PROJECT: Magellan Manifold Prepared by: Craig Tabor

TWO WEEK LOOKAHEAD SCHEDULE Date: 5-23-11

Week of Mon 5-23-


11
Responsibility
CCC Pour Manifold Containment slab addition
CCC Layout and excavate/drill the remaining 18" south piers
CCC Tie rebar cages and set in place
CCC Pour piers
CCC Form and pour retaining wall in the northwest corner of manifold
CCC Cleanup site
CCC Form and pour 18" pier underneath pipe behind the retaining wall northwest corner
CCC Form and pour 3'x3 pads underneath pipes flowing to tank valves
CCC Form and pour transformer pad west of tank #2507
CCC Form and pour 30" piers underneath piping valves going to tanks #2501 & 2505

Activity Manpower ManhoursLaborTotal Equipment

Pour manifold slab add'n. 8 6 1296 NA


Exc./Form/ Pour piers 4 16 1728
Cat 299 skid steer, mini ex, auger
Form/pour ret. wall 2 4 216 Cat 299 skid steer
Form/pour pier under pipe 2 2 108 NA
Form/pour 3'x3 pads 1 1 28 Cat 299 skid steer
Form/pour trans. pad 4 2 216 Cat 299 skid steer
Form/pour 30" piers under valves 3 5 405 Cat 299 skid steer

Totals 24 36 ###
Mon 5-23 Tues 5-24 Wed 5-25 Thurs 5-26 Fri 5-27 Sat 5-28
Mon 5-30 Tues 5-31 Wed 6-1

X
X
X X
X
X
X
hwest corner X
X
X
X

Material

NA
er, mini ex, auger
#5 Rebar, sonotube, wood
'x8' forms, wall ties, wedge pins, turnbuckles, wood
#8 Rebar, sonotube, wood
2X6
2X12, #3 Rebar
#8 Rebar, sonotube, wood
Thurs 6-2 Fri 6-3 Sat 6-4