Legend : V H W R M X AFC
: : : : : : :
Verification Hold Point Witness Point Review Monitor Responsibility App. For Construction Drawing
1.0. DOCUMENTS 1.1. QA / QC MANUAL 1.2. APPROVAL OF DRAWING AND DESIGN CALCULATION
1.3. QUALIFICATION / APPROVAL OF WELDING PROCEDURE 1.4. QUALIFICATION / APROVAL OF WELDERS AND WELDING OPERATORS 1.5. APPROVAL OF NDT PROCEDURES INCLUDING PERSONNEL CERTIFICATE
ASME SECT. VIII + DATA SHEET + OWNER SPEC. ASME SECT.IX OWNER SPEC. ASME SECT.IX ASME SECT.V
ASME SECT. VIII COMPANY APPROVAL ASME SECT.IX OWNER SPEC. ASME SECT.IX ASME SECT.V OWNER SPEC. BAPETEN
AS BUILT DRAWING DESIGN CALCULATION DATA SHEET WPS / PQR WELDER CERT. ISSUED BY MIGAS
X R
X X R
H R H
R R R
2.0. MATERIALS 2.1. REVIEW OF MILL/TEST CERTIFICATES AND CONFORMANCE TO CODE 2.2. CHECK MATERIAL (VISUAL) 2.3. DIMENSIONAL CHECK AND REPORT 2.4. CHECK THICKNESS 3.0. LAYOUT AND CUTTING 3.1. CUTTING PLATES AND OTHER STOCK 3.2. CHECK TRANSFERRING OF HEAT NUMBERS 3.3. CHECK LAY OUT AND MARKING OF SHELL 3.4. CHECK POSITION OF NOZZLE 4.0. FIT-UP 4.1. CHECK FIT-UP OF SHELL/HEAD/NOZZLES 4.1.1. LONG SEAMS 4.1.2. CIRCUM SEAMS 4.1.3. NOZZLE ATTACHMENTS 4.1.4. REINFORCEMENT PAD & TELL TALE HOLE ( IF ANY ) 4.1.5. OTHERS 5.0. WELDING 5.1. CHECK PRE-HEATING ( IF ANY ) 5.2. CHECK CONFORMANCE TO WPS 5.3. CHECK WELDERS AND WELDING OPERATORS
ASME SECT.II ASME SECT. VIII OWNER SPEC ASME SECT. VIII MILL CERT. MILL CERT.
ASME SECT.II OWNER SPEC ASME SECT. VIII ASME SECT. VIII DESIGN CALCS. DESIGN CALCS.
R X X.R. X
R H W R
R H R R
ASME SECT. VIII ASME SECT. VIII OWNER SPEC. AFC DWG AFC DWG
X X X X
M M M M
R M R R
AFC DWG
INSP. REPORTS
INSP. REPORTS
X X X X X
W W W W M
ASME SECT.IX WPS/PQR OWNER SPEC. ASME SECT. VIII ASME SECT.IX ASME SECT.IX WPS/PQR
WPS/PQR
X X X
M M M
R R/M
MATERIAL CERTS
Document No. Owner/Client Item No Description Project Title Date Rev. Page No.
: : : : : : : :
Legend : V H W R M X AFC
: : : : : : :
Verification Hold Point Witness Point Review Monitor Responsibility App. For Construction Drawing
6.0. N.D.E 6.1. BUTTWELD (LONG SEAMS, CIRCUM, SEAM & NOZZLE TO FLANGE) 6.1.1. 100% VISUAL INSPECTION AFTER WELDING 6.1.2. 100% RT BEFORE AND AFTER PWHT ( IF ANY ) 6.2. OTHER 6.2.1. UT ON NOZZLE TO SHELL/HEAD ATTACHMENT 6.2.2. MPT ON ATTACHMENT TO SHELL/HEAD 6.2.3. MPT ON NOZZLE, REPAD ATTACHED TO PRESSURE PART 6.2.4. MPI AFTER BACK GOUGING IF BACKSIDE OF ROOT PASS ACCESSIBLE MPI AFTER ROOT PASS IF BACKSIDE OF PASS INACCESSIBLE 7.0. 7.1. 7.2. 7.3. 7.4. 7.5. PWHT PROCEDURE CALIBRATION OF GAUGES PWHT OPERATION RECORD HARDNESS TEST
ASME SECT. VIII OWNER SPEC OWNER SPEC OWNER SPEC OWNER SPEC OWNER SPEC
NDE REPORTS NDE REPORTS NDE REPORTS NDE REPORTS NDE REPORTS NDE REPORTS
NDE REPORTS NDE REPORTS NDE REPORTS NDE REPORTS NDE REPORTS NDE REPORTS
X X X X X X
W R R R R R
ASME SECT. VIII ASME SECT. VIII ASME SECT. VIII ASME SECT. VIII
X X/R X R R
R R W/R R W/R
R R M R R
8.0. DIMENSIONAL AND VISUAL CHECK 8.1. CHECK ROUNDNESS OF SHELL AFTER WELDING 8.2. FINAL VISUAL AND DIMENSIONAL CHECK ( INCLUDIN WELD CONTOUR WELD SIZE AND FINISH ) 8.3. CHECK FOR COMPLETENESS OF NOZZLE SUPPORT, PADS etc ) 8.4. CHECK FOR NDE COVERAGE 8.5. CHECK SOAP SUD TEST OF PAD 8.6. INTERNAL CHECK FOR CLEAN 9.0. HYDROSTATIC 9.1. PROCEDURE 9.2. CALIBRATION OF GAUGES 9.3. HYDROTEST OPERATION 9.4. RECORD 10.0. 10.1. 10.2. 10.3. 10.4. 10.5. 10.6. 10.7. 10.8. PAINTING CHECK PAINTING MATERIAL (BATCH NO.) HUMIDITY CHECK CHECK SURFACE PREPARATION ROUGHNESS CHECK CHECK DFT OF PRIMING CHECK DFT OF SECOND COAT CHECK DFT OF TOP COAT ADHESIVE TEST
ASME SECT. VIII ASME SECT. VIII AFC DRAWING ASME SECT. VIII
ASME SECT. VIII ASME SECT. VIII AFC DRAWING ASME SECT. VIII
INSP. REPORTS INSP. REPORTS INSP. REPORTS NDE REPORTS INSP. REPORTS INSP. REPORTS
INSP. REPORTS INSP. REPORTS INSP. REPORTS NDE REPORTS INSP. REPORTS INSP. REPORTS
X X X X X X
W W W R W W
W H W R W W
ASME SECT. VIII OWNER SPEC. ASME SECT. VIII PROCEDURE ASME SECT. VIII
X X/W W R
H R H R
R R H H
INSP. REPORTS INSP. REPORTS INSP. REPORTS INSP. REPORTS INSP. REPORTS INSP. REPORTS INSP. REPORTS INSP. REPORTS
INSP. REPORTS INSP. REPORTS INSP. REPORTS INSP. REPORTS INSP. REPORTS INSP. REPORTS INSP. REPORTS INSP. REPORTS
X X X X X X X X
R W W W W W W W
M M M M M M M M
12.0. DISPATCH AND DOCUMENTATION 12.1. CHECK INTERNAL ARE INSTALLED AND TIGHTENED PROPERLY 12.2. CHECK THAT VESSEL, NAME PLATE, CONTENTS IS CORRECT AND FITTED CORRECTLY, BLIND OPENING AND SHIPPING MARKS 12.3. PACKING LIFTING AND TRANSPORTATION ARRANGEMENT 12.4. QUALITY RECORDS
AFC DRAWING AFC DRAWING PROCEDURE / AFC OWNER SPEC. OWNER SPEC.
AFC DRAWING AFC DRAWING PROCEDURE AFC DRAWING OWNER SPEC. AFC DRAWING QA DOSSIER AFC DRAWING
X X X/R X
W W R R
R R R R