MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation

Project (NCRMP) Andhra Pradesh (RFP#TPQA/NCRMP/AP-PIU/1, Credit#4772-IN)

in Joint Venture with

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP) Andhra Pradesh (RFP#TPQA/NCRMP/AP-PIU/1, Credit#4772-IN)
INDEX

1.0

Project Background

2.0

Third Party Quality Audit Consultant

3.0

Review meetings and Major Events of this Month

4.0

Status of TPQA Visits

5.0

Progress of NCRMP works

6.0

District wise status of tests conducted by TPQA

16

7.0

Details of Audit Reports Submitted during this Month

17

8.0

Observations of Submitted Reports

17

9.0

Details of Social & Environmental Reports Submitted in this Month

25

10.0

Photographs of site visits & Important Events During this month

27

in Joint Venture with

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP) Andhra Pradesh (RFP#TPQA/NCRMP/AP-PIU/1, Credit#4772-IN)

1.0 Project Background


Andhra Pradesh (AP) state has one of the longest coastal belt in India. Out of 67,362 Km of road network in the state, the nine coastal districts cover 26,000 km of road length. Every year during the period of April-May and September-December, cyclonic situations set in to the Bay of Bengal. With the recent changes in climatic conditions, the catastrophic events are increasing resulting in very devastating cyclones like Laila, Jal etc where the loss is enormous. In the 97 years ranging from 1892 to 1989, there were as many as 67 cyclones within the State. It is essential to provide safe residential accommodation to the vulnerable population during any eventuality or disaster due to natural calamities such as cyclones and associated tidal waves and storm surges. The project is formulated based on experiences of Government of Andhra Pradesh in mitigating such disasters during the past and also keeping in view the existing facilities available in the project area in Andhra Pradesh. The Government of India has applied for a credit of US$ 255 Million equivalent from the International Development Association (IDA) toward the cost of National Cyclone Risk Mitigation Project (NCRMP), and it intends to apply the proceeds to payments for goods, works, related services and consulting services under this Project. National Cyclone Risk Mitigation Project (NCRMP) Project Implementation Unit (PIU), Andhra Pradesh, headquartered at Hyderabad has invited the consultants to submit proposals for providing the consultancy services for Third Party Quality Audit for 9 coastal districts namely Srikakulam, Vijayanagarm, Visakhapatnam, East Godavari, West Godavari, Krishna, Guntur, Prakasam and Nellore. The project Construction of Multipurpose Cyclone Shelters, Roads to Cyclone Shelters, Roads to habitations and Roads & Bridges under NCRMP is funded by International Development Association and received through Government of India. This consultancy is envisaged to audit the quality of works being implemented by various line departments working under PIU. The number of works under progress / for which

agreements are concluded in each district is shown in the table below.


No. of works(Under Concluded Agreements) No. of works under Progress RHB RCS MPCS Bridges Roads (R&B) No. of works not started

District Srikakulam Vizianagaram Visakhapatnam East Godavari West Godavari Krishna Guntur Prakasham Nellore

RHB

RCS

MPCS

Bridges

Roads (R&B)

Total

6 8 2 10 5 3 14 14

1 6

4 2 2 1 -

1 1 -

11 3 8 3 10 5 5 15 20

6 8 2 0 5 2 13 14

1 6

3 2 2 1

1 1 -

1 0 0 0 10 0 1 1 0

in Joint Venture with

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP) Andhra Pradesh (RFP#TPQA/NCRMP/AP-PIU/1, Credit#4772-IN)

20 18 16 14 12 10 8 6 4 2 0

Details of works

Total no. of works Not Started Total no. of works Progress

2.0

Third Party Quality Audit Consultant.

To provide Consulting Services of Third Party Quality Auditor for Construction of Multipurpose Cyclone Shelters, Roads to Cyclone Shelters, Roads to habitations, and Roads and Bridges under NCRMP in 9 coastal districts The Commissioner for Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP has selected Egis International in JV with Egis India Consulting Engineers (I) Pvt. Ltd. On 31 May2011, the Contract for Consultancy Service was signed between The Commissioner for Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP and the Egis International in JV with Egis India Consulting Engineers (I) Pvt. Ltd. 3.0 Review Meetings and Major Activities of this month
st

The details of review meetings attended and the details of workshops attended in this are are as follows. S.No. 1 Place Guntur Activity Review meeting by SE, PR, Guntur Date 02.09.2011 Remarks Meeting was organized to review the progress and issues of NCRMP works. Meeting was organized to review the progress and issues of NCRMP works Introduction of PMC, and brief description of activities of PMC in Phase 1 &2, and activities of EPTRI for Phase 2 Two bridge works taken up by R&B, Guntur, were inspected

Vizianagaram

Review meeting by SE, PR, Vizianagaram

07.09.2011

Chambers of the CDM & EOPS & PD NCRMP.

Kick Off meeting arranged for starting the PMC Activities by M/s Feedback Ventures India Ltd

15.09.2011

Bapatla, Guntur

NCRMP works review by Shri. M. Sasidhar Reddy, Vice chairmen,

17.09.2011

in Joint Venture with

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP) Andhra Pradesh (RFP#TPQA/NCRMP/AP-PIU/1, Credit#4772-IN)
DM, followed by works inspection Guntur works by PD, NCRMP, Hyderabad. 5 Guntur, Hotel Sinduri One day State level workshop for contractors on World Bank procurement guidelines organized by PIU, NCRMP 20.09.2011 by PD, NCRMP.

All the contractors, Department Officers from R&B and PR of West Godavari, Krishna, Guntur, Prakasham and Nellore along with TPQA and PMC of NCRMP had participated in the workshop. Following Three works were inspected. 1. Road from Vempadu to Patimeeda, 2. Road from R&B road to Mulaparra upto Beach end, 3. Road from R & B road to Venkayyapalem All the contractors, Department Officers from R&B and PR of East Godavari, Visakhapatnam, Vizainagram, and Srikakulam along with TPQA and PMC of NCRMP had participated in the workshop

Visakhapatnam NCRMP works inspection

Inspection of NCRMP works of Visakhapatnam by SE, PIU, NCRMP and EE, PIU, NCRMP, Hyderabad.

21.09.2011

Visakhapatnam, Hotel Meghalaya

One day State level workshop for contractors on World Bank procurement guidelines organized by PIU, NCRMP

22.09.2011

4.0

Status of TPQA Visits:

The following table shows the details of TPQA visits to sites in respective districts. District Up to Aug'2011 Srikakulam Vizianagaram Vishakapatnam East Godavari West Godavari Krishna Guntur Prakasam Nellore 33 30 36 27 28 29 36 53 50 Total Number of Visits In Sept.'2011 29 6 12 16 12 8 17 17 23 Up to Sept'2011 62 36 48 43 40 37 53 70 73

in Joint Venture with

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP) Andhra Pradesh (RFP#TPQA/NCRMP/AP-PIU/1, Credit#4772-IN)
80 70 60 50 40 30 20 10 0 In Sept.'2011 Up to Aug'2011

No. of Visits by TPQA

5.0

Progress of NCRMP works:

The district wise progress of works is shown below. The works in the West Godavari are not started and the works in Krishna District has just started. At many places the first milestone is completed but works are not started. The line departments are to analyze the reasons for the slow progress and if necessary penalty for the slow progress as per the agreement conditions should be imposed.

Third Party Quality Audit by Egis India consulting services Summary of Activities Agreements for Packages Communicated PR R&B 3 0 6 3 3 3 2 8 13 40 5 3 0 0 0 0 2 1 0 11

S.No. 1 2 3 4 5 6 7 8 9

District Srikakulam Vizianagaram Visakhapatnam East Godavari West Godavari Krishna Guntur Prakasham Nellore Total

Status of works Progress 10 3 8 3 0 5 4 15 20 68 Not Started 1 0 0 6 10 0 1 0 0 18 51 86 81

Total Packages for which Agreements are received Total Number of works in the above packages Total number of packages for which tenders were accepted

in Joint Venture with

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Status of works in Srikakulam District up to 30.09.2011 Category Packages allotted under Phase - 1 Agreement No. / Date Road from DPN R&B road to /2010-11, Dt. Uddandapalem 30.04.2011 NCRMP/BRoad from K. Umilada Junction to Koduru /2010-11, Dt. W/AP/RHB/PRED/01/Santhab (Link Road) 30.04.2011 ommali/003 Road from Borubhadra, Malagam to /2010-11, Dt. Kollipadu via Seepuram, Gantapeta 30.04.2011 Road from R&B road Mobagam to /2010-11, Dt. NCRMP/BDuubakavanipeta via Gajapathinagaram 30.04.2011 W/AP/RHB/PRED/01/Polaki/0 Road from Talasamudram to Dola /2010-11, Dt. 06 Regulator 30.04.2011 NCRMP/BRoad from R&B road Edulavalasa - Killam /2011-12, Dt. W/AP/RHB/PRED/01/Polaki/0 to Jonnam via Talasamudram 30.04.2011 05 Construction of bridge at Km 11/6-8 of NHNCRMP/B-W/ AP/Br/R&B/01/ 46/2011, Dt. 5 to Patnavanipeta Connecting Patnavanipeta/001 17.12.2010 Sundarapalem Construction of Minor Bridge at Km 12/2-4 NCRMP/B-W/AP/Br/R&B/01/ 45/2010of NH-5 to Surampeta Road via Naruva, Surampeta/003 2011,Dt17.12.2010 mentada NCRMP/BConstruction of High level bridge across 1/2010,Dt.11.11.20 W/AP/Br/R&B/01/Bendigedda/ Bendi gedda at KM 4/10 of Pundi10 004 Parlakimidi road in Srikakulam Dt, A.P. NCRMP/BImprovesments Naupada-Venkatapuram 43/2010W/AP/RD/R&B/01/Nowpada/0 road from 0/0to15/0km 11,17.12.2010 06) Names of works under each package DHS 30.04.11 30.04.11 30.04.11 30.04.11 30.04.11 30.04.11 DFC 30.04.12 30.04.12 30.04.12 30.04.12 30.04.12 31.01.12 Progress up to 30.09.2011 Earthwork & CD works &GSB Earthwork & CD works &GSB Earthwork & CD works &GSB Earthwork & CD works &GSB Earthwork & CD works &GSB Earthwork & CD works &GSB Foundation upto well caping Completion upto below the Deck slab. Foundation upto well caping WMM Shoulders in progress

RHB

17.12.10

17.06.12

Bridges

17.12.10

17.03.12

11.11.10

11.05.12

Roads

17.12.10

17.03.12

in Joint Venture with

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of works in Vizianagaram District up to 30.09.2011

Category

Packages allotted under Phase - 1

Names of works under each package

Agreement No./ Date


31/2010-2011 Dt. 1.12.2010

DHS

DFC

Progress up to 30.09.2011
30.96% of work completed

Bridges

Road (R&B)

Construction of Minor Bridge at Km. 7/2 near Puligadda of Konada NCRMP/ B-W/ AP/ Br/ R&B/ Ramatheertham R&B Road to 02/ Puligadda/ 007 Konathalapalem via Yerukonda, Pasupam, Kollayavalasa (Z.P. Road) Construction of Minor Bridge at Km 15/2 near Chakaligedda of Konada NCRMP/ B-W/ AP/ Br/ R&B/ Ramatheertham R&B road to 02/ Chakaligadda / 008 Konatalapalem (via) Yerukonda, Pasupam, Kollayavalasa (ZP Road) Improvements to Road from Konada Ramatheertham (R&B) Road to NCRMP/B-W/AP/RD/R&B/ Konathalapalem (Via) Pasupam, 02/ Konada/009 Yerukonda, Kollayavalasa from Km 12/0 to 16/5 (Km 0/0 to 4/0 i.e. upto NH-5 crossing)

01.12.10

31.05.12

34/2010-2011 Dt. 8.12.2010

08.12.10

07.06.12

55.19% of work completed

33/2010-2011 Dt. 8.12.2010

08.12.10

07.03.12

95% of work completed

in Joint Venture with

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of works in Visakhapatnam District up to 30.09.2011 Category Packages allotted under Phase - 1 Names of works under each package
Road from Vempadu to Patimeeda

Agreement No. / Date


/2010-11, Dt. 11.01.2011 /2010-11, Dt. 11.01.2011 /2010-11, Dt. 10.03.2011 /2010-11, Dt. 28.03.2011 /2010-11, Dt. 28.03.2011 /2010-11, Dt. 11.01.2011 /2011-12, Dt. 27.04.2011 /2011-12, Dt. 27.04.2011

DHS
11.01.11

DFC
11.01.12

Progress up to 30.09.2011
Road furniture & Shoulders work in progress Road furniture & Shoulders work in progress GSB Completed GSB Completed WBM Gr.-III & Shoulders work is in progrress B.T, Road furniture & Shoulders work is in progrress WBM Gr.-III & Shoulders work is in progrress WBM Gr.-III & Shoulders work is in progress

NCRMP/BW/AP/RHB/PRED/03/Nakkap alli/001 Road from R&B road to Mulaparra upto Beach end NCRMP/BW/AP/RHB/PRED/03/Ananda puram/003 Road from R&B B.P Kallalu to Matchvanipalem

11.01.11

27.10.11

10.03.11 28.03.11 28.03.22

09.12.11 27.12.11 28.12.11

RHB

Road from R & B road to Pothu Rajannapalem NCRMP/BW/AP/RHB/PRED/03/Paravad a/004 Road from R & B road to Jalaripeta NCRMP/BW/AP/RHB/PRED/03/Rambilli /006 NCRMP/BW/AP/RHB/PRED/03/Atchuta puram/007 Road from R & B road to Venkayyapalem Road from R&B road to AvaSomavaram Road from R&B Road to Avarajam

11.01.11

11.10.11

27.04.11

26.01.12

27.04.11

26.01.12

in Joint Venture with

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of works in East Godavari District up to 30.09.2011 Category Packages allotted under Phase - 1 Names of works under each Agreement No. / Date package ROAD FROM APPROCH ROAD TO CYCLONE SHELTER AT /2011-12, Dt. ADAVIPUDI IN E.G.Dt. 20.05.2011 ROAD FROM GURAJANAPALLI TO BANDULAVARIPALEM ROAD FROM PR ROAD TO DASARIVANIPETA AND TO CYCLONE SHELTER /2011-12, Dt. 27.04.2011 /2011-12, Dt. 27.04.2011 DHS DFC Progress up to 30.09.2011 20% of work Completed 10% of work Completed 30% of work Completed

NCRMP/B-W/ AP/RCS/PRED/04/ KARAPA/001 RHB NCRMP/B-W/ AP/RHB/PRED/04/ KATRENIKONA/003

20.05.11

19.02.2012

27.04.11

26.01.2012

27.04.11

26.01.2012

in Joint Venture with

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Status of works in West Godavari District up to 30.09.2011 Category Packages allotted under Phase - 1 Names of works under each package Road from NH 214 A at Ranga Statue center to Harijanawada of Kalipatnam (E) (Mogalthuru Mandal W.G.Dist.) R&B road at Panchayat Office to Pulaparthivarithota via Badava (Mogalthuru Mandal W.G.Dist.) Mogalthuru Vempa R&B Road at Uchintha Kalava Bridge to Gogulamma Harijanapeta (Mogalthuru Mandal W.G.Dist.) From Narsapur Mogalthur R&B road to Dayadaldaspeta via Venkateswara Swamy temple (Mogalthuru Mandal W.G.Dist.) RHB Road from NH 214 A road to Harijanapeta of Kothota (Mogalthuru Mandal W.G.Dist.) R&B Road to indira nagar (via) Pochamma temple (Nasapur Mandal W.G.Dist.) Road from R&B road to Pedalanka (Nasapur Mandal W.G.Dist.) Road from LB Cheria CC road to Chillapalem of LB Cheria (Nasapur Mandal W.G.Dist.) From A-U R&B Road to Satyanarayanapuram, (Kalla Mandal W.G.Dist.) From A-U R&B Road to Mekaladibba Agreement No. / Date DHS DFC Progress up to 30.09.2011

NCRMP/B-W/AP/RHB/ PRED/05/Mogalthuru/001

/2011-12 , Dt. 27.04.2011

27.04.11

26.07.2012

Works not started

NCRMP/B-W/AP/RHB/ PRED/05/Nasapur/002

/2011-12 , Dt. 09.05.2011

09.05.11

08.05.2012

Works not started

NCRMP/B-W/AP/RHB/ PRED/05/Kalla/003

/2011-12 , Dt. 26.05.2011

26.05.11

25.02.2012

Works not started

in Joint Venture with

10

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of works in Krishna District up to 30.09.2011 Category Packages allotted under Phase -1 Names of works under each package Agreement No. / Date /2011-12 Dt.27.4.2011 DHS DFC Progress up to 30.09.2011 Jungle clearance and earth work in progress Jungle clearance and earth work in progress 27.04.11 26.01.2012 Jungle clearance and earth work in progress Jungle clearance and earth work in progress 27.04.11 26.01.2012 Jungle clearance and earth work in progress

NCRMP/BRoad connecting R&B road W/AP/RHB/PRED/06/Machipatna through Gantalammapalem m/001 Road from R & B Road to B.V Thota

27.04.11

26.01.2012

RHB

NCRMP/B/2011-12 W/AP/RHB/PRED/06/Machipatna Dt.27.4.2011 m/002 Road from Potlapalem Z.P road to Chikativanipalem

Road from Intheru R&B Road to Rangaraopet NCRMP/B/2011-12 W/AP/RHB/PRED/06/Kruthivennu Dt.27.4.2011 /003 Road from R&B road to Cyclone Shelter at Chandala

in Joint Venture with

11

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of works in GUNTUR District up to 30.09.2011 Category Packages allotted under Phase - 1 NCRMP/BW/AP/RHB/PRED/07/KARLA PALEM/001 RHB NCRMP/BW/AP/PRED/07/Nagaram/002 Names of works under each package R/f Ganapavaram R&B Road to Kesavapuri ST colony Agreement No./ Date 7/2011-2012 27.04.2011 DHS DFC Progress up to 30.09.2011 Work not started

27.04.11

26.01.2012

R/f R&B Road to Mohammad Alipalem 8/2011-2012 27.04.2011 27.04.11 26.4.2012

Earth work in progress Earth work in progress

R/f R&B Road to Katurivaripalem.

Reconstructuion of Highlevel Bridge @Km5/2 of Bapatla-Suryalaka Road across NCRMP/B79/2010-2011 perli drain in Guntur W/AP/Br/R&B/07/Bapatla/010 1.12.2010 Bridges NCRMP/BW/AP/Br/R&B/07/Bapatla/011 Reconstructuion of Highlevel Bridge @Km2/4 of Bapatla-Pandurangapuram Road across perli drain in Guntur

01.12.10

31.5.2012

Abutments and piers completed

78/2010-2011 1.12.2010

01.12.10

31.5.2012

Abutments and piers completed, one deck slab completed

in Joint Venture with

12

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of works in Prakasam District up to 30.09.2011 Names of works under each package Construction of High level Bridge at Km 16/10 of NCRMP/B-W/AP/Br/R&B/08/ BRIDGES Naguluppalapadu Kanaparthi Kanaparthi/012 road in Prakasam District Category Packages allotted under Phase - 1 Agreement No. / Date DHS DFC Progress up to 15.09.2011 Piers raised up to bed block

76/2010-11 Dated 1/12/2010

01.12.10

31.5.12

RHB

NCRMP/BRoad from Pakala ZP Road to W/AP/RHB/PRED/08/S.Konda/001 Aulavaripalem Cyclone shelter Dated 10/02/2011 NCRMP/BNCRMP/BRoad from R&B Road to W/AP/RHB/PRED/08/S.Konda/ W/AP/RHB/PRED/08/S.Konda/001 Somarajupalli 001 Dated 10/02/2011 NCRMP/BRoad from R&B road to W/AP/RHB/PRED/08/S.Konda/001 Narravaripalem Dated 10/02/2011 NCRMP/BRoad from NH5 to W/AP/RHB/PRED/08/S.Konda/002 Mulaguntapadu dated 10/02/2011 NCRMP/BRoad from R&B road to W/AP/RHB/PRED/08/S.Konda/002 Chalivendradibba dated -10/02/2011 NCRMP/BW/AP/RHB/PRED/08/S.Konda/ NCRMP/BRoad from Pakala R&B road to 002 W/AP/RHB/PRED/08/S.Konda/002 Mosanaladinne dated 10/02/2011 Road from R&B road to Binginapalli Harijanawada Cyclone Shelter NCRMP/BW/AP/RHB/PRED/08/S.Konda/002 dated 10/02/2011

10.02.11

9.2.12

GSB to bed one

10.02.11

9.2.12

GSB to bed one

10.02.11

9.2.12

Work not Resumed

10.02.11

10.02.12

Not Started

10.02.11

10.02.12

GSB to bed one

10.02.11

10.02.12

GSB to bed one

10.02.11

10.02.12

Work not Resumed

in Joint Venture with

13

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of works in Prakasam District up to 30.09.2011 Category Packages allotted under Phase - Names of works under Agreement No. / Date 1 each package Road from R&B Road NCRMP/BNCRMP/BAllur to M T Raju colony W/AP/RHB/PRED/08/Kothapatna W/AP/RHB/PRED/08/Kothapatnam/ m/003 003 Dated 27/04/2011 NCRMP/BRoad from KEM R&B W/AP/RHB/PRED/08/Kothapatnam/ Road to Sankuvarigunta 004 Dated 27/04/2011 DHS Progress up to 30.09.2011 CC road laying completed and GSB in 27.04.12 progress DFC CC road laying completed and GSB progress CC road laying completed and GSB progress GSB in progress CC road and BT laying completed Shoulders progress CC road completed & GSB in progress Culvert Encasement Work is in Progress

27.04.11

27.04.11

27.04.12

NCRMP/BW/AP/RHB/PRED/08/Kothapatna Road from KEM R & B m/004 NCRMP/BRoad to W/AP/RHB/PRED/08/Kothapatnam/ Pullareddypalem 004 Dated 27/04/2011 RHB NCRMP/BRoad from MC Road to NCRMP/BW/AP/RHB/PRED/08/Ulavapadu/0 Subbarayudu Satram W/AP/RHB/PRED/08/Ulavapadu/07 7 dated 27/04/2011 NCRMP/BNCRMP/BRoad from R&B road W/AP/RHB/PRED/08/Ulavapadu/0 W/AP/RHB/PRED/08/Ulavapadu/08 Tettu to Ramayapatnam 8 dated 27/04/2011 NCRMP/BRoad from R&B road W/AP/RHB/PRED/08/Tangutur/09 Pellur to Vasepallipadu NCRMP/BRoad from R&B road to W/AP/RHB/PRED/08/Tangutur/10 Kesupalem NCRMP/BW/AP/RHB/PRED/08/Tangutur/09 dated 16/03/2011 NCRMP/BW/AP/RHB/PRED/08/Tangutur/10 dated 16/03/2011

27.04.11

27.04.12

27.04.11

27.04.12

27.04.11

27.04.12

16.03.11

16.03.12

16.03.11

16.03.12

in Joint Venture with

14

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of works in Nellore District up to 30.09.2011 Category Packages allotted under Phase -1
NCRMP/BW/AP/RHB/PRED/09/Bogole/001

Names of works under each package

Agreement No. / Date

DHS

DFC

Progress up to 30.09.2011
WBM Gr-II Completed

RHB

RHB

RCS

Road from NH 5 to Sambasivapuram Road from 9/6 of Zuvvaladinne R&B Road to 11/0 of 34/2010-11, Dt. 19.01.2011 Zuvvaladinne R&B via Venkideshpalem(Venkateshpalem) NCRMP/BRoad from 1/6 of Zuvvaladinne R&B road to / 2010 - 11, Dt. W/AP/RHB/PRED/09/Bogole/002 Tellagunta 07.02.2011 Road from R&B road to Muttembake Via Pittuvani NCRMP/B2010-11Dt palli W/AP/RHB/PRED/09/Chittamur/003 18.01.2011 Road from R&B Chittamur to Soma Samudram Road from K.T R&B Road to Alliguntapalem Road from Km 5/8 of Chennayapalem Road NCRMP/B32/2010-11, Dt. toGummadi Bandala W/AP/RHB/PRED/09/Kavali/004 17.01.2011 Road from Pedapattapupalem R&B road to Chennayapalem H. Wada Road from R&B Road Alagani padu to Vavilla NCRMP/B/ 2011 - 12, Dt. Road from R&B road Kancharapalem HW to W/AP/RHB/PRED/09/Vidavalur/005 27.04.2011 Alaganipadu NCRMP/B/2010-11 Road from R&B Road to PatuvariKandriga W/AP/RHB/PRED/09/Muthukur/006 Dt.25.04.2011 Survepalli Pudiparthi Road to Srikanth Colony NCRMP/B/ 2011 - 12, Dt. W/AP/RHB/PRED/09/V.Chalam/007 Road from R & B Road to Edagali Kandriga 27.04.2011 NCRMP/BRoad from R&B Road Allur to Galidibbalu (via) /2010-11 Dt. W/AP/RHB/PRED/09/Allur/009 Chukavani dibba 24.01.2011 Road from R&B Road to A.S. Puram NCRMP/B2010W/AP/RCS/PRED/09/Kota/001 11Dt10.05.2011 Road from GD road to Vavillapalem NCRMP/BRoad from R&B road Kappaladoruvu to Bandlapalem /2010-11 Dt. W/AP/RCS/PRED/09/Muthukur/002 H.Wada 21.04.2011 NCRMP/B/2010-11Dt Road from Kakuvaripalem R&B Road to Vellapalm W/AP/RCS/PRED/09/Chillakur/004 23.05.2011 NCRMP/BRoad from 7/2 M.C road to Venkannapalem 2011-10 Dt W/AP/RCS/PRED/09/T.P.Gudur/005 Pattapupalem 17.05.2011 NCRMP/BRoad from R&B road to Sullurpeta Mallam to /2010-11 Dated W/AP/RCS/PRED/09/DV.Satram/008 Berjengalapalli cyclone shelter 9.05.2011

19.01.11

19.4.12 WBM Gr-III is in Progress

07.02.11 18.01.11

06.11.11 18.4.12

WBM Gr-II Completed GSB Completed GSB Completed BT is in progress

17.01.11

27.4.12

BT Completed Side Earth in progress CC Road completed

27.04.11 25.04.11 27.04.11 24.01.11 10.05.11 21.04.11 23.05.2011 17.05.2011 09.05.2011

27.7.12

Side Earth is in Progress

25.1.2012 BT Completed 27.4.2012 WBM Gr_III Completed WBM Gr_III Completed

24.4.2012 GSB is Completed 10.2.2012 Earth work in embankment Earth work in embankment

21.1.2012 WBM-Gr-III 23.2.2012 Jungle clearence is in progress

17.2.2012 GSB is in progress 9.2.2012 Construction of culvert is in progress

in Joint Venture with

15

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

6.0 District wise status of tests conducted by TPQA: Apart from monitoring the tests being conducted by the implementation team (contractors & Line department) at various stages, the Third party Quality Audit team also conducted tests to confirm its compliance with the standards. These tests are carried out in the site itself and in some cases samples are collected and testing done in outside laboratories. The details of tests conducted in the field till end of September 2011 are presented.

Summary of QC Tests - Up to 30.09.2011 S.No. 1 2 3 4 5 6 7 8 9 District Srikakulam Vizianagaram Visakhapatnam East Godavari West Godavari Krishna Guntur Prakasham Nellore Total No. Tests Done 100 122 155 39 0 0 53 95 154 Total no. of Tests Passed 85 119 154 39 0 0 53 91 154 Failed 15 3 1 0 0 0 0 4 0

160 140 120 100 80 60 40 20 0 Total no. of Tests Failed Total no. of Tests Passed

In West Godavari and Krishna districts works are just started, hence the number of tests conducted is shown as zero.

in Joint Venture with

16

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

7.0

Details of Audit Reports Submitted During this Month:

S.NO
1

District
Srikakulam

Package Number
NCRMP/BW/AP/RHD/PRED/0 1/Santhabommali/003 NCRMP/BW/AP/RHD/PRED/0 1/Santhabommali/003 NCRMP/BW/AP/RHD/PRED/0 1/Santhabommali/003 NCRMP/BW/AP/PRED/07/Na garam/002. NCRMP/BW/AP/PRED/07/Na garam/002. NCRMP/BW/AP/Br/R&B/07/Bapatla/011/ 2010 NCRMP/BW/AP/Br/R&B/07/Bapatla/010/ 2010 NCRMP/B W/AP/RCS/PRED/09/Muthuku r/002 NCRMP/BW/AP/RHB/PRED/0 9/v.chalem/007. (2 works) NCRMP/BW/AP/RCS/PRED/09/D.V.Satr am/008.

Name of work
Road from Borubadra,Malagam to Kollipadu in Santhabommali mandal. Road from DPN R&B Road to Uddandapalem in Santhabommali mandal . Road from K.Umilada jn to Koduru (link road) in Santhabommali mandal. Road from R&B Road to Katuivaripalem in Nagaram Mandal. Road from Ganapavaram R&B Road to Mohammedalipalem. Reconstruction of HLB @ Km 2/4 of Bapatla Pandurangapuram road across Perli Drain in Guntur Reconstruction of HLB @ Km 2/4 of Bapatla Suryalanka road across Perli Drain in Guntur Road from R&B Road kappaladoruvu to bandla palem H.wada Providing BT Surface to theRroad from R&B road to Edagali kandriga Road from R&B Road Sullurpeta-Mallam to Berijangalapalli CycloneShelter.

Srikakulam

Srikakulam

Guntur

Guntur

Guntur

Guntur

Nellore

Nellore

10

Nellore

8.0

Observations in the submitted reports: Name of Work 1 2 :Road from Borubadra,Malagam to Kollipadu in Santhabommali mandal.

15.00 % value of the work is completed. GSB work is in progress. Earthwire for widening and 3 culverts are completed. Combined milestones for three works in this package : Milestone 1 : Earthwork, CD Works, GSB - 4 months. Milestone 2 : WBM Gr-II, Gr-III and Shoulders - 8 months. Milestone 3 : BT and Road funiture - 12 months.

in Joint Venture with

17

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
3 The width of shoulder formation is verified from 0/0 to 2/250 Km., Shoulders portion in some areas have slipped and the same may be rectified. Formation width is less than 7.50 mts from Km: 1/600 to 1/900, & from Km:2/350 to 2/530. From Km:1/600 to 1/900 the road level is lower than the surrounding fields level, and in this stretch sand may occur in monsoon period, this aspect needs examination. The tank bund portion from Km 2.350 to 2.530 , the height difference between road top level and field level is more than 3.0mts. But no slope protection work is provided. Safety measures like providing caution boards and providing helmets is to be done. White wash shall be done to parapet walls of the existing culverts for the clear visibility of vechicular traffic. Some of the KM & HM Stones are missing in this working road stretch. The field officers are requested to erect them immediately. Compliance shall be submitted para wise earlier after attending to the above remarks. Name of Work 1 :Road from DPN R&B Road to Uddandapalem in Santhabommali mandal.

4 5 6

7 8 9 10

13.00 % value of the work is completed. Earth work for Shoulders upto existing road level is completed.All the four CD works are completed. 2 layers of WBM+OGPC+SC is to be done from Km 0.0 to 1/850. Combined milestones for 3 works in this package Milestone 1 : Earthwork, CD Works, GSB - 4 months. Milestone 2 : WBM Gr-II, Gr-III and Shoulders - 8 months. Milestone 3 : BT and Road funiture - 12 months. The width of shoulder formation is verified from 0/0 to 1/850 Km.At some location sholders have slipped and gullies formed which shall be rectified. The conrtactor has not established QC laboratory and no testing equipment is avaialable at sites. Alignment of culverts are not to proper lines and grades. Caution boards need to be fixed to guide the vehicular traffic. White wash shall be done to parapet walls of the existing culverts for the clear visibility to vechicular traffic. Some of the KM & HM Stones are missing in this working road stretch.The field officers are requested to erect them immediately. Cautionary and mandatory signboards at necessary points on along the edge of sharp curves, school places and village name boards shall be errected, Compliance shall be submitted parawise earlier after attending to the above remarks.

3 4 5 6 7

8 9

10

in Joint Venture with

18

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Name of Work 1 2 :Road from K.Umilada jn to Koduru (link road) in Santhabommali mandal.

25.00 % value of the work is completed. All the 3 culverts completed. Earthwire for widening embankment is completed. GSB work is in progress Combined Milestones for three works in this Package : Milestone 1 : Earthwork, CD Works, GSB - 4 months. Milestone 2 : WBM Gr-II, Gr-III and Shoulders - 8 months. Milestone 3 : BT and Road funiture - 12 months. The width of shoulder formation is verified from 0/0 Km to 1/265Km. At some location shoulders have slipped and gullies formed which shall be rectified. The Contractor has not provided Q/C laboratory at site. From CH:1/100 to 1/265 the road level is lower than the surrounding fields level. Pipe culverts alignment & headwall line, are not maintained properly. Old narrow pipe culvert between Ch:1/100 to 1/200 were not replaced and it may be prone to accidents. Safety measurements are not taken while execution of the work like providing safety helmets and Caution boards..etc. White wash shall be done to parapet walls of the existing culverts for the clear visibility of vehicular traffic. Some of the KM & HM Stones are missing in this working road stretch. The field officers are requested to erect them immediately. Cautionary and mandatory signboards shall be at necessary points like sharp curves and schools. Compliance shall be submitted para wise earlier after attending to the above remarks. Name of Work: Road from R&B Road to Katuivaripalem in Nagaram Mandal.

3 4 5 6 7 8 9 10 11 12

Progress: Earth work is in progress. GSB , CD Works and WBM are not taken up. The progress of work is very poor as per the mile stones stipulated in the Agreement . With this speed it is very difficult to complete the work within the Agreement period. The Executive Engineer (PR) Tenali is requested to take necessary measures to speed up the work so as to achieve the mile stones stipulated in the agreement. Milestone 1 : Earthwork, GSB , CD Works and WBM - 4 months. (26.08.2011) Milestone 2 : CC Pavement - 8 months (26.12.2011) Milestone 3 : BT Shoulder and Road furniture - 12 months (26.04.2012). Site order book is not being maintained by the field officers. The field officers are requested to maintain invariably the site order book and get the instructions from the inspecting officers from time to time.

in Joint Venture with

19

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

The field officers have not furnished the test results for Embankment soil .The field officers are requested to furnish the Soil test results to the T.P.Q.A. staff for verification. The earth work done in the widening portion is not yet compacted. It is to be compacted in layers and the the field density shall be compared with laboratory density for ensuring the specified relative compaction. Material Registers are not available. The field officers are requested to maintain the material registers and same shall be furnished to the T.P.Q.A. staff for verification. The field officers have not furnished the Mix designs for various grades of concrete (cc pavemant and culverts).The field officers are requested to furnish the mix designs to the T.P.Q.A. staff for verification. KM & HM Stones are not available on the working road stretch. The field officers are requested to erect them after compaction of widened portions. The project informatory boards with all details were not provided as per agreement. The same may be provided immediately at site as per the guidelines given by PIU, NCRMP. Cautionary signboards at necessary points and village name boards shall be erected. Guide stones shall be fixed along the outer edge of all the sharp curves. Extra width fof formation is necessary at sharp curves The field officers are requested to furnish the test reports of water and ensure its suitability for concreting before proceeding with CC pavement work. The quality control tests should be conducted as per IRC SP-11, maintain Q.C. record and the same shall be produced to Q.A. wing for verification. The Dy. Executive Engineer and Executive Engineer should also conduct the tests as per the guide lines of IRC SP-11. No Quality Control lab is available at site. The Executive Engineer is requested to give necessary instructions to the contractor and see that the Quality lab is established at site within a week. Safety measures for workers such as Helmets, Gum shoes, jackets etc., are to be provided by the contractor. DCBM, TBM Stones not available at site. The field officers are requested to fix the DCBM & TBM Stones and carry the levels and same shall be furnished the DCBM & TBM list to the T.P.Q.A. staff for verification. Pre-levels of earth work are not submitted by the field officer. Hence The field officers are requested to furnish the pre levels to the T.P.Q.A. staff for verification. Compliance shall be submitted para wise at an early date after attending to the above remarks. Name of Work : Road from Ganapavaram R&B Road to Mohammedalipalem.

10

11

12

14

15

16 17

in Joint Venture with

20

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
1 Progress: Earth work is in progress. GSB , CD Works and WBM are not taken up. The progress of work is very poor as per the mile stones stipulated in the Agreement . With this speed it is very difficult to complete the work within the Agreement period. The Executive Engineer (PR) Tenali is requested to take necessary measures to speed up the work so as to achieve the mile stones stipulated in the agreement. Milestone 1 : Earthwork, GSB , CD Works and WBM - 4 months. (26.08.2011) Milestone 2 : CC Pavement - 8 months (26.12.2011) Milestone 3 : BT Shoulder and Road furniture - 12 months (26.04.2012). Site order book is not being maintained by the field officers. The field officers are requested to maintain invariably the site order book and get the instructions from the inspecting officers from time to time.

The field officers have not furnished the test results for Embankment soil .The field officers are requested to furnish the Soil test results to the T.P.Q.A. staff for verification. The earth work done in the widening portion is not yet compacted. It is to be compacted in layers and the the field density shall be compared with laboratory density for ensuring the specified relative compaction. Material Registers are not available. The field officers are requested to maintain the material registers and same shall be furnished to the T.P.Q.A. staff for verification. The field officers have not furnished the Mix designs for various grades of concrete (cc pavement and culverts).The field officers are requested to furnish the mix designs to the T.P.Q.A. staff for verification. KM & HM Stones are not available on the working road stretch.The field officers are requested to erect them after compaction of widened portions. The project informatory boards with all details were not provided as per agreement. The same may be provided immediately at site as per the guidelines given by PIU, NCRMP. Cautionary signboards at necessary points and village name boards shall be erected. Guide stones shall be fixed along the outer edge of all the sharp curves. Extra width of formation is necessary at sharp curves The field officers are requested to furnish the test reports of water and ensure its suitability for concreting before proceeding with CC pavement work. The quality control tests should be conducted as per IRC SP-11, maintain Q.C. record and the same shall be produced to Q.A. wing for verification. The Dy. Executive Engineer and Executive Engineer should also conduct the tests as per the guide lines of IRC SP-11. No Quality Control lab is available at site. The Executive Engineer is requested to give necessary instructions to the contractor and see that the Quality lab is established at site within a week.

10

11

12

13

in Joint Venture with

21

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
14 Safety measures for workers such as Helmets, Gum shoes, jackets etc., are to be provided by the contractor. DCBM, TBM Stones not available at site.The field officers are requested to fix the DCBM & TBM Stones and carry the levels and same shall be furnished the DCBM & TBM list to the T.P.Q.A. staff for verification. Pre-levels of earth work are not submitted by the field officer. Hence The field officers are requested to furnish the pre levels to the T.P.Q.A. staff for verification. Compliance shall be submitted para wise at an early date after attending to the above remarks. Name of Work : RECONSTRUCTION OF HLB@Km 2/4 OF BAPATLAPANDURANGAPURAM ROAD ACROSS PERALI DRAIN IN GUNTUR

15

16

17

1 2

Progress of work: Reinforcement fabrication for one deck slab is completed. Site order book is not being maintained by the field officers. The field officers are instructed to maintain invariably the site order book and get the instructions from the inspecting officers.

The field officers are requested to get the samples of steel tested from every consignment of steel , before it is used. The steel should be protected from rusting till the concrete is placed by applying cement coating properly as per clause 1603 of MORT&H standard specification. Steel and cement stock register should be maintained with proper incoming and usage recording should be maintained. The existing bridge being used for directing traffic it should be properly barricaded on the either side as most of railing got collapsed. Reflective caution boards should be erected at entry and exit of the bridge.

Safety measures for workers such as Helmets, Gum shoes, jackets etc., are to be provided by the contractor. Caution boards, sign boards are to be kept. The field officers have not furnished the copies of the Bills of Cement and Steel utilized on the bridge. The same shall be furnished to the TPQA staff during the inspections for verification.

9 10

Measurements of piers, bed blocks and abutments are verified and found to be fairly tallying. At some locations, honey combing is observed at some places. Finishing shall be carried out as per clause 1714 of MORT&H standard specifications for Road & Bridge works. Reinforcement grills for one deck slab are verified with reference to the drawing and found to be fairly tallying.

11

in Joint Venture with

22

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
12 13 Extra care shall be taken to check the quality of water used for mixing in concrete and curing concrete. Samples of cement and steel are collected by TPQA staff and sent for confirmatory testing. The results will be furnished in the next QC report. Name of Work : RECONSTRUCTION OF HLB@Km 5/2 OF BAPATLA-SURYALANKA ROAD ACROSS PERALI DRAIN IN GUNTUR

1 2

Progress of work: 2 abutments and 7 piers completed upto bed block level. Bed block over one pier is completed. Site order book is not being maintained by the field officers. The field officers are instructed to maintain invariably the site order book and get the instructions from the inspecting officers. The dimensions of bed block laid over P5 are measured and found taillling with drawing, but the bed block offset all around the pier is not seen as it is flushed with the pier. The pier is bluged at the bottom of bed block, because of which the offset is not seen.(Photograph attached.) Proper Shuttering shall be used and finishing shall be carried out as per clause 1700 of MORT&H Standard specification for Road and Bridge works. The field officers are requested to get the samples of steel tested from every consignment of steel , before it is used. The steel should be protected from rusting till the concrete is placed by applying cement coating properly. The overhead electrical lines passing across the structure should be shifted as it is posing danger to proceed further above the piers. Safety measures for workers such as Helmets, Gum shoes, jackets etc., are to be provided by the contractor. Caution boards, sign boards are to be kept. The field officers have not furnished the copies of the Bills of Cement and Steel utilized on the bridge. The same shall be furnished to the TPQA staff during the inspections for verification. As daily backwaters flow in the Perali drain, curing the structure with the this water should be avoided. Samples of cement and steel are collected by TPQA staff and sent for confirmatory testing. The results will be furnished in the next QC report. Name of work: Road from R&B Road kappaladoruvu to bandla palem H.wada

4 5 6

7 8

9 10

Review of Progress Milestone 1 - Earthwork, Pipe Culverts, GSB - (06.05.2011) Milestone 2 - WBM Gr. III and shoulders (06.08.2011) Milestone 3 - BT & Road furniture (21.01.2012) Even though the traget date fixed for second milestone is closed, work stipulated to be completed by the end of first milestone was not completed fully. Value of work completed is about 15.25% of the agreement value. Progress of work need to be accelarated. Reasons for slow progress shall be furnished.

in Joint Venture with

23

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
2 3 4 It is observed that the shoulder material is not properly mixed (Sand & Gravel Mix). It shall be scarified, uniformly mixed, watered and compacted to the required density. The measurements like width and thickness of the WBM Gr-III from Km 0/0TO3/088 are verified and found to be tallying with the required measurements. The details are given in Annexure - 1. Review of degree of Quality Control exercised:

The summary QC tests by field officers shown under 3.0 of this QCR are noted from the following: 1) Test records shown by line departmental officers

2) Test results like CBR and Plasticity Index etc., obtained from local testing facilities. This aspect requires further improvement and commitment of senior engineers such as SEs and EEs. Setting up of a QC lab for conducting most of the regular tests for each package by the contractor is necessary. The line departmental officers also require one laboratory for each sub-division or Division depending on the workload for ensuring better quality control. In the present case, no QC lab was established by the contractor so far. Also, no QC lab was available at Sub Division or Division. Name of Work :Providing BT Surface to the Road from R&B road to Edagali kandriga 1 Works to be done as per Milestone: Mile stone 1:- Earth work, pipe culverts, GSB: 4 months. (26.04.2011) Mile stone 2:- WBM Gr-II, Gr-III and Shoulders: 8 months. (26.08.2011) Mile stone 3:- BT and Road funiture: 12 months. (26.04.2012) 51% of value of the work is completed. Gravel shoulders is in progress The measurements like width and thickness of the GSB Layer from Km 0/0 to 0/570 are verified and found to be tallying with the required measurements. The details are given in Annexure - 1. The measurements like width and thickness of the WBM Gr.-2 Layer from Km 0/0 to 0/570 are verified and found tallying with the required measurements. The details are given in Annexure - 2. During inspection it was observed that trimming of slopes was not done properly from Km 0/0 to0/570. The field officers have not furnished the cement bills for verification. At KM 0/0 the water sump located in the shoulder portion should be revomed. The Field officers are requested to provide village name boards, sign boards &caution boards. The joints in the CC pavement are not constructed as per Agrrement specifiction. All the joints are formed with mastic pads. It seems that nieither the contractor nor the line departmental offficers went hrough the agreement specification. It may not cause structural problem but the appearance is not very good.

2 3 4 5 6 7 8 9

in Joint Venture with

24

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
9 Review of degree of Quality Control exercised: The summary QC tests by field officers shown under 4.0 of this QCR are noted from the following: 1) Test records shown by line departmental officers 2) Test results like CBR and Plasticity Index etc., obtained from local testing facilities. This aspect requires further improvement and commitment of senior engineers such as SEs and EEs. Setting up of a QC lab for conducting most of the regular tests for each package by the contractor is necessary. The line departmental officers also require one laboratory for each sub-division or Division depending on the workload for ensuring better quality control. In the present case, no QC lab was established by the contractor so far. Also, no QC lab was available at Sub Division or Division Name of Work : Road from R&B Road Sullurpeta-Mallam to Berijangalapalli Cyclone Shelter. 1 Works to be done as per Milestone: Mile stone 1:- Earth work, pipe culverts, GSB: 3 months (08.08.2011) Mile stone 2:- WBM Gr-II, Gr-III , Shoulders and CC Pavement: 3 months (08.11.2011) Mile stone 3:- BT,CC Pavement, and Road funiture: 3 months (08.02.2012) Progress is behind established milestone. First milestone completed but culverts and GSB not completed. At embankment locations required slopes are not being provided. Safety barricading should be provided at the culvert excavation locations at Km 3/2. All the CD Works need to be completed urgently as there locations are prone to accident. Side Slopes needs to be trimmed to required slopes after the shoulder construction. Vibratory compactor is being used in earth work compaction. Review of degree of Quality Control exercised: The summary QC tests by field officers shown under 3.0 of this QCR are noted from the following: 1) Test records shown by line departmental officers 2) Test results like CBR and Plasticity Index etc., obtained from local testing facilities. This aspect requires further improvement and commitment of senior engineers such as SEs and EEs. Setting up of a QC lab for conducting most of the regular tests for each package by the contractor is necessary. The line departmental officers also require one laboratory for each sub-division or Division depending on the workload for ensuring better quality control

2 3 4 5 6 7

9.0 Details of Social & Environmental Reports Submitted in this Month: S.NO Package Number West Godavari District 1. NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/001 2. 3. 4. 5. NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/001 NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/001 NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/001 NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/001 Name of Work R&B Road at Panchayat office to Pulaparthivarithota via Badava Mogaltur Vempa R&B Road at Uchintha kalava Bridge to Harijanapeta. Road from NH 214 A at Ranga Statue centre to Harijanawada of Kalipatnam (E). Road from NH 214A Road to Harijanawada of Kothota. Narsapur Mogaltur R&B Road to Dayadaldaspeta via Venkateshwara Swamy Temple. Road from LB Cheria CC Road to Chillapalem of LB Cheria. Road from R&B Road to Pedalanka. Road from R&B to Indiaranagar (via) Pochamma

6. 7. 8.

NCRMP/B-W/AP/RHB/PRED/05/Narsapur/002 NCRMP/B-W/AP/RHB/PRED/05/Narsapur/002 NCRMP/B-W/AP/RHB/PRED/05/Narsapur/002

in Joint Venture with

25

MONTHLY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Temple Road from A-U Road to Satyanarayanapuram. Road from A-U Road to Mekaladibba.

NCRMP/BW/AP/RHB/PRED/05/Kalla/003 10. NCRMP/BW/AP/RHB/PRED/05/Kalla/003 Krishna District 1. NCRMP/BW/AP/RHB/PRED/06/Machilipatnam/001 2. NCRMP/BW/AP/RHB/PRED/06/Machilipatnam/002 3. NCRMP/BW/AP/RHB/PRED/06/Machilipatnam/002 4. NCRMP/BW/AP/RHB/PRED/06/Kruthivennu/003 5. NCRMP/BW/AP/RHB/PRED/06/Kruthivennu/003 EAST Godavari District 1 NCRMP/B-W/AP/RCS/PRED/04/Karapa/001 2 3 NCRMP/B-W/AP/RHB/PRED/04/Karapa/001 NCRMP/B-W/AP/RHB/PRED/04/Katreni kona/003

9.

Road Connecting R&B Road Gantalammapalem. Road from R&B Road to B.V.Thota.

through

Road from Potalapalem Z.P.Road to Chikativanipalem. Road from R&B Road to Cyclone Shelter at Chandala. Road from Intheru R&B Road to Rangaraopet.

Approach road to Cyclone Shelter at Adavipudi Road from Gurajanapalli to Bandulavaripalem Road from PR road to Dasarivanipeta and to Cyclone Shelter

in Joint Venture with

26

QUARTERLY SUMMARY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
10.0 Photographs of site visits & Important Events During this month:

Inspection of works by Sri T.Radha, I.A.S, Commissioner, Disaster Management in Guntur District on 17-09-2011

Inspection of works by Sri T.Radha, I.A.S, Commissioner, Disaster Management in Guntur District on 17-09-2011

Inspection of works by Sri T.Radha, I.A.S, Commissioner, Disaster Management in Guntur District on 17-09-2011

Inspection of works by Sri T.Radha, I.A.S, Commissioner, Disaster Management in Guntur District on 17-09-2011

in Joint Venture with

26

QUARTERLY SUMMARY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP one day State level Workshop for Contractors on the World Bank Procurement Procedures at Sindhoori hotel, Guntur for 5 districts on 20-09-2011. Dr Shetty from Administrative Staff College of India delivering the lecture.

NCRMP one day State level Workshop for Contractors on the World Bank Procurement Procedures at Sindhoori hotel, Guntur for 5 districts on 20-09-2011. Delegates listen to Manohar Raos inaugural address.

NCRMP one day State level Workshop for Contractors on the NCRMP one day State level Workshop for Contractors on the World Bank Procurement Procedures at Meghalaya hotel, World Bank Procurement Procedures at Meghalaya hotel, Vijag for 4 districts on 22-09-2011. Ravinder, Sectorial officer Vijag for 4 districts on 22-09-2011. PM, PIU inviting the guests and delegates. Sri.R.Venkateswara Rao giving replies to the doubts raised by contractors.

in Joint Venture with

27

QUARTERLY SUMMARY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
TPQA-NCRMP inspection on 21-09-2011. Road Vempudi to Patimeeda. Dip left unattended on Mulaparra road. TPQA-NCRMP inspection on 21-09-2011. Road Vempudi to Patimeeda. NCRMP PIU officials and TPQA engineers are seen

TPQA-NCRMP inspection on 21-09-2011. R&B road to Venkayyapalem. CC road in the village limits.

TPQA-NCRMP inspection on 21-09-2011. Road Vempudi to Patimeeda. R&B road to Venkayyapalem. Necessity for protective work being explained by field officers.

in Joint Venture with

28

QUARTERLY SUMMARY REPORT Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP-TPQA inspection on 08-09-201. Sulluripeta to Mallam R&B road to Berijangalapalli Cyclone shelter in Nellore District. NCRMP-TPQA inspection on 08-09-201. R&B road Muttembaka via Pittuvanipalli in Chittamur Mandal in Nellore District. GSB done and undulations are noticed. Shoulders require thorough compaqction.

NCRMP-TPQA inspection on 08-09-201. Chittamur to Somasamudram in Nellore District. Earthwork in progress needs systematic OMC layer by layer compaction.

NCRMP-TPQA inspection on 08-09-201. Chittamur to Somasamudram in Nellore District. Chittamur village where CC road is to be done.

in Joint Venture with