SCHOOL OF NAVAL ARCHITECTURE AND OCEAN ENGINEERING INDIAN MARITIME UNIVERSITY VISHAKAPATNAM CAMPUS
PROJECT GUIDE SUBMITTED BY Sri U.S RAMESH CHIEF MANAGER,SMDR TECH (NA-OE) VISHAKAPATNAM 2011-13 BATCH PRAMOD K.B M-
IMU-VISHAKAPATNAM CAMPUS
Page 1
OBJECTIVE: The main objective of the project is to estimate the cost of construction of the given vessel from the empirical formulae recommended by J Carreyette. and analyse for an optimal technique for cost estimation during design stage of a Ship.
Name of Vessel Operator (NCAOR) Owner Date of commission : : : : O.R.V SAGAR KANYA National Centre for Antarctic and Ocean Research Ministry of Earth Sciences ,Government of India. March 1983
Vessel Parameters
Length over all Length ,LBP Breadth overall Depth to main deck Draught Mass displacement Gross Tonnage Net Tonnage Vol.displacement Engine Electric propulsion Speed Endurance m m m m m tonne 1554.5 s 4209 RT 1029 RT 1516.585 m3 2x1230 kw 14.25 knots 45 days/10,000 nautical miles 100.34 89 16.39 9.8 5.6
IMU-VISHAKAPATNAM CAMPUS
Page 2
Introduction
In recent years, there is severe competition in the shipbuilding industry due to the increased shipbuilding capacity compared with demand. The shipbuilding yard has to deal with a highly variable product that makes bidding on contracts very difficult. The pricing for new shipbuilding could have a high risk especially with minimal profit margins and precious little time available. To reduce such risk in estimation, there should be a quick and accurate means to accomplish reasonable and reliable cost estimate method. Cost is concerned with how much money the shipbuilder will pay for shipyard labour to build the ship ,subcontractors to assist ,all materials and equipment contained in the completed vessel, miscellaneous services and establishment charges.
Methodology
IMU-VISHAKAPATNAM CAMPUS
Page 3
IMU-VISHAKAPATNAM CAMPUS
Page 5
IMU-VISHAKAPATNAM CAMPUS
Page 6
1)
Labour costs
The estimation of labour man-hours for ship production is considered an important item during the early stage of negotiation before signing the contract. With few information about the ship during the preliminary design stage, it is necessary to apply a good prediction method for estimating the ship production man-hours
H=xn
IMU-VISHAKAPATNAM CAMPUS
Page 7
a)
If Rh-actual man hours per tonne of net steel Cb-block coefficient at laden summer draught Ws-net steelweight in tonnes L-LBP in metres A'-factor from table 1
IMU-VISHAKAPATNAM CAMPUS
Page 8
A plot of' A' for different wage rates Assuming overheads as 100% ,value of A' was plotted as shown and for a wage rate of 3.78 /hr, A' was obtained to be 3580 Total steelwork labour costs
H = RhWs = A'*Ws2/3L1/3 / Cb
= 3580 1.44224482/3 891/3/ 0.5798 = 10015617 Determination of Cb,Steel weight,outfit weight and machinery weight is given in APPENDIX 1.
Co1=C'Wo2/3
Where Co1-total cost of outfit labour C'-factor given in table 2 Wo-outfit weight,tonnes Table 2
Average wage rate of direct labour /hr 1.6 2 2.4 75% 8350 10425 12500 Overheads 100% 9550 11925 14300 125 % 1075 0 1342 5 1610 0
IMU-VISHAKAPATNAM CAMPUS
Page 10
From this corresponding to a wage rate of 7.16 /hr value of C'=42677 Total outfit labour costs = 42677 628.09 = 6260023.6
2/3
IMU-VISHAKAPATNAM CAMPUS
Page 11
CM1=F'P0.82
CM1-total cost of Machinery installation labour F'-factor given in table 3 P-Service propulsive horsepower
Table 3
Average wage rate of direct labour /hr 1.6 2 2.4 Overheads 75% 323 404 485 100% 369 461 553 125% 415 519 622
IMU-VISHAKAPATNAM CAMPUS
Page 12
A plot of' F' for different wage rates From this corresponding to a wage rate of 7.16 /hr value of F'=1650
2) Material costs
a) Steel material costs
IMU-VISHAKAPATNAM CAMPUS
Page 13
Csm=B'Ws
CsM-total steel material cost B'-factor given in table 4 Ws-net steelweight,tonnes Table 4
Average price of shipbuilding steel /tonne 150 200 250 Wastage +welding rods 8% 178 237 296 10% 182 242 303 13% 186 248 310
IMU-VISHAKAPATNAM CAMPUS
Page 14
A plot of' B' for different prices of steel From this corresponding to a steel rate of 146 /tonne value of B'=181.2 Total steel material costs = 181.2 2448.582 = 889922
IMU-VISHAKAPATNAM CAMPUS
Page 15
Com=D'Wo0.95
CoM-total steel material cost D'-factor given in table 5 Wo-outfit weight,tonnes Table 5
DATE Jun-75 Jun-76 Jun-77 D' 1500 1725 2011
Taking linear extrapolation in june 1983 D'= 3550 Total outfit material costs = 3231334.99
IMU-VISHAKAPATNAM CAMPUS
Page 16
c) Machinery cost
CM=G'P0.82
CM-total cost of Machinery G'-factor given in table 6 P-Service propulsive horsepower Table 6
DATE Jun-75 Jun-76 Jun-77 G' 735 845 980
Taking linear extrapolation in june 1983 F'= 1715 Total Machinery Installation costs = 1422396.5
IMU-VISHAKAPATNAM CAMPUS Page 17
3)
Additional cost
a) Thrusters
CT=48000+3500 0Tt
CT-cost at mid '77 rates
Tt-thrust in tonnes
(Assuming 20 % escalation)
IMU-VISHAKAPATNAM CAMPUS
Page 18
b) Stabilisers
CST = 3313/4
CST-cost at mid '77 rates()
IMU-VISHAKAPATNAM CAMPUS
Page 19
(Assuming 20 % escalation)
Where
And
IMU-VISHAKAPATNAM CAMPUS
Page 21
Assumptions
Vessel is built with 75%-85% Grade 'A' steel and remaining B,E,AH,DH or EH.No other material like Aluminium is accounted for.
Page 22
IMU-VISHAKAPATNAM CAMPUS
This estimate does not take into account research equipment onboard or special cargo handling devices,winches etc.
APPENDIX 1.
Determination of block coefficient Cb
We Know
Mass Displacement
=LBTCb1.005
So
IMU-VISHAKAPATNAM CAMPUS Page 23
Cb =/(L BT 1.005)
= 4855/(8916.395.61.0251.005)
= 0.5798
Steel Weight:
= 2267.2
= 2342.32
Where
IMU-VISHAKAPATNAM CAMPUS
Page 24
E=L(B+T)+0.85L(D-T)+0.85(l1*h1)+0.75*(l2*h2)
= 2937.421
=0.2934
Machinery Weight:
=437.08 tons
IMU-VISHAKAPATNAM CAMPUS Page 25
= 414.4 tonne
WO = Co (CN/1000) 0.825
where Co = 2103 (A constant between 2103 & 2412) H. Benford CN - cubic number = (LBD/1000)
IMU-VISHAKAPATNAM CAMPUS
Page 26
= 422.54 tonnes
where CHE = 1023 (A constant between 1023 & 1196) H. Benford CN - cubic number = (LBD/1000)
= 205.54 tonnes
IMU-VISHAKAPATNAM CAMPUS
Page 27
REFERENCES
1)
J. Carreyette- Priliminary ship cost estimation,RINA,1977 Mishra S.C - Priliminary Ship Design,IMUVisakhapatnam Ahmad .M.Rashwan Estimation of ship Production manhours,Alexandria university,Egypt.
2)
3)
R. Munro-Smith Elements of shp desgn, (19751995) H. Schneekluth and V. Bertram- Ship Design for Efficiency and Economy,1998.
6)
********************
IMU-VISHAKAPATNAM CAMPUS
Page 28
IMU-VISHAKAPATNAM CAMPUS
Page 29