VERTICAL ALIGNMENT REVISION

Name of Bridge: CABIANGON

Middle Ordinate Distance Vertical Revised Original


Grades (%) LVC Tangent Variance
Remarks Station Direction Parabola (MO) from PVI Offset (Y) Finished Grade Finished Grade
Elevation
g1 , g2 LVC1 , LVC2 =(g2-g1) LVC / 800 (m) (m) (FG)
PVC 0+123.500 55.748 m 30.000 m 0.0000 55.748 m
0+140.000 54.495 m 13.500 m 0.1724 54.667 m
0+150.000 53.736 m 3.500 m 0.4448 54.181 m
--- 0.000 m --- ---
-7.594 % (-) 30 m
--- 0.000 m --- ---
APPROACH "B"

--- 0.000 m --- ---


--- 0.000 m --- ---
OPENS
1st CURVE PVI 0+153.500 0.570 m 53.470 m 0.000 m 0.5700 54.040 m
UPWARD
0+160.000 53.470 m 6.500 m 0.3498 53.820 m
0+170.000 53.470 m 16.500 m 0.1154 53.585 m
--- 0.000 m --- ---
0.000 % Straight 30 m
--- 0.000 m --- ---
--- 0.000 m --- ---
--- 0.000 m --- ---
PVT 0+183.500 53.470 m 30.000 m 0.0000 53.470 m
Designed by: RDPA