot pintu bh 1.0000 4,500.00 4,500.00
Tenaga :
Tukang kayu oh 0.4500 30,000.00 13,500.00
Jumlah 4,500.00 13,500.00 18,000.00
Keuntungan Maksimal 10 % 1,800.00
Jumlah 19,800.00
Dibuilatkan 19,800.00
43 1BH PASANG SLOT JENDELA
Bahan :
Slot jendela bh 1.0000 4,500.00 4,500.00
Tenaga :
Tukang kayu oh 0.1500 30,000.00 4,500.00
Jumlah 4,500.00 4,500.00 9,000.00
Keuntungan Maksimal 10 % 900.00
Jumlah 9,900.00
Dibuilatkan 9,900.00
44 1BH PASANG KUNCI TANAM KAMAR MANDI
Bahan :
Kunci tanam kamar mandi bh 1.0000 65,000.00 65,000.00
Tenaga :
Tukang kayu oh 0.3500 30,000.00 10,500.00
Jumlah 65,000.00 10,500.00 75,500.00
Keuntungan Maksimal 10 % 7,550.00
Jumlah 83,050.00
Dibuilatkan 83,050.00
45 1BH PASANG SPRING KNIP
Bahan :
Spring knip bh 1.0000 10,000.00 10,000.00
Tenaga :
Tukang kayu oh 0.5000 30,000.00 15,000.00
Jumlah 10,000.00 15,000.00 25,000.00
Keuntungan Maksimal 10 % 2,500.00
Jumlah 27,500.00
Dibuilatkan 27,500.00
46 1BH PASANG KAIT ANGIN
Bahan :
Kait angin type sendok ,stainles bh 1.0000 6,000.00 6,000.00
Tenaga :
Tukang kayu oh 0.1500 30,000.00 4,500.00
Jumlah 6,000.00 4,500.00 10,500.00
Keuntungan Maksimal 10 % 1,050.00
Jumlah 11,550.00
Dibuilatkan 11,550.00
HARGA
JUMLAH HARGA JUMLAH HARGA
SATUAN
NO. URAIAN SAT. KOEF.
BAHAN /
UPAH BAHAN UPAH BAHAN + UPAH
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
1 2 3 4 5 6 7 8
47 1TTK PASANG TITIK CAHAYA
Bahan :
Kabel NYM 3 x 2,5 m' 8.2440 4,500.00 37,098.00
Solatif kabel roll 0.3330 3,000.00 999.00
Pipa Kabel btg 1.5000 3,000.00 4,500.00
T-Dus bh 1.0000 500.00 500.00
Inbow Dus bh 1.0000 1,000.00 1,000.00
Tenaga :
Upah Kerja ls 1.0000 20,000.00 20,000.00
Jumlah 44,097.00 20,000.00 64,097.00
Keuntungan Maksimal 10 % 6,409.70
Jumlah 70,506.70
Dibuilatkan 70,500.00
48 1TTK PASANG TITIK DAYA/STOP KONTAK
Bahan :
Kabel NYM 3 x 2,5 m' 6.8700 4,500.00 30,915.00
Solatif kabel roll 0.3330 3,000.00 999.00
Pipa Kabel btg 1.5000 3,000.00 4,500.00
T-Dus bh 1.0000 500.00 500.00
Inbow Dus bh 1.0000 1,000.00 1,000.00
Tenaga :
Upah Kerja ls 1.0000 20,000.00 20,000.00
Jumlah 37,914.00 20,000.00 57,914.00
Keuntungan Maksimal 10 % 5,791.40
Jumlah 63,705.40
Dibuilatkan 63,700.00
49 1BH PASANG ARMATUR STOP KONTAK
Bahan :
Stop kontak 250 watt "Broco" bh 1.0000 7,500.00 7,500.00
Alat bantu ls 1.0000 1,000.00 1,000.00
Tenaga :
Upah Kerja ls 1.0000 10,000.00 10,000.00
Jumlah 8,500.00 10,000.00 18,500.00
Keuntungan Maksimal 10 % 1,850.00
Jumlah 20,350.00
Dibuilatkan 20,350.00
50 1BH PASANG ARMATUR SAKLAR TUNGGAL
Bahan :
Saklar tunggal "Broco" bh 1.0000 7,500.00 7,500.00
Alat bantu ls 1.0000 1,000.00 1,000.00
Tenaga :
Upah Kerja ls 1.0000 10,000.00 10,000.00
Jumlah 8,500.00 10,000.00 18,500.00
Keuntungan Maksimal 10 % 1,850.00
Jumlah 20,350.00
Dibuilatkan 20,350.00
51 1BH PASANG ARMATUR SAKLAR GANDA
Bahan :
Saklar ganda "Broco" bh 1.0000 10,000.00 10,000.00
Alat bantu ls 1.0000 1,000.00 1,000.00
Tenaga :
Upah Kerja ls 1.0000 10,000.00 10,000.00
Jumlah 11,000.00 10,000.00 21,000.00
Keuntungan Maksimal 10 % 2,100.00
Jumlah 23,100.00
Dibuilatkan 23,100.00
52 1BH PASANG LAMPU PIJAR 25 WATT
Bahan :
Lampu pijar Sek Phillips 25 watt bh 1.0000 7,500.00 7,500.00
Pitting lampu "Broco" bh 1.0000 5,000.00 5,000.00
Alat bantu ls 1.0000 1,000.00 1,000.00
Tenaga :
Upah Kerja ls 1.0000 10,000.00 10,000.00
Jumlah 13,500.00 10,000.00 23,500.00
Keuntungan Maksimal 10 % 2,350.00
Jumlah 25,850.00
Dibuilatkan 25,850.00
HARGA
JUMLAH HARGA JUMLAH HARGA
SATUAN
NO. URAIAN SAT. KOEF.
BAHAN /
UPAH BAHAN UPAH BAHAN + UPAH
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
1 2 3 4 5 6 7 8
53 1M2 PASANGAN LANTAI KERAMIK 20/20 POLOS
Bahan :
Keramik putih / polos 20/20, sek MULIA m2 1.0100 37,500.00 37,875.00
PC kg 8.0000 750.00 6,000.00
Pasir pasang kg 0.0300 65,000.00 1,950.00
Semen putih kg 0.0130 2,000.00 26.00
Tenaga :
Pekerja org 0.2500 25,000.00 6,250.00
Tukang batu org 0.4000 30,000.00 12,000.00
Kepala tukang batu org 0.0500 35,000.00 1,750.00
Mandor org 0.0250 40,000.00 1,000.00
Jumlah 45,851.00 21,000.00 66,851.00
Keuntungan Maksimal 10 % 6,685.10
Jumlah 73,536.10
Dibuilatkan 73,530.00
54 1M2 PASANGAN LANTAI KERAMIK 20/20 WARNA CORAK
Bahan :
Keramik warna/corak 20/20, sek MULIA m2 1.0100 42,500.00 42,925.00
PC kg 8.0000 750.00 6,000.00
Pasir pasang kg 0.0300 65,000.00 1,950.00
Semen putih kg 0.0130 2,000.00 26.00
Tenaga :
Pekerja org 0.2500 25,000.00 6,250.00
Tukang batu org 0.4000 30,000.00 12,000.00
Kepala tukang batu org 0.0500 35,000.00 1,750.00
Mandor org 0.0250 40,000.00 1,000.00
Jumlah 50,901.00 21,000.00 71,901.00
Keuntungan Maksimal 10 % 7,190.10
Jumlah 79,091.10
Dibuilatkan 79,090.00
55 1M2 PASANGAN DINDING BATU AMPIG
Bahan :
BATU AMPIG m2 1.0100 50,000.00 50,500.00
PC kg 8.0000 750.00 6,000.00
Pasir pasang kg 0.0300 65,000.00 1,950.00
Semen putih kg 0.0130 2,000.00 26.00
Tenaga :
Pekerja org 0.2500 25,000.00 6,250.00
Tukang batu org 0.4000 30,000.00 12,000.00
Kepala tukang batu org 0.0500 35,000.00 1,750.00
Mandor org 0.0250 40,000.00 1,000.00
Jumlah 58,476.00 21,000.00 79,476.00
Keuntungan Maksimal 10 % 7,947.60
Jumlah 87,423.60
Dibuilatkan 87,420.00
56 1M2 PASANGAN DINDING KERAMIK 20/25 CORAK WARNA
Bahan :
Keramik corak warna 20/25, MULIA m2 1.0100 37,500.00 37,875.00
PC kg 8.0000 750.00 6,000.00
Pasir pasang kg 0.0300 65,000.00 1,950.00
Semen putih kg 0.0130 2,000.00 26.00
Tenaga :
Pekerja org 0.2500 25,000.00 6,250.00
Tukang batu org 0.4000 30,000.00 12,000.00
Kepala tukang batu org 0.0500 35,000.00 1,750.00
Mandor org 0.0250 40,000.00 1,000.00
Jumlah 45,851.00 21,000.00 66,851.00
Keuntungan Maksimal 10 % 6,685.10
Jumlah 73,536.10
Dibuilatkan 73,530.00
57 1M2 PASANGAN LANTAI KERAMIK UK. 30/30 CM PUTIH POLOS
Bahan :
Ubin kramik putih 30/30 cm putih polos m2 1.0100 31,000.00 31,310.00
Semen portland kg 8.0000 750.00 6,000.00
Pasir pasang m3 0.0300 65,000.00 1,950.00
Semen warna (putih) kg 0.0130 2,000.00 26.00
Tenaga :
Pekerja oh 0.2500 25,000.00 6,250.00
Tk. Batu oh 0.4000 30,000.00 12,000.00
Kepala tukang batu oh 0.0500 35,000.00 1,750.00
Mandor oh 0.0250 40,000.00 1,000.00
Jumlah 39,286.00 21,000.00 60,286.00
Keuntungan Maksimal 10 % 6,028.60
Jumlah 66,314.60
Dibuilatkan 66,310.00
58 1M2 PASANGAN LANTAI KERAMIK UK. 30/30 CM WARNA CORAK
Bahan :
Ubin kramik putih 30/30 cm warna corak m2 1.0100 34,000.00 34,340.00
Semen portland kg 8.0000 750.00 6,000.00
Pasir pasang m3 0.0300 65,000.00 1,950.00
Semen warna (putih) kg 0.0130 2,000.00 26.00
Tenaga :
Pekerja oh 0.2500 25,000.00 6,250.00
Tk. Batu oh 0.4000 30,000.00 12,000.00
Kepala tukang batu oh 0.0500 35,000.00 1,750.00
Mandor oh 0.0250 40,000.00 1,000.00
Jumlah 42,316.00 21,000.00 63,316.00
Keuntungan Maksimal 10 % 6,331.60
Jumlah 69,647.60
Dibuilatkan 69,640.00
59 1M2 PASANGAN MARMER
Bahan :
Marmer m2 1.0000 250,000.00 250,000.00
Semen portland kg 13.0000 750.00 9,750.00
Pasir pasang m3 0.0300 65,000.00 1,950.00
Campuran kedap air kg 1.0000 2,000.00 2,000.00
Tenaga :
Pekerja oh 1.0000 25,000.00 25,000.00
Tk. Batu oh 0.2000 30,000.00 6,000.00
Kepala tukang batu oh 1.0000 35,000.00 35,000.00
Mandor oh 0.0480 40,000.00 1,920.00
Jumlah 263,700.00 67,920.00 331,620.00
Keuntungan Maksimal 10 % 33,162.00
Jumlah 364,782.00
Dibuilatkan 364,780.00
70 1M2 PASANGAN PAVING BLOCK NATURAL, T = 6 CM
Bahan :
Paving Block natural t = 6 cm m2 1.1000 23,000.00 25,300.00
Pasir beton m3 0.1000 120,000.00 12,000.00
Tenaga :
Pekerja oh 0.1500 25,000.00 3,750.00
Tk. Batu oh 0.2500 30,000.00 7,500.00
Kepala tukang batu oh 0.0250 35,000.00 875.00
Mandor oh 0.0020 40,000.00 80.00
Jumlah 37,300.00 12,205.00 49,505.00
Keuntungan Maksimal 10 % 4,950.50
Jumlah 54,455.50
Dibuilatkan 54,450.00
71 1M2 PASANGAN PAVING BLOCK WARNA, T = 6 CM
Bahan :
Paving Block warna t = 6 cm m2 1.1000 25,000.00 27,500.00
Pasir beton m3 0.1000 120,000.00 12,000.00
Tenaga :
Pekerja oh 0.1500 25,000.00 3,750.00
Tk. Batu oh 0.2500 30,000.00 7,500.00
Kepala tukang batu oh 0.0250 35,000.00 875.00
Mandor oh 0.0020 40,000.00 80.00
Jumlah 39,500.00 12,205.00 51,705.00
Keuntungan Maksimal 10 % 5,170.50
Jumlah 56,875.50
Dibuilatkan 56,870.00
72 1M2 PASANGAN PAVING BLOCK NATURAL, T = 8 CM
Bahan :
Paving Block natural t = 8 cm m2 1.1000 27,500.00 30,250.00
Pasir beton m3 0.1000 120,000.00 12,000.00
Tenaga :
Pekerja oh 0.1500 25,000.00 3,750.00
Tk. Batu oh 0.2500 30,000.00 7,500.00
Kepala tukang batu oh 0.0250 35,000.00 875.00
Mandor oh 0.0020 40,000.00 80.00
Jumlah 42,250.00 12,205.00 54,455.00
Keuntungan Maksimal 10 % 5,445.50
Jumlah 59,900.50
Dibuilatkan 59,900.00
HARGA
JUMLAH HARGA JUMLAH HARGA
SATUAN
NO. URAIAN SAT. KOEF.
BAHAN /
UPAH BAHAN UPAH BAHAN + UPAH
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
1 2 3 4 5 6 7 8
73 1M2 PASANGAN PAVING BLOCK WARNA, T = 8 CM
Bahan :
Paving Block warna t = 8 cm m2 1.1000 30,000.00 33,000.00
Pasir beton m3 0.1000 120,000.00 12,000.00
Tenaga :
Pekerja oh 0.1500 25,000.00 3,750.00
Tk. Batu oh 0.2500 30,000.00 7,500.00
Kepala tukang batu oh 0.0250 35,000.00 875.00
Mandor oh 0.0020 40,000.00 80.00
Jumlah 45,000.00 12,205.00 57,205.00
Keuntungan Maksimal 10 % 5,720.50
Jumlah 62,925.50
Dibuilatkan 62,920.00
74 1M' PASANGAN SALURAN GREVEL BETON 1/2 DIA 20 CM + PASANGAN
Bahan :
Grevel beton 1/2 Dia 20 cm m' 1.0000 22,500.00 22,500.00
Item Pekerjaan :
Galian tanah m3 0.3600 14,100.00 5,076.00
Urugan Tanah Kembali m3 0.1400 6,050.00
Urugan pasir T = 5 cm m3 0.0500 52,150.00 2,607.50
Pasangan bata 1 PC : 3 PS m2 1.0000 54,650.00 54,650.00
Plesteran + Acian 1 PC : 3 PS m2 0.8000 152,350.00 121,880.00
Tambahan Upah ls 1.0000 1,000.00 1,000.00
Jumlah 207,713.50 207,713.50
Keuntungan Maksimal 10 % 20,771.35
Jumlah 228,484.85
Dibuilatkan 228,480.00
75 1BH BAK KONTROL UK. DALAM 25 25 CM
Item Pekerjaan :
Galian tanah m3 0.0810 14,100.00 1,142.10
Pasangan bata 1 PC : 5 PS m2 0.6225 54,650.00 34,019.63
Plesteran 1 PC : 5 PS m2 0.3125 152,350.00 47,609.38
Tutup beton tinggi 5 cm m3 0.0045 430,140.00 1,935.63
Jumlah 84,706.73 84,706.73
Keuntungan Maksimal 10 % 8,470.67
Jumlah 93,177.40
Dibuilatkan 93,170.00
76 1UNIT PEKERJAAN SEPTICKTANK UK. 2.50 X 2.00 X 1.50 M
Bahan :
Soket T PVC 4" bh 2.0000 4,000.00 8,000.00
Pipa hitam 1 1/2" m' 0.8000 2,000.00 1,600.00
Pasangan ijuk kg 75.0000 3,000.00 225,000.00
Piva PVC 4" berlobang jenis ( D ) m' 4.5000 20,000.00 90,000.00
Item Pekerjaan :
Galian tanah m3 7.5000 14,100.00 105,750.00
Pasir urug tinggi 5 cm m3 0.2300 52,150.00 11,994.50
Pasangan bata 1 bata 1 : 3 + plesteran 1 : 3 m2 21.5100 227,690.00 4,897,611.90
Plat beton tutup + balok m3 0.4300 430,140.00 184,960.20
Galian tanah untuk rembesan m3 5.0000 14,100.00 70,500.00
Urugan kerikil 3/5 cm m3 1.4000 100,000.00 140,000.00
Urugan kembali perataan tanah m3 1.0000 6,650.00 6,650.00
Bak kontrol 25 x 25 ( uk. Dalam ) bh 2.0000 93,170.00 186,340.00
Upah :
Tambahan upah ls 1.0000 100,000.00 100,000.00
Jumlah 5,928,406.60 100,000.00 6,028,406.60
Keuntungan Maksimal 10 % 602,840.66
Jumlah 6,631,247.26
Dibuilatkan 6,631,240.00
77 1M' PASANGAN SALURAN AIR BERSIH PVC 1/2"
Bahan :
Pipa PVC 1/2" m' 1.0000 3,000.00 3,000.00
Tenaga :
Upah ls 1.0000 2,000.00 2,000.00
Jumlah 3,000.00 2,000.00 5,000.00
Keuntungan Maksimal 10 % 500.00
Jumlah 5,500.00
Dibuilatkan 5,500.00
78 1M' PASANGAN SALURAN AIR HUJAN PVC 3"
Bahan :
Pipa PVC 3" m' 1.0000 15,000.00 15,000.00
Tenaga :
Upah ls 1.0000 2,000.00 2,000.00
Jumlah 15,000.00 2,000.00 17,000.00
Keuntungan Maksimal 10 % 1,700.00
Jumlah 18,700.00
Dibuilatkan 18,700.00
79 1M' PASANGAN SALURAN AIR KOTOR PVC 4"
Bahan :
Pipa PVC 4" m' 1.0000 20,000.00 20,000.00
Tenaga :
Upah ls 1.0000 2,000.00 2,000.00
Jumlah 20,000.00 2,000.00 22,000.00
Keuntungan Maksimal 10 % 2,200.00
Jumlah 24,200.00
Dibuilatkan 24,200.00
Bahan :
Cat Tembok SANLEX kg 0.1750 10,000.00 1,750.00
Rol Cat bh 0.0100 6,000.00 60.00
Steger Werk ls 0.5000 2,500.00 1,250.00
Ampelas lbr 0.5000 2,000.00 1,000.00
Tenaga :
Pekerja oh 0.1060 25,000.00 2,650.00
Tk. Cat oh 0.1860 30,000.00 5,580.00
Kepala tukang cat oh 0.0200 35,000.00 700.00
Mandor oh 0.0060 40,000.00 240.00
Jumlah 4,060.00 9,170.00 13,230.00
Keuntungan Maksimal 10 % 1,323.00
Jumlah 14,553.00
Dibuilatkan 14,550.00
81 1M2 PENGECATAN DINDING SANLEX (3X)
Bahan :
Cat Tembok SANLEX kg 0.1800 10,000.00 1,800.00
Plamur Tembok kg 0.1600 17,500.00 2,800.00
Rol Cat bh 0.0100 6,000.00 60.00
Steger Werk ls 1.0000 2,500.00 2,500.00
Ampelas lbr 0.5000 2,000.00 1,000.00
Tenaga :
Pekerja oh 0.1060 25,000.00 2,650.00
Tk. Cat oh 0.1800 30,000.00 5,400.00
Kepala tukang cat oh 0.0200 35,000.00 700.00
Mandor oh 0.0100 40,000.00 400.00
Jumlah 8,160.00 9,150.00 17,310.00
Keuntungan Maksimal 10 % 1,731.00
Jumlah 19,041.00
Dibuilatkan 19,040.00
82 1M2 PENGECATAN PLAFOND SANLEX (2X)
Bahan :
Cat Tembok SANLEX kg 0.1750 10,000.00 1,750.00
Rol Cat bh 0.0100 6,000.00 60.00
Steger Werk ls 1.0000 5,000.00 5,000.00
Ampelas lbr 0.5000 2,000.00 1,000.00
Tenaga :
Pekerja oh 0.1330 25,000.00 3,325.00
Tk. Cat oh 0.2000 30,000.00 6,000.00
Kepala tukang cat oh 0.0200 35,000.00 700.00
Mandor oh 0.0060 40,000.00 240.00
Jumlah 7,810.00 10,265.00 18,075.00
Keuntungan Maksimal 10 % 1,807.50
Jumlah 19,882.50
Dibuilatkan 19,880.00
83 1M2 PENGECATAN PLAFOND SANLEX (3X)
Bahan :
Cat Tembok SANLEX kg 0.2000 7,000.00 1,400.00
Plamur Tembok kg 0.1600 17,500.00 2,800.00
Rol Cat bh 0.0100 6,000.00 60.00
Steger Werk ls 1.0000 5,000.00 5,000.00
Ampelas lbr 0.5000 2,000.00 1,000.00
Tenaga :
Pekerja oh 0.1000 25,000.00 2,500.00
Tk. Cat oh 0.1800 30,000.00 5,400.00
Kepala tukang cat oh 0.0200 35,000.00 700.00
Mandor oh 0.0100 40,000.00 400.00
Jumlah 10,260.00 9,000.00 19,260.00
Keuntungan Maksimal 10 % 1,926.00
Jumlah 21,186.00
Dibuilatkan 21,180.00
HARGA
JUMLAH HARGA JUMLAH HARGA
SATUAN
NO. URAIAN SAT. KOEF.
BAHAN /
UPAH BAHAN UPAH BAHAN + UPAH
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
1 2 3 4 5 6 7 8
84 1M2 PLABURAN BIDANG KAYU DENGAN POLITUR
Bahan :
Politur ltr 0.1500 8,500.00 1,275.00
Politur jadi ltr 0.3720 22,000.00 8,184.00
Kertas ampelas lbr 0.1500 2,000.00 300.00
Kuas 3" bh 0.0100 3,500.00 35.00
Tenaga :
Tk. Cat oh 0.0600 30,000.00 1,800.00
Kepala tukang cat oh 0.0160 35,000.00 560.00
Mandor oh 0.0025 40,000.00 100.00
Jumlah 9,794.00 2,460.00 12,254.00
Keuntungan Maksimal 10 % 1,225.40
Jumlah 13,479.40
Dibuilatkan 13,470.00
85 1M2 PLABURAN BIDANG KAYU DENGAN CAT RESIDU/SOLIGNEM
Bahan :
Residu ltr 0.3000 2,500.00 750.00
Minyak tanah/solar ltr 0.0300 4,500.00 135.00
Kwas 3" bh 0.0200 3,500.00 70.00
Tenaga :
Pekerja oh 0.0200 25,000.00 500.00
Tukang cat oh 0.1000 30,000.00 3,000.00
Mandor oh 0.0100 40,000.00 400.00
Jumlah 955.00 3,900.00 4,855.00
Keuntungan Maksimal 10 % 485.50
Jumlah 5,340.50
Dibuilatkan 5,340.00
86 1M2 PENGECATAN KAYU (2X)
Bahan :
Cat kayu merk SEIV kg 0.2000 28,000.00 5,600.00
Ampelas kayu lbr 0.4000 2,000.00 800.00
Minyak cat terpentin ltr 0.1500 12,500.00 1,875.00
Kwas 3" bh 0.0500 3,500.00 175.00
Tenaga :
Pekerja oh 0.1333 25,000.00 3,332.50
Tukang cat oh 0.2000 30,000.00 6,000.00
Kepala tukang cat oh 0.0200 35,000.00 700.00
Mandor oh 0.0060 40,000.00 240.00
Jumlah 8,450.00 10,272.50 18,722.50
Keuntungan Maksimal 10 % 1,872.25
Jumlah 20,594.75
Dibuilatkan 20,590.00
87 1M2 PENGECATAN KAYU (3X) BERIKUT MENIE
Bahan :
Meni kayu kg 0.1670 12,500.00 2,087.50
Plamur kayu kg 0.0830 12,000.00 996.00
Cat kayu merk SEIV kg 0.2000 28,000.00 5,600.00
Ampelas kayu lbr 0.4000 2,000.00 800.00
Minyak cat terpentin ltr 0.1500 12,500.00 1,875.00
Kwas 3" bh 0.0500 3,500.00 175.00
Tenaga :
Pekerja oh 0.2000 25,000.00 5,000.00
Tukang cat oh 0.3000 30,000.00 9,000.00
Kepala tukang cat oh 0.0300 35,000.00 1,050.00
Mandor oh 0.0100 40,000.00 400.00
Jumlah 11,533.50 15,450.00 26,983.50
Keuntungan Maksimal 10 % 2,698.35
Jumlah 29,681.85
Dibuilatkan 29,680.00
HARGA
JUMLAH HARGA JUMLAH HARGA
SATUAN
NO. URAIAN SAT. KOEF.
BAHAN /
UPAH BAHAN UPAH BAHAN + UPAH
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
1 2 3 4 5 6 7 8
88 1M2 LABURAN MENIE KAYU (2X)
Bahan :
Meni kayu kg 0.1113 12,500.00 1,391.25
Ampelas kayu lbr 0.0667 2,000.00 133.40
Minyak cat terpentin ltr 0.0200 12,500.00 250.00
Kwas 3" bh 0.0333 3,500.00 116.55
Tenaga :
Pekerja oh 0.1000 25,000.00 2,500.00
Tukang cat oh 0.0500 30,000.00 1,500.00
Kepala tukang cat oh 0.0125 35,000.00 437.50
Mandor oh 0.0080 40,000.00 320.00
Jumlah 1,891.20 4,757.50 6,648.70
Keuntungan Maksimal 10 % 664.87
Jumlah 7,313.57
Dibuilatkan 7,310.00
89 1M3 LANTAI KERJA 1PC : 3PS : 5KR (Rabat)
Bahan :
PC ( 50 kg ) kg 173.0000 750.00 129,750.00
Pasir beton m3 0.5000 120,000.00 60,000.00
Split pecah mesin 2/3 m3 0.8700 130,000.00 113,100.00
Peralatan ls 1.0000 1,000.00 1,000.00
Tenaga :
Pekerja org 2.0000 25,000.00 50,000.00
Tukang batu org 0.5000 30,000.00 15,000.00
Kepala tukang org 0.0500 35,000.00 1,750.00
Mandor org 0.0100 40,000.00 400.00
Sewa Alat Berat ls 1.0000 65,000.00 65,000.00
Jumlah 303,850.00 132,150.00 436,000.00
Keuntungan Maksimal 10 % 43,600.00
Jumlah 479,600.00
Dibuilatkan 479,600.00
90 1M3 MEMBUAT BETON TUMBUK 1PC : 3 PS : 5 KR
Bahan :
Semen portlannd kg 218.0000 750.00 163,500.00
Pasir beton m3 0.5200 120,000.00 62,400.00
Koral beton - split m3 0.8700 130,000.00 113,100.00
Tenaga :
Pekerja oh 1.6500 25,000.00 41,250.00
Tukang batu oh 0.2500 30,000.00 7,500.00
Kepala tukang batu oh 0.0025 35,000.00 87.50
Mandor oh 0.0800 40,000.00 3,200.00
Jumlah 339,000.00 52,037.50 391,037.50
Keuntungan Maksimal 10 % 39,103.75
Jumlah 430,141.25
Dibuilatkan 430,140.00
91 1M3 BETON SITE MIX K 200
Bahan :
Semen portlannd kg 340.0000 750.00 255,000.00
Pasir beton m3 0.5400 120,000.00 64,800.00
Koral beton - split m3 0.8300 130,000.00 107,900.00
Tenaga :
Pekerja oh 1.5000 25,000.00 37,500.00
Tukang batu oh 0.5000 30,000.00 15,000.00
Kepala tukang batu oh 0.0500 35,000.00 1,750.00
Mandor oh 0.0100 40,000.00 400.00
Peralatan ls 1.0000 10,000.00 10,000.00
Jumlah 427,700.00 64,650.00 492,350.00
Keuntungan Maksimal 10 % 49,235.00
Jumlah 541,585.00
Dibuilatkan 541,580.00
HARGA
JUMLAH HARGA JUMLAH HARGA
SATUAN
NO. URAIAN SAT. KOEF.
BAHAN /
UPAH BAHAN UPAH BAHAN + UPAH
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
1 2 3 4 5 6 7 8
92 1M3 COR BETON SITE MIX K225
Bahan :
PC kg 395.0000 750.00 296,250.00
Pasir beton Cimalaka m3 0.4900 120,000.00 58,800.00
Split pecah mesin 2/3 m3 0.8100 130,000.00 105,300.00
Tenaga :
Pekerja org 1.5000 25,000.00 37,500.00
Tk.Batu org 0.5000 30,000.00 15,000.00
Kepala tukang batu org 0.0500 35,000.00 1,750.00
Mandor org 0.0100 40,000.00 400.00
Peralatan ls 1.0000 10,000.00 10,000.00
Jumlah 460,350.00 64,650.00 525,000.00
Keuntungan Maksimal 10 % 52,500.00
Jumlah 577,500.00
Dibuilatkan 577,500.00
93 1KG PEMBESIAN DENGAN BESI POLOS U - 24 & U - 32
Bahan :
Besi beton polos kg 1.0500 7,000.00 7,350.00
Kawat beton kg 0.0100 10,000.00 100.00
Tenaga :
Pekerja oh 0.0300 25,000.00 750.00
Tukang besi oh 0.0200 30,000.00 600.00
Kepala tukang besi oh 0.0100 35,000.00 350.00
Mandor oh 0.0100 40,000.00 400.00
Peralatan Spancer ls 1.0000 200.00 200.00
Jumlah 7,450.00 2,300.00 9,750.00
Keuntungan Maksimal 10 % 975.00
Jumlah 10,725.00
Dibuilatkan 10,720.00
94 1M2 PASANGAN BEKISTING PAPAN ( ANALISA BOW )
Bahan :
Kaso 5/7 Borneo, 2 x pakai ( 0,5 % ) m3 0.0200 1,000,000.00 20,000.00
Papan Terentang, 2 x pakai ( 50 % ) m3 0.0200 205,000.00 4,100.00
Paku 5 - 7 cm kg 0.4000 8,000.00 3,200.00
Tenaga :
Pekerja org 0.1200 25,000.00 3,000.00
Tk.Kayu org 0.1500 30,000.00 4,500.00
Kepala tukang kayu org 0.1500 35,000.00 5,250.00
Mandor org 0.0500 40,000.00 2,000.00
Pekerja (bongkar cetakan) org 0.1200 30,000.00 3,600.00
Jumlah 27,300.00 18,350.00 45,650.00
Keuntungan Maksimal 10 % 4,565.00
Jumlah 50,215.00
Dibuilatkan 50,210.00
95 1M2 PASANGAN BEKISTING MULTIPLEK 9 MM ( ANALISA BOW )
Bahan :
Kaso 5/7 Borneo, 2 x pakai ( 50 % ) m3 0.0280 1,000,000.00 28,000.00
Multiplek 9 mm 2 x pakai ( 50 % ) lbr 0.3470 60,000.00 20,820.00
Paku 5 - 7 cm kg 0.4000 8,000.00 3,200.00
Tenaga :
Pekerja org 0.2000 25,000.00 5,000.00
Tk.Kayu org 0.5000 30,000.00 15,000.00
Kepala tukang kayu org 0.0500 35,000.00 1,750.00
Mandor org 0.0100 40,000.00 400.00
Pekerja (bongkar cetakan) org 0.4000 30,000.00 12,000.00
Jumlah 52,020.00 34,150.00 86,170.00
Keuntungan Maksimal 10 % 8,617.00
Jumlah 94,787.00
Dibuilatkan 94,780.00
96 1M2 PASANGAN STOOTWERK
Bahan :
Kayu dolken, 2 x pakai ( 50 % ) btg 9.0000 8,750.00 78,750.00
Papan Albasiah, 2 x pakai ( 75 % ) m3 0.0200 205,000.00 4,100.00
Paku 5 - 7 cm kg 0.5000 8,000.00 4,000.00
Tenaga :
Pekerja org 0.1500 25,000.00 3,750.00
Tk.Kayu org 0.2000 30,000.00 6,000.00
Kepala tukang kayu org 0.2000 35,000.00 7,000.00
Mandor org 0.0200 40,000.00 800.00
Jumlah 86,850.00 17,550.00 104,400.00
Keuntungan Maksimal 10 % 10,440.00
Jumlah 114,840.00
Dibuilatkan 114,840.00
HARGA
JUMLAH HARGA JUMLAH HARGA
SATUAN
NO. URAIAN SAT. KOEF.
BAHAN /
UPAH BAHAN UPAH BAHAN + UPAH
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
1 2 3 4 5 6 7 8
97 1M3 PEKERJAAN BETON PONDASI PLAT 1,00 X 1,00 Tul = 227,280 KG (16 - 20)
Item Pekerjaan :
Cor Beton K - 225 m3 1.0000 577,500.00 577,500.00
Tulangan beton besi U24 kg 227.2800 10,720.00 2,436,441.60
Bekisting papan m2 0.6000 50,210.00 30,126.00
Jumlah 3,044,067.60 3,044,067.60
Dibuilatkan 3,044,000.00
98 1M3 PEKERJAAN BETON KOLOM STRUKTUR 20/35 Tul = 182,143 KG (8 dia 14 + dia 10 - 20)
Item Pekerjaan :
Cor Beton K - 225 m3 1.0000 577,500.00 577,500.00
Tulangan beton besi U24 kg 182.1430 10,720.00 1,952,572.96
Bekisting papan m2 15.0000 50,210.00 753,150.00
Jumlah 3,283,222.96 3,283,222.96
Keuntungan Maksimal 10 % 328,322.30
Jumlah 3,611,545.26
Dibuilatkan 3,611,540.00
99 1M3 PEKERJAAN BETON KOLOM SELASAR 15/20 Tul = 151,260 KG (4 dia 12 + dia 8 - 20)
Item Pekerjaan :
Cor Beton K - 225 m3 1.0000 577,500.00 577,500.00
Tulangan beton besi U24 kg 151.2600 10,720.00 1,621,507.20
Bekisting papan m2 15.0000 50,210.00 753,150.00
Jumlah 2,952,157.20 2,952,157.20
Keuntungan Maksimal 10 % 295,215.72
Jumlah 3,247,372.92
Dibuilatkan 3,247,370.00
100 1M3 PEKERJAAN BETON KOLOM PRAKTIS 12/12 Tul = 226,064 KG (4 dia 10 + dia 8 - 20)
Item Pekerjaan :
Cor Beton K - 225 m3 1.0000 577,500.00 577,500.00
Tulangan beton besi U24 kg 226.0640 10,720.00 2,423,406.08
Bekisting papan m2 16.6667 50,210.00 836,835.01
Jumlah 3,837,741.09 3,837,741.09
Keuntungan Maksimal 10 % 383,774.11
Jumlah 4,221,515.20
Dibuilatkan 4,221,510.00
101 1M3 PEKERJAAN BETON BALOK INDUK 20/60 Tul = 211,130 KG (8 dia 19 + 2 dia 12 + dia 10 - 15)
Item Pekerjaan :
Cor Beton K - 225 m3 1.0000 577,500.00 577,500.00
Tulangan beton besi U24 kg 211.1300 10,720.00 2,263,313.60
Bekisting papan m2 9.6670 50,210.00 485,380.07
Jumlah 3,326,193.67 3,326,193.67
Keuntungan Maksimal 10 % 332,619.37
Jumlah 3,658,813.04
Dibuilatkan 3,658,810.00
102 1M3 PEKERJAAN BETON BALOK ANAK 20/30 Tul = 109,000 KG (5 dia 12 + dia 8 - 15)
Item Pekerjaan :
Cor Beton K - 225 m3 1.0000 577,500.00 577,500.00
Tulangan beton besi U24 kg 109.0000 10,720.00 1,168,480.00
Bekisting papan m2 9.3330 50,210.00 468,609.93
Jumlah 2,214,589.93 2,214,589.93
Keuntungan Maksimal 10 % 221,458.99
Jumlah 2,436,048.92
Dibuilatkan 2,436,040.00

103 1M PASANGAN KONTRUKSI KUDA - KUDA BAJA RINGAN ( PABRIKASI )


Bahan :
Baja Ringan ( Pabrikasi ) m 1.0000 350,000.00 350,000.00 350,000.00
Jumlah 350,000.00
Dibuilatkan 350,000.00
104 1M1 PASANGAN GENTENG PALENTONG
Bahan :
Genteng palentong bh 4.0000 1,000.00 4,000.00
Peralatan ls 1.0000 500.00 500.00
Tenaga :
Pekerja oh 0.1500 25,000.00 3,750.00
Tukang batu oh 0.2000 30,000.00 6,000.00
Kepala tukang batu oh 0.0100 35,000.00 350.00
Mandor oh 0.0100 40,000.00 400.00
Jumlah 4,500.00 10,500.00 15,000.00
Keuntungan Maksimal 10 % 1,500.00
Jumlah 16,500.00
Dibuilatkan 16,500.00
105 1M LIST PROFIL PLAFOND GYPSUM ( PABRIKASI )
Bahan + Upah
GYPSUM m2 1.0000 25,000.00 25,000.00
Jumlah 25,000.00 25,000.00
Keuntungan Maksimal 10 % 2,500.00
Jumlah 27,500.00
Dibuilatkan 27,500.00
HARGA SATUAN PEKERJAAN
PEMBANGUNAN RUMAH TINGGAL SATU LANTAI
TYPE 40

HARGA SATUAN
NO URAIAN PEKERJAAN
( Rp. )

1 2 3
1 1M2 PEKERJAAN PENGUKURAN SITE 1,430.00
2 1M3 PEKERJAAN STRIPPING SEDALAM 0,1 M 1,590.00
3 1M2 PEMBERSIHAN LAPANGAN DAN PERATAAN 4,950.00
4 1M' PASANGAN BOUWPLANK 13,940.00
5 1M3 GALIAN TANAH BIASA KEDALAMAN 1 M 15,510.00
6 1M3 GALIAN TANAH BIASA KEDALAMAN 2 M 19,500.00
7 1M3 URUGAN TANAH KEMBALI 6,650.00
8 1M3 URUGAN PASIR 57,360.00
9 1M3 PASANGAN PONDASI BATU KOSONG AANSTAMPING 147,640.00
10 1M3 PASANGAN PONDASI BATU KALI 1 PC : 5 PS 310,150.00
11 1M2 PASANGAN BATA MERAH TEBAL 1/2 BATA 1PC : 3 PS 60,110.00
12 1M2 PASANGAN BATA MERAH TEBAL 1/2 BATA 1PC : 5 PS 48,150.00
13 1M2 PLESTERAN DINDING + ACIAN 1 : 5 22,110.00
14 1M2 FINISHING ACIAN 11,600.00
15 1M3 PASANGAN KUSEN PINTU / JENDELA KAYU SAMARINDA 5,611,650.00
16 1M3 PASANGAN KUSEN PINTU / JENDELA KAYU KAMPER SAMARINDA 5,611,650.00
17 1M2 PASANGAN PINTU PANEL KAYU SAMARINDA 297,820.00
18 1M2 PASANGAN DAUN PINTU TEAK WOOD 4 MM RANGKA KY. SAMARINDA 435,840.00
19 1M2 PASANGAN DAUN JENDELA KACA KAYU SAMARINDA 145,310.00
20 1M' PASANGAN PAPAN JALUSI KAYU BORNEO SUPER 1,5/12 13,510.00
21 1M2 PASANGAN KACA TEBAL 3 MM + List 64,620.00
22 1M2 PASANGAN KACA TEBAL 5 MM + List 78,370.00
23 1M1 PASANGAN BUBUNG GENTENG PALENTONG 41,270.00
24 1M2 PASANGAN RANGKA LANGIT - LANGIT ( GRID 50 X 100 ) KAYU albasiah 29,650.00
25 1M2 PASANGAN PLAFOND GYPSUM ( PABRIKASI ) 23,650.00
26 1M1 PASANGAN LIST PLANK (3X30 CM), KAYU BORNEO 14,530.00
27 1M1 PEKERJAAN PAPAN RUITER 2/20, KAYU BORNEO 11,090.00
28 1M1 PEKERJAAN PAPAN RUITER 2/20, KAYU BORNEO SUPER 20,290.00
29 1M1 PEKERJAAN TALANG DATAR BJLS 28 65,680.00
30 1BH PASANG BAK FIBER GLASS 167,070.00
31 1BH PASANG KLOSET JONGKOK 500,000.00
HARGA SATUAN
NO URAIAN PEKERJAAN
( Rp. )
1 2 3
32 1BH PASANG ENGSEL PINTU 13,750.00
33 1BH PASANG ENGSEL JENDELA KUPU - KUPU 13,200.00
34 1BH PASANG KUNCI TANAM BIASA 115,500.00
35 1BH PASANG SLOT PINTU 19,800.00
36 1BH PASANG SLOT JENDELA 9,900.00
37 1BH PASANG KUNCI TANAM KAMAR MANDI 83,050.00
38 1BH PASANG SPRING KNIP 27,500.00
39 1BH PASANG KAIT ANGIN 11,550.00
40 1TTK PASANG TITIK CAHAYA 70,500.00
41 1TTK PASANG TITIK DAYA/STOP KONTAK 40,000.00
42 1BH PASANG ARMATUR STOP KONTAK 20,350.00
43 1BH PASANG ARMATUR SAKLAR TUNGGAL 20,350.00
44 1BH PASANG ARMATUR SAKLAR GANDA 23,100.00
45 1BH PASANG LAMPU PIJAR 25 WATT 25,850.00
46 1M2 PASANGAN LANTAI KERAMIK 20/20 POLOS 73,530.00
47 1M2 PASANGAN LANTAI KERAMIK 20/20 WARNA CORAK 79,090.00
48 1M2 PASANGAN DINDING BATU AMPIG 87,420.00
49 1M2 PASANGAN DINDING KERAMIK 20/25 CORAK WARNA 73,530.00
50 1M2 PASANGAN LANTAI KERAMIK UK. 30/30 CM PUTIH POLOS 66,310.00
51 1M2 PASANGAN LANTAI KERAMIK UK. 30/30 CM WARNA CORAK 69,640.00
52 1M2 PASANGAN MARMER 364,780.00
53 1M2 PASANGAN PAVING BLOCK NATURAL, T = 6 CM 54,450.00
54 1M2 PASANGAN PAVING BLOCK WARNA, T = 6 CM 56,870.00
55 1M2 PASANGAN PAVING BLOCK NATURAL, T = 8 CM 59,900.00
56 1M2 PASANGAN PAVING BLOCK WARNA, T = 8 CM 62,920.00
57 1M' PASANGAN SALURAN GREVEL BETON 1/2 DIA 20 CM + PASANGAN 228,480.00
58 1BH BAK KONTROL UK. DALAM 25 25 CM 93,170.00
59 1UNIT PEKERJAAN SEPTICKTANK UK. 2.50 X 2.00 X 1.50 M 6,631,240.00
60 1M' PASANGAN SALURAN AIR BERSIH PVC 1/2" 5,500.00
61 1M' PASANGAN SALURAN AIR HUJAN PVC 3" 18,700.00
62 1M' PASANGAN SALURAN AIR KOTOR PVC 4" 24,200.00
63 PENGECATAN DINDING SANLEX ( 2 X ) 14,550.00
64 1M2 PENGECATAN DINDING SANLEX (3X) 19,040.00
65 1M2 PENGECATAN PLAFOND SANLEX (2X) 19,880.00
66 1M2 PENGECATAN PLAFOND SANLEX (3X) 21,180.00
67 1M2 PLABURAN BIDANG KAYU DENGAN POLITUR 13,470.00
68 1M2 PLABURAN BIDANG KAYU DENGAN CAT RESIDU/SOLIGNEM 5,340.00
69 1M2 PENGECATAN KAYU (2X) 20,590.00
70 1M2 PENGECATAN KAYU (3X) BERIKUT MENIE 29,680.00
71 1M2 LABURAN MENIE KAYU (2X) 7,310.00
72 1M3 LANTAI KERJA 1PC : 3PS : 5KR (Rabat) 479,600.00
73 1M3 MEMBUAT BETON TUMBUK 1PC : 3 PS : 5 KR 430,140.00
74 1M3 BETON SITE MIX K 200 541,580.00
75 1M3 COR BETON SITE MIX K225 577,500.00
76 1KG PEMBESIAN DENGAN BESI POLOS U - 24 & U - 32 10,720.00
77 1M2 PASANGAN BEKISTING PAPAN ( ANALISA BOW ) 50,210.00
78 1M2 PASANGAN BEKISTING MULTIPLEK 9 MM ( ANALISA BOW ) 94,780.00
79 1M2 PASANGAN STOOTWERK 114,840.00
80 1M3 PEKERJAAN BETON PONDASI PLAT 1,00 X 1,00 Tul = 227,280 KG (16 - 20) 3,044,000.00
81 1M3 PEKERJAAN BETON KOLOM STRUKTUR 20/35 Tul = 182,143 KG (8 dia 14 + dia 10 - 20) 3,611,540.00
82 1M3 PEKERJAAN BETON KOLOM SELASAR 15/20 Tul = 151,260 KG (4 dia 12 + dia 8 - 20) 3,247,370.00
83 1M3 PEKERJAAN BETON KOLOM PRAKTIS 12/12 Tul = 226,064 KG (4 dia 10 + dia 8 - 20) 4,221,510.00
84 1M3 PEKERJAAN BETON BALOK INDUK 20/60 Tul = 211,130 KG (8 dia 19 + 2 dia 12 + dia 10 - 15) 3,658,810.00
85 1M3 PEKERJAAN BETON BALOK ANAK 20/30 Tul = 109,000 KG (5 dia 12 + dia 8 - 15) 2,436,040.00
86 1 PASANG KUNCI PINTU BESAR 80,000.00
87 LANTAI KERAMIK 20/20 (1 m2) 40,000.00
88 1 M2 BATU AMPIG 87,420.00
89 PABRIKASI BAJA RINGAN 90,000.00
90 GENTENG BETON 16,500.00
91 RENG BAJA RINGAN 70,000.00
92 LIST PROFIL GYPSUM ( PABRIKASI ) 9,000.00
93 Out le TV Braco Integra 70,000.00
94 Genteng Beton Plat 40,000.00
BILL OF QUANTITY
PEMBANGUNAN RUMAH TINGGAL SATU LANTAI
TYPE 40

Harga Satuan Jumlah Harga


No. Uraian Pekerjaan Sat Volume
(Rp.) (Rp.)
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
1 Pengukuran kembali (Site) m2 100.000 1,430.00 143,000.00
2 Pas. Bouwplank m1 70.750 13,940.00 986,255.00
3 Perataan Lahan (Striping) m2 100.000 1,590.00 159,000.00
4 Pengadaan air bersih ls 1.000 100,000.00 100,000.00
Jumlah 1,388,255.00
II PEKERJAAN TANAH
1 Galian Tanah Pondasi Setempat m3 12.000 19,500.00 234,000.00
2 Galian Tanah Biasa Pondasi Menerus dan Sloop ( bangunan utama & pagar) m3 34.215 15,510.00 530,670.00
3 Urugan Tanah Kembali m3 11.554 6,650.00 76,831.94
4 Urugan Pasir di Bawah Pondasi & Sloop m3 1.804 57,360.00 103,484.61
Jumlah 944,986.55
III PEKERJAAN BETON
1 Pas. Beton Lantai Kerja di Bawah Pondasi & Sloop m3 1.804 479,600.00 865,258.35
2 Pas. Cor Beton Sloof 15/20 m3 2.123 577,500.00 1,225,743.75
3 Pas. Beton Kolom Struktur 15/20 m3 1.496 3,611,540.00 5,402,141.53
4 Pas. Beton Kolom Praktis 15/15 m3 0.628 4,221,510.00 2,651,108.28
5 Pas. Beton Ring Balk 15/20 m3 2.123 577,500.00 1,225,743.75
Jumlah 11,369,995.66
IV PEKERJAAN PASANGAN PONDASI,DINDING & PLESTERAN
1 Pas. Pondasi Batu Kali 1 Pc : 5 Ps m3 12.381 310,150.00 3,840,044.69
2 Pas. Batu Kosong m3 5.519 147,640.00 814,751.34
3 Pas. Dinding Bata Biasa, 1 Pc : 5 Ps m2 191.265 48,150.00 9,209,409.75
4 Plesteran Dinding + Acian 1 : 5 m3 382.530 22,110.00 8,457,738.30
5 Batu Tempel m2 22.5 87,420.00 1,966,950.00
Jumlah 24,288,894.08
V PEKERJAAN KUSEN PINTU / JENDELA & KACA
1 Pas. Kusen Pintu / Jendela, Ky. Kamper samarinda/setara m3 0.572 5,611,650.00 3,210,424.97
2 Pas. Daun Pintu Panel Papan Kayu samarinda m2 8.015 297,820.00 2,386,878.39
3 Pas. Daun Jendela Kaca, Kayu samarinda m2 1.943 145,310.00 282,366.39
4 Pas. Kaca Polos 5 mm m2 6.249 78,370.00 489,718.46
5 Pas. Pintu Ruangan bh 4.000 60,000.00 240,000.00
6 Pas. Kunci Pintu Utama bh 1.000 80,000.00 80,000.00
7 Pas. Engsel pintu dan jendela bh 15.000 13,200.00 198,000.00
8 Pas. Slot Jendela bh 10.000 9,900.00 99,000.00
Jumlah 6,986,388.20
VI PEKERJAAN LANTAI DAN SANITAIR
1 Urugan Pasir di Bawah Lantai t = 5 cm m3 2.20 57,360.00 126,192.00
2 Pas. Lantai keramik 30 x 30 cm, m2 38.250 66,310.00 2,536,357.50
3 Pas. Lantai keramik wc/teras ukuran 20 x 20 cm m2 8.625 40,000.00 345,000.00
4 Pas, Lantai keramik carport 30 x 30 cm m2 15.000 69,640.00 1,044,600.00
Jumlah 4,052,149.50
VII PEKERJAAN KAMAR MANDI
1 1 set kloset duduk bh 1.000 500,000.00 500,000.00
2 1 set bak mandi bh 1.000 167,070.00 167,070.00
3 Floor Drain bh 1.000 15,000.00 15,000.00
4 Kran Air bh 4.000 27,000.00 108,000.00
5 Saluran pembuangan air kotor Dia 3" M' 22.000 11,000.00 242,000.00
6 Saluran Air Bersih Pvc Dia 1/2" m1 17.000 7,000.00 119,000.00
7 Septictank & Resapan Unit 1.000 500,000.00 500,000.00
Jumlah 1,651,070.00
VIII PEKERJAAN ATAP & LANGIT-LANGIT
1 Pas. Konst Kuda-kuda konstruksi baja ringan ( Pabrikasi ) m2 47.400 90,000.00 4,266,000.00
2 Pas. Penutup Atap Genteng beton plat m2 64.160 40,000.00 2,566,400.00
6 Pas. Bumbungan Genteng beton m1 8.000 41,270.00 330,160.00
7 Pas. List Plank 3/30 Kayu papan Borneo super m1 16.040 14,530.00 233,061.20
8 Pas. Rangka Plafond (Grid 100 x 100) m2 88.000 29,650.00 2,609,200.00
9 Pas. Plafond GYPSUM uk. 100 x 100 cm m2 44.000 23,650.00 1,040,600.00
10 Pas. List Profil 1 x 5 cm m1 69.000 9,000.00 621,000.00
Jumlah 11,666,421.20
IX PEKERJAAN CAT DAN LABURAN
1 Pengecatan kusen Pintu dan Jendela (3x) m2 21.060 29,680.00 625,048.93
3 Plituran Pintu Panel m2 7.625 13,470.00 102,702.02
4 Pengecatan Plafond Baru (3x) m2 44.000 21,180.00 931,920.00
Jumlah 1,659,670.94
X PEKERJAAN INSTALASI LISTRIK
1 Pas. Titik Lampu + Instalasi ttk 8.000 70,500.00 564,000.00
2 out le TV braco Integra bh 1.000 70,000.00 70,000.00
3 Pas. Armatur Stop Kontak + Instalasi bh 8.000 40,000.00 320,000.00
Jumlah 954,000.00

XI PEKERJAAN PEMBERSIHAN LS 1 100000 100,000.00


Jumlah 100,000.00
0
0
0

0
0
100
70.75

1.5 12
0.4836 34.215
11.554
0.0255 1.804

2.123
0.1662 1.4958 2.44 5.54
0.06975 0.62775
2.123

0.175 12.381
0.078 5.519
20.64 38.250 211.905 191.265
5.738 11.4759

1.86 14.88 #REF!


4.87 8.36 5.24
0.0381 0.07155 0.07305 0.3108 0.0786 0.5721
8.0145 0.400725
6.528 1.664 0.4096 5.1392 1.1096 0.31244 1.310971707
8.192 1.9432 5.1392 1.1096 6.2488 0.031244

44 2.2
38.25
8.625
15

4.01 32.08 64.16


16.04

44 0.5 88
55
69

10.530 21.0596
7.6245
REKAPITULASI BILL OF QUANTITY (BOQ)
PEMBANGUNAN RUMAH TINGGAL 1 LANTAI
TYPE 40

JUMLAH
No. ITEM PEKERJAAN
(Rp.)

1 2 3
I Pekerjaan Persiapan 1,388,255.00
II Pekerjaan Tanah 944,986.55
III Pekerjaan Beton 11,369,995.66
IV Pekerjaan Pasangan Pondasi,Dinding & Plesteran 24,288,894.08
V Pekerjaan Kusen Pintu/Jendela & Kaca 6,986,388.20
VI Pekerjaan Lantai dan Sanitair 4,052,149.50
VII Pekerjaan Kamar Mandi 1,651,070.00
VII Pekerjaan atap & Langit-langit 11,666,421.20
VIII Pekerjaan Cat dan Laburan 1,659,670.94
IX Pekerjaan Instalasi Listrik 954,000.00
Jumlah A 64,961,831.13