TESTING & PRECOMMISSIONING PROCEDURE FOR FUSIBLE PLUG LOOP PANEL FPP-8010

TPDP-A TOPSIDES

PROCEDURE No: PSP-TPDP-A-T18-08 REVISION 0 Page 1 of 5

TABLE OF CONTENTS Section 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 Description PURPOSE SCOPE REFERENCES DEFINITIONS SAFETY RESPONSIBILITIES PROCEDURE PREPARATION PROCEDURE TEST REPORT Page 2 2 2 2 2 3 3 3 4

APPENDICES APPENDIX I APPENDIX II APPENDIX III APPENDIX IV CHECK SHEET FUSIBLE PLUG LOOP SCHEMATIC SYSTEM SUB-SYSTEM DEFINITION FAT PROCEDURE

TESTING & PRECOMMISSIONING PROCEDURE FOR FUSIBLE PLUG LOOP PANEL FPP-8010
TPDP-A TOPSIDES 1.0 PURPOSE

PROCEDURE No: PSP-TPDP-A-T18-08 REVISION 0 Page 2 of 5

The objective for the test is to ensure that the performance of fusible plug loop panel on the completed package can meet the requirement as specified in Client's specification and to check any deviations. 2.0 SCOPE This procedure covers the requirements and conditions for function testing of Fusible Plug Loop Panel. 3.0 REFERENCES CSP-T20: Testing and Pre-commissioning guidelines. CSP-04 Project specific procedure guidelines. Fusible plug loop schematic P-0809-1234-02. FAT procedure.

4.0 DEFINITIONS PCVL PMT JHA CLIENT CA 5.0 SAFETY Safety is of paramount importance during all stages of the project. Therefore, all project safety standards, procedures and guidelines must be complied with. The JHA must be conducted by all pre-commissioning team prior to commencement of the work. : PC Vietnam Limited : PTSC Procedure Management Team : Job Hazardous Analysis : PCVL : Certification Authority.

TESTING & PRECOMMISSIONING PROCEDURE FOR FUSIBLE PLUG LOOP PANEL FPP-8010
TPDP-A TOPSIDES 6.0 RESPONSIBILITIES

PROCEDURE No: PSP-TPDP-A-T18-08 REVISION 0 Page 3 of 5

a. Test Engineer shall be responsible for conducting / supervising all inspections and tests and signing of records all relevant documents. b. Test Engineer shall ensure that all function tests are in accordance with specified requirement. c. CA shall be responsible for certifying the pump after testing. 7.0 PROCEDURE PREPARATION The following utilities and temporary systems will be required to complete the test procedure: 7.1. Power 24VDC supply system Check and ensure that a 24VDC power supply source is provided to all transmitters of Fusible Plug Loop schematic. 7.2. Pneumatic supply system Compressed air system shall be provided for operation of Fusible Plug Loop Panel. 7.3. Valves Two (2) three way valves are needed for simulation. 8.0 PROCEDURE 8.1 Test start-up a. Isolate and make the test circuit as following steps:      Open valves VB-1, VB-3, VB-5, VB-7, VB-9 Close valves VB-2, VB-4, VB-6, VB-8 Adjust filter regulator PCV-8013 at 58psig Adjust pressure regulator PCV-8011 and PCV-8012 at 40psig Connect three way valves (for simulation) to bulkhead B1 and B6 with closed status of vent port for initial position.

TESTING & PRECOMMISSIONING PROCEDURE FOR FUSIBLE PLUG LOOP PANEL FPP-8010
TPDP-A TOPSIDES

PROCEDURE No: PSP-TPDP-A-T18-08 REVISION 0 Page 4 of 5

b. Supply compressed air to Instrument Gas Supply B1 (at inlet of three way valve) and Nitrogen Supply Bulkhead B3. c. Verify that Pressure Gauge PG-8011 indicates 40psig d. Open VB-4, VB-6 and close VB-3, VB-5 to test the function of Pressure Control Valve PCV-8012 and verify that Pressure Gauge PG-8011 still indicates 40psig e. Push to charge relay HS-8011 to charge the fusible plug loop f. Verify that Pressure Gauge PG-8012 indicates 40psig g. At the same time three (3) pressure transmitters PZT-8011A/B/C will show pressure 40psig h. Release pressure in fusible plug loop on three way valve at bulkhead B6 to simulate fire situation i. Verify that pressure in fusible plug loop be lost and pressure gauge PG-8012 and three pressure transmitters PZT-8011A/B/C indicate less than 15psig j. Release inlet pressure on three way valve at bulkhead B1 to simulate pressure loss of instrument air supply k. The three-way pilot Operated Valve (SR-8011) will switch over flowing from Regulator PCV-8013. Verify that pressure gauge PG-8012 maintains showing pressure 40psig (In future flow going from Regulator PCV-8013 will be nitrogen provided for replacing utility gas in the case of loss of utility gas pressure less than 73 psig.) 8.2 Test Completion Ensure that all components are set back as before test.

9.0 TEST REPORT Test records are to be submitted to PCVL. Complete pre-commissioning and testing check sheet as per attached. ITS-1004

TESTING & PRECOMMISSIONING PROCEDURE FOR FUSIBLE PLUG LOOP PANEL FPP-8010
TPDP-A TOPSIDES

PROCEDURE No: PSP-TPDP-A-T18-08 REVISION 0 Page 5 of 5

Note: Above check sheet with full signature from PTSC and PCVL will be submitted to PCVL prior to test start-up.