Anda di halaman 1dari 2

SCHEDULE OF WORK

NAME OF WORK:-MOEI&Fans RMO P/Sets etc at Hyderabad Estate Nepean Sea Road,Mumbai.
SUB HEAD :-Refilling of carbon-di-oxide fire Extinguisher
HEAD OF A/C :-2216 Hsg

Sno Item of work Qty Rate Unit Amount Rmk

1 Refilling of Carbon-di-oxide fire extinguisher of following


capacity upto the pressure of 263 Kgf/sq cm as
specified by the BIS i/c assembling the same and
painting with approved colour, testing etc as reqd.
a)2 Kg 50 Jobs 369.00 Job 18,450.00 MR

TOTAL 18,450.00

Terms and conditions:-


1)Materials are to be got approved by E-in-C
2)No T&P will be supplied to contractor.
3)Work has to be carried out to the entire satisfaction of E-in-C
4)Rates quoted should be inclusive of all taxes and duties.

FireExtingusherPED
Sheet2

ANALYSIS OF RATES
Sno Description Rate Unit Qty Amount

Refilling of CO2 extingusher-2Kg


A MATERIALS
1)Carbon-di-oxide 60.00 1 Kg 2 Kg 120.00
2) Red colour enamel paint 145.00 1 Lt 0.08 Lt 11.60
3)Cartage to and fro 10.00 1 LS 1 LS 10.00

Total A 141.60

B Labour
1)Mason 126.00 1 Day 0.05 Day 6.30
2)Khalasi 122.00 1 Day 0.05 Day 6.10
3)Testing charges 175.00 1 LS 1 LS 175.00
Total B 187.40
Total(A+B) 329.00

C T&P @ 2% of(A+B) 6.58


Total(A+B+C) 335.58

D Overhead and Profit @ 10% 33.56

Total(A+B+C+D) 369.14

E WCT @ 2% 7.38

Total(A+B+C+D+E) 376.52
377.00

Refilling of CO2 extingusher-3.2Kg


A MATERIALS
1)Carbon-di-oxide 60.00 1 Kg 3.2 Kg 192.00
2) Red colour enamel paint 145.00 1 Lt 0.08 Lt 11.60
3)Cartage to and fro 10.00 1 LS 1 LS 10.00

Total A 213.60

B Labour
1)Mason 126.00 1 Day 0.05 Day 6.30
2)Khalasi 122.00 1 Day 0.05 Day 6.10
3)Testing charges 200.00 1 LS 1 LS 200.00
Total B 212.40
Total(A+B) 426.00

C T&P @ 2% of(A+B) 8.52


Total(A+B+C) 434.52

D Overhead and Profit @ 10% 43.45

Total(A+B+C+D) 477.97

E WCT @ 2% 9.56

Total(A+B+C+D+E) 487.53
488.00

Page 2