Anda di halaman 1dari 43

H

in Power Systems

White Paper On Limits, Measurements & Enforcement

TRACTION INSTALLATION DIRECTORATE Research, Designs & Standards Organisation Ministry of Railways PO: Manaknagar, Lucknow-226 011 August 2012

Table of Contents
1. Introduction!
1.1. Power Quality: Background! 1.2. Denition of power quality! 1.3. Various aspects of power quality! 1.4. Effect of harmonics! 1 1 2 2 3 5 5 5 10 14 14 16 17 18 19 19 22 27 31 i

2.

Governing Standards: Explanation & Interpretation!


2.1. Fundamental Issues! 2.2. Regulations! 2.3. Discussion!

3.

IEEE-519: 1992: The Document & Commentary!


3.1. Background! 3.2. Issues with IEEE 519-1992: Experts Perspective! 3.3. Key Aspects of IEEE 519-1992! 3.4. Nuances!

4.

The Ecosystem of Standards!


4.1. The US Standards/Guidelines! 4.2. The British Standard: Engineering Recommendation G5/4-1! 4.3. IEC 61000 Family of Standards!

5. 6.

Conclusion! Annexure A!

Harmonics in Power Systems

1.

Introduction

1.1. Power Quality: Background


Electrical power is now the principal form of energy consumed globally. From the smallest of domestic chores to giant machines, electricity is to be found as the energy form of choice. Practically all energy which is used is centrally generated at few power stations and the same gets poured in to the grid and thereafter gets distributed to the customers. Like a highway, which is required to carry higher amounts of trafc, rules of engagement of the users, transmission agencies and the generating units have to be established, else the system would stop working or just collapse. Electricity Grid, is described as the biggest and most complex machine ever made. The commodity handled on the Grid is highly perishable and there must always be a perfect balance between the energy generated at the generating stations and the energy consumed by the consumers. A mismatch will make the Grid unstable and trip it-serious, physical damage will occur if the Grid is not adequately protected. As the Grid gets several generators pooling energy in and several consumers drawing out, the discipline needs to be followed by all the participants. Thus, on one hand, the customer expects stable power supply in terms of availability, waveform delity and frequency; the customers are supposed to draw power in the prescribed regimen, which should not affect other stakeholders. Various standards prescribe the standards to which a customer should get power and also, they stipulate the power drawal regimen. To illustrate, in case the customer draws power at poor power factor, though, the physical utilisation of power is low, the generating units and the transmission lines nevertheless gets stressed to full measure. Thus, there is mechanism designed to make customers draw power at good power factor, so that the rest of the system gets stressed only to the extent of utilisation. As the loads become more non-linear, issue of harmonics and discipline thereof has assumed increasing importance. The general appreciation of power utilisation hitherto has been based on linear loads and voltage/currents measured at 50 Hz.

Harmonics in Power Systems

1.2. Denition of power quality


The term has been best described in the open encyclopedia-the Wikipedia1 as: Power quality is the set of limits of electrical properties that allows electrical systems to function in their intended manner without signicant loss of performance or life. The term is used to describe electric power that drives an electrical load and the load's ability to function properly with that electric power. IEEE 1159-2009 talks of power quality as wide variety of electromagnetic phenomena that characterizes the voltage and current at a given time and at a given location on the power system. C. Sankaran in his book, Power Quality (CRC Press) denes the term as: Power quality is a set of electrical boundaries that allows a piece of equipment to function in its intended manner without signicant loss of performance or life expectancy.

1.3. Various aspects of power quality 2


ASPECT DEFINITION

Magnitude (regulation)

Long term level of voltage established through transformer taps and dynamically controlled by regulators. Measurement of voltage magnitude over the long term serves the basis for the capture and characterization of other power quality disturbances.

Unbalance

Condition of the 3 phase power system where the rms magnitude or phase angle of the line voltages are not equal. This is usually determined as a percent of the ratio of negative sequence component to positive sequence component.

Harmonics

Components of electricity with frequencies which are an integral multiple of the fundamental frequency. This is usually expressed in Total Harmonic Distortion or as individual harmonic order (frequency) components.

Flicker

Periodic uctuation of voltage that results in icker of lighting, particularly incandescent lighting. This is typically causes by uctuating loads such as hoists, reciprocating pumps, arc furnaces, etc.

Generation occurs at 50 Hz, which is the frequency of the grid. The generators make available a 3- voltage on the grid. As loads get connected, currents ow and power
1 2

http://en.wikipedia.org/wiki/Power_quality http://www.hydroone.com/IndustrialLDCs/Pages/PQDenitions.aspx
Harmonics in Power Systems

gets transacted. The generators need to be loaded evenly on their phases and are designed for taking certain specied amount of unbalance. However, the loads on the grid are suitably distributed over phases, the generators see largely balanced loads. However, some old stations can have difculty in meeting unbalanced loads. This aspect has been touched upon later while discussing the British Standard ER G5/4-1. It may be noted that the discussion on harmonics in Indian context is limited to the integral multiple of the fundamental frequencies, whereas perusal of IEEE 519-1992, IEC 61000 family of Standards and British ER G5/4-1 and several commentaries and many more papers reveal need to include inter-harmonics (non-integral multiples of the fundamental) and subharmonics (fractions of the fundamental frequency). This is an area which needs to be covered in Indian Regulatory framework.

1.4. Effect of harmonics3


AT EFFECT

Circuit Breakers Capacitor Banks

Malfunction Overheating Insulation Breakdown Failure of internal fuses

Protection Equipment Measuring devices Transformer reactors Motors

False tripping Wrong measurements Overheating Increased noise levels Overheating

Telephones Transmission lines Electronic devices

Noise Overheating Wrong pulses on data transmission Over/under voltage Flickering screens

Power Quality in Electrical Systems, Alexander Kusko, Marc T. Thompson, McGraw Hill
Harmonics in Power Systems

AT

EFFECT

Incandescent lamps

Reduced life Flicker

Harmonics in Power Systems

2.

Governing Standards: Explanation & Interpretation

2.1. Fundamental Issues


It is the responsibility of the utility to provide voltage with nil THD (Total Harmonic Distortion)

VTHD =
Since,

/
/

n n=2 2 1

V2 n

# 100%

!!

...[1]

VRMS =

n n=1

V2 ! n

...[2]

The equation # (1) can also be written as:

VTHD =
Where, VTHD Vn VRMS

V2 - V2 RMS 1 # 100% 2 V1 !

...[3]

: : :

Voltages Total Harmonic Distortion nth Harmonic Root Mean Square of Voltage

VTHD is hence measure of the amount by which the Voltage is distorted. Depending upon the conguration of power supply and type of load, the harmonic content will change. To illustrate, 3rd harmonic or 150 Hz component indicates presence of single phase rectier load, whereas, odd harmonics without triplens, indicate a full bridge rectier on 3-phase supply.

2.2. Regulations
Harmonics as as aspect of power quality is fairly new and there still exists considerable confusion on application of the harmonic measures. This section will explore various Indian regulations in vogue.

2.2.1.

Central Electricity Authority (Grid Standards) Regulations, 2010


These Regulations stipulate that the transmission licensee shall ensure voltage to conform to the following:

Harmonics in Power Systems

SR. NO.

S Y S T E M V O LTA G E ( K V RMS)

THD (%)

INDIVIDUAL HARMONIC O F A PA RT I C U L A R FREQUENCY

1 2 3 4

765 400 220 33 to 132

1.5 2.0 2.5 5.0

1.0 1.5 2.0 3.0

The CEA (Grid Standards) Regulations, 2010 dene VTHD as:


VTHD =

40 n=2 2 1

V2 n

# 100%

...[4]

Further, this Clause stipulates: Provided that the standard on Harmonic Distortion shall come into force concurrently with clause 3 of Part IV of the Schedule to the Central Electricity Authority (Technical Standards for Connectivity to the Grid) Regulations, 2007.

2.2.2.

Central Electricity Authority (Technical Standards for Connectivity to the Grid) Regulations, 2007
There are two very signicant directions in these Regulations, they being:

2.2.2.i. 2.2.2.i.a.

Reactive Power 4: The distribution licensees shall provide adequate reactive compensation to compensate the inductive reactive power requirement in their system so that they do not depend upon the Grid for reactive power support.

2.2.2.i.b.

The power factor of the distribution system and the bulk consumer shall not be less than 0.95.

See also Cl.4.6.1 and 6.6 of Central Electricity Regulatory Commission (Indian Electricity Grid Code)

Regulations, 2010. It is clear from CEA and CERCs referred Regulations that reactive power ow (either leading or lagging) should not transact on connected network not owned by IR. This should be seen as long term view to be taken by railways in planning for pf improvement.
! Harmonics in Power Systems

2.2.2.ii.

Voltage and Current Harmonics (Cl. 3 of Part IV of the Schedule, which is referred above at 2.2.1):

2.2.2.ii.a. The total harmonic distortion for voltage at the connection point shall not exceed 5% with no individual harmonic higher than 3%. 2.2.2.ii.b. The total harmonic distortion for the current drawn from the transmission system at the connection point shall not exceed 8%5. 2.2.2.ii.c. The limits prescribed shall be implemented in a phased manner so as to achieve complete compliance not later that ve years from the date of publication of these regulations in the Ofcial Gazette. It is seen that the above stipulations dont refer to any International/National Standard or Practice. This Regulation, in Part II of Schedule, for Grid Connectivity Standards applicable to the Generating Units talks about applicability of IEEE-519 for new generating units.

2.2.3.
2.2.3.i.

Chhattisgarh State Electricity Supply Code-2011


In the Chapter 2, harmonics are to be governed by IEEE STD 519-1992, namely IEEE Recommended Practices and Requirements for Harmonic Control in Electrical Power Systems.

2.2.3.ii.

Clause 3.7 of the Code is most explicitly lays down the responsibility of the user:

2.2.3.ii.a. The maximum permissible limit of harmonics as specied in Institute of Electrical and Electronics Engineers (IEEE) standard 519 (1992) adopted in clause (5) of part-II of Central Electricity Authority (Technical Standard of Connectivity to the Grid) Regulations 20076 (hereafter CEA (Technical Standard Regulations) is as follows: Voltage distortion limit Utilities responsibility

This appears to be anomalous, as for current, THD limit cant be stipulated. This is

because in lightly loaded conditions, the THD is likely to be very poor.


6

This Clause appears under Grid Connectivity Standards applicable to the Generating Units and appears

in the section for New Generating Units, whereas, the States Electricity Supply Code-2011, brings this as the governing standard for customer-utility interface.
! Harmonics in Power Systems

B U S V O LTA G E

MAXIMUM INDIVIDUAL V O LTA G E D I S T O RT I O N

T O TA L M A X I M U M V O LTA G E D I S T O RT I O N

33 kV & 132 kV 220 kV 400 kV

3.0 2.0 1.5

5.0 2.5 2.0

Current distortion Users responsibility The total harmonics distortion for current drawn from the transmission system at the connection point shall not exceed 8%.

2.2.4.

IEEE Std. 519-1992: IEEE Recommended Practices and Requirements for Harmonic Control in Electrical Power Systems

2.2.4.i.

It was was rst introduced in 1981 and comprehensively revised in 1992. It is interesting to note that though the document has been published as a Standard by IEEE Standards Board and approved by American National Standards Institute (the document is recognised as American National Standard), in its title it is referred to be Recommended Practices and in its abstract this is referred to as a Guide.

2.2.4.ii.

In the foreword to the Standard, it is mentioned: This recommended practice recognises the responsibility that the users have not to degrade the voltage of the utility serving other users by requiring non-linear currents from the utility. It also recognises the responsibility of the utilities to provide users with close to a sine wave of voltage .

2.2.4.iii.

The standard lays down the following limits for the voltage harmonics: Voltage Distortion Limits of IEEE 519-1992 given in Table 11.1

Bus Voltage at PCC 69 kV and below 69.001 kV through 161 kV 161.001 kV and above

Individual Voltage Distortion (%) Total Voltage Distortion THD (%) 3.0 1.5 1.0 5.0 2.5 1.5

NOTE: High-voltage systems can have up to 2.0% THD where the cause is an HVDC terminal that will attenuate by the time it is tapped for a user.
! Harmonics in Power Systems

2.2.4.iv.

The standard lays down the following limits (combining Table 10.3, 10.4 and 10.5 of IEEE 519-1992) for the current harmonics:
Maximum Harmonic Current Distor2on limits (Ih) in Percent of IL Individual Harmonic Order (Odd Harmonics) Table 10.3 of IEEE 519-1992 Current Distor;on Limits for General Distribu;on Systems 120 V < Vn 69 kV <11 11h<17 17h<23 23h<35 35h 4.0 7.0 10.0 12.0 15.0

ISC/IL <20* 20<50 50<100 100<1000 >1000

TDD 5.0 8.0 12.0 15.0 20.0

2.0 1.5 0.6 0.3 3.5 2.5 1.0 0.5 4.5 4.0 1.5 0.7 5.5 5.0 2.0 1.0 7.0 6.0 2.5 1.4 Table 10.4 of IEEE 519-1992 Current Distor;on Limits for General Sub transmission Systems 69 kV < Vn 161 kV <20* 2.0 1.0 0.75 0.3 0.15 20<50 3.5 1.75 1.25 0.5 0.25 50<100 5.0 2.25 2.0 0.75 0.35 100<1000 6.0 2.75 2.5 1.0 0.5 >1000 7.5 3.5 3.0 1.25 0.7 Table 10.5 of IEEE 519-1992 Current Distor;on Limits for General Transmission Systems (>161 kV) Dispersed Genera;on and Cogenera;on Vn > 161 kV <50 2.0 1.0 0.75 0.3 0.15 50 3.0 1.5 1.15 0.45 0.22 Even harmonics are limited to 25% of the odd harmonic limits above. Current distortions that result in a dc offset, e.g. half-wave converters, are not allowed.

2.5 4.0 6.0 7.5 10.0

2.5 3.75

* All power generation equipment is limited to these values of current distortion, regardless of actual Isc/IL. Where Isc = maximum short-circuit current at PCC. IL = maximum demand load current (fundamental frequency component) at PCC.

2.2.4.v.

It can be seen the above values for voltages apply for the utilities, dealt in Section 11 of the Recommended Practices and for current in Section 10 apply on the customers. Though, the limits on voltage appear to be straight forward, those for current need to be interpreted.

2.2.4.vi.

A deeper study of the literature and the document itself, indicates imperative need of taking a nuanced view of the situation. It is also required to appreciate the fact as to how this document evolved to become a Recommended Practice. This White Paper dwells on the issues in implementing the limits stipulated in

Harmonics in Power Systems

the document and takes a closer look of the documents intent and evolution in Chapter 3.

2.3. Discussion
2.3.1. As seen from the foregoing, the CEAs Regulations in vogue in the country, make a mention of harmonics expected at the point of common coupling (PCC) but are silent on the standards these limits are based on and the method of arriving at these limits. 2.3.2. Explicit reference to IEEE 519-1992 has been given in Chattisgarh State Electricity Supply Code-2011 vis-a-vis customer interface. 2.3.3. The reference to IEEE 519-1992 has not been made with respect to user-utility interaction in CEAs Regulations. They nd mention in Central Electricity Authority (Technical Standards for Connectivity to the Grid) Regulations, 2007s Part II of Schedule, for Grid Connectivity Standards applicable to the Generating Units. This as can be noted that this link of CEAs Regulations with IEEE 519-1992 is with connecting new generating units to the grid and not about consumer-utility interface. 2.3.4. The CEAs Regulations and individual States stipulations are silent on the modus operandi of measurements. It should be noted that for penal provisions, extent of trespass7 should be established. This presumes: 2.3.4.1. 2.3.4.2. Having the red line drawn clearly, to indicate the limit: and having a veriable mechanism to reliably establish the extent of trespass. 2.3.5. However, as perusal of various documents indicate, real time, veriable means of establishing trespass is not possible through IEEE 519-1992 as established in the next chapter. 2.3.6. For penalty to be tenable, existing CEA framework gravitating to IEEE 519-1992 is inadequate. With IRs substantial stake in electric traction (more than 60% turnover is from electried networks), it is in IRs interests to zealously guard health of the power sector and work towards a superior power quality regime.

borrowing the phrase from Paulo F. Ribeiros term from his paper Common Misapplications of the IEEE
Harmonics in Power Systems

519 Harmonic Standard: Voltage or Current Limits. The paper is available on IEEE Xplore digital library.
!

10

2.3.7.

It is seen that treatment of harmonics in the CEAs guidelines leans heavily upon IEEE 519-1992 and it would be safe to surmise that this document would form the basis of measurements and interpretation of the results. It is hence, in order, to deliberate in detail the IEEE-519 standard and its various commentaries. As the matter is being dealt for the rst time on institutional level in the country for the enforcement of limits on harmonics, it is prudent to bring forth various aspects of this document and their implications. It would be seen that straight forward THD measurement is not possible and there is need to cover lot of ground before implementation of this regime.

2.3.8.

To appreciate the imperative and urgent need to deliberate on the history, limits and philosophy of the Recommended Practices, we need to pause and take a quick overview of two known instances where the application of harmonic limits is being sought:

2.3.8.i.

In case of TANGEDCO, the CEA guidelines have been implemented with 15% at penalty on the violation of the laid norms vide Tariff Order no. 1 of 2012. As the Tariff Order is derived from the CEA guidelines, they also inherit the lack of clarity on modus operandi of implementation. From the Tariff Order it is seen that there is element of ungraduated penalty, which fails to take cognisance of extent of violation or extent of trespass.

2.3.8.ii.

Punjab, instead of levying penalty has proposed higher tariff slab and the case is being contested.

2.3.9.

It is worrying that application of IEEE 519s recommendations has not been done in the spirit of the document. It should be noted that these Recommended Practices are guidelines for system design and the application of individual limits can be erroneous as IEEE 519: 1992 itself mentions at Cl. 10.4.2 (and elaborated in Ribeiros paper referred later in this White Paper)... Although the effects of harmonics on electric equipment, appliances, etc. are not fully understood at this time, it is recognized that the stated current distortion limits can be exceeded for periods of time without causing damage to equipment. When evaluating the user compliance with the stated limits, it is recommended that probability distribution plots be developed from he recorded data and analyzed. If the limits are only exceeded for a short period of time, the condition could be considered acceptable.

2.3.10.

Apart from the above there is need of more clarity in the measurements as given below:

Harmonics in Power Systems

11

SR. NO.

ASPECT

I M PA C T

Calculation of TDD (Total Demand Distortion)

This should be done on the maximum load current as per IEEE 519-1992. Method of arriving at this value needs to be established. IEEE 519-1992 recommends that the load current be calculated as the average current of the maximum demand for the preceding 12 months. However, it is not clear how this can be applied to users with low load factors as traction loads. Practice of plain measurements of THD for current is WRONG application of IEEE 519. In almost all harmonic analysers, THD is measured, this, then is converted as TDD.

System level study for harmonics This determines ability of the system to and resonance tolerate harmonics. It needs to be seen that genesis of IEEE 519 was in introduction of static converters which drew harmonic currents in a system with capacitors provided. As the Recommended Practices are system level document, one needs to establish the vulnerability of the utility to a customers non-linear load.

Measurement Period

The Recommended Practice mention 10/15 minute period to arrive at levels of harmonic currents. Also, IEEE-519 recognises that stated distortion limits can be exceeded.

Extent of distortions

Any penalty needs to be graduated to the extent of violation.

Calculation/estimation currents

of

load There is recommended method to arrive at the loads to be considered while working out TDD. However, clear method needs to be established given highly dynamic nature of the traction load.

Harmonics in Power Systems

12

2.3.11.

Indian Railways under Ministry of Railways has been model customer since decades and view their responsibility to be so with due seriousness. Introduction of new generation of locomotives and electrical multiple units mitigate harmonics at the source itself. Being part of the Government, the Railways are keen to establish methods to implement equitable, practical and sustainable Power Quality regimen.

2.3.12.

This document is a step to work out the interpretation of IEEE-519 in the country consistent with the document itself.

Harmonics in Power Systems

13

3.

IEEE-519: 1992: The Document & Commentary

3.1. Background
As has been seen in the foregoing, the CEA Regulations lean on the IEEE 519-1992. It is hence prudent to take a deeper look of the same. Though, there are other such standards world wide, the IEEE 519-1992 is discussed rst. It is important to understand the background of the IEEE-519 and its evolution to appreciate various values given. To get most authoritative view, paper by the Co-Chairman (Ray P. Stratford) and the Secretary (Christopher K. Duffey) of the joint task force which prepared the current version was referred to and salient points are discussed as under: 3.1.1.
8The

electrical energy in the USA in 1970s was principally charged for based on

demand and kWHrs. This prompted users to install capacitors extensively in their networks. The oil embargo of 1973 pushed the energy prices steeply. This encouraged use of capacitor even more. About this time the solid state drives matured. These drives needed harmonic currents. Increasing demand of harmonic currents and proliferation of capacitors together was perceived as serious development as this threatened the health of the electrical ecosystem. 3.1.2. Accordingly the Static Power Converter Committee of the Industry Applications Society started work on a document which emerged as IEEE 519-1981, IEEE Guide for Harmonic Control and Reactive Compensation of Static Power Converters. This document, though was meant to aid in the application of solid state converters, the utilities found it useful and accordingly a subgroup for study of harmonics was set up by the IEEE, Power Engineering Society under T&D Committee. When IEEE-519-1981 came up for review, a joint effort between original authoring committee, viz. Static Power Converter Committee and the Power Engineering Society was initiated. 3.1.3. Signaling wider acceptance of 1981 document, the new document received new name. To appreciate the changed thrust as reected in the participation of the document reviewing committee, the following table can be perused:
8

Christopher K. Duffey & Ray P. Stratford: Update of Harmonic Standard IEEE-519: IEEE Recommended

Practices and Requirements for Harmonic Control in Electric Power Systems published in IEEE Transactions on Industry Applications, Vol 25, No.6 Nov/Dec 1989
! Harmonics in Power Systems

14

OLD NAME OF IEEE 591-1981

NEW NAME OF IEEE 519-1992

IEEE Guide for Harmonic Control and Recommended Practices and Reactive Compensation of Static Power Converters Requirements for Harmonic Control In Electric Power Systems

The 1981 version gave limits for the voltage distortion only. Utilities faced unresolved issue of single customer taking up full harmonic current absorption capacity. This did not permit distribution among users to draw harmonic currents. This led to creation of the criteria which limits the harmonic currents drawn. It is this philosophy which is sought to be implemented. 3.1.4. It is seen that the authors saw this document to address a system problem. The standard saw imperative need of grading the requirement placed on the user by: 3.1.4.i. Clarifying the need to specify the strength of the network the user is connected to and 3.1.4.ii. 3.1.5. Level of load user draws. This was achieved by dening key metric viz:

SCR =
SCR!

I Short_Circuit I Load !
!

...[5]

: Short Circuit Ratio : Maximum short circuit current at PCC : Maximum load current (fundamental) at PCC

IShort_Circuit! ILoad !
!

The numerator denotes the available short-circuit level at the PCC (Point of Common Coupling). Higher level indicates stronger network as it can support a higher level of current. The ratio thus provides a way to size a customer. Larger customer is one who has a lower ratio, and as can be seen from the Table #10.1 of IEEE 519-1992 reproduced below, smaller customers can draw larger harmonic currents.

Harmonics in Power Systems

15

Table 10.1 of IEEE 519-1992 Basis for Harmonic Current Limits


SCR at PCC 10 20 50 100 1000 Maximum Individual Frequency Voltage Harmonic (%) 2.5 3.0% 2.0 2.5% 1.0 1.5% 0.5 1.0% 0.05 0.10% Related Assumption Dedicated system 1 2 large customers A few relatively large customers 5 20 medium size customers Many small customers

Above table gives user classication.

3.2. Issues with IEEE 519-1992: Experts Perspective


Further, paper of Paulo F.Ribeiro9 who has been a key resource on application of IEEE 519 and on a top level chair of IEEE Power Quality Subcommittee, as can be seen on the website of IEEE SA (Standards Association), has been referred10 . As can be seen, this paper is very recent and has come by after CEA guidelines have come. The salient issues touched by Ribeiro being: 3.2.1. 3.2.2. The IEEE 519 is not in reality a standard, its a recommended practice. The objective of the recommendation is many times misunderstood and consequently erroneously interpreted and applied. 3.2.3. 3.2.4. Issue of current vis-a-vis voltage limitation needs deliberation. Though harmonic voltage is the ultimate measure of system integrity, harmonic currents, even with harmonic voltages are in limit can cause problems in series equipment like transformers and shunt equipment like capacitors. 3.2.5. Exceeding the harmonic current limits proposed by IEEE 519 and for one particular customer does not translate directly to a violation of the harmonic voltages. The limits prescribed, when aggregated with all other possible users at the same PCC could possibly result in a voltage distortion in excess of limits prescribed in IEEE 519. This point mentioned by Ribeiro needs to be read along with Cl 10.4.2 of IEEE 519-1992, which mentions ...it is recognized that the stated
9

grouper.ieee.org/groups/td/pq/orgchart/2009-07-15%20PQ%20Subcom%20Organization%20Chart.pdf Common Misapplications of the IEEE 519 Harmonic Standard: Voltage or Current Limits, Paulo F. Ribeiro,

10

This paper appears in: Power and Energy Society General Meeting - Conversion and Delivery of Electrical Energy in the 21st Century, 2008 IEEE, Date of Conference: 20-24 July 2008
! Harmonics in Power Systems

16

current distortion limits can be exceeded for periods of time without causing harm to the equipment. When evaluating user compliance with stated limits, it is recommended hat probability distribution plots be developed from the recorded data and analyzed. If the limits are only exceeded for a short period of time, the condition could be considered acceptable. 3.2.6. Ribeiro cautions when utilizing these current limits to avoid designing or installing unnecessary and expensive ltering equipment. 3.2.7. He notes (note that this paper is as recent as 2008), ... Perhaps in future new diagnostic indices could be developed to assist in application of harmonic distortion recommendations... 3.2.8. Though IEEE 519 establishes or rather recommends that harmonic current limitation is the responsibility of end users and that of harmonic voltage is with the utility, as a simplied procedure for distortion control, end users are recommended to use both limits with sensitivity and discrimination to avoid installing unnecessary ltering equipment or neglecting possible local resonances which could cause internal interference and damages...Furthermore, considering that the present current limits were determined based on typical system impedances of 20 years ago, and much has changed in terms of system impedance, harmonic source characteristics and background distortion content, it is expected that the recommended limits for both voltage and current be used. approach. 3.2.9. He concludes by noting...Excess of (current) limits on PCC or internal to an installation should not be immediately interpreted as the need for installation of ltering equipment. Harmonic Voltage limits, however, when exceeded at the PCC or within an installation should immediately require an overall checkup of the installation. Thus, one of the principal contributors to the IEEE-519 advocates caution against use of voltage for utility and current for user

3.3. Key Aspects of IEEE 519-1992


Cl 10.4 of IEEE 519-1992 mentions...The recommended current distortion limits are concerned with the following indice (sic): 3.3.1. TDD: Total demand distortion (RSS), harmonic current distortion in % of maximum demand load current (15 or 30 min demand)

Harmonics in Power Systems

17

3.3.2.

The limits listed in Tables 10.3, 10.4, and 10.5 11 should be used as system design values for the worst casefor normal operation (conditions lasting longer than one hour). For shorter periods, during start-ups or unusual conditions, the limits may be exceeded by 50%.

3.3.3.

...It is recommended that the load current, IL, be calculated as the average current of the maximum demand for the preceding 12 months.

3.3.4.

Formulating above, we get:

I TDD =
3.4. Nuances
3.4.1.

I 2 + I 2 + I 2 + I 2 + ... 2 3 4 5 # 100% 2 I Load


...[6]

To measure the current harmonics, practice is to carry out measurements with harmonic analysers, which carry out snapshot THD (current) measurements which is clearly not the TDD as mentioned in the IEEE 519-1992. From the point of view of Railways, where the load is highly dynamic and the sub-stations see poor load factors, following need to be decided:

3.4.1.i.

What is the demand load-should it be contract demand (CD) or maximum demand (MD) or transformer rating? Taking CD appears to be plausible way as this determines provisioning of upstream equipment and also reects IRs assessment of its load. This is the approach taken in IEC TR 61000-3-6.

3.4.1.ii. 3.4.1.iii. 3.4.1.iv.

Measurements be done on 15/30 min period instead of taking snapshot of THD Conditions lasting for more than 1 hour be considered Direction of harmonics to be established. It is seen that being connected to a grid can make other customers harmonics travel to capacitor bank owned by some one else. There are some manufacturers who claim that their equipment can measure the direction of ow of harmonics. This has been refuted in several peer reviewed papers, like An Investigation on the Validity of PowerDirection Method for Harmonic Source Determination authored by Wilsun Xu and Yilu Liu (IEEE Transactions on Power Delivery, Vol. 18 No. 1 January 2003)

3.4.2.
11

There is need to look at the practice followed globally and the developments.

Table in Para 2.2.4.iv


Harmonics in Power Systems

18

4.

The Ecosystem of Standards


The problem of power quality has been studied under generic label of Electromagnetic Compatibility. There are several international standards which govern the EMC domain. Infact, with all these standards, there exists extensive commentaries and guidelines on their application. The most extensive set of guidelines are laid by IEC. They have been developed by experts and have been voted upon by participating nations. Whereas, the IEEE 519-1992 has been developed by the volunteers and is a guideline. British Regulations G5/4-1 govern the harmonics in power systems. From the available information following information is compiled. It is seen that Harmonics is but one dimension of Power Quality. Various documents, world wide have addressed the issue in a comprehensive manner. This is imperative as these issues usually are not amenable to piecemeal resolution/mitigation. The principal standards, viz. IEEE 519-1992, IEC-61000 family and the British ER G5/4-1 are all supposed to be accompanied by application guidelines. IEEE 519-1991s application guideline is under preparation. It would be hence noted, that the reference of IEEE 519 inuenced limits per se does not serve the long term purpose. CEAs Regulations have stated a laudable objective to usher in better power quality regime. However, a reference to IEEE-519-1992 and addressing just the harmonics part of the power quality domain needs further clarity.

4.1. The US Standards/Guidelines


4.1.1. IEEE Recommended Practices and Requirements for Harmonic Control in Electrical Power Systems, IEEE 519-1992
This document is part of a fast evolving family of documents addressing various aspects of power quality. Leading researchers have expressed their concern on the inadequacies of the document which has come by more than two decades ago. This document has been discussed in the Chapter #3 of this White Paper in some detail.

Harmonics in Power Systems

19

4.1.2.
4.1.2.i.

Guide for Applying Harmonic Limits on Power Systems (P519A):


This document is being prepared by P519A Task Force of the Harmonics Working Group (IEEE PES T&D Committee) and SCC22-Power Quality.

4.1.2.ii.

This documents need was felt to develop means of implementation of IEEE 519:1992 and incorporate better understanding of the harmonics. This is not yet published and the work is still on.

4.1.2.iii. 4.1.2.iv.

This also indicates the uidity in the applicability of IEEE 519-1992. P519A/D5 is available on the internet, this is dated May 4,1996. It is understood to have been withdrawn and a new draft is likely to come up.

Harmonics Standards

IEEE

British

IEC

G5/4-1 IEC 61000-2 IEC 61000-3 IEC 61000-4

IEEE 1159-2009

IEEE 519-1992

IEEE 519.1 IEEE 1159.1 IEEE 1159.2 IEEE 1159.3

4.1.2.v.

Shown above are the principal documents on harmonics.

Harmonics in Power Systems

20

4.1.3.

IEEE Recommended Practice for Monitoring Electric Power Quality, IEEE 1159-2009

4.1.4.

The standard aims to dene the practice for monitoring power quality and gives overview of various aspects of the measurements.

4.1.5. 4.1.6.

Denes power quality phenomena. Direct users in the proper monitoring and data interpretation of electromagnetic phenomena that cause power quality problems.

4.1.7. 4.1.8. 4.1.8.i.

Offers a tutorial on power system disturbances and their common causes. To summarise: IEEE 1159: Provide general guidelines for PQ measurements & standard denitions for the different categories of PQ problems.

4.1.8.ii.

IEEE 1159.1: Develop guidelines for instrumentation requirements associated with different types of PQ phenomena. The Standard is maintained by the Task Force on Recommended Practice for Power Quality.

4.1.8.iii.

IEEE 1159.2: Develop guidelines for characterizing different PQ phenomena. The Standard is maintained by Task Force on Characterization of a Power Quality Event Given An Adequately Sampled Set of Digital Data Points (Characterization of the Sampled Data)

4.1.8.iv.

IEEE 1159.3: Dene an interchange format that can be used to exchange PQM information b/w different apps. The Standard is maintained by Task Force on the Transfer of Power Quality Data (Interchange data format).

4.1.9.

1250-2011 - IEEE Guide for Identifying and Improving Voltage Quality in Power Systems
12The

use of some electrical equipment attached to typical power systems

creates voltage quality concerns. There is an increasing awareness that some equipment is not designed to withstand the surges, faults, distortion, and
12The

description is the abstract of the standard, taken from the link: http://ieeexplore.ieee.org/xpl/

articleDetails.jsp?tp=&arnumber=5744556&contentType=Standards&sortType%3Dasc_p_Sequence%26lter %3DAND%28p_Publication_Number%3A5744554%29
! Harmonics in Power Systems

21

reclosing duty present on typical utility distribution systems. Traditional concerns about steady-state voltage levels and light icker due to voltage uctuation also remain. These concerns are addressed by this guide by documenting typical levels of these aspects of voltage quality and indicating how to improve them. Other documents that treat these subjects in more detail are referenced.

4.2. The British Standard: Engineering Recommendation G5/4-1


4.2.1. These Recommendations are by the Energy Networks Association (ENA). The rst version was published in February 2001 and the revision came in October 2005. It may be noted that the ETR 122 was the companion guide on the application of the G5/4 standard. 4.2.2. With deregulation of the power sector in Britain, a hierarchy of documents was created. These documents in turn permitted unbundling of various layers of power sector. 4.2.3. To quote from the Appendix A of ER G5/4: The planning levels in this Recommendations are to be used by NOCs13 as reference levels against which they assess the suitability for connection to their systems of large loads and equipment which are rated over 16 A and are subject to their consent. They are specic to UK supply systems but are based on IEC Technical Report 61000-3-6. Compatibility levels for public system harmonics are specied in IEC Basic Standards 61000-2-2 and 61000-2-12. The immunity test levels for equipment are higher levels based on the specied compatibility levels. If network distortion exceeds the relevant compatibility level, experience has shown that there will be a sudden increase in equipment failures and customer complaints. The precise relationship between specied compatibility levels and planning levels depends on the disturbance phenomenon being considered and whether or not they are load related....The margins between planning and levels and compatibility level depend upon the electrical characteristics of the supply network, the background levels of

13

NOC as dened in ER G5/4: A generic term embracing Grid Operating Companies and Distribution
Harmonics in Power Systems

Network Operators.
!

22

distortion, the nature of the disturbance (continuous or random), load proles, and load density of the supply system area. Planning levels stipulated by the NOCs are there fore subject to national and local supply system conditions. 4.2.4. It is seen that an elaborate three stage process (Cl. 5) has been laid out to assess connection of non-linear equipment. This assessment procedure is intended to be generally applicable to any non-linear equipment that has a harmonic current emission in to the electricity supply system irrespective of the direction of the fundamental frequency power ow. Therefore there is no differentiation between loads and generation as far as the procedure is concerned. Any specic references to load or generation should therefore be treated as implying the general case of non-linear equipment. [Cl. 5.1.5]...Measurements of background harmonic levels are generally needed for Stage 2 and always for Stage 3 assessments. The responsibility for making these measurements lies with the NOC....In general, the background harmonics should be assessed over atleast a 7 day period when the PCC fault levels are representative of post-connection conditions. 4.2.5. As can be noted, the G5/4 repeatedly veers around to new connections. This is further explained by commentary on G5/4-1:
14...Where

a user wishes to install new equipment to extend an existing installation, and

where agreement to connect has already been established under previous rules, it is possible that the connection of additional equipment could involve a new and lower limit being applied to the whole installation under the terms of a new agreement. This would be retrospective, and therefore difcult to enforce. In these circumstances agreement to connect without increase in the aggregate harmonic current loading should be forthcoming, although the overall connection may be for a higher power.

14

Para 7 of Managing Harmonics-A guide to ENA Engineering Recommendation G5/4-1, 6th Edition: 2011.

Published by GAMBICA, which is the national organisation representing the interests of companies in the instrumentation, control, automation and laboratory technology industry in the UK. It can be accessed at: http://www.gambica.org.uk/
! Harmonics in Power Systems

23

Where a user wishes to replace existing equipment with new equipment of similar functionality, there should be no need to repeat the application procedure, if documentary evidence exists that the levels of harmonic currents generated by the new equipment do not exceed the existing levels. 4.2.6. Another key aspect of the ER G5/4 is the focus on voltage harmonics. The current harmonics limits in turn is assessed by capacity of the utility to supply without voltage at point of connection exceeding the stipulated limits. This is perhaps the only practical method of evaluation. It may be noted that when IEEE 519-1981 evolved to its 1992 version, the current limits were brought in. Juxtaposing the IEEE 519-1992 with ER G5/4 and IEC family of standards, it is clear why current limits were recommended. IEEE 519 being recommendation gives framework for system design and not for enforcement. As would be brought out in the following, implementation of limits on existing network is quite difcult and all other standards talk about connection of new loads. Also the standards which now have been enforced are far more detailed. 4.2.7. The ER G5/4 has very pragmatic view on the limits and hence mentions in Cl. 10 that ...In exceptional circumstances, where for example a customer is located in an area remote from other customers and it is certain that only that customers equipment will be connected to the local network, the Distribution Network Operator (DNO) may assess new load under Stage 2 using compatibility levels appropriate to the network voltage, instead of planning levels. To appreciate the difference between planning levels and compatibility levels, following graphs from IEC TR 61000-3-6: 2008 can be referred. Following graph illustrates basic voltage quality concepts with time/ location statistics covering the whole system:

Harmonics in Power Systems

24

TR 61000-3-6 IEC:2008(E) TR 61000-3-6 IEC:2008(E)

17 17

Compatibility level Compatibility level Immunity Immunity Planning test test Planning levels levels levels levels

Probability Probability density density

System System disturbance disturbance level level Disturbance level Disturbance level

Equipment Equipment immunity immunity level level

IEC 091/08 IEC 091/08

LICENSED TO RESEARCH DESIGNS & STANDARDS ORGANISATION (RDSO) LICENSED TO RESEARCH THIS LOCATION ONLY, SUPPLIED BY BOOK SUPPLY BUREAU. FOR INTERNAL USE AT DESIGNS & STANDARDS ORGANISATION (RDSO) FOR INTERNAL USE AT THIS LOCATION ONLY, SUPPLIED BY BOOK SUPPLY BUREAU.

Figure 1 Following graph illustrates basic voltage quality time/ Illustration of basic voltage quality concepts with concepts Figure 1 Illustration of basic voltage quality concepts with time/ location statistics covering the whole system location one site covering whole system: relevant to statisticswithin thethe whole system

with time statistics

Probability Probability density density

Compatibility level Compatibility level Planning Planning level level Assessed Assessed level level

Site Site disturbance disturbance level level Disturbance level Disturbance level

Local Local equipment equipment immunity immunity level level


IEC 092/08 IEC 092/08

Figure 2 Illustration of basic voltage quality concepts with time Figure 2 Illustration of basic voltage quality concepts with time This buttresses to one that application of system statistics relevant furthersite within the wholeharmonics limits statistics relevant to one site within the whole system

is not

As Figure 2 illustrates, the probability distributions of disturbance and immunity levels at any As Figure 2 illustrates, the probability distributions of disturbance and immunity levels at any one site are normally narrower than those in the whole power system, so that at most one site are normally narrower than those in the whole power system, so that at most Stage of overlap of procedure and immunity level distributions. locations 4.2.8. is little or3 no assessment disturbance which covers connection at > 33 kV, is worth there locations there is little or no overlap of disturbance and immunity level distributions. Interference is therefore not generally a major concern, and equipment is anticipated to Interference is therefore notto appreciatemajorintent of the equipment is anticipated pragmatism of quoting generally a the concern, andmore probable than Figure to function satisfactorily. Electromagnetic compatibility is therefore authors and the inherent 1 function satisfactorily. Electromagnetic compatibility is therefore more probable than Figure 1 appears to suggest. appears to suggest. the Recommendations:
4.4 4.4 Emission levels Emission levels 15The

straightforward exercise.

The co-ordination approach recommended in this report relies on individual emission levels The co-ordination approach recommended in this report relies on individual emission levels non-linear levels. For being provided by the customer. Where the being derived from the planning equipment this reason, the same indices are applied both customer is being derived from the planning levels. For this reason, the same indices are applied both when evaluating actual measurements against the emission limits and against the planning when evaluating actual measurements against the emission limits and against the planning connecting a system containing non-linear equipment, the NOC will be required either levels. levels. One or more of the following indices can be used to compare the actual emission level with One or more of the will following indices can be used to compare the actual emission level with the customers emission enable the customer to evaluate his system harmonic performance, or to model part limit. More than one index may be needed in order to assess the the customers emission limit. More than one index may be needed in order to assess the impact of higher emission levels allowed for short periods of time such as during bursts or impact of higher emission levels allowed for short periods of time such as during bursts or start-up conditions. of the customers system with in the Stage 3 assessment. start-up conditions.

Stage 3 of the assessment will be made by the NOC with the characteristics of the

to provide the customer with the system harmonic impedance values at the PCC which

The 95 % weekly value of U hsh (or I hsh ), the r.m.s. value of individual harmonics over The 95 % weekly value of U hsh (or I hsh ), the r.m.s. value of individual harmonics over "short" 10 min periods, should not exceed the emission limit. "short" 10 min periods, should not exceed the emission limit. 15 Cl. 8.1 of Engineering Recommendations G5/4
! Harmonics in Power Systems

25

It should be read with Section VIII of Ribeiros earlier quoted paper Common Misapplications of the IEEE 519 Harmonic Standard: Voltage or Current Limits: Although IEEE 519 establishes or rather recommends that harmonic current limitation is the responsibility the end-users (customers) and that harmonic voltage is the responsibility of the system owners or operators (utilities), as a simplied procedure for distortion control, end-users are recommended to use both limits with sensitivity and discrimination to avoid both installing unnecessary ltering equipment or neglecting possible local resonances which could cause internal interference and damages. Furthermore, considering that the present current limits were determined based on typical system impedances of 20 years ago, and that much has changed in terms of system impedance, harmonic source characteristics and background distortion content, it is expected that the recommended limits for both voltage and currents be utilized with . Continuing with the ER G5/4, section 8.2 reads as: The assessment of the connection of new non-linear equipment consists of: 4.2.8.i. 4.2.8.ii. 4.2.8.iii. Measuring the levels of distortion already existing on the system, Calculating the distortion which will be caused by the new equipment, and Predicting the possible effect on harmonic levels by an addition of the results of (4.2.8.i) and (4.2.8.ii) Connection of the equipment is acceptable if the results of (4.2.8.iii) are less than the THD and the harmonic voltage planning levels for individual harmonic order. 4.2.9. 4.2.9.i. Other key salient points of ER G5/4 being: In addition to the assessment based on conditions at the PCC, assessment at other locations to be undertaken to establish directly the possibility of resonance effects (Cl 8.2). 4.2.9.ii. Recommends use of harmonic analysis program even for simple network calculations (Cl 8.3.1).

Harmonics in Power Systems

26

4.2.9.iii.

Assessment to include factors like time (time of day), duration of operation (Cl. 8.3.2).

4.2.9.iv.

Only the +ve and -ve triplen components associated with lack of balance between the three phases needs to be considered (Cl. 8.3.2).

4.2.9.v.

If more than one traction supply point is involved, it is likely that different phase pairs will be used for unbalance mitigation. Before summation of harmonics with relatively stable background level, the assessed contribution from each should be made taking in to account both the degree of coordination between the respective traction load currents and the phase difference between the harmonic components (Cl. 8.3.3).

4.3. IEC 61000 Family of Standards


This is truly most elaborate family of standards. Very carefully drafted and voted upon by member nations, these standards strike the thou shalt not... tone. The degree of detail to be found in these standards make them very comprehensive. It is beyond the scope of this White Paper to dwell upon all of these, however, IEC Technical Report 61000-3-6 2nd Edition published in February 2008 is a very recent document and merits closer look.

4.3.1.

IEC/TR

61000-3-6

2nd

Edition:

February

2008-Electromagnetic

compatibility (EMC) Part 3-6: Limits Assessment of emission limits for the connection of distorting installations to MV, HV and EHV power systems.
4.3.1.i. This document is a Technical Report and not a Standard. To appreciate the difference, it is instructive to quote from the foreword of this document: The main task of the IEC technical committees is to prepare international standards. However, a technical committee may propose the publication of a technical report when it has collected data of a different kind from that which is normally published as an International Standard, for example state of the art. 4.3.1.ii. Further, the document mentions, this edition is signicantly more streamlined than the rst edition, and it reects the experiences gained in the application of the rst edition (published in 1996). As part of this streamlining process, this second edition does not address communications circuit interference. It may be
! Harmonics in Power Systems

27

noted that IEEE 519-1992 still carries this legacy. IEC sub committee, SC 77A responsible for this TR invited inputs from CIGRE Study Committee C4 and CIRED Study Committee S2 in 2002. A joint task force was set up in 2003. This makes this TR most authoritative, substantive and current of all documents on the harmonics aspect of power quality. 4.3.1.iii. As can be seen, the TR focuses on voltage aspect. To quote from the Cl. 1, the Scope, The report addresses the allocation of the capacity of the system to absorb disturbances. ... This report gives guidance for the coordination of the harmonic voltages between different voltage levels in order to meet the compatibility levels at the point of utilisation. 4.3.1.iv. The key premise being...The development of emission limits (voltage or current) for individual equipment or a customers installation should be based on the effect that these emission limits will have on the quality of the voltage. This should be seen with the observations of Ribeiro quoted earlier in the discussion of IEEE 519-1992. This philosophy is to be found in ER G5/4-1, which is the British Standard for harmonics. 4.3.1.v. The TR brings the concept of planning levels (Cl 4.2.1) which are the harmonic voltage levels that can be used for the purpose of determining emission limits, taking in to consideration all distorting installations. Planning levels are specied by the system operator or owner for all system voltage levels and can be considered as internal quality objectives if the system operator or owner and may even be made available to individual customer on request. Planning level for harmonics are equal to or lower than compatibility levels and they should allow coordination of harmonic voltages between different voltage levels....this report outlines procedures for using these planning levels to establish the emission limits for individual customers. 4.3.1.vi. Cl 6.2 Note 3: If the installation exceeds the harmonic voltage emission limits it may be because:
!

The system impedance is high due to the presence if harmonic resonance conditions, The installation is resonating with the supply system, or The harmonic currents generated by the installation are too high.
Harmonics in Power Systems

28

4.3.1.vii.

It is thus seen that the before putting the cause of voltage harmonics on the customers door step, two more possible causes need to be ruled out.

4.3.1.viii. Cl 6.4 clearly calls for information on the system harmonic impedance as a prerequisite both for the system operator or owner for assessing emission limits and for the customer in order to assess the emission levels of the considered installation 4.3.1.ix. 4.3.1.x. Impedance for converting emission limits from voltage to current Impedance for pre-connection assessment of emission levels Impedance for assessing actual emission levels Cl. 6.4.4 gives general guidelines for assessing the system harmonic impedance Thus it is seen that TR 61000-3-6 faces the issue of harmonic disturbances with acknowledgement to the complexity of the problem. There is clear mention that the harmonic impedance of the system may vary signicantly with time (Cl 6.4.4). It is a point which has been noted by Ribeiro in his paper quoted earlier. Further, with growth of power sector in the country it is safe to presume that these values would see frequent revisions. 4.3.1.xi. The document aims to have equitable apportionment of the actual harmonic absorption capability to various users. For each customer only a fraction of the global emission limits will be allowed. A reasonable approach is to take the ratio between the agreed power and the total supply capability...Such a criterion is related to the fact that the agreed power of a customer is often linked with his share in the investment costs of the power system. This translates closest to the Contract Demand. This should settle the issue of denominator in determination of TDD as per IEEE 519-1992. 4.3.1.xii. Very important point is made in Cl 8.2.2.2 & 9.2.3: It may be preferred to specify harmonic current limits to the distorting installation, even if the aim is to limit the harmonic voltages in the system. It will be the responsibility of the system operator or owner to provide data concerning the frequency-dependent impedance of the system, in order to enable expressing these limits in terms of harmonic currents. 4.3.1.xiii. The Cl 8.3 and 9.3 mentions that... In all the cases, when appropriate the system operator or owner may decide to allocate higher emission limits under stage 3. A careful
! Harmonics in Power Systems

29

study of the connection should always be carried out, taking account of the pre-existing distortion and of the expected contribution from the considered installation for different possible operating conditions. Acceptance of higher than normal emission limits may be given to customers only on a conditional basis and limitations may be specied by the system operator or owner, for instance-temporary Stage 3 limits for as long as spare supply capacity remains available in the system for allowing more emissions, as long as most other customers do not make full use of their normal stage 2 emissions limits, the time needed for a new installation, in order to implement additional corrective measures whenever needed. 4.3.1.xiv. It is thus seen that the TR acknowledges background harmonics and considers impact of a load thereon. The TR 61000-3-6 not just focuses on voltage instead of current, it also works on equitable apportionment of the available capacity of harmonic absorption. Also relaxation of limits is permissible if other consumers are not able to utilise this limit. This is most economical implementation. The document instead of arriving at the xed current limits as in IEEE 519-1992 and mentioned in CEA Regulations, gives limits on voltage harmonics. The relationship between voltage harmonics and current harmonics is also established but only after realistic determination of the systems harmonic impedance, a subject dealt in considerable detail. 4.3.1.xv. Other documents of IEC 61000 family of interest are listed in Annexure A. It can be seen in the Annexure that scores of standards need to be created to make limits enforceable. IEEE 519-1992, at best can be used as recommended guideline to declare the intent, however, it is grossly inadequate for creating an enforceable regime.

Harmonics in Power Systems

30

5.

Conclusion
drafted standards, notably IEC- 61000 family of standards and British Standard ER G5/4-1 have emerged in the past few years. Some of these came after the CEA Regulations of 2007 were promulgated, which appear to lean on much older IEEE 519-1992. As level of harmonic limits have been laid down by CEA, following immediate issues emerge:

5.1. Harmonic levels in power system has been extensively researched and very carefully

5.1.1.

A limit has been placed on current THD, whereas current distortions cant be meaningful without referencing them to a xed value. This is because of the fact that in general THD changes with load and infact under low loads, THD can be very high.

5.1.2.

Different standards have addressed this issue. IEEE 519-1992 for instance has taken average current of the maximum demand of preceding 12 months, whereas, IEC Technical Report 61000-3-6 takes agreed power between customer and the grid as the value to be used. Agreed power approach has been recommended by IEC as systems technical rating is done based on this value. This value for Indian scenario is Contract Demand.

5.1.3.

Key issue which is addressed by various Standards is that every power system has a capacity of sourcing harmonic currents, with limit being determined by the level of harmonic currents which lead to voltage. unacceptable distortion of

5.1.3.1.

IEC/TR 61000-3-6 (February 2008) and BR G5/4-1 (2005) lay elaborate method for arriving at this limit. Having assessed this limit, various Standards/ Practices arrive at methods to apportion this capacity amongst various users.

5.1.3.2.

It may be noted that IEEE 519-1992, a 20 year old document tried to address the issue by suggesting limits on current TDD. This being a design guideline, its applicability at user end in isolation has been questioned in recent literature.

5.1.4.

We also have to consider the latest international document viz. IEC TR 61000-3-6 (February2008) to peruse the need of apportioning the capacity to

Harmonics in Power Systems

31

source harmonics at various levels in the power system. It may be noted that IEC sub committee, SC 77A responsible for this TR invited inputs from CIGRE Study Committee C4 and CIRED Study Committee S2 in 2002. A joint task force was set up in 2003. This makes this TR most authoritative, substantive and current of all documents on the harmonics aspect of power quality. 5.2. With regards to applicability of IEEE 519-1992, it needs to be noted that this is a system design Recommended Practice. Latest commentaries have been quite vocal to voice the inadequacies of this document. Ribeiro, as discussed earlier has cautioned against use of only current limits. Further, to quote Cl 10.4.2 of IEEE 519-1992,... Although the effects of harmonics on electric equipment, appliances, etc. are not fully understood at this time, it is recognized that the stated current distortion limits can be exceeded for periods of time without causing damage to equipment. When evaluating the user compliance with the stated limits, it is recommended that probability distribution plots be developed from he recorded data and analyzed. If the limits are only exceeded for a short period of time, the condition could be considered acceptable. 5.3. Thus, it clearly emerges that: 5.3.1. IEEE 519-1992 can at best be used a preliminary system design guide. In view of much better researched documents like IEC/TR 61000-3-6, published in 2008, which has been drafted taking inputs from CIRED and CIGRE, making it most authoritative document on the subject. This document has dealt the subject taking cognisance of due complexity of the system. 5.3.2. 5.3.3. IEEE 519-1992 is inadequate to be used as document for enforcing the limits. Measurements carried out by Utilities should consider Cl. 10.4.2 of IEEE 519-1992. Further, the denominator of the TDD calculation should be contract demand. 5.4. It may be seen that, in Cl. 6(6) of Central Electricity Authority (Technical Standards for Connectivity to the Grid) Regulations, 2007, possible need of study to assess transmission system capability, transient stability, voltage stability, losses, voltage regulation, harmonics, voltage icker, electromagnetic transients, machine dynamics, ferro resonance, metering requirements, protective relaying, sub-station grounding and fault duties, has been given. Whereas in the Cl. 3 of Part IV of the Schedule, only
! Harmonics in Power Systems

32

limits on harmonics are given. As discussed earlier, giving absolute limit on current THD is not technically correct approach. Ministry of Railways are approaching the Central Electricity Authority for needed clarity. Also, on the issue of measurements, matter is being discussed with CPRI. 5.5. On the matter of penal provisions following emerge: 5.5.1. IEEE 519-1992 being system design guideline is not only quaint but also inadequate to be used as basis for penalty. 5.5.2. For penalties, rst a limit needs to be arrived at. As can be seen in latest literature, IEC and British guidelines (IEC and British Standards are to be factored in as mentioned at Cl. 1, Part I of Schedule to CEA(Technical Standards for Connectivity to the Grid) Regulations, 2007) a very different approach has been taken (vis-a-vis that of IEEE 519-1992). Thus basing the limits on the approach given by IEEE 519-1992 would lead to misdirected investments. 5.5.3. In the approaches of at penalty, the element of extent of trespass has not been factored in. Also, as argued by Ribeiro, in his paper quoted earlier, it is not correct to take current limits as the nal deciding factors. This approach is technically grossly sub-optimal and should not form basis for justifying investments. Another important technical aspect is discussed below. 5.6. Another important aspect which emerges on perusal of Cl. 6(6) of Central Electricity Authority (Technical Standards for Connectivity to the Grid) Regulations, 2007, is the fact that this Regulation is not as yet implemented. Given the recent disturbances in the Grid, these aspects will also be dealt in more elaborate matter. This would have possible impact on the design of mitigation equipment installed today as limits of other aspects are not yet known. 5.7. Railways need to keep, nevertheless a sharp eye on the system harmonics for the safety of the traction supply network. Incidences of resonance have been documented and need to be kept in check to avoid system disturbances. 5.8. Long before the CEA Regulations came or the IEEE 519-1992 made an impact, IR was already working on mitigation of harmonics at the load end. IRGP-140, the contract signed in July 1993 with erstwhile ABB Transportation, Switzerland, for the Transfer of Technology (ToT) of new generation of electric locomotives - included a harmonic
! Harmonics in Power Systems

33

lter. Locomotives based on this technology are now in serial production. Similarly, all new AC EMUs introduced in Mumbai suburban following DC to AC conversion are provided with harmonic mitigation. All new 25 kV AC Metro stock being introduced in the country are also equipped with harmonic management components. It needs to be agged that IRs requirement of harmonic containment is also for the safe operation of signal circuits. Assessment of harmonics has been key component of rolling stock clearance due to this reason. Thus, it can be seen that IR has been doing load level measurements and containment Regulations came about. 5.9. To appreciate, the approach taken internationally, one must peruse the ecosystem of standards created by IEC as cryptically mentioned in Annexure A. much before these

Harmonics in Power Systems

34

6.

Annexure A

Following tables have been given to help appreciate that harmonics form a part of larger eld of EMC and should be dealt holistically. The sheer number of standards on the issue is staggering as can be seen below. IEC 61000 Part - 1
Standard Number IEC/TR 61000-1-1 Ed. 1.0 b IEC/TS 61000-1-2 Ed. 2.0 en IEC/TR 61000-1-3 Ed. 1.0 en IEC/TR 61000-1-4 Ed. 1.0 en IEC/TR 61000-1-5 Ed. 1.0 en Standard Title Electromagnetic compatibility (EMC) - Part 1: General - Section 1: Application and interpretation of fundamental denitions and terms Electromagnetic compatibility (EMC) - Part 1-2: General - Methodology for the achievement of functional safety of electrical and electronic systems including equipment with regard to electromagnetic phenomena Electromagnetic compatibility (EMC) - Part 1-3: General - The effects of high-altitude EMP (HEMP) on civil equipment and systems Electromagnetic compatibility (EMC) - Part 1-4: General - Historical rationale for the limitation of power-frequency conducted harmonic current emissions from equipment, in the frequency range up to 2 kHz Electromagnetic compatibility (EMC) - Part 1-5: General - High power electromagnetic (HPEM) effects on civil systems

IEC 61000 Part - 2


Electromagnetic compatibility (EMC) - Part 2: Environment - Section 1: Description of the environment - Electromagnetic environment for EC/TR 61000-2-1 Ed. 1.0 b low-frequency conducted disturbances and signalling in public power supply systems Electromagnetic compatibility (EMC) - Part 2-2: Environment IEC 61000-2-2 Ed. 2.0 b Compatibility levels for low-frequency conducted disturbances and signalling in public low-voltage power supply systems Electromagnetic compatibility (EMC) - Part 2: Environment - Section IEC/TR 61000-2-3 Ed. 1.0 b 3: Description of the environment - Radiated and non-networkfrequency-related conducted phenomena Electromagnetic compatibility (EMC) - Part 2-4: Environment IEC 61000-2-4 Ed. 2.0 b Compatibility levels in industrial plants for low-frequency conducted disturbances Electromagnetic compatibility (EMC) - Part 2: Environment - Section IEC/TS 61000-2-5 Ed. 1.0 b 5: Classication of electromagnetic environments. Basic EMC publication Electromagnetic compatibility (EMC) - Part 2-5: Environment IEC/TR 61000-2-5 Ed. 2.0 b Description and classication of electromagnetic environments Electromagnetic compatibility (EMC) - Part 2: Environment - Section IEC/TR 61000-2-6 Ed. 1.0 b 6: Assessment of the emission levels in the power supply of industrial plants as regards low-frequency conducted disturbances

H a r m o n i c s i n Tr a c t i o n P o w e r S u p p l y

Electromagnetic compatibility (EMC) - Part 2: Environment - Section 7: Low frequency magnetic elds in various environments Electromagnetic compatibility (EMC) - Part 2-8: Environment IEC/TR 61000-2-8 Ed. 1.0 b Voltage dips and short interruptions on public electric power supply systems with statistical measurement results Electromagnetic compatibility (EMC) - Part 2: Environment - Section IEC 61000-2-9 Ed. 1.0 b 9: Description of HEMP environment - Radiated disturbance. Basic EMC publication Electromagnetic compatibility (EMC) - Part 2-10: Environment IEC 61000-2-10 Ed. 1.0 b Description of HEMP environment - Conducted disturbance Electromagnetic compatibility (EMC) - Part 2-11: Environment IEC 61000-2-11 Ed. 1.0 b Classication of HEMP environments Electromagnetic compatibility (EMC) - Part 2-12: Environment IEC 61000-2-12 Ed. 1.0 b Compatibility levels for low-frequency conducted disturbances and signalling in public medium-voltage power supply systems Electromagnetic compatibility (EMC) - Part 2-13: Environment - HighIEC 61000-2-13 Ed. 1.0 en power electromagnetic (HPEM) environments - Radiated and conducted IEC/TR 61000-2-14 Ed. 1.0 Electromagnetic compatibility (EMC) - Part 2-14: Environment en Overvoltages on public electricity distribution networks IEC/TR 61000-2-7 Ed. 1.0 b

IEC 61000 Part - 3


IEC 61000-3-2 Ed. 3.2 b IEC 61000-3-2 Amd.1 Ed. 3.0 b Electromagnetic compatibility (EMC) - Part 3-2: Limits - Limits for harmonic current emissions (equipment input current 16 A per phase) Amendment 1 - Electromagnetic compatibility (EMC) - Part 3-2: Limits Limits for harmonic current emissions (equipment input current 16 A per phase) Amendment 2 - Electromagnetic compatibility (EMC) - Part 3-2: Limits Limits for harmonic current emissions (equipment input current 16 A per phase) Corrigendum 1 - Electromagnetic compatibility (EMC) - Part 3-2: Limits Limits for harmonic current emissions (equipment input current 16 A per phase) Electromagnetic compatibility (EMC) - Part 3-3: Limits - Limitation of voltage changes, voltage uctuations and icker in public low-voltage supply systems, for equipment with rated current 16 A per phase and not subject to conditional connection Amendment 1 - Electromagnetic compatibility (EMC) - Part 3: Limits Section 3: Limitation of voltage uctuations and icker in low-voltage supply systems for equipment with rated current <= 16 A Amendment 2 - Electromagnetic compatibility (EMC) - Part 3-3: Limits Limitation of voltage changes, voltage uctuations and icker in public lowvoltage supply systems, for equipment with rated current <= 16 A per phase and not subject to conditional Electromagnetic compatibility (EMC) - Part 3-4: Limits - Limitation of emission of harmonic currents in low-voltage power supply systems for equipment with rated current greater than 16 A Electromagnetic compatibility (EMC) - Part 3-5: Limits - Limitation of voltage uctuations and icker in low-voltage power supply systems for equipment with rated current greater than 75 A
H a r m o n i c s i n Tr a c t i o n P o w e r S u p p l y

IEC 61000-3-2 Amd.2 Ed. 3.0 b

IEC 61000-3-2 Ed. 3.2 b Cor.1

IEC 61000-3-3 Ed. 2.0 b

IEC 61000-3-3 Amd.1 Ed. 1.0 b

IEC 61000-3-3 Amd.2 Ed. 1.0 b

IEC/TS 61000-3-4 Ed. 1.0 b

IEC/TS 61000-3-5 Ed. 2.0 b


!

ii

IEC/TS 61000-3-5 Ed. 2.0 b Cor.1 IEC/TS 61000-3-5 Ed. 2.0 b Cor.2 IEC/TR 61000-3-6 Ed. 2.0 en

IEC/TR 61000-3-7 Ed. 2.0 en

IEC 61000-3-8 Ed. 1.0 b

IEC 61000-3-11 Ed. 1.0 b

IEC 61000-3-12 Ed. 2.0 b

IEC/TR 61000-3-13 Ed. 1.0 en IEC/TR 61000-3-13 Ed. 1.0 en Cor.1 IEC/TR 61000-3-14 Ed. 1.0 en

IEC/TR 61000-3-15 Ed. 1.0 en

Corrigendum 1 - Electromagnetic compatibility (EMC) - Part 3-5: Limits Limitation of voltage uctuations and icker in low-voltage power supply systems for equipment with rated current greater than 75 A Corridendum 2 - Electromagnetic compatibility (EMC) - Part 3-5: Limits Limitation of voltage uctuations and icker in low-voltage power supply systems for equipment with rated current greater than 75 A Electromagnetic compatibility (EMC) - Part 3-6: Limits - Assessment of emission limits for the connection of distorting installations to MV, HV and EHV power systems Electromagnetic compatibility (EMC) - Part 3-7: Limits - Assessment of emission limits for the connection of uctuating installations to MV, HV and EHV power systems Electromagnetic compatibility (EMC) - Part 3: Limits - Section 8: Signalling on low-voltage electrical installations - Emission levels, frequency bands and electromagnetic disturbance levels Electromagnetic compatibility (EMC) - Part 3-11: Limits - Limitation of voltage changes, voltage uctuations and icker in public low-voltage supply systems - Equipment with rated current <= 75 A and subjet to conditional connection Electromagnetic compatibility (EMC) - Part 3-12: Limits - Limits for harmonic currents produced by equipment connected to public low-voltage systems with input current >16 A and 75 A per phase Electromagnetic compatibility (EMC) - Part 3-13: Limits - Assessment of emission limits for the connection of unbalanced installations to MV, HV and EHV power systems Corrigendum 1 - Electromagnetic compatibility (EMC) - Part 3-13: Limits Assessment of emission limits for the connection of unbalanced installations to MV, HV and EHV power systems Electromagnetic compatibility (EMC) - Part 3-14: Assessment of emission limits for harmonics, interharmonics, voltage uctuations and unbalance for the connection of disturbing installations to LV power systems Electromagnetic compatibility (EMC) - Part 3-15: Limits - Assessment of low frequency electromagnetic immunity and emission requirements for dispersed generation systems in LV network

IEC 61000 Part - 4


IEC 61000-4-1 Ed. 3.0 b IEC 61000-4-2 Ed. 2.0 b IEC 61000-4-2 Amd.1 Ed. 1.0 b Electromagnetic compatibility (EMC) - Part 4-1: Testing and measurement techniques - Overview of IEC 61000-4 series Electromagnetic compatibility (EMC) - Part 4-2: Testing and measurement techniques - Electrostatic discharge immunity test Amendment 1 - Electromagnetic compatibility (EMC) - Part 4: Testing and measurement techniques - Section 2: Electrostatic discharge immunity test. Basic EMC Publication Amendment 2 - Electromagnetic compatibility (EMC) - Part 4: Testing and measurement techniques - Section 2: Electrostatic discharge immunity test. Basic EMC Publication Electromagnetic compatibility (EMC) - Part 4-3: Testing and measurement techniques - Radiated, radio-frequency, electromagnetic eld immunity test

IEC 61000-4-2 Amd.2 Ed. 1.0 b

IEC 61000-4-3 Ed. 3.2 b

H a r m o n i c s i n Tr a c t i o n P o w e r S u p p l y

iii

Amendment 1 - Electromagnetic compatibility (EMC) - Part 4-3: Testing IEC 61000-4-3 Amd.1 Ed. 3.0 b and measurement techniques - Radiated, radio-frequency, electromagnetic eld immunity test Amendment 2 - Electromagnetic compatibility (EMC) - Part 4-3: Testing IEC 61000-4-3 Amd.2 Ed. 3.0 b and measurement techniques - Radiated, radio-frequency, electromagnetic eld immunity test Corrigendum 2 - Electromagnetic compatibility (EMC) - Part 4-4: Testing IEC 61000-4-4 Ed. 2.0 b Cor.2 and measurement techniques - Electrical fast transient/burst immunity test Electromagnetic compatibility (EMC) - Part 4-4: Testing and measurement IEC 61000-4-4 Ed. 2.1 b techniques - Electrical fast transient/burst immunity test Amendment 1 - Electromagnetic compatibility (EMC) - Part 4-4: Testing IEC 61000-4-4 Amd.1 Ed. 2.0 b and measurement techniques - Electrical fast transient/burst immunity test Electromagnetic compatibility (EMC) - Part 4-5: Testing and measurement IEC 61000-4-5 Ed. 2.0 b techniques - Surge immunity test Electromagnetic compatibility (EMC) - Part 4-6: Testing and measurement IEC 61000-4-6 Ed. 3.0 b techniques - Immunity to conducted disturbances, induced by radiofrequency elds Amendment 1 - Electromagnetic compatibility (EMC) - Part 4-6: Testing IEC 61000-4-6 Amd.1 Ed. 2.0 b and measurement techniques - Immunity to conducted disturbances, induced by radio-frequency elds Amendment 2 - Electromagnetic compatibility (EMC) - Part 4-6: Testing IEC 61000-4-6 Amd.2 Ed. 2.0 b and measurement techniques - Immunity to conducted disturbances, induced by radio-frequency elds Electromagnetic compatibility (EMC) - Part 4-7: Testing and measurement techniques - General guide on harmonics and interharmonics IEC 61000-4-7 Ed. 2.1 b measurements and instrumentation, for power supply systems and equipment connected thereto Amendment 1 - Electromagnetic compatibility (EMC) - Part 4-7: Testing and measurement techniques - General guide on harmonics and IEC 61000-4-7 Amd.1 Ed. 2.0 b interharmonics measurements and instrumentation, for power supply systems and equipment connected thereto Electromagnetic compatibility (EMC) - Part 4-8: Testing and measurement IEC 61000-4-8 Ed. 2.0 b techniques - Power frequency magnetic eld immunity test Amendment 1 - Electromagnetic compatibility (EMC) - Part 4: Testing and IEC 61000-4-8 Amd.1 Ed. 1.0 b measurement techniques - Section 8: Power frequency magnetic eld immunity test. Basic EMC Publication Electromagnetic compatibility (EMC) - Part 4-9: Testing and measurement IEC 61000-4-9 Ed. 1.1 b techniques - Pulse magnetic eld immunity test Amendment 1 - Electromagnetic compatibility (EMC) - Part 4: Testing and IEC 61000-4-9 Amd.1 Ed. 1.0 b measurement techniques - Section 9: Pulse magnetic eld immunity test. Basic EMC Publication Electromagnetic compatibility (EMC) - Part 4-10: Testing and IEC 61000-4-10 Ed. 1.1 b measurement techniques - Damped oscillatory magnetic eld immunity test Amendment 1 - Electromagnetic compatibility (EMC) - Part 4: Testing and IEC 61000-4-10 Amd.1 Ed. 1.0 b measurement techniques - Section 10: Damped oscillatory magnetic eld immunity test. Basic EMC Publication Electromagnetic compatibility (EMC) - Part 4-11: Testing and measurement IEC 61000-4-11 Ed. 2.0 b techniques - Voltage dips, short interruptions and voltage variations immunity tests
! H a r m o n i c s i n Tr a c t i o n P o w e r S u p p l y

iv

IEC 61000-4-12 Ed. 2.0 b IEC 61000-4-28 Ed. 1.2 b

IEC 61000-4-13 Ed. 1.1 b

IEC 61000-4-13 Amd.1 Ed. 1.0 b

IEC 61000-4-14 Ed. 1.2 b IEC 61000-4-14 Amd.1 Ed. 1.0 b IEC 61000-4-14 Amd.2 Ed. 1.0 b

IEC 61000-4-15 Ed. 2.0 b

IEC 61000-4-15 Ed. 2.0 b Cor.1

IEC 61000-4-15 Amd.1 Ed. 1.0 b

IEC 61000-4-16 Ed. 1.2 b

IEC 61000-4-16 Amd.1 Ed. 1.0 b

IEC 61000-4-16 Amd.2 Ed. 1.0 b IEC 61000-4-17 Ed. 1.2 b IEC 61000-4-17 Amd.1 Ed. 1.0 b

IEC 61000-4-17 Amd.2 Ed. 1.0 b IEC 61000-4-18 Ed. 1.1 b IEC 61000-4-18 Amd.1 Ed. 1.0 b IEC 61000-4-20 Ed. 2.0 b

Electromagnetic compatibility (EMC) - Part 4-12: Testing and measurement techniques - Ring wave immunity test Electromagnetic compatibility (EMC) - Part 4-28: Testing and measurement techniques - Variation of power frequency, immunity test for equipment with input current not exceeding 16 A per phase Electromagnetic compatibility (EMC) - Part 4-13: Testing and measurement techniques - Harmonics and interharmonics including mains signalling at a.c. power port, low frequency immunity tests Amendment 1 - Electromagnetic compatibility (EMC) - Part 4-13: Testing and measurement techniques - Harmonics and interharmonics including mains signalling at a.c. power port, low frequency immunity tests Electromagnetic compatibility (EMC) - Part 4-14: Testing and measurement techniques - Voltage uctuation immunity test for equipment with input current not exceeding 16 A per phase Amendment 1 - Electromagnetic compatibility (EMC) - Part 4-14: Testing and measurement techniques - Voltage uctuation immunity test Amendment 2 - Electromagnetic compatibility (EMC) - Part 4-14: Testing and measurement techniques - Voltage uctuation immunity test for equipment with input current not exceeding 16 A per phase Electromagnetic compatibility (EMC) - Part 4-15: Testing and measurement techniques - Flickermeter - Functional and design specications Corrigendum 1 - Electromagnetic compatibility (EMC) - Part 4-15: Testing and measurement techniques - Flickermeter - Functional and design specications Amendment 1 - Electromagnetic compatibility (EMC) - Part 4: Testing and measurement techniques - Section 15: Flickermeter - Functional and design specications Electromagnetic compatibility (EMC) - Part 4-16: Testing and measurement techniques - Test for immunity to conducted, common mode disturbances in the frequency range 0 Hz to 150 kHz Amendment 1 - Electromagnetic compatibility (EMC) - Part 4-16: Testing and measurement techniques - Test for immunity to conducted, common mode disturbances in the frequency range 0 Hz to 150 kHz Amendment 2 - Electromagnetic compatibility (EMC) - Part 4-16: Testing and measurement techniques - Test for immunity to conducted, common mode disturbances in the frequency range 0 Hz to 150 kHz Electromagnetic compatibility (EMC) - Part 4-17: Testing and measurement techniques - Ripple on d.c. input power port immunity test Amendment 1 - Electromagnetic compatibility (EMC) - Part 4-17: Testing and measurement techniques - Ripple on d.c. input power port immunity test Amendment 2 - Electromagnetic compatibility (EMC) - Part 4-17: Testing and measurement techniques - Ripple on d.c. input power port immunity test Electromagnetic compatibility (EMC) - Part 4-18: Testing and measurement techniques - Damped oscillatory wave immunity test Amendment 1 - Electromagnetic compatibility (EMC) - Part 4-18: Testing and measurement techniques - Damped oscillatory wave immunity test Electromagnetic compatiility (EMC) - Part 4-20: Testing and measurement techniques - Emission and immunity testing in transverse electromagnetic (TEM) waveguides
H a r m o n i c s i n Tr a c t i o n P o w e r S u p p l y

Amendment 1 - Electromagnetic compatibility (EMC) - Part 4-20: Testing IEC 61000-4-20 Amd.1 Ed. 1.0 b and measurement techniques - Emission and immunity testing in transverse electromagnetic (TEM) waveguides Electromagnetic compatibility (EMC) - Part 4-22: Testing and measurement techniques - Radiated emissions and immunity measurements in fully anechoic rooms (FARs) Electromagnetic compatibility (EMC) - Part 4-23: Testing and IEC 61000-4-23 Ed. 1.0 b measurement techniques - Test methods for protective devices for HEMP and other radiated disturbances Electromagnetic compatibility (EMC) - Part 4: Testing and measurement IEC 61000-4-24 Ed. 1.0 b techniques - Section 24: Test methods for protective devices for HEMP conducted disturbance - Basic EMC Publication Electromagnetic compatibility (EMC) - Part 4-25: Testing and IEC 61000-4-25 Ed. 1.0 b measurement techniques - HEMP immunity test methods for equipment and systems Amendment 1 - Electromagnetic compatibility (EMC) - Part 4-25: Testing IEC 61000-4-25 Amd.1 Ed. 1.0 b and measurement techniques - HEMP immunity test methods for equipment and systems IEC 61000-4-22 Ed. 1.0 b Amendment 1 - Electromagnetic compatibility (EMC) - Part 4-27: Testing IEC 61000-4-27 Amd.1 Ed. 1.0 b and measurement techniques - Unbalance, immunity test for equipment with input current not exceeding 16 A per phase Amendment 1 - Electromagnetic compatibility (EMC) - Part 4-28: Testing IEC 61000-4-28 Amd.1 Ed. 1.0 b and measurement techniques - Variation of power frequency, immunity test Amendment 2 - Electromagnetic compatibility (EMC) - Part 4-28: Testing IEC 61000-4-28 Amd.2 Ed. 1.0 b and measurement techniques - Variation of power frequency, immunity test for equipment with input current not exceeding 16 A per phase Electromagnetic compatibility (EMC) - Part 4-29: Testing and IEC 61000-4-29 Ed. 1.0 b measurement techniques - Voltage dips, short interruptions and voltage variations on d.c. input power port immunity tests Electromagnetic compatibility (EMC) - Part 4-30: Testing and IEC 61000-4-30 Ed. 2.0 b measurement techniques - Power quality measurement methods Electromagnetic compatibility (EMC) - Part 4-32: Testing and IEC/TR 61000-4-32 Ed. 1.0 en measurement techniques - High-altitude electromagnetic pulse (HEMP) simulator compendium Electromagnetic compatibility (EMC) - Part 4-33: Testing and IEC 61000-4-33 Ed. 1.0 en measurement techniques - Measurement methods for high-power transient parameters Electromagnetic compatibility (EMC) - Part 4-34: Testing and measurement techniques - Voltage dips, short interruptions and voltage IEC 61000-4-34 Ed. 1.1 b variations immunity tests for equipment with mains current more than 16 A per phase Amendment 1 - Electromagnetic compatibility (EMC) - Part 4-34: Testing and measurement techniques - Voltage dips, short interruptions and IEC 61000-4-34 Amd.1 Ed. 1.0 b voltage variations immunity tests for equipmentwith mains current more than 16 A per phase Electromagnetic compatibility (EMC) - Part 4-35: Testing and IEC/TR 61000-4-35 Ed. 1.0 en measurement techniques - HPEM simulator compendium
! H a r m o n i c s i n Tr a c t i o n P o w e r S u p p l y

vi

IEC 61000 Part - 5


IEC/TR 61000-5-1 Ed. 1.0 b IEC/TR 61000-5-2 Ed. 1.0 b IEC/TR 61000-5-3 Ed. 1.0 b IEC/TS 61000-5-4 Ed. 1.0 b Electromagnetic compatibility (EMC) - Part 5: Installation and mitigation guidelines - Section 1: General considerations - Basic EMC publication Electromagnetic compatibility (EMC) - Part 5: Installation and mitigation guidelines - Section 2: Earthing and cabling Electromagnetic compatibility (EMC) - Part 5-3: Installation and mitigation guidelines - HEMP protection concepts Electromagnetic compatibility (EMC) - Part 5: Installation and mitigation guidelines - Section 4: Immunity to HEMP - Specications for protective devices against HEMP radiated disturbance. Basic EMC Publication Electromagnetic compatibility (EMC) - Part 5: Installation and mitigation guidelines - Section 5: Specication of protective devices for HEMP conducted disturbance. Basic EMC Publication Electromagnetic compatibility (EMC) - Part 5-6: Installation and mitigation guidelines - Mitigation of external EM inuences Electromagnetic compatibility (EMC) - Part 5-7: Installation and mitigation guidelines - Degrees of protection provided by enclosures against electromagnetic disturbances (EM code) Electromagnetic compatibility (EMC) - Part 5-8: Installation and mitigation guidelines - HEMP protection methods for the distributed infrastructure Electromagnetic compatibility (EMC) - Part 5-9: Installation and mitigation guidelines - System-level susceptibility assessments for HEMP and HPEM

IEC 61000-5-5 Ed. 1.0 b IEC/TR 61000-5-6 Ed. 1.0 en IEC 61000-5-7 Ed. 1.0 b IEC/TS 61000-5-8 Ed. 1.0 en IEC/TS 61000-5-9 Ed. 1.0 en

H a r m o n i c s i n Tr a c t i o n P o w e r S u p p l y

vii

Anda mungkin juga menyukai