NO.
1
ITEM
PIPING ARM DAN PIPING BOOM
MASALAH
KELEBIHAN ORDER OLEH CV CB. PIPING SUDAH DILENGKAPI OLEH KI PADA UNIT PC200 MASIH ADA DI CV CB. USUL PIN : SUPPLY KI TANPA PIN. HARGA PIPING MAHAL DIFFERENCE HARGA RELATED PARTS TANPA PIPING DAN DENGAN PIPING BEDA JAUH. TIDAK ADA VENDOR YANG MEMBUAT CERTIFICATE OF WARR UNTUK BARANG YANG MENEMPEL PADA UNIT DISKUSI DENGAN USER : ( YPU ) * DIHITUNG MULAI DARI DELIVERY * WARRANTY : UNLIMITED HOUR, SATU TAHUN
WARRANTY CERTIFICATE
DRAWING
PROC SATU HARUS MEMILIKI SETIAP DRAWING DARI BARANG YANG DIPESAN KE VENDOR. CONTOH : CABIN WA500, 380, DLL. SETIAP DRAWING WAJIB DICOLLECT DIMASUKKAN DALAM SATU ORDNER KHUSUS DI FITRI CUSTOMER TIDAK MENGINGINKAN CAB GUARD & STEEL CANOPY PADA UNIT. SEHINGGA ATTACHMENT TSB. DILEPAS DAN PTUT AKAN MEMBELI ATTACHMENT TSB.
STEEL CANOPY CV CB
PIN PERLU MELAKUKAN PENGECEKAN PADA MATERIAL DARI ATTACHMENT YANG DIORDER OLEH PIN ( CEK KEKERASAN DAN CEK JENIS PLAT / MATERIAL ) UNTUK MEYAKINKAN BAHWA HARDNESS, JENIS MATERIAL SESUAI SPEC YANG DISYARATKAN
STANDARISASI AC
BANYAK VENDOR AC DENGAN KEMAMPUAN DAN CARA PEMASANGAN YANG BERAGAM PROBLEM AC YANG TERJADI JUGA KARENA KONDISI EKSTRIM DI SITE
NUT PKB
PROBLEM AC RAPP. COMPLAINT KERAS RAPP TO UT. MENJADI TOPIK UTAMA YANG KELUHAN RAPP.
AUDIT FINDINGS
10 CABIN RA
CABIN RA MASIH BELUM SEBAGUS CB VATOR. CABIN CB VATOR SUDAH DILAKUKAN BERBAGAI MODIF. RA HARUS TURUT MENGIKUTI MODIF CB VATOR SEPERTI : PENAMBAHAN GLASSWOOL & BUSA PADA BAGIAN DALAM CABIN PERUBAHAN DESIGN UNTUK AC. PERMINTAAN PRODUCT AKAN CABIN CUKUP TINGGI. PERMINTAAN PRODUCT AKAN CABIN SELALU MENDADAK. PENGERJAAN CABIN PERLU 14 HARI. VATOR MINTA FORECAST CABIN. AKAN STOCK TANPA PERLU PTUT BUKA PO
11 FORECAST CABIN
12 MEETING RABUAN
WET KIT : SUSAH DIHUBUNGI. LEADTIME PEMASANGAN LAMA. MINTA VENDOR LAIN SELAIN GALANG.
13 MUD GUARD
VENDOR MUDGUARD SAAT INI HANYA SATU VENDOR. MUTU MUDGUARD KURANG BAIK, BAUT SERING LEPAS. AGAR MINTA VENDOR UNTUK MENGGUNAKAN LOCK NUT.
PR DARI USER AUTO EMAIL KE PIN. PERUBAHAN PIC DI MKT AUTO EMAIL DARI BEBERAPA USER KE PIN, BELUM DAPAT DIAKTIFKAN.
15 VESSEL SAMARINDA
VENDOR SIAP KIRIM BARANG. USER SEDANG CARI KAPAL UNTUK KIRIM KE SMD
16 BRACKET HD785
BRACKET STANDARISASI HD785 DISUPPLY OLEH PT UT. 100 SET BRACKET SUDAH DIORDER DAN SEBAGIAN SUDAH DIGUNAKAN UNTUK INSTALASI AUTOLUB HD785
OLLOWED up
STEP
* BICARAKAN DENGAN PRODUCT DALAM RAPAT MINGGUAN * PIPING DI CB SUPAYA DIPAKAI * VENDOR BUAT CERT OF WARR * DISCUSS DENGAN USER RE WARR * WARR : MANA YANG DULUAN WAKTU ATAU KM ? AJI
PIC
DUE DATE
RABUAN DGN USER
CONTINUOUSLY
* MINTA USER BUKA PR * KIRIM PO KE RA UTK REPAIR KIRIM PO KE TIMAAG UTK PAINTING * COPY INVOICE KE WAHYU FIN POTONG AR
AJI
21-May-12
CV CB MODIF STEEL CAN SESUAI DRAWING YANG SUDAH DISTANDARISASI. MINTA DRAWING KE CV CB. BILA BUKA PO, CATAT EFISIENSI
AJI
SOON
* AKAN DIBEBANKAN KE WARDEL * PR VIA SERVICE DIVISION, CEK HARGA * SPEC YANG SEDERHANA SAJA * MINTA APPROVAL SUGI UNTUK WARDEL * KERJASAMA DGN SVC DIV, BUAT STANDARISASI AC * BUAT SOP INSTALASI AC WITH NOVEM * AREA KONDISI EKSTRIM, DIPASANG NETT DI MUKA KONDENSOR * INSTALLATION DRAWING * APPROVAL SERVICE DIVISION * PARTS BOOK * UPDATE SPECIAL CASES AC KE PT DENSO SETELAH HARGA KELUAR KIRIM VENDOR KE PKB BIAYA BEBAN UT. YANG WARRANTY PARTS BEBAN NUT BUTIR 6 : S/D AKHIR TAHUN 2012 BUTIR 7 : S/D AKHIR MEI 2012 REPORT RESULT : AKHIR MEI 2012 * PIHAK RA LAKUKAN SURVEY CABIN VATOR * MINTA REPORT PROGRESS MODIF
AJI
SOON
UP TO FINAL OF PROJECT
OKTORA
ASAP
FITRI AJI
OKTORA
SOON
* BICARAKAN DALAM WEEKLY MTG * MINTA FORECAST 3 BULAN KE MUKA * AJUKAN KE VATOR / RA * INFO USER : HINDARI ORDER DADAKAN
AJI
* INFO KE USER BAHWA DAHULU DITAWARKAN VENDOR LAIN, USER TIDAK SETUJU, KARENA SPEC YANG MASUK DGN SCANIA ADALAH WET KIT GALANG. * INFO VENDOR LOCK NUT PADA PO * CARI ALTERNATIF VENDOR MUDGRD * VIA WEB, TIDAK ADA. CARI SOURCING LAIN * LIST PIC YANG BERHAK BUAT PR * LIST PIC YANG TDK HAK BUAT PR * REQUEST KE CIS, APPROVAL ACCTG * BLOCK YANG TDK HAK BUAT PR ( REPORT KE ACCTG ) * DISCUSS DGN USER OTORISASI PR * KAPAL BERANGKAT : 18 MEI 2012 * UPDATE KE SMD & VENDOR * MONITOR KETIBAAN * VENDOR BERANGKATKAN MANPOWER * CEK KE SVD DIV, BERAPA SISA BRACKET * ORDER BRACKET KE VENDOR * COBA VENDOR LAIN
AJI
SOON
OKTORA HERTIN
CONTINUOUSLY
AJI
ASAP
ASAP
RULLI
DONE
OUTSTANDING JOBS to
NO.
1
ITEM
STANDARISASI LOG SPEC
INOVASI 2012
REPAIR AC AUDI
TOTAL : 22 UNIT DI CIKARANG. SATU UNIT DARI 22, REPAIR LEBIH SULIT 2 UNIT DARI 22, PERLU DIBICARAKAN DENGAN USER.
PROBLEM UTE : BARANG DAN JASA MINTA DIPISAH, KARENA INSTALASI BARU DILAKUKAN JIKA UNIT READY. TENGGANG WAKTU LAMA PROBLEM UTE : BILA DIPISAH, WARDEL BENGKAK. JASA TIDAK MASUK COST UNIT
e FOLLOWED up
STEP
* SPIRITNYA SOP DIBUAT FINAL * UJI COBA DILANJUT BILA ADA DEMAND AJI
PIC
DUE DATE
KEEP ATTENTION IF ANY DEMAND 22-May-12
* SIAPKAN MATERI * SELASA, 22 MEI PRESENTASI DGN CPMD * FITRI & AFRIZAL, JIKA PUNYA IDE INOVASI, BISA DISHARE. * KOORDINASI DENGAN USER UNTUK AC YANG BELUM SELESAI DIREPAIR * BAYAR AC YANG SUDAH DIREPAIR (19) * UTE TAGIH SESUAI PO * COMM DUMMY * ARRANGE MTG LAGI DGN UTE
ALL
FITRI
AJI, OKTORA
OUTSTANDING JOBS t
NO.
1
ITEM
PIPING ARM DAN PIPING BOOM
WARRANTY CERTIFICATE
DRAWING
STEEL CANOPY CV CB
STANDARISASI AC
NUT PKB
AUDIT FINDINGS
10
CABIN RA
11
FORECAST CABIN
12
MEETING RABUAN
13
MUD GUARD
14
15
VESSEL SAMARINDA
16
BRACKET HD785
17
18
INOVASI 2012
19
REPAIR AC AUDI
20
21
STANDARISASI D155
PROC SATU HARUS MEMILIKI SETIAP DRAWING DARI BARANG YANG DIPESAN KE VENDOR. CONTOH : CABIN WA500, 380, DLL. SETIAP DRAWING WAJIB DICOLLECT DIMASUKKAN DALAM SATU ORDNER KHUSUS DI FITRI CUSTOMER TIDAK MENGINGINKAN CAB GUARD & STEEL CANOPY PADA UNIT. SEHINGGA ATTACHMENT TSB. DILEPAS DAN PTUT AKAN MEMBELI ATTACHMENT TSB. PR BELUM DIBATALKAN BUAT PO KE RADIUS AGUNG CHECK SLI-NYA
CHECK KE CAHAYA BAJA MINTA DRAWING DAN PHOTO PERBAIKAN STEEL CANOPY STOCK DI RA DAN ATU MASIH BANYAK, IN CASE JIKA DIBUTUHKAN PIN PERLU MELAKUKAN PENGECEKAN PADA MATERIAL DARI ATTACHMENT YANG DIORDER OLEH PIN ( CEK KEKERASAN DAN CEK JENIS PLAT / MATERIAL ) UNTUK MEYAKINKAN BAHWA HARDNESS, JENIS MATERIAL SESUAI SPEC YANG DISYARATKAN CHECK KE DARMONO SERVICE MINTA HARGA KE DARMONO MINTA IZIN MASUK SRD - IZIN KE SUGIYANTO
BANYAK VENDOR AC DENGAN KEMAMPUAN DAN CARA PEMASANGAN YANG BERAGAM PROBLEM AC YANG TERJADI JUGA KARENA KONDISI EKSTRIM DI SITE
MINTA QUOTATION KE ALLMAKES KEMUNGKINAN NET / RAM MEETING DENGAN ENGINEERING SERVICE MEETING DENGAN TEAM AMK PROBLEM AC RAPP. COMPLAINT KERAS RAPP TO UT. MENJADI TOPIK UTAMA YANG KELUHAN RAPP. MENUNGGU LIST OF ITEMS YANG AKAN DIBAWA KRU 2 ORANG BERANGKAT KE PKB, JIKA COMPONENT TIBA DI PKB MINTA NOMOR HP DARI KRU YANG BERANGKAT KE PKB INFORMASIKAN KE SDH PKB MENGENAI SKEDUL REPAIR AC TEMUAN AUDIT DIJABARKAN PADA LAPORAN AUDIT BUTIR 6 DAN 7.
DIINGATKAN LAGI USER PADA MEETING RABU / JUM'AT CABIN RA MASIH BELUM SEBAGUS CB VATOR. CABIN CB VATOR SUDAH DILAKUKAN BERBAGAI MODIF. RA HARUS TURUT MENGIKUTI MODIF CB VATOR SEPERTI : PENAMBAHAN GLASSWOOL & BUSA PADA BAGIAN DALAM CABIN PERUBAHAN DESIGN UNTUK AC. DIATUR AGAR RA BISA LIHAT CABIN VATOR YANG SUDAH DIMODIF PERMINTAAN PRODUCT AKAN CABIN CUKUP TINGGI. PERMINTAAN PRODUCT AKAN CABIN SELALU MENDADAK. PENGERJAAN CABIN PERLU 14 HARI. VATOR MINTA FORECAST CABIN. AKAN STOCK TANPA PERLU PTUT BUKA PO
WET KIT : SUSAH DIHUBUNGI. LEADTIME PEMASANGAN LAMA. MINTA VENDOR LAIN SELAIN GALANG. TANYAKAN KEPADA USER SCANIA : APAKAH PERLU LAGI DIHADIRKAN MR. TOM PITTAM DI PT UT
VENDOR MUDGUARD SAAT INI HANYA SATU VENDOR. MUTU MUDGUARD KURANG BAIK, BAUT SERING LEPAS. AGAR MINTA VENDOR UNTUK MENGGUNAKAN LOCK NUT. AJI MINTA INFO KE REKAN DI INDOTRUCK, MENGENAI MUD GUARD PR DARI USER AUTO EMAIL KE PIN. PERUBAHAN PIC DI MKT AUTO EMAIL DARI BEBERAPA USER KE PIN, BELUM DAPAT DIAKTIFKAN. COBA CEK YANG TIDAK AUTHORIZED UNTUK BUAT PR ---- DIBLOCK
VENDOR SIAP KIRIM BARANG. USER SEDANG CARI KAPAL UNTUK KIRIM KE SMD CHECK VESSEL DAN UNIT NISSAN SUDAH SAMPAI DI MANA JIKA SUDAH TIBA DI UT SMD, INFO KE VENDOR UNTUK BERANGKAT KE SMD BRACKET STANDARISASI HD785 DISUPPLY OLEH PT UT. 100 SET BRACKET SUDAH DIORDER DAN SEBAGIAN SUDAH DIGUNAKAN UNTUK INSTALASI AUTOLUB HD785
SUDAH DIBUATKAN DRAFT SOP STANDARISASI LOG SPEC OLEH ENG SERVICE. SUDAH DIUJI-COBA UNTUK FABRIKASI. TERHENTI, KARENA DEMAND LOG SPEC BELUM ADA. SESUAI KPI DAN INSTRUKSI DIREKSI, SATU ORANG SATU MATERI. DARI PROC 1 DEPT : MINIMAL 4 MATERI HARI SELASA, SIAPKAN MASING-MASING MATERI BERIKUT KERTAS KERJA, UNTUK WORKSHOP DENGAN CPMD TOTAL : 22 UNIT DI CIKARANG. SATU UNIT DARI 22, REPAIR LEBIH SULIT 2 UNIT DARI 22, PERLU DIBICARAKAN DENGAN USER. MASIH ADA DUA UNIT YANG HARUS MENDAPATKAN GUIDANCE DARI TEAM SCANIA. PROBLEM UTE : BARANG DAN JASA MINTA DIPISAH, KARENA INSTALASI BARU DILAKUKAN JIKA UNIT READY. TENGGANG WAKTU LAMA PROBLEM UTE : BILA DIPISAH, WARDEL BENGKAK. JASA TIDAK MASUK COST UNIT
FOLLOWED up
STEP
* BICARAKAN DENGAN PRODUCT DALAM RAPAT MINGGUAN * PIPING DI CB SUPAYA DIPAKAI * VENDOR BUAT CERT OF WARR * DISCUSS DENGAN USER RE WARR * WARR : MANA YANG DULUAN WAKTU ATAU KM ? AJI
PIC
DUE DATE
RABUAN DGN USER
* MINTA USER BUKA PR * KIRIM PO KE RA UTK REPAIR KIRIM PO KE TIMAAG UTK PAINTING * COPY INVOICE KE WAHYU FIN POTONG AR
AJI
21-May-12
CV CB MODIF STEEL CAN SESUAI DRAWING YANG SUDAH DISTANDARISASI. MINTA DRAWING KE CV CB. BILA BUKA PO, CATAT EFISIENSI
AJI
SOON
* AKAN DIBEBANKAN KE WARDEL * PR VIA SERVICE DIVISION, CEK HARGA * SPEC YANG SEDERHANA SAJA * MINTA APPROVAL SUGI UNTUK WARDEL
AJI
SOON
* KERJASAMA DGN SVC DIV, BUAT STANDARISASI AC * BUAT SOP INSTALASI AC WITH NOVEM * AREA KONDISI EKSTRIM, DIPASANG NETT DI MUKA KONDENSOR * INSTALLATION DRAWING * APPROVAL SERVICE DIVISION * PARTS BOOK * UPDATE SPECIAL CASES AC KE PT DENSO SETELAH HARGA KELUAR
KIRIM VENDOR KE PKB BIAYA BEBAN UT. YANG WARRANTY PARTS BEBAN NUT
OKTORA
ASAP
BUTIR 6 : S/D AKHIR TAHUN 2012 BUTIR 7 : S/D AKHIR MEI 2012 REPORT RESULT : AKHIR MEI 2012
FITRI AJI
OKTORA
SOON
* BICARAKAN DALAM WEEKLY MTG * MINTA FORECAST 3 BULAN KE MUKA * AJUKAN KE VATOR / RA * INFO USER : HINDARI ORDER DADAKAN * INFO KE USER BAHWA DAHULU DITAWARKAN VENDOR LAIN, USER TIDAK SETUJU, KARENA SPEC YANG MASUK DGN SCANIA ADALAH WET KIT GALANG.
AJI
AJI
SOON
* INFO VENDOR LOCK NUT PADA PO * CARI ALTERNATIF VENDOR MUDGRD * VIA WEB, TIDAK ADA. CARI SOURCING LAIN
OKTORA HERTIN
CONTINUOUSLY
* LIST PIC YANG BERHAK BUAT PR * LIST PIC YANG TDK HAK BUAT PR * REQUEST KE CIS, APPROVAL ACCTG * BLOCK YANG TDK HAK BUAT PR ( REPORT KE ACCTG ) * DISCUSS DGN USER OTORISASI PR * KAPAL BERANGKAT : 18 MEI 2012 * UPDATE KE SMD & VENDOR * MONITOR KETIBAAN * VENDOR BERANGKATKAN MANPOWER * CEK KE SVD DIV, BERAPA SISA BRACKET * ORDER BRACKET KE VENDOR * COBA VENDOR LAIN
AJI
ASAP
RULLI
DONE
* SPIRITNYA SOP DIBUAT FINAL * UJI COBA DILANJUT BILA ADA DEMAND
AJI
* SIAPKAN MATERI * SELASA, 22 MEI PRESENTASI DGN CPMD * FITRI & AFRIZAL, JIKA PUNYA IDE INOVASI, BISA DISHARE. * KOORDINASI DENGAN USER UNTUK AC YANG BELUM SELESAI DIREPAIR * BAYAR AC YANG SUDAH DIREPAIR (19)
ALL
22-May-12
FITRI
* UTE TAGIH SESUAI PO * COMM DUMMY * ARRANGE MTG LAGI DGN UTE
HERTIN
* SIAPKAN UNIT, MATERIAL, BRACKET * AMK SIAPKAN BOM * MANDIRI JAYA PERCEPAT DELIVERY BRACKET
RULLI, FITRI
28-May-12
OUTSTANDING JOBS
NO.
2 3 7 8 10 13 15
23
ITEM
WARRANTY DRAWING STANDARISASI NUT PKB CABIN RA MUD GUARD VESSEL SAMARINDA
STANDARISASI
be FOLLOWED up
STEP
* VENDOR BUAT CERT OF WARR MINTA VENDOR UNTUK * KERJASAMA DGN SVC DIV, BUAT KIRIM VENDOR KE PKB * PIHAK RA LAKUKAN SURVEY CABIN * INFO VENDOR LOCK NUT PADA PO * KAPAL BERANGKAT : 18 MEI 2012
* DISKUSIKAN DENGAN VENDOR VATOR
PIC
AJI, RULLI, OKTORA AJI, RULLI, OKTORA AJI, OKTORA OKTORA OKTORA OKTORA AJI & OKTORA
OKTORA
DUE DATE
RABUAN DGN USER CONTINUOUSLY UP TO FINAL ASAP SOON CONTINUOUSLY ASAP
ASAP