Anda di halaman 1dari 29

COST ESTIMATION TECHNIQES IN SHIPBUILDING

REPORT ON COST ESTIMATION OF O.R.V SAGAR KANYA

SCHOOL OF NAVAL ARCHITECTURE AND OCEAN ENGINEERING INDIAN MARITIME UNIVERSITY VISHAKAPATNAM CAMPUS

PROJECT GUIDE SUBMITTED BY Sri U.S RAMESH CHIEF MANAGER,SMDR TECH (NA-OE) VISHAKAPATNAM 2011-13 BATCH PRAMOD K.B M-

IMU-VISHAKAPATNAM CAMPUS

Page 1

COST ESTIMATION TECHNIQES IN SHIPBUILDING

OBJECTIVE: The main objective of the project is to estimate the cost of construction of the given vessel from the empirical formulae recommended by J Carreyette. and analyse for an optimal technique for cost estimation during design stage of a Ship.
Name of Vessel Operator (NCAOR) Owner Date of commission : : : : O.R.V SAGAR KANYA National Centre for Antarctic and Ocean Research Ministry of Earth Sciences ,Government of India. March 1983

Vessel Parameters
Length over all Length ,LBP Breadth overall Depth to main deck Draught Mass displacement Gross Tonnage Net Tonnage Vol.displacement Engine Electric propulsion Speed Endurance m m m m m tonne 1554.5 s 4209 RT 1029 RT 1516.585 m3 2x1230 kw 14.25 knots 45 days/10,000 nautical miles 100.34 89 16.39 9.8 5.6

IMU-VISHAKAPATNAM CAMPUS

Page 2

COST ESTIMATION TECHNIQES IN SHIPBUILDING

Introduction
In recent years, there is severe competition in the shipbuilding industry due to the increased shipbuilding capacity compared with demand. The shipbuilding yard has to deal with a highly variable product that makes bidding on contracts very difficult. The pricing for new shipbuilding could have a high risk especially with minimal profit margins and precious little time available. To reduce such risk in estimation, there should be a quick and accurate means to accomplish reasonable and reliable cost estimate method. Cost is concerned with how much money the shipbuilder will pay for shipyard labour to build the ship ,subcontractors to assist ,all materials and equipment contained in the completed vessel, miscellaneous services and establishment charges.

Methodology

IMU-VISHAKAPATNAM CAMPUS

Page 3

COST ESTIMATION TECHNIQES IN SHIPBUILDING

Compensated Gross tonnage


The Compensated Gross Tonnage, CGT, is considered as a worldwide yardstick for shipyard output in commercial shipbuilding replacing the traditional measures, manhours/tonne steel weight, and this concept have been developed from 1960s.This coefficient reflects the amount of work necessary to produce that particular type and size of ship.One gross ton of a passenger ship, for example, with its sophisticated accommodation and public spaces, contains a significantly greater level of work content than one gross ton of a bulk carrier which is effectively little more than a large steel box with an engine on the back.One CGT of either ship on the other hand should contain roughly equivalent work content.The system has now been highly developed and is fundamental to the analysis of shipbuilding activity.
IMU-VISHAKAPATNAM CAMPUS Page 4

COST ESTIMATION TECHNIQES IN SHIPBUILDING

For a general cargo vessel

CGTCARGO = 27* (4209^0.64)


= 5634.278 For Research vessel (NCCV)

CGTR.V = 46* (4209^0.62)


= 8123 Dividing both we get a factor of 1.442 which is multiplied with steel ,outfit labour and material costs respectively

IMU-VISHAKAPATNAM CAMPUS

Page 5

COST ESTIMATION TECHNIQES IN SHIPBUILDING

IMU-VISHAKAPATNAM CAMPUS

Page 6

COST ESTIMATION TECHNIQES IN SHIPBUILDING

1)

Labour costs

The estimation of labour man-hours for ship production is considered an important item during the early stage of negotiation before signing the contract. With few information about the ship during the preliminary design stage, it is necessary to apply a good prediction method for estimating the ship production man-hours

If H- man hours x - size variable -constant n<=1

H=xn

IMU-VISHAKAPATNAM CAMPUS

Page 7

COST ESTIMATION TECHNIQES IN SHIPBUILDING

a)

Steel work manhours

If Rh-actual man hours per tonne of net steel Cb-block coefficient at laden summer draught Ws-net steelweight in tonnes L-LBP in metres A'-factor from table 1

Rh= A' / [Cb(Ws/L)1/3]


Table 1
Average wage rate of direct labour /hr 1.6 2 2.4 Overheads 75% 700 875 1050 100% 800 1000 1200 125% 900 1125 1350

IMU-VISHAKAPATNAM CAMPUS

Page 8

COST ESTIMATION TECHNIQES IN SHIPBUILDING

A plot of' A' for different wage rates Assuming overheads as 100% ,value of A' was plotted as shown and for a wage rate of 3.78 /hr, A' was obtained to be 3580 Total steelwork labour costs

H = RhWs = A'*Ws2/3L1/3 / Cb
= 3580 1.44224482/3 891/3/ 0.5798 = 10015617 Determination of Cb,Steel weight,outfit weight and machinery weight is given in APPENDIX 1.

b) Outfit labour cost


IMU-VISHAKAPATNAM CAMPUS Page 9

COST ESTIMATION TECHNIQES IN SHIPBUILDING

Assuming no subcontracting,We have

Co1=C'Wo2/3
Where Co1-total cost of outfit labour C'-factor given in table 2 Wo-outfit weight,tonnes Table 2
Average wage rate of direct labour /hr 1.6 2 2.4 75% 8350 10425 12500 Overheads 100% 9550 11925 14300 125 % 1075 0 1342 5 1610 0

IMU-VISHAKAPATNAM CAMPUS

Page 10

COST ESTIMATION TECHNIQES IN SHIPBUILDING

A plot of' C' for different wage rates

From this corresponding to a wage rate of 7.16 /hr value of C'=42677 Total outfit labour costs = 42677 628.09 = 6260023.6
2/3

IMU-VISHAKAPATNAM CAMPUS

Page 11

COST ESTIMATION TECHNIQES IN SHIPBUILDING

c) Machinery Installation labour cost


Assuming no subcontracting,We have

CM1=F'P0.82
CM1-total cost of Machinery installation labour F'-factor given in table 3 P-Service propulsive horsepower

Table 3
Average wage rate of direct labour /hr 1.6 2 2.4 Overheads 75% 323 404 485 100% 369 461 553 125% 415 519 622

IMU-VISHAKAPATNAM CAMPUS

Page 12

COST ESTIMATION TECHNIQES IN SHIPBUILDING

A plot of' F' for different wage rates From this corresponding to a wage rate of 7.16 /hr value of F'=1650

Total Machinery Installation costs = 1650 1.15 3058


0.82

= 1368861.62 (Accounting 15% increase for twin screw ships.)

2) Material costs
a) Steel material costs

IMU-VISHAKAPATNAM CAMPUS

Page 13

COST ESTIMATION TECHNIQES IN SHIPBUILDING

Csm=B'Ws
CsM-total steel material cost B'-factor given in table 4 Ws-net steelweight,tonnes Table 4
Average price of shipbuilding steel /tonne 150 200 250 Wastage +welding rods 8% 178 237 296 10% 182 242 303 13% 186 248 310

IMU-VISHAKAPATNAM CAMPUS

Page 14

COST ESTIMATION TECHNIQES IN SHIPBUILDING

A plot of' B' for different prices of steel From this corresponding to a steel rate of 146 /tonne value of B'=181.2 Total steel material costs = 181.2 2448.582 = 889922

Total steel material costs

IMU-VISHAKAPATNAM CAMPUS

Page 15

COST ESTIMATION TECHNIQES IN SHIPBUILDING

b) Outfit material costs

Com=D'Wo0.95
CoM-total steel material cost D'-factor given in table 5 Wo-outfit weight,tonnes Table 5
DATE Jun-75 Jun-76 Jun-77 D' 1500 1725 2011

Taking linear extrapolation in june 1983 D'= 3550 Total outfit material costs = 3231334.99

IMU-VISHAKAPATNAM CAMPUS

Page 16

COST ESTIMATION TECHNIQES IN SHIPBUILDING

c) Machinery cost

CM=G'P0.82
CM-total cost of Machinery G'-factor given in table 6 P-Service propulsive horsepower Table 6
DATE Jun-75 Jun-76 Jun-77 G' 735 845 980

Taking linear extrapolation in june 1983 F'= 1715 Total Machinery Installation costs = 1422396.5
IMU-VISHAKAPATNAM CAMPUS Page 17

COST ESTIMATION TECHNIQES IN SHIPBUILDING

(Accounting 15% increase for twin screw ships.)

3)

Additional cost
a) Thrusters

CT=48000+3500 0Tt
CT-cost at mid '77 rates

Tt-thrust in tonnes

Total thruster costs = 389820.35

(Assuming 20 % escalation)

IMU-VISHAKAPATNAM CAMPUS

Page 18

COST ESTIMATION TECHNIQES IN SHIPBUILDING

b) Stabilisers

CST = 3313/4
CST-cost at mid '77 rates()

IMU-VISHAKAPATNAM CAMPUS

Page 19

COST ESTIMATION TECHNIQES IN SHIPBUILDING

-Volume displ. In tonnes.

Total stabiliser costs = 231020.84

(Assuming 20 % escalation)

Total cost of Vessel


IMU-VISHAKAPATNAM CAMPUS Page 20

COST ESTIMATION TECHNIQES IN SHIPBUILDING

The total cost of ship is defined as follows:

Total cost = Total Labour cost + Total material cost

Where

Total Labour cost = Direct Labour cost + Overheads +Profit

And

Total Materials cost = Suppliers cost + Handling and wastage + Profit

IMU-VISHAKAPATNAM CAMPUS

Page 21

COST ESTIMATION TECHNIQES IN SHIPBUILDING

Total cost = 23808897

= 36903945.42 (INR) (thirty seven million approximately)

Assumptions

Vessel is built with 75%-85% Grade 'A' steel and remaining B,E,AH,DH or EH.No other material like Aluminium is accounted for.
Page 22

IMU-VISHAKAPATNAM CAMPUS

COST ESTIMATION TECHNIQES IN SHIPBUILDING

No part of the ship is built by subcontracters

Overheads are taken to be 100% and profit as 10%.

Complexity of construction in steelwork is neglected.

This estimate does not take into account research equipment onboard or special cargo handling devices,winches etc.

No life cycle costs have been considered.

APPENDIX 1.
Determination of block coefficient Cb

We Know

Mass Displacement
=LBTCb1.005

So
IMU-VISHAKAPATNAM CAMPUS Page 23

COST ESTIMATION TECHNIQES IN SHIPBUILDING

Cb =/(L BT 1.005)

= 4855/(8916.395.61.0251.005)

= 0.5798

Steel Weight:

Watson & Gilfan.

= 2267.2

= 2342.32

Where

K- constant for different vessels E- Hull numeral

IMU-VISHAKAPATNAM CAMPUS

Page 24

COST ESTIMATION TECHNIQES IN SHIPBUILDING

k= 0.045 for research vessels.

E=L(B+T)+0.85L(D-T)+0.85(l1*h1)+0.75*(l2*h2)

= 2937.421

=0.2934

Optimising. and taking 8% margin for scrap weight.

Wst= 2448.582 tonnes

Machinery Weight:

Wm = (0.98) BHP / 10 + 200 Munrosmith

=437.08 tons
IMU-VISHAKAPATNAM CAMPUS Page 25

COST ESTIMATION TECHNIQES IN SHIPBUILDING

= 414.4 tonne

( Taking 10% more for twin screw engines.)

Total Outfit Weight:

Outfit weight is divided into outfit and hull eqipment weight

outfit weight is calculated as follows

WO = Co (CN/1000) 0.825

where Co = 2103 (A constant between 2103 & 2412) H. Benford CN - cubic number = (LBD/1000)

IMU-VISHAKAPATNAM CAMPUS

Page 26

COST ESTIMATION TECHNIQES IN SHIPBUILDING

= 422.54 tonnes

Hull equipment weight is calculated as follows

WHE = CHE(CN/1000) 0.825

where CHE = 1023 (A constant between 1023 & 1196) H. Benford CN - cubic number = (LBD/1000)

= 205.54 tonnes

Total outfit weight= 628.04 tonnes

IMU-VISHAKAPATNAM CAMPUS

Page 27

COST ESTIMATION TECHNIQES IN SHIPBUILDING

REFERENCES

1)

J. Carreyette- Priliminary ship cost estimation,RINA,1977 Mishra S.C - Priliminary Ship Design,IMUVisakhapatnam Ahmad .M.Rashwan Estimation of ship Production manhours,Alexandria university,Egypt.

2)

3)

4) Watson,D.G.M and GILFILLAN,A.W.:Some Ship Design Methods.Trans.RINA,Vol 119,1977,p 279.


5)

R. Munro-Smith Elements of shp desgn, (19751995) H. Schneekluth and V. Bertram- Ship Design for Efficiency and Economy,1998.

6)

********************

IMU-VISHAKAPATNAM CAMPUS

Page 28

COST ESTIMATION TECHNIQES IN SHIPBUILDING

IMU-VISHAKAPATNAM CAMPUS

Page 29

Anda mungkin juga menyukai