Anda di halaman 1dari 1

Questions on Project Communication Management

1. The process of Manage Stakeholders Expectations is part of which process group? a. Planning b. Monitoring and Control c. Executing d. Initiating

2.

The project you are managing has nine stakeholders. How many channel of communications are there between these stakeholders? a. 9 b. 8 c. 45 d. 36

3.

Which of the following is not an example of formal communication? a. Contract b. email c. Project status report d. Status meeting

4.

Which of the following process is not included in project communication knowledge area? a. Documenting Project Closure b. Plam Communications c. Distribute Information d. Managing Stakeholder Expectations

Answers
1. 2. 3. 4. c. Manage Stakeholder Expectations is part of executing process group. d. There will be (9*8)/2 channel of communication. b. Communication via email is not considered a formal communication. a. Document Project Closure is not a process in Project communication knowledge area.

Anda mungkin juga menyukai