Type 40
Type 40
NO URAIAN SAT
( Rp. )
1 2 3 4
A BAHAN AGREGAT KASAR DAN BAHAN PEREKAT
1 Tanah urug m3 12,000.00
2 Pasir urug m3 40,000.00
3 Pasir pasang m3 65,000.00
4 Pasir beton Cimalaka m3 120,000.00
5 Batu belah pondasi m3 70,000.00
6 Batu pecah mesin 1/2 m3 140,000.00
7 Batu pecah mesin 2/3 m3 130,000.00
8 Batu pecah 3/5 m3 100,000.00
9 Batu apung Kg 11,000.00
10 semen tiga roda Kg 750.00
11 Semen putih Kg 2,000.00
12 Semen warna muda Kg 2,000.00
13 Semen warna tua Kg 2,000.00
14 Lem putih Fox Kg 12,000.00
J BAHAN FINISHING
1 Cat dasar tembok, indo 9000 sealer water base Kg 7,000.00
2 Cat kayu sek SEIV Kg 28,000.00
3 Cat dasr kayu ltr 5,000.00
4 Meni kayu besi Bola Mas Kg 12,500.00
5 Plincoat ltr 10,000.00
6 Cat tembok, sek SANLEK kg 10,000.00
7 Dempul tembok (plamur Sanlek) Kg 17,500.00
8 Dempul kayu cap Kucing Kg 12,000.00
9 Thiner (minyak cat) ltr 12,500.00
10 Solignem (a blek 10 ltr) ltr 2,500.00
11 Spirtus ltr 3,500.00
12 Minyak tanah/solar ltr 4,500.00
13 Politur ltr 8,500.00
14 Plitur jadi Ultran ltr 22,000.00
15 Kertas ampelas kayu-tembok lbr 2,000.00
16 Kape kayu 2" bh 2,500.00
17 Kape tembok bh 2,500.00
18 Kuas 3-4" bh 3,500.00
19 Roll cat bh 6,000.00
DAFTAR HARGA SATUAN UPAH
0
0
0
HARGA DASAR
NO. URAIAN SAT
( Rp. )
1 2 3 4
1 Pekerja Org/hr 25,000.00
2 Tukang batu / tukang kayu Org/hr 30,000.00
3 Tukang besi profil / tukang las Org/hr 30,000.00
4 Tukang besi beton Org/hr 30,000.00
5 Tukang cat Org/hr 30,000.00
6 Tukang gali Org/hr 30,000.00
7 Kepala tukang batu / kayu Org/hr 35,000.00
8 Kepala tukang besi profil / las Org/hr 35,000.00
9 Kepala tukang besi beton Org/hr 35,000.00
10 Kepala tukang cat Org/hr 35,000.00
11 Kepala tukang gali Org/hr 35,000.00
12 Mandor Org/hr 40,000.00
ANALISA HARGA SATUAN PEKERJAAN
PEMBANGUNAN RUMAH SATU LANTAI TYPE II
HARGA
JUMLAH HARGA JUMLAH HARGA
SATUAN
NO. URAIAN SAT. KOEF.
BAHAN /
UPAH BAHAN UPAH BAHAN + UPAH
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
1 2 3 4 5 6 7 8
1 1M2 PEKERJAAN PENGUKURAN SITE
Bahan :
Peralatan lot 0.5000 1,000.00 500.00
Tenaga :
Pekerja Oh 0.0200 25,000.00 500.00
Tukang Oh 0.0100 30,000.00 300.00
Jumlah 500.00 800.00 1,300.00
Keuntungan Maksimal 10 % 130.00
Jumlah 1,430.00
Dibuilatkan 1,430.00
2 1M3 PEKERJAAN STRIPPING SEDALAM 0,1 M
Tenaga
Pekerja Oh 0.0500 25,000.00 1,250.00
Mandor Oh 0.0050 40,000.00 200.00
Jumlah 1,450.00 1,450.00
Keuntungan Maksimal 10 % 145.00
Jumlah 1,595.00
Dibuilatkan 1,590.00
4 1M2 PEMBERSIHAN LAPANGAN DAN PERATAAN
Tenaga :
Pekerja Oh 0.1000 25,000.00 2,500.00
Mandor Oh 0.0500 40,000.00 2,000.00
Jumlah 4,500.00 4,500.00
Keuntungan Maksimal 10 % 450.00
Jumlah 4,950.00
Dibuilatkan 4,950.00
5 1M' PASANGAN BOUWPLANK
Bahan :
Kayu papan 3/20 m3 0.0070 410,000.00 2,870.00
Kayu kaso albasiah m3 0.0120 300,000.00 3,600.00
Paku 2" - 5" kg 0.0200 8,000.00 160.00
Tenaga :
Tukang kayu oh 0.1000 30,000.00 3,000.00
Pekerja oh 0.1000 25,000.00 2,500.00
Kepala tukang kayu oh 0.0100 35,000.00 350.00
Mandor oh 0.0050 40,000.00 200.00
Jumlah 6,630.00 6,050.00 12,680.00
Keuntungan Maksimal 10 % 1,268.00
Jumlah 13,948.00
Dibuilatkan 13,940.00
HARGA
JUMLAH HARGA JUMLAH HARGA
SATUAN
NO. URAIAN SAT. KOEF.
BAHAN /
UPAH BAHAN UPAH BAHAN + UPAH
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
1 2 3 4 5 6 7 8
6 1M3 GALIAN TANAH BIASA KEDALAMAN 1 M
Tenaga :
Pekerja oh 0.4000 25,000.00 10,000.00
Mandor oh 0.0400 40,000.00 1,600.00
Alat Bantu ls 1.0000 2,500.00 2,500.00
Jumlah 14,100.00 14,100.00
Keuntungan Maksimal 10 % 1,410.00
Jumlah 15,510.00
Dibuilatkan 15,510.00
7 1M3 GALIAN TANAH BIASA KEDALAMAN 2 M
Tenaga :
Pekerja oh 0.5260 25,000.00 13,150.00
Mandor oh 0.0520 40,000.00 2,080.00
Alat Bantu ls 1.0000 2,500.00 2,500.00
Jumlah 17,730.00 17,730.00
Keuntungan Maksimal 10 % 1,773.00
Jumlah 19,503.00
Dibuilatkan 19,500.00
10 1M3 URUGAN TANAH KEMBALI
Tenaga :
Pekerja oh 0.1900 25,000.00 4,750.00
Mandor oh 0.0200 40,000.00 800.00
Alat Bantu[ ls 1.0000 500.00 500.00
Jumlah 6,050.00 6,050.00
Keuntungan Maksimal 10 % 605.00
Jumlah 6,655.00
Dibuilatkan 6,650.00
11 1M3 URUGAN PASIR
Bahan :
Pasir urug m3 1.2000 40,000.00 48,000.00
Tenaga :
Pekerja oh 0.1500 25,000.00 3,750.00
Mandor oh 0.0100 40,000.00 400.00
Alat Bantu ls 1.0000 2,000.00
Jumlah 48,000.00 4,150.00 52,150.00
Keuntungan Maksimal 10 % 5,215.00
Jumlah 57,365.00
Dibuilatkan 57,360.00
12 1M3 PASANGAN PONDASI BATU KOSONG AANSTAMPING
Bahan :
Batu belah 15 - 20 cm m3 1.2000 70,000.00 84,000.00
Pasir urug m3 0.4000 40,000.00 16,000.00
Tenaga :
Pekerja oh 0.5000 25,000.00 12,500.00
Tukang batu oh 0.5620 30,000.00 16,860.00
Kepala tukang batu oh 0.0750 35,000.00 2,625.00
Mandor oh 0.0560 40,000.00 2,240.00
Jumlah 100,000.00 34,225.00 134,225.00
Keuntungan Maksimal 10 % 13,422.50
Jumlah 147,647.50
Dibuilatkan 147,640.00
HARGA SATUAN
NO URAIAN PEKERJAAN
( Rp. )
1 2 3
1 1M2 PEKERJAAN PENGUKURAN SITE 1,430.00
2 1M3 PEKERJAAN STRIPPING SEDALAM 0,1 M 1,590.00
3 1M2 PEMBERSIHAN LAPANGAN DAN PERATAAN 4,950.00
4 1M' PASANGAN BOUWPLANK 13,940.00
5 1M3 GALIAN TANAH BIASA KEDALAMAN 1 M 15,510.00
6 1M3 GALIAN TANAH BIASA KEDALAMAN 2 M 19,500.00
7 1M3 URUGAN TANAH KEMBALI 6,650.00
8 1M3 URUGAN PASIR 57,360.00
9 1M3 PASANGAN PONDASI BATU KOSONG AANSTAMPING 147,640.00
10 1M3 PASANGAN PONDASI BATU KALI 1 PC : 5 PS 310,150.00
11 1M2 PASANGAN BATA MERAH TEBAL 1/2 BATA 1PC : 3 PS 60,110.00
12 1M2 PASANGAN BATA MERAH TEBAL 1/2 BATA 1PC : 5 PS 48,150.00
13 1M2 PLESTERAN DINDING + ACIAN 1 : 5 22,110.00
14 1M2 FINISHING ACIAN 11,600.00
15 1M3 PASANGAN KUSEN PINTU / JENDELA KAYU SAMARINDA 5,611,650.00
16 1M3 PASANGAN KUSEN PINTU / JENDELA KAYU KAMPER SAMARINDA 5,611,650.00
17 1M2 PASANGAN PINTU PANEL KAYU SAMARINDA 297,820.00
18 1M2 PASANGAN DAUN PINTU TEAK WOOD 4 MM RANGKA KY. SAMARINDA 435,840.00
19 1M2 PASANGAN DAUN JENDELA KACA KAYU SAMARINDA 145,310.00
20 1M' PASANGAN PAPAN JALUSI KAYU BORNEO SUPER 1,5/12 13,510.00
21 1M2 PASANGAN KACA TEBAL 3 MM + List 64,620.00
22 1M2 PASANGAN KACA TEBAL 5 MM + List 78,370.00
23 1M1 PASANGAN BUBUNG GENTENG PALENTONG 41,270.00
24 1M2 PASANGAN RANGKA LANGIT - LANGIT ( GRID 50 X 100 ) KAYU albasiah 29,650.00
25 1M2 PASANGAN PLAFOND GYPSUM ( PABRIKASI ) 23,650.00
26 1M1 PASANGAN LIST PLANK (3X30 CM), KAYU BORNEO 14,530.00
27 1M1 PEKERJAAN PAPAN RUITER 2/20, KAYU BORNEO 11,090.00
28 1M1 PEKERJAAN PAPAN RUITER 2/20, KAYU BORNEO SUPER 20,290.00
29 1M1 PEKERJAAN TALANG DATAR BJLS 28 65,680.00
30 1BH PASANG BAK FIBER GLASS 167,070.00
31 1BH PASANG KLOSET JONGKOK 500,000.00
HARGA SATUAN
NO URAIAN PEKERJAAN
( Rp. )
1 2 3
32 1BH PASANG ENGSEL PINTU 13,750.00
33 1BH PASANG ENGSEL JENDELA KUPU - KUPU 13,200.00
34 1BH PASANG KUNCI TANAM BIASA 115,500.00
35 1BH PASANG SLOT PINTU 19,800.00
36 1BH PASANG SLOT JENDELA 9,900.00
37 1BH PASANG KUNCI TANAM KAMAR MANDI 83,050.00
38 1BH PASANG SPRING KNIP 27,500.00
39 1BH PASANG KAIT ANGIN 11,550.00
40 1TTK PASANG TITIK CAHAYA 70,500.00
41 1TTK PASANG TITIK DAYA/STOP KONTAK 40,000.00
42 1BH PASANG ARMATUR STOP KONTAK 20,350.00
43 1BH PASANG ARMATUR SAKLAR TUNGGAL 20,350.00
44 1BH PASANG ARMATUR SAKLAR GANDA 23,100.00
45 1BH PASANG LAMPU PIJAR 25 WATT 25,850.00
46 1M2 PASANGAN LANTAI KERAMIK 20/20 POLOS 73,530.00
47 1M2 PASANGAN LANTAI KERAMIK 20/20 WARNA CORAK 79,090.00
48 1M2 PASANGAN DINDING BATU AMPIG 87,420.00
49 1M2 PASANGAN DINDING KERAMIK 20/25 CORAK WARNA 73,530.00
50 1M2 PASANGAN LANTAI KERAMIK UK. 30/30 CM PUTIH POLOS 66,310.00
51 1M2 PASANGAN LANTAI KERAMIK UK. 30/30 CM WARNA CORAK 69,640.00
52 1M2 PASANGAN MARMER 364,780.00
53 1M2 PASANGAN PAVING BLOCK NATURAL, T = 6 CM 54,450.00
54 1M2 PASANGAN PAVING BLOCK WARNA, T = 6 CM 56,870.00
55 1M2 PASANGAN PAVING BLOCK NATURAL, T = 8 CM 59,900.00
56 1M2 PASANGAN PAVING BLOCK WARNA, T = 8 CM 62,920.00
57 1M' PASANGAN SALURAN GREVEL BETON 1/2 DIA 20 CM + PASANGAN 228,480.00
58 1BH BAK KONTROL UK. DALAM 25 25 CM 93,170.00
59 1UNIT PEKERJAAN SEPTICKTANK UK. 2.50 X 2.00 X 1.50 M 6,631,240.00
60 1M' PASANGAN SALURAN AIR BERSIH PVC 1/2" 5,500.00
61 1M' PASANGAN SALURAN AIR HUJAN PVC 3" 18,700.00
62 1M' PASANGAN SALURAN AIR KOTOR PVC 4" 24,200.00
63 PENGECATAN DINDING SANLEX ( 2 X ) 14,550.00
64 1M2 PENGECATAN DINDING SANLEX (3X) 19,040.00
65 1M2 PENGECATAN PLAFOND SANLEX (2X) 19,880.00
66 1M2 PENGECATAN PLAFOND SANLEX (3X) 21,180.00
67 1M2 PLABURAN BIDANG KAYU DENGAN POLITUR 13,470.00
68 1M2 PLABURAN BIDANG KAYU DENGAN CAT RESIDU/SOLIGNEM 5,340.00
69 1M2 PENGECATAN KAYU (2X) 20,590.00
70 1M2 PENGECATAN KAYU (3X) BERIKUT MENIE 29,680.00
71 1M2 LABURAN MENIE KAYU (2X) 7,310.00
72 1M3 LANTAI KERJA 1PC : 3PS : 5KR (Rabat) 479,600.00
73 1M3 MEMBUAT BETON TUMBUK 1PC : 3 PS : 5 KR 430,140.00
74 1M3 BETON SITE MIX K 200 541,580.00
75 1M3 COR BETON SITE MIX K225 577,500.00
76 1KG PEMBESIAN DENGAN BESI POLOS U - 24 & U - 32 10,720.00
77 1M2 PASANGAN BEKISTING PAPAN ( ANALISA BOW ) 50,210.00
78 1M2 PASANGAN BEKISTING MULTIPLEK 9 MM ( ANALISA BOW ) 94,780.00
79 1M2 PASANGAN STOOTWERK 114,840.00
80 1M3 PEKERJAAN BETON PONDASI PLAT 1,00 X 1,00 Tul = 227,280 KG (16 - 20) 3,044,000.00
81 1M3 PEKERJAAN BETON KOLOM STRUKTUR 20/35 Tul = 182,143 KG (8 dia 14 + dia 10 - 20) 3,611,540.00
82 1M3 PEKERJAAN BETON KOLOM SELASAR 15/20 Tul = 151,260 KG (4 dia 12 + dia 8 - 20) 3,247,370.00
83 1M3 PEKERJAAN BETON KOLOM PRAKTIS 12/12 Tul = 226,064 KG (4 dia 10 + dia 8 - 20) 4,221,510.00
84 1M3 PEKERJAAN BETON BALOK INDUK 20/60 Tul = 211,130 KG (8 dia 19 + 2 dia 12 + dia 10 - 15) 3,658,810.00
85 1M3 PEKERJAAN BETON BALOK ANAK 20/30 Tul = 109,000 KG (5 dia 12 + dia 8 - 15) 2,436,040.00
86 1 PASANG KUNCI PINTU BESAR 80,000.00
87 LANTAI KERAMIK 20/20 (1 m2) 40,000.00
88 1 M2 BATU AMPIG 87,420.00
89 PABRIKASI BAJA RINGAN 90,000.00
90 GENTENG BETON 16,500.00
91 RENG BAJA RINGAN 70,000.00
92 LIST PROFIL GYPSUM ( PABRIKASI ) 9,000.00
93 Out le TV Braco Integra 70,000.00
94 Genteng Beton Plat 40,000.00
BILL OF QUANTITY
PEMBANGUNAN RUMAH TINGGAL SATU LANTAI
TYPE 40
0
0
100
70.75
1.5 12
0.4836 34.215
11.554
0.0255 1.804
2.123
0.1662 1.4958 2.44 5.54
0.06975 0.62775
2.123
0.175 12.381
0.078 5.519
20.64 38.250 211.905 191.265
5.738 11.4759
44 2.2
38.25
8.625
15
44 0.5 88
55
69
10.530 21.0596
7.6245
REKAPITULASI BILL OF QUANTITY (BOQ)
PEMBANGUNAN RUMAH TINGGAL 1 LANTAI
TYPE 40
JUMLAH
No. ITEM PEKERJAAN
(Rp.)
1 2 3
I Pekerjaan Persiapan 1,388,255.00
II Pekerjaan Tanah 944,986.55
III Pekerjaan Beton 11,369,995.66
IV Pekerjaan Pasangan Pondasi,Dinding & Plesteran 24,288,894.08
V Pekerjaan Kusen Pintu/Jendela & Kaca 6,986,388.20
VI Pekerjaan Lantai dan Sanitair 4,052,149.50
VII Pekerjaan Kamar Mandi 1,651,070.00
VII Pekerjaan atap & Langit-langit 11,666,421.20
VIII Pekerjaan Cat dan Laburan 1,659,670.94
IX Pekerjaan Instalasi Listrik 954,000.00
Jumlah A 64,961,831.13