Progress / Schedule Status

LM

Planned % (Execution) Actual % (Execution) Variance

CU 23.83% 11.45% -12.38%

Act.% Plan.%

11.45% 23.83% 0% 25% 50% 75% 100%

Time Elapsed 220 Time Remaining 235 Schedule Performance Index (SPI)

48.05%

Competion Date (Clause 14pgm) Expected Finish (Updated pgm) 23-Mar-13 4-Jul-13 Major reasons for Delay : Finalization of PS items & Delay in Engineering works * Above % Based on Updated Baseline Rev 04

Varience (Days) -104

Resources Status

Total Average Manpower (Nos.) Total Actual Average Manpower (Nos.)

420 Nos 511 Nos