Responsibility
Plumbing Work Foreman, Pipe Fitters, Construction Co-ordinator, Project Engineer, Site Supervisor and Project Manager
Discussion
In order to ensure the integrity of pipeline in and around the area will perform pressure testing. The pressure testing procedures adopted the recommended standards and practises. The procedures also outline proper safety practises that must be followed in order to minimize risks.
Requirements
Tools and Equipment All personnel within test area shall be required to wear eye and hearing Personnel Protection Equipment (PPE). Hard Hat, safety shoe and dust mask. Quick Couplings, Air Compressor, Hydraulic Pressure Portable Pump set and Pressure Gauge.
2. Ensure that no high pressure testing occur in the work place. 3. Ensure personnel conducting the test stand behind a barrier during pressurization. 4. Mark and barricade the work area. Results: After following the above procedures, the necessary steps to ensure safety will be complete.
15. After the pneumatic pressure test have been approved, continue a second testing by using a hydraulic test the next day. Followed the procedure as Item 1 to 10. Hold the maximum test pressure of 200 PSI for 4 Hours. 16. Obtain confirmation of a successful test by the System Owner/ M+W Personnel after 4 hours time period. 17. Remove the pressure, with caution to avoid escaping air stream, debris and high decibel noise level. 18. Complete the appropriate following forms Pressure/Leak Testing Sheet and recorded the test data and place them in the appropriate engineering files at specified by the Project Engineer. Results After completing these steps, pressure testing is completed. Once the test is successfully completed, then the new pipeline is ready for connection.