BUILT-UP RATE

Concrete Ready Mixed Cost/m3


Item G15 G20 G25 G30 G35 G40 G45
A Material Cost 158.00 165.00 173.00 182.00 192.00 203.00 215.00
B Wastage 5% 7.90 8.25 8.65 9.10 9.60 10.15 10.75
C Sub-total (A+B) 165.90 173.25 181.65 191.10 201.60 213.15 225.75
abour 17 17.00 17.00 17.00 17.00 17.00 17.00 17.00
E Sub-total (C+D) 182.90 190.25 198.65 208.10 218.60 230.15 242.75
!rofit 10% 18.29 19.03 19.87 20.81 21.86 23.02 24.28
G Total (E+F) 201.19 209.28 218.52 228.91 240.46 253.17 267.03
H Round Up 201.20 209.30 218.50 228.90 240.50 253.20 267.00
Concrete Ready Mixed Cost/m2
G15 G20 G25 G30 G35 G40 G45
50 mm thk 10.06 10.47 10.93 11.45 12.03 12.66 13.35
75 mm thk 15.09 15.70 16.39 17.17 18.04 18.99 20.03
100 mm thk 20.12 20.93 21.85 22.89 24.05 25.32 26.70
125 mm thk 25.15 26.16 27.31 28.61 30.06 31.65 33.38
150 mm thk 30.18 31.40 32.78 34.34 36.08 37.98 40.05
175 mm thk 35.21 36.63 38.24 40.06 42.09 44.31 46.73
200 mm thk 40.24 41.86 43.70 45.78 48.10 50.64 53.40
225 mm thk 45.27 47.09 49.16 51.50 54.11 56.97 60.08
275 mm thk 55.33 57.56 60.09 62.95 66.14 69.63 73.43
300 mm thk 60.36 62.79 65.55 68.67 72.15 75.96 80.10
BUILT-UP RATE
BRC Cost /m2
Standard Price List From Persatuan Dawai Keluli Malaysia
A4 A5 A6 A7 A8 A9 A10 A11 A12 A13
A Material Cost 7.50 11.60 15.00 20.40 26.70 33.70 41.60 50.40 66.60 78.20
B Discount 65% 4.88 7.54 9.75 13.26 17.36 21.91 27.04 32.76 43.29 50.83
C Sub-total (A-B) 2.63 4.06 5.25 7.14 9.35 11.80 14.56 17.64 23.31 27.37
astage & Laps 20% 0.53 0.81 1.05 1.43 1.87 2.36 2.91 3.53 4.66 5.47
E Sub-total (C+D) 3.15 4.87 6.30 8.57 11.21 14.15 17.47 21.17 27.97 32.84
Labour 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50
Sub-total (E+F) 4.65 6.37 7.80 10.07 12.71 15.65 18.97 22.67 29.47 34.34
!rofit 10% 0.47 0.64 0.78 1.01 1.27 1.57 1.90 2.27 2.95 3.43
I Total (G+H) 5.12 7.01 8.58 11.07 13.99 17.22 20.87 24.93 32.42 37.78
J Round Up 5.12 7.01 8.58 11.07 13.99 17.22 20.87 24.93 32.42 37.78
B5 B6 B7 B8 B9 B10 B11 B12 B13
A Material Cost 22.90 25.20 30.60 40.10 47.10 54.90 63.70 81.40 93.00
B Discount 65% 14.89 16.38 19.89 26.07 30.62 35.69 41.41 52.91 60.45
C Sub-total (A-B) 8.02 8.82 10.71 14.04 16.49 19.22 22.30 28.49 32.55
astage & Laps 20% 1.60 1.76 2.14 2.81 3.30 3.84 4.46 5.70 6.51
E Sub-total (C+D) 9.62 10.58 12.85 16.84 19.78 23.06 26.75 34.19 39.06
Labour 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50
Sub-total (E+F) 11.12 12.08 14.35 18.34 21.28 24.56 28.25 35.69 40.56
!rofit 10% 1.11 1.21 1.44 1.83 2.13 2.46 2.83 3.57 4.06
I Total (G+H) 12.23 13.29 15.79 20.18 23.41 27.01 31.08 39.26 44.62
J Round Up 12.23 13.29 15.79 20.18 23.41 27.01 31.08 39.26 44.62
BUILT-UP RATE
SteeI Bar Cost/Kg
Y10 Y12 Y16 - Y32 R6 R8 R10 R12
A Material Cost 2.28 2.25 2.18 2.15 2.12 2.10 2.10
B Wastage 5% 0.11 0.11 0.11 0.11 0.11 0.11 0.11
C Sub-total (A+B) 2.39 2.36 2.29 2.26 2.23 2.21 2.21
abour 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40
E Sub-total (C+D) 2.79 2.76 2.69 2.66 2.63 2.61 2.61
!rofit 10% 0.28 0.28 0.27 0.27 0.26 0.26 0.26
Total (E+F) 3.07 3.04 2.96 2.92 2.89 2.87 2.87
Round Up 3.07 3.04 2.96 2.92 2.89 2.87 2.87
BILL NO. 1 : INTERMEDIATE UNIT
Item Unit Qty Rate (RM) Amount (RM)
FRAME
Jibrated reinforced concrete Crade 2 as
described, in
A Columns. m3 1 209.30 209.30
B RooI beams. m3 2 209.30 418.60
ild steel bar reinforcement as described
C 6mm Diameter, in columns (links). kg 129 2.92 376.68
D 8mm Diameter, in rooI beams (stirrups). kg 108 2.89 312.12
High tensile steel bar reinforcement as
described
E 12mm Diameter, in columns. kg 118 3.04 358.72
F 16mm Diameter, in columns. kg 38 2.96 112.48
G 10mm Diameter, in rooI beams. kg 112 3.07 343.84
H m2 4 21.85 87.40
J m2 10 32.78 327.80
K m2 5 11.07 55.35
L m2 5 8.58 42.90
M ReI. A8 (weight 3.95 kg/m2), in Iooting m2 7 13.99 97.93
150mm Thick rooI slabs.
Description
RM 2,743.12
Carried to Summary of Bill No. 1
Jibrated reinforced concrete Crade 25 as
described, in
100mm Thick rooI slabs.
Steel fabric reinforcement as described,
including laps, cutting, bending and notching
around obstructions (measured nett : no allow
for laps)
ReI. A7 (weight 3.02 kg/m2), in rooI slabs.
ReI. A6 (weight 2.22 kg/m2), in rooI slab.
B1/1