Anda di halaman 1dari 10

Wai Kee (Zens) Construction & Transportation Co., Ltd.

METHOD STATEMENT Concreting Method for Concourse Roof


Ref No: CSF/MS/0181D Page No: 1 Issue: 0 Date: 5 Mar 12

K0736-11C - New Entrance and Concourse at University Station

Content
Objective References Procedure and Method 1.1 Preparation Works before Pouring Concrete 1.2 Concreting of Concourse Roof (Method 1) 1.3 Concreting of Concourse Roof (Method 2) 1.4 Plant/ labour Safety and Environmental 1.5 1.6 1.7 Noise Air Quality Safety Training

Hazard/Risk Assessments Appendix Appendix Appendix Appendix Appendix Appendix A Hazard / Risk Assessment B Relevant Drawing C Concreting Sequence and Construction Joint D Concreting Method for Concourse Roof E Catalogue and information of 20-ton crane.

Issued by: Joseph Chong Site Engineer Checked by: Antony Lo

Checked by: Daniel Ng Safety Officer Approved by: Raymond Au

Wai Kee (Zens) Construction & Transportation Co., Ltd.


METHOD STATEMENT Concreting Method for Concourse Roof
Deputy Site Agent
Ref No: CSF/MS/0181D Page No: 2 Issue: 0 Date: 5 Mar 12

K0736-11C - New Entrance and Concourse at University Station Site Agent

1.0

Objective
This method statement provides the detailed concreting sequence and construction joint location for concourse roof for the Project K0736-11C New Entrance and Concourse at University Station.

2.0

References
Drawing no.: K0736/T/UNI/MTR/A10/S-01D to S-08D

3.0

Procedure and Method

3.1 Preparation Works before Pouring Concrete 1. 2. 3. Erect scaffold and working platform on the concourse and the platform No.1 (Detailed design was submitted separately); Erect soffit formworks and falsework for roof beam construction (Detailed design was submitted separately); Rebar fixing for roof beams.

3.2 Concreting of Concourse Roof (Method 1)


1. 2. Cast the concourse roof according to concreting sequence and construction joint location as shown in Appendix D; Cast the concourse roof behind the platform no.1 using concrete pump truck and the truck boom (arm) should not exceed the designated line. Appendix C); 3. 4. 5. 6. Cast the three nos. of cantilever beams on the Platform No.1 using hand tool (Please refer to Appendix C); Tarpaulin should be used to fence off the working platform during the concreting of the cantilever beams; Apply retarder on the construction joint if necessary; Clean the construction joint. (Please refer to

3.3 Concreting of Concourse Roof (Method 2)


1. Cast the concourse roof according to agreed concreting sequence and construction joint.

Wai Kee (Zens) Construction & Transportation Co., Ltd.


METHOD STATEMENT Concreting Method for Concourse Roof
2.

Ref No: CSF/MS/0181D Page No: 3

Issue: 0 Date: 5 Mar 12

K0736-11C - New Entrance and Concourse at University Station


Cast the concourse roof beam and kerb by using mobile crane (20-ton) with concrete bucket. 3. Operation for lifting concrete bucket would be limited and agreed on site. 4. 5. 6. For the location of kerb outside the limited operation, handtool would be used for transportation of the concrete. Person with sufficient experience and providing signal to operator would be appointed. The 20-ton KATO NK-200H mobile crane shall be set up as per the following criteria derived from the load chart. i. ii. iii. iv. v. vi. vii. Boom length = 23m Minimum boom elevation angle = 450 Maximum working radius = 11m Minimum jib height = 22m Outrigger extension = 3.05m from centre of gravity. Maximum safe working load = 5.15 ton Each concrete load (one bucket) = 2.4 ton < safe working load, safe

3.4 Plant /Labour Plant i ii Concrete Pump Truck Concrete Mixed Truck Concrete compactor Hand tools

iii
iv Labour Resources i ii iii iv

Skilled Labour Rigger Carpenter Steel fixer

v Concreter
vi Plant Operator vii Truck Driver

4.0
4.1

Safety and Environmental


Noise 4.1.1 General work will be carried out during normal working hours (i.e. 08:00 to

Wai Kee (Zens) Construction & Transportation Co., Ltd.


METHOD STATEMENT Concreting Method for Concourse Roof
18:00).

Ref No: CSF/MS/0181D Page No: 4

Issue: 0 Date: 5 Mar 12

K0736-11C - New Entrance and Concourse at University Station

4.1.2

The site supervisor / foreman will inspect all plants, which is likely to cause excessive noise levels to determine if it may be operated in a manner to minimize noise during the works.

4.2 Air Quality 4.2.1 Effective water spray will be used as necessary during construction to ensure air quality. 4.3 Safety Training 4.3.1 Safety Induction Training Course Workers shall attend the Induction Training Course conducted by the Safety Officer before the commencement of works. The Safety Officer and Site Engineer shall explain the safety requirements and nature of the work to all workers. 4.3.2 General Site Safety All workers must go through a briefing conducted by the Safety Officer before commencement of any work. 4.3.3 Special Skill Training Crane drivers, plant operators and such must be trained and certified. All workers shall be fully trained to use all Personal Protective Equipment, such as safety helmet, eye goggles, ear plugs, safety shoes/boots, safety harness and lifelines, and reflective vest/belts. All workers on site shall obtain Green Card. 4.3.4 MTRC Training if necessary Competent Person CP(T) Training Competent Person CP(NT) Training Railway Safety Induction (RSI) Training

5.0

Hazard/Risk Assessments
Hazard / Risk Assessments refers to Appendix A

6.0

Appendix
Appendix A Hazard / Risk Assessment

Wai Kee (Zens) Construction & Transportation Co., Ltd.


METHOD STATEMENT Concreting Method for Concourse Roof
Appendix B Relevant Drawing Appendix C Concreting Sequence and Construction Joint Location Appendix D Concreting Method of Concourse Roof Appendix E Catalogue and information of 20-ton crane

Ref No: CSF/MS/0181D Page No: 5

Issue: 0 Date: 5 Mar 12

K0736-11C - New Entrance and Concourse at University Station

Appendix A

Wai Kee (Zens) Construction & Transportation Co., Ltd.


METHOD STATEMENT Concreting Method for Concourse Roof
Ref No: CSF/MS/0181D Page No: 6 Issue: 0 Date: 5 Mar 12

K0736-11C - New Entrance and Concourse at University Station

Appendix B

Wai Kee (Zens) Construction & Transportation Co., Ltd.


METHOD STATEMENT Concreting Method for Concourse Roof
Ref No: CSF/MS/0181D Page No: 7 Issue: 0 Date: 5 Mar 12

K0736-11C - New Entrance and Concourse at University Station

Appendix C

Wai Kee (Zens) Construction & Transportation Co., Ltd.


METHOD STATEMENT Concreting Method for Concourse Roof
Ref No: CSF/MS/0181D Page No: 8 Issue: 0 Date: 5 Mar 12

K0736-11C - New Entrance and Concourse at University Station

Appendix D

Wai Kee (Zens) Construction & Transportation Co., Ltd.


METHOD STATEMENT Concreting Method for Concourse Roof
Ref No: CSF/MS/0181D Page No: 9 Issue: 0 Date: 5 Mar 12

K0736-11C - New Entrance and Concourse at University Station

Appendix E

Anda mungkin juga menyukai