Task Duration

ID 3D Files Approved 14 days


Sculpts sent to China 2 days

Print Materials
Preliminary Dummies (White boxes from factory or packaging supplier) 2 days
Dummies Approved 5 days
Files Approved for Manufacturer (Post packaging content and files to FTP) 2 days
Manufacturers Proof Received 10 days
Manufacturers Proof Approved 3 days
Print Manufacturing for FEPs 5 days

Electronics (When applicable per project)


Final Electronic Functional Spec 6 wks
Software program development 5 wks
Electronics Demo Board Arrives 2 days
Software revisions 2 wks
Software testing 8 days
Electronics approved for masking 7 days
Chips arrive in Hong Kong 6 wks
Chips transferred from HK to China manufacturing plant 0 days
IC approved for PCB assembly 6 days

Plastics
CAD Files Approved 15 days
Final Model Approved 30 days
Final Model Created and Shipped 10 days
Final Model Arrives at Cranium 3 days
Final Model Adjustments Made 5 days
Final Model Approved 0 days
Final Materials Commit 0 days

Tooling 60 days
Tool Creation 6 wks
1st Shot 2 wks
1st Shot Approved 4 days
1st Shot Revision 4 days
2nd Shot 4 days
2nd Shot Approved 3 days
Tooling Complete 0 days

Plastics Manufacturing 5 days


FEP Arrives 7 days
FEP Approved 1 wk
BOM Lock 0 days
Manufacturing Start 0 days
Pre-Production 2 wks
Week 1-2: X units 2 wks
Week 3: X units 1 wk
Week 4: X units 1 wk
FOB 1 0 days
Shipping and Stocking 18 days
Avail to sell (at DC) 0 days
Start Finish
12/19/2006 1/16/2007
1/17/2007 1/18/2007

2/23/2007 2/26/2007
4/20/2007 4/27/2007
5/18/2007 5/22/2007
5/22/2007 6/5/2007
6/5/2007 6/8/2007
6/8/2007 6/15/2007

12/21/2006 2/9/2007
2/12/2007 3/16/2007
3/19/2007 3/20/2007
3/21/2007 4/3/2007
4/4/2007 4/13/2007
4/16/2007 4/24/2007
4/25/2007 6/12/2007
6/12/2007 6/12/2007
6/13/2007 6/20/2007

1/19/2007 2/8/2007
2/9/2007 3/22/2007
2/9/2007 3/12/2007
3/13/2007 3/15/2007
3/16/2007 3/22/2007
3/22/2007 3/22/2007
3/22/2007 3/22/2007

3/23/2007 6/14/2007
3/23/2007 5/10/2007
5/11/2007 5/24/2007
5/25/2007 5/30/2007
5/31/2007 6/5/2007
6/6/2007 6/11/2007
6/12/2007 6/14/2007
6/14/2007 6/14/2007

6/15/2007 6/21/2007
6/22/2007 7/2/2007
7/3/2007 7/9/2007
7/9/2007 7/9/2007
7/9/2007 7/9/2007
7/10/2007 7/23/2007
7/24/2007 8/6/2007
8/7/2007 8/13/2007
8/14/2007 8/20/2007
8/20/2007 8/20/2007
8/21/2007 9/13/2007
9/13/2007 9/13/2007