Basic Steps in Construction Scheduling and Management

Page 1 of 5

Steps for Construction Scheduling, Construction Management, Arrow Diagrams, CPM Calculations, Node Diagrams and CPM Calculator.
Search
Home Construction Management & Cost Control Steps in Construction Scheduling Online Primavera Training Learn Primavera P6 Online Try Our Free eLearning Demo CPMSolutions.ca/Primavera-Online

Construction Management
Construction Scheduling Construction Project Quality Construction Management Resource Levelling Allocation Project Controlling Schedule Policies of Construction Projects

Construction Scheduling Use Microsoft Project Effectively! Templates, Manuals, Tools, Services www.constructionscheduling.com Master Project Management Earn Your Project Management MA Online. Request for Information! WaldenU.edu/Project-Manage

Steps in Construction Scheduling


Advertisements

Planning & Scheduling


Planning: Process of choosing the method and order of work Scheduling: Process of determining the interrelationship of associated timings of operations.

Steps in Construction Scheduling


Splitting of the project into work activities Determining logic relationships/interrelationships between activities. Construction of Network Diagrams. Assigning durations to work activities. CPM Calculations resulting in start times, finish times and float calculations of activities. Marking of critical Path Construction of Bar Charts / Time phased diagrams.

P3 Video Tutorials
2. How to create new Project 3. Adding activities & Task Type 4. Adding Successors 5. How to create WBS Codes 6. Grouping & Sorting in P3 7. Calendars & Holidays 8. Relationship & Scheduling 9. Filters & Progress Reporting 10. Customizing Bar Charts 11. Customizing Layouts in P3 12. Coming Soon 13. Coming Soon

Activity
An element of work performed during the course of a project. Or An amount of work that can be identified so that we know what it involves and can recognize, when it starts and finishes. An activity normally has an expected duration, an expected cost, and expected resource requirements

Network Diagrams
Any schematic display of the logical relationship of project activities. Always drawn from left to right to reflect project chronology. Usually a combination of arrows and nodes.

Mainly of two types:


1. Arrow Diagram 2. Node Diagram / Precedence Diagram

Arrow Diagrams
Activities shown by Arrows. Relationship between activities shown by nodes / events. Length of arrows does not obey any scale. Start-to-finish relationships. Dummies. Numbering of nodes / events. Milestones
Building Construction Primavera P3 Construction Company Primavera Scheduling

P6 Video Tutorials
Primavera P6 Video Tutorials How to install P6 Tutorial New Project in P6 Tutorial 1 Working in P6 - Tutorial 2 Primavera Jobs

Ads by Google

Subscribe Primavera Tuts


Primavera Questions & Answers

http://www.aboutcivil.com/steps-in-construction-scheduling.html

5/26/2011

Basic Steps in Construction Scheduling and Management

Page 2 of 5

About Us | Site Map | Privacy Policy | Contact Us | 2010 SJ Soft Technologies

Activity Durations
Activity duration is forecasted by any of the several means, including: 1. Check Past Records. 2. Check Standards and / or cost guides, if available. 3. Ask the workers, who will do it 4. make an educated guess Any time units may be allotted to activity durations like days, hours, weeks, months, shifts, etc. In CPM, a single duration is forecasted for an activity. In PERT (Program Evaluation & Review Techniques), 3 durations are forecasted for an activity and mean taken by weighted average method. Then, Projects Duration or any Event Completion Time is calculated by probability distribution.

CPM Calculations
Calculates the following for each activity EST = Earliest Starting Time EFT = Earliest Finishing Time LST = Latest Starting Time LFT = Latest Finishing Time TF = Total Float FF = Free Float Total Float is Maximum time for which an activity can be delayed without delaying the project. Free Float is maximum time for which an activity cane be delayed without delaying the start of proceeding activity. Total Float = Free Float + Interfering Float

Critical Path
The path (or paths) in the network diagram, from start to finish, on which all the activities have zero total and free floats, is called Critical Path. It is the longest path (or paths) from start to finish in a net work diagram. It gives minimum normal time to complete a project. It is usually marked by double lined arrows in a network diagram. SINGLE SPAN BRIDGE PROJECT (ACTIVITY DESCRIPTION)

http://www.aboutcivil.com/steps-in-construction-scheduling.html

5/26/2011

Basic Steps in Construction Scheduling and Management

Page 3 of 5

http://www.aboutcivil.com/steps-in-construction-scheduling.html

5/26/2011

Basic Steps in Construction Scheduling and Management

Page 4 of 5

Node Diagrams
Activities shown by Nodes, relationship between Activities shown by arrows or links. Easier to construct. Generally no need of dummies. Instead dummies used only to give single start or finish. CPM Calculations similar to Arrow diagrams.

http://www.aboutcivil.com/steps-in-construction-scheduling.html

5/26/2011

Basic Steps in Construction Scheduling and Management

Page 5 of 5

Bar Chart
Gives Pictorial Representation of Activities. Activities begin at EST and show their EFT, FF, TF, Durations, etc. Arrows at the relative ends to show dependency. Status Line Concept Unable to show complete interdependency between Activities. Time-scaled Network Diagrams show complete interdependency between Activities.
Primavera Scheduling Construction Companies CPM Schedule Employee Scheduling

Ads by Google

Relate Experiments
Construction Project Quality Management Quality is an ever-changing state (i.e., what is considered quality today may not be good enough to be considered quality tomorrow)... Cost Control Management Techniques Involves determining what physical resources (people, equipment, materials etc) and what quantities of each should be used to perform project activities... Project Control Schedule Value Engineering The techniques for project control scheduling and control value engineering...
Beauty & Fashion Cosmetics Cosmetic Surgery Designer Footwear Perfume Sunglasses Women's Apparel Entertainment Books Concert Tickets Games Fantasy Football MP3 Download Toys Computers Computer Games Domain Hosting Domain Registration Free Internet Firewall Printers Finance Credit Card Help Debt Consolidation Financial Adviser Investing Loans Tax Attorney Electronics DVDs Digital Cameras Laptops Mobile Phones MP3 Players Video Games Travel Airline Tickets Car Rental Cruises Golf Vacation Romantic Getaways Vacation Packages
Chitika | Select

http://www.aboutcivil.com/steps-in-construction-scheduling.html

5/26/2011

Anda mungkin juga menyukai