Anda di halaman 1dari 3

A New Approach for Placement of

FACTS Devices in Open Power Markets


S.N. Singh, A.K. David
Author Affiliations: EPSM, Energy Program, Asian Institute of
Technology, Bangkok, Thailand; Department of Electrical Engi-
neering, Hong Kong Polytechnic University, Kowloon, Hong Kong.
Abstract: Power system restructuring requires expanding unused
potentials of transmission systems due to environmental, right-of-way,
and cost problems, which are major hurdles for power transmission net-
work expansion. FACTS devices can be an alternative to reduce the
flows in heavily loaded lines, resulting in an increased loadability, low
system loss, improved stability of the network, reduced cost of produc-
tion, and fulfilled contractual requirements by controlling the power
flows in the network. This letter suggests first, the few optimal loca-
tions of FACTS devices and then determines the best optimal location
in order to reduce the production cost along with the device cost. The
allocation and requirement are also discussed. The effectiveness of the
proposed methods is demonstrated on an IEEE 14-bus system.
Keywords: FACTS devices, congestion management, open power
market.
Introduction: Power systems may be forced to operate at almost
full capacity. Patterns of generation that result in heavy flows tend to in-
cur greater losses, and to threaten stability and security, ultimately
making certain generation patterns economically undesirable. Trans-
mission constraints rule out certain combinations of supply and de-
mand due to potential power outages of varying severity. Hence, there
is an interest in better utilization of available power system capacities
by installing new devices such as flexible ac transmission systems
(FACTS) [1]. Variable series capacitors, phase shifters and unified
power flowcontrollers can be utilized to change the power flowin lines
by changing the their parameters to achieve various objectives.
FACTS devices can improve system performance considerably by
controlling the power flows in the network without generation resched-
uling or topological changes. Using controllable components such as
controllable series capacitors and phase shifters line flows can be
changed in such a way that thermal limits are not violated, losses mini-
mized, stability margin increased, contractual requirement fulfilled etc,
without violating specified power dispatch. It is important ascertain the
location for placement of these devices because of their considerable
costs.
There are several methods for finding optimal locations of FACTS
devices in both vertically integrated and unbundled power systems
[2]-[3]. The literature does not suggest a simple and reliable method for
determining the optimal location in a deregulated environment. In prac-
tice, it may not be possible to deliver all bilateral and multilateral con-
tracts in full and to supply all pool demand, at least cost, due to
violation of operating constraints such as voltage limits and line
over-loads. Congestion in a transmission system, whether vertically or-
ganized or unbundled, cannot be permitted except for very short dura-
tion, for fear of cascade outages with uncontrolled loss of load. Some
corrective measures such as outage of congested branches (lines or
transformers), using FACTS devices, operation of transformer taps,
re-dispatch of generation and curtailment of pool loads and/or bilateral
contracts can relieve congestion.
In this letter, a method to determine the few locations of thyristor
controlled series compensators (TCSC) and thyristor controlled phase
angle regulators (TCPAR) in the network has been suggested based on
the sensitivity of the real power flowperformance index. Thereafter, the
optimal location is decided based on the maximizing social benefit but
minimizing the price based curtailment of pool and bilateral dispatch
by ensuring minimum device cost. The proposed algorithm has been
demonstrated on a sample system.
Problem Formulation: Normal Transmission Dispatch: Transmis-
sion dispatch in an unbundled environment will be a mix of pool and bi-
lateral/multilateral transactions. The optimal dispatch will be the
delivery of all bilateral and multilateral transactions in full and to sup-
ply of all pool demand at least cost without any security violations. This
case can be termed the normal condition. It has been assumed that the
independent system operator (ISO) provides all loss compensation ser-
vices that are caused by bilateral or multilateral transactions and dis-
patches pool power to make good transmission losses including the
losses associated with the delivery of contract transaction [5]. Mathe-
matically, the normal dispatch problem can be written as,
( ) ( )
min
P
i pi
i I
j pj
j I
pi
G D
C P B D

(1)
subject to
( )
~
, , , , , , L P D P Q V
p p t
X
k
= 0
(2)
( )
~
, , , , , , , G P D Q V
p p
P X
t k
0
(3)
where I
G
and I
D
are the sets of pool generator and load buses, respec-
tively; P

and D
pj
are active powers of pool generator-i with bid priceC
i
and pool load-j with bid price B
j
, respectively; P
p
, D
p
, P
t
, Q, V, and
are vectors of pool power injections, pool power extractions, bilateral
contracts, reactive powers, voltage magnitudes, and voltage angles, re-
spectively. Equality constraints (2) is a set of contracted transaction re-
lationships and power balance equations. Expression (3) is a set of
inequality constraints indicating the magnitude (mathematically upper
limits) of pool demands in addition to the usual system operating con-
58 0272-1724/01/$10.002001 IEEE IEEE Power Engineering Review, September 2001
Figure 4. Injection model of TCPAR
Figure 3. Equivalent circuit of TCPAR
Table 1. Generator data
Generator Bid Price ($/h) Specified Voltage
1 0.005 P
2
+ 3.71 P 1.08
2 0.005 P
2
+ 3.52 P 1.08
3 0.005 P
2
+ 3.89 P 1.08
4 0.005 P
2
+ 2.45 P 1.08
Figure 2. Injection model of TCSC
Figure 1. Model of TCSC
straints such as bus voltage levels and line overloads. X
k
is the control
parameter of FACTS device placed in line-k.
In the above formulation, it is assumed that the generation pattern
and FACTS devices alleviate the congestion of the systemcompletely.
Objective Function: Due to high cost of FACTS devices, it is neces-
sary to use cost-benefit analysis to analyze whether a new FACTS de-
vice is cost effective amongst several candidate locations when actually
installed. The TCSC cost in line-k is given by
C k c x k P
c l tcsc
Base_ power ( ) . ( ). . =
2
(4)
where c is the unit investment cost of FACTS ($/MVAR), x k
c
( ) is the
series capacitive reactance, and P
l
is the power flow in line-k. It is as-
sumed that the cost of TCPAR is same for all the lines. Therefore, for
TCPARthe objective function will be the same as (1) subject to the con-
straints (2) and (3).
The objective function for placement of TCSC will be
( ) ( )
min
P
i pi
i I
j pj
j I
pi
G D
C P B D C


+
tcsc
t
(5)
where
C
C k
t
tcsc
tcsc
=
. ( )
8760
and
=
+
+
r r
r
n
n
( )
( )
1
1 1
(6)
= the capital recovery factor (CRF),
r = the interest rate,
n = the capital recovery plan.
It is assumed that the investment cost of the TCSC is $50/KVAr.
Considering the interest rate r =0.05, the capital recovery period n =10
years, the capital recovery factor can be computed, i.e., =0.1295.
Thus the cost of TCSC is approximated as $17.74/MVAr/day.
Static Modeling of FACTS Devices: The power injection approach
has been suggested for static modeling of FACTS devices.
Thyristor Controlled Series Compensator: The model of a transmis-
sion line with a TCSC connected between bus-i and bus-j is shown in
Figure 1. In steady state, the TCSC can be considered as a static
reactance jx
c
. The change in the line flow due to series capacitance
can be represented as a line without series capacitance with additional
power (complex) injections at the receiving( ) S
jc
and sending( ) S
ic
ends
as shown in Figure 2. The real power injections due to series capacitor
at bus-i ( ) P
ic
and bus-j ( ) P
jc
can be written as [4]
[ ]
P V G VV G B
ic i ij i j ij ij ij ij
= +
2
cos sin
(7)
[ ]
P V G VV G B
jc j ij i j ij ij ij ij
=
2
cos sin
(8)
where
G
x r x x
r x r x x
ij
c ij c ij
ij ij ij ij c
=

+ +
( )
( )( ( ) )
2
2 2 2 2
and
( )
( ) ( )
B
x r x x x
r x r x x
ij
c ij ij c ij
ij ij ij ij c
=
+
+ +

2 2
2 2 2
2
.
Thyristor Controlled Phase Angle Regulator: The static model of a
TCPAR and transmission line between bus-i and bus-j is shown in
Figure 3. From basic circuit theory, the injection equivalent circuit of
Figure 4 can be obtained. The injected active power at bus-i ( ) P
is
and
bus-j ( ) P
js
of a line having a phase shifter are
[ ]
P V K G VV K G B
is i ij i j ij ij ij ij
=
2 2
sin cos
(9)
[ ]
P VV K G B
js i j ij ij ij ij
= + sin cos
(10)
IEEE Power Engineering Review, September 2001 59
Table 2. Sensitivity factors
Line -k Line
Rating
MW
Power
Flow
(MW)
TCSC
(a
k
c
)
TCPAR
(a
k
s
)
Line -k
Line Rating
MW
Power Flow
(MW)
TCSC
(a
k
c
)
TCPAR
(a
k
s
)
No. i - j No. i-j
1 8-3 150.0 23.5 -0.585 -2.683 11 2-9 150.0 95.0 1.419 1.485
2 9-6 150.0 49.9 2.721 5.535 12 6-7 50.0 49.9 2.722 5.645
3 9-7 150.0 27.9 -0.950 -3.372 13 7-10 50.0 14.4 0.442 2.658
4 4-8 150.0 100.3 -3.978 -4.066 14 3-11 150.0 59.8 -1.280 -2.139
5 2-8 150.0 96.8 1.435 1.502 15 3-12 50.0 19.7 -0.302 -1.511
6 1-9 150.0 90.3 0.441 0.482 16 3-13 50.0 45.2 0.877 1.865
7 8-9 150.0 0.6 0.015 -0.265 17 7-14 50.0 5.6 0.015 -0.077
8 4-2 90.0 96.8 2.502 3.460 18 11-10 50.0 4.7 -1.129 -2.407
9 2-1 90.0 6.9 0.053 0.943 19 12-13 50.0 3.3 -0.037 -1.520
10 6-5 50.0 0.0 0.000 0.000 20 13-14 50.0 20.2 0.066 0.277
Table 3. Optimal generation schedule
Generators Base Case TCSC in Line-4
TCPAR in
Line-4 Line-8
G1 89.9 + j 27.8 87.0 + j 28.8 86.1 + j 23.6 86.0 + j 27.3
G2 107.5 + j 88.6 110.2 + j 88.5 108.1 + j 72.7 107.8 + j 126.1
G3 110.7 + j 80.2 104.8 + j 80.9 102.9 + j 74.7 103.6 + j 79.6
G4 190.2 - j 1.4 196.6 - j 1.1 201.2 + j 2.6 201.1 -j 24.3
Total Cost ($/h) 1948.68 1948.18 1943.1 1945.1
where K tan .
Optimal Locations of Facts Devices: The severity of the system
loading under normal and contingency cases can be described by a real
power line flow performance index [7], as given below.
PI
w
n
P
P
m
m
N
lm
lm
n
l

j
(
,
\
,
(

2
1
2
max
(11)
where P
lm
is the real power flow, P
lm
max
is the rated capacity of line-m, n is
the exponent, and w
m
a real non-negative weighting coefficient that
may be used to reflect the importance of lines. PI will be small when all
the lines are within their limits and reach a high value when there are
overloads. Thus, it provides a good measure of severity of the line over-
loads for a given state of the power system. In this study, the value of the
exponent has been taken as 2 and w
m
= 1.0.
The real power flowPI sensitivity factors with respect to the param-
eters of TCSCand TCPARplaced in line-k, one at a time, are defined as
a
PI
x
k
c
ck
x
ck

0
(12)
a
PI
k
s
k
k

0
.
(13)
Using (11), the sensitivity of PI with respect to FACTS device pa-
rameter X
k
(x
ck
for TCSC and
k
for TCPAR) connected between bus-i
and bus-j for the case n 2, can be written as


j
(
,
\
,
(

PI
X
w P
P
P
X
k
m lm
m
N
lm
lm
k
l
3
1
4
1
max
.
(14)
The real power flow in a line-m (P
lm
) can be represented in terms of
real power injections using dc power flow equations [7] where s is the
slack bus, as
P
S P m k
S P P m k
lm
mn n
n
n s
N
mn n
n
n s
N
j

1
1
for
for

(15)
where S
mn
is the mnth element of matrix [S] which relates line flow
with power injections at the buses without FACTS devices and N is the
number of buses in the system.
Using (15), the following relationship can be derived,

j
(
,
\
,
(

+
P
X
S
P
X
S
P
X
m k
S
P
X
S
lm
k
mi
i
k
mj
j
k
mi
i
k
for
mj
j
k
j
k
P
X
P
X
m k

j
(
,
\
,
( +

for .
(16)
The terms


P
x
i
ck
x
ck
0
,


P
x
j
ck
x
ck
0
,


P
i
k
k

0
, and


P
j
k
k
0
can be obtained using (7)-(10), and the sensitivity factors a
k
c
and a
k
s
can
now be found.
Criteria for Optimal Location: The FACTS device should be placed
on the most sensitive lines. With the sensitivity indices computed for
each type of FACTS device, TCPAR should be placed in a line (k) hav-
ing largest absolute value of the sensitivity factor. TCSC should be
placed in a line (k) having largest negative value of the sensitivity fac-
tor, however. The final placement is decided after solving the
optimization problem.
Simulation Results: The approach has been examined on a modi-
fied IEEE 14-bus system [5] consisting of four real power generator
buses and one voltage-regulating bus. Generators at buses 1, 2, 3, and 4
bid into the pool. Generator at bus-1 is taken as the reference bus. Volt-
age magnitudes at load buses are kept within the range of 0.95-1.10.
The prices bid by generators are given in Table 1 where P is in MWand
$ is a monetary unit that may be scaled by any arbitrary constant with-
out affecting the results.
The generation schedule obtained from optimal dispatch without
considering the line flow limit and FACTS devices was 86.0, 108.0,
103.7, and 200.4 MWfor generators 1, 2, 3, and 4, respectively. With this
generation schedule, it was found that the real power flows in lines were
within the rating limit except line-2, which was 96.8 MW. The rating of
each line is given in Table 2. Sensitivities were calculated for FACTS de-
vices (TCSCand TCPAR) placed in every line one at a time for this oper-
ating condition. The sensitivities of the real power performance index
with respect to TCSC and TCPAR are presented in Table 2. The highest
negative sensitivities in the case of TCSC and the highest absolute value
of sensitivities in the case of TCPAR are presented in bold type.
The sensitivity factor of TCSC for line-4 is the most negative com-
pared to the other lines and, hence, the most suitable for the TCSC
placement. Branches 2 and 12 are the most sensitive for TCPAR place-
ment but have not been considered due to connecting the tertiary wind-
ing of the transformer. The next choices for placement of TCPAR
would be line-4 and line-8. Table 2 also shows that the placement of
TCPAR in line-8 is the other choice as the magnitude of sensitivity fac-
tors is the next highest. This sensitivity is positive, which indicates that
the phase angle shift of the TCPAR should be negative.
The optimal dispatch, described in the second section of this letter
[(1)-(3)], with TCSCin line-4, TCPARin line-4, and in line-8, taken one
at a time, was obtained and presented in Table 3. Table 3 also shows the
optimal dispatch without FACTS devices (base case). The optimal value
of capacitive reactance of TCSCplaced in line-4 was 0.0132 pu. This in-
dicates that 5.93 % of compensation is optimal. However, the optimal
values of phase angle of TCPARplacement in line-4 and line-8 were 5.77
and -3.95 , respectively. The placement of TCPAR in line-4 gives less
pool generation price compared to other cases. The variation of optimal
pool real power generation with each FACTS device is very small.
Conclusions: In this letter, a sensitivity-based approach has been
developed for determining the optimal placement of FACTS devices in
an electricity market having pool and contractual dispatches. In a sys-
tem, first, the few locations of FACTS devices can be decided based on
the sensitivity factors a
k
c
and a
k
s
and then the optimal dispatch problem
is solved to select the optimal location and parameter settings. Test re-
sults obtained on a test system show that new sensitivity factors along
with FACTS device cost could be effectively used for optimal location
of FACTS devices.
References:
[1] N.G. Hingorani, Flexible AC transmission, IEEE Spectrum,
pp. 40-45, Apr. 1993.
[2] R. Rajaraman, F. Alvarado, A. Maniaci, R. Camfield, and S.
Jalali, Determination of location and amount of series compensation
to increase power transfer capability, IEEETrans. Power Syst., vol. 13,
pp. 294-299, May 1998.
[3] E.J. de Oliveri, J.W.M. Lima, and J.L.R. Pereira, Flexible AC
Transmission system devices: Allocation and transmission pricing,
Electric Power and Energy Syst., vol. 21, pp. 111-118, 1999.
[4] S.N. Singh and A.K. David, Congestion management by
otimising FACTS device allocation, in Proc. Int. Conf. Electric Utility
Deregulation and Restructuring and Power Technologies 2000, City
University, London, 4-7 April 2000, pp. 23-28.
[5] R.S. Fang and A.K. David, Optimal dispatch under transmis-
sion contracts, IEEE Trans. Power Syst., vol. 14, pp. 732-737, May
1999.
Copyright Statement: ISSN 0282-1724/01/$10.00 2001 IEEE.
Manuscript received 18 January 2001. This paper is published herein in
its entirety.
60 IEEE Power Engineering Review, September 2001

Anda mungkin juga menyukai