Project Name : Construction Of Centralized Industrial Area at Halul Island Client : QATAR PETROLEUM Contractor : Orientals Enterprises L.L.C.

CONCRETE POURING REPORT


DATE OF CASTING: DELIVERY Sr.No. INVOICE NO.
1 2 3 4 5 6 7 8 9 10 11

12-Apr-12 Truck No.


158558 115138 158558 158558 158558 158558 158558

Loading
7:25 7:45 8:00 9:00 9:30 10:15 11:10

arrival
7:30 7:56 8:20 9:10 9:40 10:30 11:25

Hours pouring
7:45 8:15 8:25 9:12 9:41 10:30 11:40

leaving
7:50 8:19 8:42 9:18 9:50 10:55 12:00

Concrete Grade: 40N/OPC-Blinding 3 Slump temp. Vol.(m ) Qty. Cumul mm C


6 4 6 6 6 6 2 6 10 16 22 28 34 36 170 170 170 170 170 170 170 29.1 29.1 29.1 29.1 29.1 29.1 29.1

BUILDING : OFFICE BLOCK AREA B STRUCTURE: BLINDING GL(7-9,A'-G') Total Cubes Cubes Amb. Location Cube Crushing Date temp. C 7 Days 28 Days Number Taken
25 7-9 10-12 3 3 02-B 02-B 19-Apr-12 10-May-12

CUBE CRUSHING FOR CONCRETE CONFIRMATION


CUBE AGE 7 DAYS 28 DAYS Average Concrete Compressive strength (Mpa)

Limit
>75% OF CG >40 Mpa within limit within limit test failed test failed

RESULTS/STATUS
further test required further test required OE to submit rectification proposal OE to submit rectification proposal

REMARKS

CONTRACTOR:- ORIENTALS ENTERPRISES


Name: Sign: Date:

ALVIN BADECAO- OE QA/QC ENGR.

NOTE: 40 N WAS USED AS BLINDING AS PER QP APPROVAL