Harga Satuan
NO.
No.
(1)
DESCRIPTION
UNIT
MATERIAL
LABOUR
TRANSPORTATION
TOTAL COST
TYPE/PRODUCT
Uraian
Satuan
Transpor
(Rp)
(6)
Tipe/ Produk
(3)
Pekerja
(Rp)
(5)
Harga Total
(Rp)
(2)
Material
(Rp)
(4)
(8)
DIVISI : ELECTRICAL
A. Panel Works
1 MCCB 320-800 A 3P
2 MCCB 252-630 A 3P
3 MCCB 200-250 A 3P
4 MCCB 160-400 A
5 MCCB 160-200 A
6 MCCB 125-160 A 3P
7 MCCB 100-125 A 3P
8 MCCB 80-100 A 3P
9 MCCB 64-80 A 3P
10 MCCB 50-63 A 3P
11 MCCB 40-50 A 3P
12 MCCB 32-40 A 3P
13 MCCB 16-25 A 3P
14 MCCB 100 A 3P
15 MCCB 80 A 3P
16 MCCB 50 A 3P
17 MCCB 40 A 3P
18 MCCB 32 A 3P
19 MCCB 25 A 3P
20 MCCB 20 A 3P
21 MCCB 16 A 3P
22 MCB 40 A 3P
23 MCB 32 A 3P
24 MCB 25 A 3P
25 MCB 20 A 3P
26 MCB 16 A 3P
27 MCB 10 A 3P
28 MCB 6 A 3P
29 MCB 40 A 1P
30 MCB 32 A 1P
31 MCB 20 A 1P
32 MCB 16 A 1P
33 MCB 10 A 1P
34 MCB 6 A 1P
35 CT 5000/5A
36 CT 1000/5A
37 CT 800/5A
38 CT 400/5A
39 CT 125/5A
40 CT 160/5A
41 CT 25/5A
42 kWH Meter
43 Indicator Lamp
44 Fuse 4 A
45 Amper meter
46 Volt meter
47 Selector switch
48 Cosphi meter
49 Arrester
50 Timer Switch
51 Kontaktor
52 Busbar CU 5 (100 x 5 mm)
53 Busbar CU 5 (50 x 5 mm)
54 Busbar CU 5 (20 x 5 mm)
55 Busbar CU 5 (15 x 3 mm)
56 Busbar CU 5 (15 x 2 mm)
57 Busbar CU 5 (12 x 2 mm)
58 Busbar CU 3 (12 x 2 mm)
59 Grounding cable BC 4 mm2
60 Grounding cable BC 6 mm2
61 Grounding cable BC 10 mm2
62 Grounding cable BC 16 mm2
63 Grounding cable BC 25 mm2
64 Grounding cable BC 35 mm2
65 Grounding cable BC 50 mm2
66 Grounding cable BC 70 mm2
67 Box panel 200 x 80 x 60 cm
68 Box panel 120 x 80 x 40 cm
69 Box panel 80 x 60 x 40 cm
70 Box panel 60 x 40 x 30 cm
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
unit
unit
unit
unit
265,000.00
250,000.00
235,000.00
220,000.00
205,000.00
190,000.00
175,000.00
160,000.00
145,000.00
130,000.00
115,000.00
100,000.00
85,000.00
150,000.00
140,000.00
130,000.00
120,000.00
110,000.00
100,000.00
90,000.00
80,000.00
115,000.00
105,000.00
95,000.00
85,000.00
75,000.00
65,000.00
55,000.00
75,000.00
65,000.00
55,000.00
45,000.00
35,000.00
25,000.00
2,560,000.00
1,280,000.00
640,000.00
320,000.00
160,000.00
80,000.00
40,000.00
150,000.00
100,000.00
125,000.00
150,000.00
200,000.00
125,000.00
135,000.00
175,000.00
180,000.00
120,000.00
350,000.00
250,000.00
225,000.00
200,000.00
175,000.00
150,000.00
125,000.00
25,000.00
40,000.00
55,000.00
70,000.00
85,000.00
100,000.00
115,000.00
130,000.00
12,500,000.00
10,000,000.00
8,000,000.00
6,000,000.00
265,000.00
250,000.00
235,000.00
220,000.00
205,000.00
190,000.00
175,000.00
160,000.00
145,000.00
130,000.00
115,000.00
100,000.00
85,000.00
150,000.00
140,000.00
130,000.00
120,000.00
110,000.00
100,000.00
90,000.00
80,000.00
115,000.00
105,000.00
95,000.00
85,000.00
75,000.00
65,000.00
55,000.00
75,000.00
65,000.00
55,000.00
45,000.00
35,000.00
25,000.00
2,560,000.00
1,280,000.00
640,000.00
320,000.00
160,000.00
80,000.00
40,000.00
150,000.00
100,000.00
125,000.00
150,000.00
200,000.00
125,000.00
135,000.00
175,000.00
180,000.00
120,000.00
350,000.00
250,000.00
225,000.00
200,000.00
175,000.00
150,000.00
125,000.00
25,000.00
40,000.00
55,000.00
70,000.00
85,000.00
100,000.00
115,000.00
130,000.00
12,500,000.00
10,000,000.00
8,000,000.00
6,000,000.00
UNIT PRICE
Harga Satuan
NO.
No.
(1)
DESCRIPTION
UNIT
MATERIAL
LABOUR
TRANSPORTATION
TOTAL COST
TYPE/PRODUCT
Uraian
Satuan
Transpor
(Rp)
(6)
Tipe/ Produk
(3)
Pekerja
(Rp)
(5)
Harga Total
(Rp)
(2)
Material
(Rp)
(4)
60 x 40 x 20 cm
50 x 40 x 25 cm
40 x 30 x 20 cm
50 x 30 x 20 cm
unit
unit
unit
unit
71
72
73
74
Box Panel
Box Panel
Box Panel
Box Panel
Power Cable
NYY 5x4 mm2
NYY 4 X120 mm2
NYY 4 X 70 mm2
NYY 4 X 50 mm2
NYY 4 X 35 mm2
NYY 4 X 25 mm2
NYY 4 X 16 mm2
NYY 4X10 mm
NYY 4X 6 mm
NYY 4 X 4 mm
NYY 3 X 4 mm
NYY 3 X 6 mm
NYY 1 X 240 mm
NYY 1 X 185 mm
NYY 1 X 70 mm
NYY 1 X 50 mm
NYM 2 x 2,5 mm2
NYM 3 x 2,5 mm`2
NYM 2 x 1,5 mm2
Kabel NYA 185 mm
Kabel NYA 150 mm
Kabel NYA 120 mm
Kabel NYA 95 mm
Kabel NYA 70 mm
Kabel NYA 50 mm
Kabel NYA 35 mm
Kabel NYA 25 mm
Kabel NYA 16 mm
Kabel NYA 10 mm
Kabel NYA 6 mm
Kabel NYA 4 mm
Kabel NYA 2,5 mm
Kabel, NYMHY 3 x 1,5 mm1
Kabel, NYMHY 3 x 2,5 mm2
Kabel, NYMHY 2 x 1,5 mm2
Kabel, NYFGbY 1 x 240 mm2
Kabel, NYFGbY 3 x 4 mm2
Kabel, NYFGbY 3 x 2,5 mm2
Kabel, N2XSY 1 x 150 mm2
FRC 3 x 6 mm
FRC 3 x 10 mm
FRC 4 x 2,5 mm
FRC 4 x 4 mm
FRC 4 x 6 mm
FRC 4 x 10 mm
FRC 5 x 4 mm
FRC 5 x 6 mm
FRC 5 x 10 mm
FRC 5 x 25 mm
Konduit dia 20 mm
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
(8)
7,500,000.00
5,000,000.00
4,000,000.00
4,500,000.00
7,500,000.00
5,000,000.00
4,000,000.00
4,500,000.00
m
m
m'
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
40,000.00
400,000.00
240,000.00
175,000.00
130,000.00
95,000.00
80,000.00
70,000.00
45,000.00
30,000.00
25,000.00
35,000.00
215,000.00
165,000.00
65,000.00
45,000.00
11,000.00
14,000.00
8,500.00
205,000.00
165,000.00
130,000.00
100,000.00
75,000.00
60,000.00
40,000.00
25,000.00
17,500.00
13,500.00
10,500.00
7,800.00
5,000.00
30,000.00
35,000.00
25,000.00
75,000.00
4,500.00
3,200.00
175,000.00
35,000.00
53,000.00
22,000.00
33,000.00
46,000.00
75,000.00
90,000.00
115,000.00
130,000.00
150,000.00
7,500.00
40,000.00
400,000.00
240,000.00
175,000.00
130,000.00
95,000.00
80,000.00
70,000.00
45,000.00
30,000.00
25,000.00
35,000.00
215,000.00
165,000.00
65,000.00
45,000.00
11,000.00
14,000.00
8,500.00
205,000.00
165,000.00
130,000.00
100,000.00
75,000.00
60,000.00
40,000.00
25,000.00
17,500.00
13,500.00
10,500.00
7,800.00
5,000.00
30,000.00
35,000.00
25,000.00
75,000.00
4,500.00
3,200.00
175,000.00
35,000.00
53,000.00
22,000.00
33,000.00
46,000.00
75,000.00
90,000.00
115,000.00
130,000.00
150,000.00
7,500.00
1
2
3
4
Cable Tray
Kabel Tray 400 x 100 mm
Elbow 400 x 100 mm
Tee 400 x 100 mm
Cross 400 x 100 mm
m
bh
bh
bh
96,000.00
45,000.00
45,000.00
45,000.00
96,000.00
45,000.00
45,000.00
45,000.00
1
2
3
4
m
bh
bh
bh
90,000.00
40,000.00
40,000.00
40,000.00
90,000.00
40,000.00
40,000.00
40,000.00
1
2
3
4
m
bh
bh
bh
85,000.00
38,000.00
38,000.00
38,000.00
85,000.00
38,000.00
38,000.00
38,000.00
UNIT PRICE
Harga Satuan
NO.
DESCRIPTION
UNIT
MATERIAL
LABOUR
TRANSPORTATION
TOTAL COST
TYPE/PRODUCT
Uraian
Satuan
Transpor
(Rp)
(6)
Tipe/ Produk
(3)
Pekerja
(Rp)
(5)
Harga Total
(Rp)
(2)
Material
(Rp)
(4)
No.
(1)
1
1
1
Cable Ladder
Kabel Ladder 400 x 100 mm
Kabel Ladder 300 x 100 mm
Kabel Tray 200 x 100 mm
1
2
3
4
5
6
7
8
9
10
11
1
2
3
4
5
6
7
8
9
1
2
3
4
5
6
7
8
9
10
11
Ceiling Speaker 3 w
Ceiling Speaker 6 w
Volume Kontrol
Terminal Box - TS. SB 20 pairs
Mixer/ Zone Selection/ Power Amplifier 240 Watt
Power Amplifier 240 Watt
Microphone Pagging system
Radio & Antena AM/FM Tuner, CD Player, MP3
Cassette Player
Equalizer
MDF - SS
Telephone System
1
2
3
4
5
Computer System
1
2
3
4
5
6
Outlet Data
HUB 12 ports
HUB 24 ports
Patch Panel 24 Ports RJ 45
19" Cabinet Rack
Cable UTP Cat. 5 4 Pairs
CCTV
1
2
3
4
5
(8)
m
m
m
225,000.00
200,000.00
85,000.00
225,000.00
200,000.00
85,000.00
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
65,000.00
95,000.00
75,000.00
110,000.00
50,000.00
20,000.00
22,000.00
25,000.00
20,000.00
25,000.00
30,000.00
65,000.00
95,000.00
75,000.00
110,000.00
50,000.00
20,000.00
22,000.00
25,000.00
20,000.00
25,000.00
30,000.00
bh
bh
bh
bh
bh
bh
bh
unit
unit
125,000.00
125,000.00
75,000.00
75,000.00
50,000.00
50,000.00
150,000.00
90,000.00
120,000.00
125,000.00
125,000.00
75,000.00
75,000.00
50,000.00
50,000.00
150,000.00
90,000.00
120,000.00
bh
bh
bh
unit
unit
unit
unit
unit
unit
unit
unit
110,000.00
170,000.00
115,000.00
3,750,000.00
4,500,000.00
3,750,000.00
325,000.00
1,100,000.00
250,000.00
2,250,000.00
2,500,000.00
110,000.00
170,000.00
115,000.00
3,750,000.00
4,500,000.00
3,750,000.00
325,000.00
1,100,000.00
250,000.00
2,250,000.00
2,500,000.00
bh
bh
unit
unit
unit
55,000.00
55,000.00
1,600,000.00
1,100,000.00
3,500,000.00
55,000.00
55,000.00
1,600,000.00
1,100,000.00
3,500,000.00
ea
ea
ea
unit
unit
m
55,000.00
75,000.00
110,000.00
2,450,000.00
775,000.00
7,500.00
55,000.00
75,000.00
110,000.00
2,450,000.00
775,000.00
7,500.00
unit
unit
unit
unit
m
1,925,000.00
962,500.00
2,035,000.00
1,650,000.00
3,500.00
1,925,000.00
962,500.00
2,035,000.00
1,650,000.00
3,500.00
SAT
HRG. SAT
(Rp)
1.00
2.00
4.00
1.00
2.00
3.00
1.00
6.00
6.00
6.00
2.00
2.00
2.00
2.00
6.00
1.00
3.00
1.25
1.00
unit
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
m'
m'
ls
12,500,000.00
250,000.00
235,000.00
175,000.00
160,000.00
145,000.00
130,000.00
100,000.00
125,000.00
150,000.00
200,000.00
125,000.00
135,000.00
150,000.00
640,000.00
175,000.00
130,000.00
350,000.00
2,331,250.00
13.00
16.00
1.00
OH
OH
ls
55,000.00
47,000.00
8,975,312.50
VOL
MATERIAL
LABOUR
TOTAL
(Rp)
PANEL
PANEL LVMDP
a Bahan
Box panel 200 x 80 x 60 cm
MCCB 252-630 A 3P
MCCB 200-250 A 3P
MCCB 100-125 A 3P
MCCB 80-100 A 3P
MCCB 63-80 A 3P
MCCB 50 A 3P
Indicator Lamp
Fuse 4A
Ampermeter
Volt meter
Selector switch
Cosphi meter
kWH Meter
CT 800/5A
Arrester
Grounding cable BC 70 mm2
Busbar CU 5 (100 x 5 mm)
Accessories
b Upah
- Tukang Listrik
- Pembantu
- Peralatan
SDP-KANTOR
a Bahan
Box panel 80 x 60 x 40 cm
MCCB 125-160 A 3P
MCCB 125-140 A 3P
MCCB 80-100 A 3P
MCCB 64-80 A 3P
MCCB 50 A 3P
Indicator Lamp
Fuse 4A
Ampermeter
Volt meter
Selector switch
Arrester
Grounding cable BC 50 mm2
Busbar CU 5 (20 x 5 mm)
Accessories
b Upah
- Tukang Listrik
- Pembantu
- Peralatan
1.00
1.00
1.00
1.00
10.00
10.00
1.00
unit
bh
bh
bh
bh
bh
ls
10,000,000.00
250,000.00
150,000.00
235,000.00
120,000.00
120,000.00
1,303,500.00
11.00
16.00
1.00
OH
OH
ls
55,000.00
47,000.00
5,018,475.00
1.00
1.00
1.00
2.00
3.00
3.00
3.00
3.00
3.00
1.00
1.00
1.00
3.00
1.25
1.00
unit
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
m'
m'
ls
8,000,000.00
190,000.00
190,000.00
160,000.00
145,000.00
130,000.00
100,000.00
125,000.00
150,000.00
200,000.00
125,000.00
175,000.00
115,000.00
225,000.00
1,177,625.00
7.00
5.00
1.00
OH
OH
ls
55,000.00
47,000.00
4,533,856.25
12,500,000.00
500,000.00
940,000.00
175,000.00
320,000.00
435,000.00
130,000.00
600,000.00
750,000.00
900,000.00
400,000.00
250,000.00
270,000.00
300,000.00
3,840,000.00
175,000.00
390,000.00
437,500.00
2,331,250.00
715,000.00
752,000.00
8,975,312.50
Sub total
36,086,062.50
605,000.00
752,000.00
5,018,475.00
Sub total
20,713,975.00
385,000.00
235,000.00
4,533,856.25
Sub total
18,107,731.25
10,000,000.00
250,000.00
150,000.00
235,000.00
1,200,000.00
1,200,000.00
1,303,500.00
8,000,000.00
190,000.00
190,000.00
320,000.00
435,000.00
390,000.00
300,000.00
375,000.00
450,000.00
200,000.00
125,000.00
175,000.00
345,000.00
281,250.00
1,177,625.00
URAIAN PEKERJAAN
SDP-WORKSHOP
a Bahan
Box panel 80 x 60 x 40 cm
MCCB 320-800 A 3P
MCCB 125-140 A 3P
MCCB 80-100 A 3P
MCCB 64-80 A 3P
MCCB 50 A 3P
Indicator Lamp
Fuse 4A
Ampermeter
Volt meter
Selector switch
Arrester
Grounding cable BC 50 mm2
Busbar CU 5 (20 x 5 mm)
Accessories
b Upah
- Tukang Listrik
- Pembantu
- Peralatan
PP- AC- L1
a Bahan
Box panel 80 x 60 x 40 cm
MCB 32 A 3P
MCB 20 A 1P
MCB 10 A 1P
Indicator Lamp
Fuse 4A
Volt meter
Selector switch
Grounding cable BC 25 mm2
Busbar CU 5 (15 x 3 mm)
Accessories
b Upah
- Tukang Listrik
- Pembantu
- Peralatan
PP- AC- L2
a Bahan
Box panel 80 x 60 x 40 cm
MCCB 100-125 A 3P
MCB 20 A 1P
MCB 16 A 1P
MCB 10 A 1P
Indicator Lamp
Fuse 4A
Volt meter
Selector switch
Grounding cable BC 25 mm2
Busbar CU 5 (15 x 3 mm)
Accessories
b Upah
- Tukang Listrik
- Pembantu
- Peralatan
VOL
SAT
HRG. SAT
(Rp)
1.00
1.00
1.00
2.00
3.00
3.00
3.00
3.00
3.00
1.00
1.00
1.00
3.00
1.25
1.00
unit
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
m'
m'
ls
8,000,000.00
265,000.00
190,000.00
160,000.00
145,000.00
130,000.00
100,000.00
125,000.00
150,000.00
200,000.00
125,000.00
175,000.00
115,000.00
225,000.00
1,185,125.00
7.00
9.00
1.00
OH
OH
ls
55,000.00
47,000.00
4,562,731.25
1.00
1.00
5.00
7.00
3.00
3.00
1.00
1.00
3.00
1.25
1.00
unit
bh
bh
bh
bh
bh
bh
bh
m'
m'
ls
8,000,000.00
105,000.00
55,000.00
35,000.00
100,000.00
125,000.00
200,000.00
125,000.00
85,000.00
200,000.00
1,013,000.00
7.00
5.00
1.00
OH
OH
ls
55,000.00
47,000.00
3,900,050.00
1.00
1.00
12.00
2.00
1.00
3.00
3.00
1.00
1.00
3.00
1.25
1.00
unit
bh
bh
bh
bh
bh
bh
bh
bh
m'
m'
ls
8,000,000.00
175,000.00
55,000.00
45,000.00
35,000.00
100,000.00
125,000.00
200,000.00
125,000.00
85,000.00
200,000.00
1,046,500.00
7.00
5.00
1.00
OH
OH
ls
55,000.00
47,000.00
4,029,025.00
MATERIAL
LABOUR
TOTAL
(Rp)
8,000,000.00
265,000.00
190,000.00
320,000.00
435,000.00
390,000.00
300,000.00
375,000.00
450,000.00
200,000.00
125,000.00
175,000.00
345,000.00
281,250.00
1,185,125.00
385,000.00
423,000.00
4,562,731.25
Sub total
18,407,106.25
385,000.00
235,000.00
3,900,050.00
Sub total
15,663,050.00
385,000.00
235,000.00
4,029,025.00
Sub total
16,160,525.00
8,000,000.00
105,000.00
275,000.00
245,000.00
300,000.00
375,000.00
200,000.00
125,000.00
255,000.00
250,000.00
1,013,000.00
8,000,000.00
175,000.00
660,000.00
90,000.00
35,000.00
300,000.00
375,000.00
200,000.00
125,000.00
255,000.00
250,000.00
1,046,500.00
URAIAN PEKERJAAN
PP- WORKSHOP
a Bahan
Box Panel 60 x 40 x 20 cm
MCCB 125 -160 A 3P
MCB 40 A 3P
MCB 16 A 1P
Indicator Lamp
Fuse 4A
Volt meter
Selector switch
Grounding cable BC 25 mm2
Busbar CU 5 (15 x 3 mm2)
Accessories
b Upah
- Tukang Listrik
- Pembantu
- Peralatan
PP- Kantor L1
a Bahan
Box Panel 60 x 40 x 20 cm
MCCB 32 A 3P
MCB 10 A 1P
Indicator Lamp
Fuse 4A
Volt meter
Selector switch
Grounding cable BC 25 mm2
Busbar CU 5 (15 x 3 mm2)
Accessories
b Upah
- Tukang Listrik
- Pembantu
- Peralatan
PP- Kantor L2
a Bahan
Box Panel 60 x 40 x 20 cm
MCB 40 A 3P
MCB 10 A 1P
Indicator Lamp
Fuse 4A
Volt meter
Selector switch
Grounding cable BC 25 mm2
Busbar CU 5 (15 x 3 mm2)
Accessories
b Upah
- Tukang Listrik
- Pembantu
- Peralatan
VOL
SAT
HRG. SAT
(Rp)
1.00
1.00
1.00
12.00
3.00
3.00
1.00
1.00
3.00
1.25
1.00
unit
bh
bh
bh
bh
bh
bh
bh
m'
m'
ls
7,500,000.00
190,000.00
115,000.00
45,000.00
100,000.00
125,000.00
200,000.00
125,000.00
85,000.00
200,000.00
985,000.00
7.00
5.00
1.00
OH
OH
ls
55,000.00
47,000.00
3,792,250.00
1.00
1.00
12.00
3.00
3.00
1.00
1.00
3.00
1.25
1.00
unit
bh
bh
bh
bh
bh
bh
m'
m'
ls
7,500,000.00
110,000.00
35,000.00
100,000.00
125,000.00
200,000.00
125,000.00
85,000.00
200,000.00
953,500.00
7.00
5.00
1.00
OH
OH
ls
55,000.00
47,000.00
3,670,975.00
1.00
1.00
15.00
3.00
3.00
1.00
1.00
3.00
1.25
1.00
unit
bh
bh
bh
bh
bh
bh
m'
m'
ls
7,500,000.00
115,000.00
35,000.00
100,000.00
125,000.00
200,000.00
125,000.00
85,000.00
200,000.00
964,500.00
7.00
5.00
1.00
OH
OH
ls
55,000.00
47,000.00
3,713,325.00
MATERIAL
LABOUR
TOTAL
(Rp)
7,500,000.00
190,000.00
115,000.00
540,000.00
300,000.00
375,000.00
200,000.00
125,000.00
255,000.00
250,000.00
985,000.00
385,000.00
235,000.00
3,792,250.00
Sub total
15,247,250.00
385,000.00
235,000.00
3,670,975.00
Sub total
14,779,475.00
385,000.00
235,000.00
3,713,325.00
Sub total
14,942,825.00
7,500,000.00
110,000.00
420,000.00
300,000.00
375,000.00
200,000.00
125,000.00
255,000.00
250,000.00
953,500.00
7,500,000.00
115,000.00
525,000.00
300,000.00
375,000.00
200,000.00
125,000.00
255,000.00
250,000.00
964,500.00
URAIAN PEKERJAAN
PP- CRANE
a Bahan
Box Panel 60 x 40 x 20 cm
MCCB 64-80 A 3P
MCB 40 A 3P
MCB 16 A 1P
Indicator Lamp
Fuse 4A
Ampermeter
Volt meter
Selector switch
CT 160/5A
Grounding cable BC 25 mm2
Busbar CU 5 (15 x 3 mm2)
Accessories
b Upah
- Tukang Listrik
- Pembantu
- Peralatan
LP- Kantor L1
a Bahan
Box Panel 60 x 40 x 20 cm
MCB 32 A 3P
MCB 6 A 1P
Indicator Lamp
Fuse 4A
Volt meter
Selector switch
Grounding cable BC 25 mm2
Busbar CU 5 (15 x 3 mm2)
Accessories
b Upah
- Tukang Listrik
- Pembantu
- Peralatan
VOL
SAT
HRG. SAT
(Rp)
1.00
1.00
2.00
1.00
3.00
3.00
3.00
1.00
1.00
3.00
3.00
1.25
1.00
unit
bh
bh
bh
bh
bh
bh
bh
bh
bh
m'
m'
ls
7,500,000.00
145,000.00
120,000.00
45,000.00
100,000.00
125,000.00
150,000.00
200,000.00
125,000.00
80,000.00
85,000.00
200,000.00
1,012,500.00
7.00
5.00
1.00
OH
OH
ls
55,000.00
47,000.00
3,898,125.00
1.00
1.00
1.00
2.00
2.00
3.00
3.00
3.00
1.00
1.00
3.00
3.00
1.25
1.00
unit
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
m'
m'
ls
7,500,000.00
145,000.00
75,000.00
65,000.00
55,000.00
100,000.00
125,000.00
150,000.00
200,000.00
125,000.00
80,000.00
85,000.00
200,000.00
1,015,500.00
7.00
5.00
1.00
OH
OH
ls
55,000.00
47,000.00
3,909,675.00
1.00
1.00
15.00
3.00
3.00
1.00
1.00
3.00
1.25
1.00
unit
bh
bh
bh
bh
bh
bh
m'
m'
ls
7,500,000.00
105,000.00
25,000.00
100,000.00
125,000.00
200,000.00
125,000.00
85,000.00
200,000.00
948,500.00
7.00
5.00
1.00
OH
OH
ls
55,000.00
47,000.00
3,651,725.00
MATERIAL
LABOUR
TOTAL
(Rp)
7,500,000.00
145,000.00
240,000.00
45,000.00
300,000.00
375,000.00
450,000.00
200,000.00
125,000.00
240,000.00
255,000.00
250,000.00
1,012,500.00
385,000.00
235,000.00
3,898,125.00
Sub total
15,655,625.00
385,000.00
235,000.00
3,909,675.00
Sub total
15,700,175.00
385,000.00
235,000.00
3,651,725.00
Sub total
14,705,225.00
7,500,000.00
145,000.00
75,000.00
130,000.00
110,000.00
300,000.00
375,000.00
450,000.00
200,000.00
125,000.00
240,000.00
255,000.00
250,000.00
1,015,500.00
7,500,000.00
105,000.00
375,000.00
300,000.00
375,000.00
200,000.00
125,000.00
255,000.00
250,000.00
948,500.00
URAIAN PEKERJAAN
LP- Kantor L2
a Bahan
Box Panel 60 x 40 x 20 cm
MCB 32 A 3P
MCB 6 A 1P
Indicator Lamp
Fuse 4A
Volt meter
Selector switch
Grounding cable BC 25 mm2
Busbar CU 5 (15 x 3 mm2)
Accessories
b Upah
- Tukang Listrik
- Pembantu
- Peralatan
LP- WORKSHOP
a Bahan
Box Panel 60 x 40 x 20 cm
MCCB 80-100 A 3P
MCB 16 A 1P
Indicator Lamp
Fuse 4A
Volt meter
Selector switch
Grounding cable BC 25 mm2
Busbar CU 5 (15 x 3 mm2)
Accessories
b Upah
- Tukang Listrik
- Pembantu
- Peralatan
VOL
SAT
HRG. SAT
(Rp)
1.00
1.00
18.00
3.00
3.00
1.00
1.00
3.00
1.25
1.00
unit
bh
bh
bh
bh
bh
bh
m'
m'
ls
7,500,000.00
105,000.00
25,000.00
100,000.00
125,000.00
200,000.00
125,000.00
85,000.00
200,000.00
956,000.00
7.00
5.00
1.00
OH
OH
ls
55,000.00
47,000.00
3,680,600.00
1.00
1.00
25.00
3.00
3.00
1.00
1.00
3.00
1.25
1.00
unit
bh
bh
bh
bh
bh
bh
m'
m'
ls
7,500,000.00
160,000.00
45,000.00
100,000.00
125,000.00
200,000.00
125,000.00
85,000.00
200,000.00
1,029,000.00
7.00
5.00
1.00
OH
OH
ls
55,000.00
47,000.00
3,961,650.00
1.00
1.00
9.00
3.00
3.00
1.00
1.00
1.00
1.00
3.00
1.25
1.00
unit
bh
bh
bh
bh
bh
bh
bh
bh
m'
m'
ls
7,500,000.00
160,000.00
35,000.00
100,000.00
125,000.00
200,000.00
125,000.00
120,000.00
350,000.00
85,000.00
200,000.00
995,000.00
7.00
5.00
1.00
OH
OH
ls
55,000.00
47,000.00
3,830,750.00
1.00
2.00
bh
bh
45,000.00
55,000.00
5.00
155,000.00
MATERIAL
LABOUR
TOTAL
(Rp)
7,500,000.00
105,000.00
450,000.00
300,000.00
375,000.00
200,000.00
125,000.00
255,000.00
250,000.00
956,000.00
385,000.00
235,000.00
3,680,600.00
Sub total
14,816,600.00
385,000.00
235,000.00
3,961,650.00
Sub total
15,900,650.00
385,000.00
235,000.00
3,830,750.00
Sub total
15,395,750.00
775,000.00
Sub total
930,000.00
7,500,000.00
160,000.00
1,125,000.00
300,000.00
375,000.00
200,000.00
125,000.00
255,000.00
250,000.00
1,029,000.00
7,500,000.00
160,000.00
315,000.00
300,000.00
375,000.00
200,000.00
125,000.00
120,000.00
350,000.00
255,000.00
250,000.00
995,000.00
45,000.00
110,000.00
URAIAN PEKERJAAN
VOL
SAT
HRG. SAT
(Rp)
MATERIAL
LABOUR
TOTAL
(Rp)
KABEL
NYY 4 X 16 mm
NYY 4 X 16 mm2
Tenaga Kerja :
Mandor
Tukang listrik
Pembantu tukang listrik
NYY 4X10 mm
NYY 4X10 mm
Tenaga Kerja :
Mandor
Tukang listrik
Pembantu tukang listrik
NYY 4X6 mm
NYY 4X6 mm
Tenaga Kerja :
Mandor
Tukang listrik
Pembantu tukang listrik
NYY 4X25mm
NYY 4X25mm
Tenaga Kerja :
Mandor
Tukang listrik
Pembantu tukang listrik
NYY 4X35 mm
NYY 4X35 mm
Tenaga Kerja :
Mandor
Tukang listrik
Pembantu tukang listrik
NYY 1X50 mm
NYY 1X50 mm
Tenaga Kerja :
Mandor
Tukang listrik
Pembantu tukang listrik
NYFGbY 4(1x240) mm
NYFGbY 4(1x240) mm
Galian
Pasir Urug
Bata
Pemadatan
Accessories
Tenaga Kerja :
Tukang listrik
Pembantu tukang listrik
Peralatan
1.00
80,000.00
0.01
0.02
0.02
Oh
Oh
Oh
70,000.00
55,000.00
47,000.00
1.00
70,000.00
0.01
0.02
0.02
Oh
Oh
Oh
70,000.00
55,000.00
47,000.00
1.00
45,000.00
0.01
0.02
0.02
Oh
Oh
Oh
70,000.00
55,000.00
47,000.00
1.00
95,000.00
0.02
0.03
0.03
Oh
Oh
Oh
70,000.00
55,000.00
47,000.00
1.00
130,000.00
0.02
0.03
0.03
Oh
Oh
Oh
70,000.00
55,000.00
47,000.00
1.00
45,000.00
0.02
0.03
0.03
Oh
Oh
Oh
70,000.00
55,000.00
47,000.00
1.00
0.65
0.22
15.00
0.52
1.00
m
m3
m3
Bh
m3
ls
75,000.00
48,500.00
134,375.00
70,992.00
32,250.00
121,773.75
0.06
0.08
1.00
Oh
Oh
Oh
55,000.00
47,000.00
468,828.94
80,000.00
700.00
1,100.00
940.00
Sub total
82,740.00
700.00
1,100.00
940.00
Sub total
72,740.00
700.00
1,100.00
940.00
Sub total
47,740.00
1,400.00
1,650.00
1,410.00
Sub total
99,460.00
1,400.00
1,650.00
1,410.00
Sub total
134,460.00
1,400.00
1,650.00
1,410.00
Sub total
49,460.00
3,300.00
3,760.00
468,828.94
Sub total
1,815,400.19
70,000.00
45,000.00
95,000.00
130,000.00
45,000.00
75,000.00
31,525.00
29,562.50
1,064,880.00
16,770.00
121,773.75
URAIAN PEKERJAAN
FRC 4X6mm
FRC 4X6mm
BC 4 mm
Tenaga Kerja :
Mandor
Tukang listrik
Pembantu tukang listrik
FRC 4X4 mm
FRC 4X4 mm
BC 4 mm
Tenaga Kerja :
Mandor
Tukang listrik
Pembantu tukang listrik
FRC 5X6 mm
FRC 5X6 mm
BC 6 mm
Tenaga Kerja :
Mandor
Tukang listrik
Pembantu tukang listrik
FRC 5X4 mm
FRC 5X4 mm
BC 4 mm
Tenaga Kerja :
Mandor
Tukang listrik
Pembantu tukang listrik
FRC 5X25 mm
FRC 5X25 mm
BC 10 mm
Tenaga Kerja :
Mandor
Tukang listrik
Pembantu tukang listrik
CABLE TRAY
Cabel Tray
a Bahan
-Kabel Tray 200 x 100 mm
- Elbow 200 x 100 mm
-Tee 200 x 100 mm
-Support material (jarak 2 m)
-Accessories
b Tenaga
-Pekerja
-Tukang Listrik
-Peralatan
VOL
SAT
HRG. SAT
(Rp)
1.00
1.00
m
m
46,000.00
25,000.00
0.03
0.05
0.05
Oh
Oh
Oh
70,000.00
55,000.00
47,000.00
1.00
1.00
m
m
33,000.00
25,000.00
0.03
0.05
0.05
Oh
Oh
Oh
70,000.00
55,000.00
47,000.00
1.00
1.00
m
m
115,000.00
40,000.00
0.03
0.05
0.05
Oh
Oh
Oh
70,000.00
55,000.00
47,000.00
1.00
1.00
m
m
90,000.00
25,000.00
0.03
0.05
0.05
Oh
Oh
Oh
70,000.00
55,000.00
47,000.00
1.00
1.00
m
m
150,000.00
55,000.00
0.02
0.03
0.03
Oh
Oh
Oh
70,000.00
55,000.00
47,000.00
1.10
0.03
0.02
1.00
1.00
m'
ea
ea
ls
ls
85,000.00
38,000.00
38,000.00
9,513.40
10,464.74
0.12
0.13
1.00
OH
OH
ls
47,000.00
55,000.00
40,289.25
MATERIAL
LABOUR
TOTAL
(Rp)
46,000.00
25,000.00
2,100.00
2,750.00
2,350.00
Sub total
78,200.00
2,100.00
2,750.00
2,350.00
Sub total
65,200.00
2,100.00
2,750.00
2,350.00
Sub total
162,200.00
2,100.00
2,750.00
2,350.00
Sub total
122,200.00
1,400.00
1,650.00
1,410.00
Sub total
209,460.00
5,828.00
6,875.00
40,289.25
Sub Total
168,104.39
33,000.00
25,000.00
115,000.00
40,000.00
90,000.00
25,000.00
150,000.00
55,000.00
93,500.00
950.00
684.00
9,513.40
10,464.74
URAIAN PEKERJAAN
Cabel Tray
a Bahan
-Kabel Tray 300 x 100 mm
-Elbow 300 x 100 mm
-Tee 300 x 100 mm
-Support material (jarak 2 m)
-Accessories
b Tenaga
-Pekerja
-Tukang Listrik
-Peralatan
Cabel Ladder
a Bahan
-Kabel Tray 300 x 100 mm
-Support material
-Accessories
b Tenaga
-Pekerja
-Tukang Listrik
-Peralatan
VOL
SAT
HRG. SAT
(Rp)
1.10
0.03
0.02
1.00
1.00
m'
ea
ea
ls
ls
90,000.00
40,000.00
40,000.00
10,072.00
11,079.20
0.12
0.13
1.00
OH
OH
ls
47,000.00
55,000.00
42,654.92
1.10
1.00
1.00
m'
ls
ls
90,000.00
9,900.00
10,890.00
0.12
0.13
1.00
OH
OH
ls
47,000.00
55,000.00
41,926.50
1.10
0.03
0.02
1.00
1.00
m'
ea
ea
ls
ls
96,000.00
45,000.00
45,000.00
10,753.50
11,828.85
0.12
0.13
1.00
OH
OH
ls
47,000.00
55,000.00
45,541.07
MATERIAL
LABOUR
TOTAL
(Rp)
99,000.00
1,000.00
720.00
10,072.00
11,079.20
5,828.00
6,875.00
42,654.92
Sub Total
177,229.12
5,828.00
6,875.00
41,926.50
Sub Total
174,419.50
5,828.00
6,875.00
45,541.07
Sub Total
188,361.42
1,170,000.00
Sub Total
1,404,000.00
870,000.00
Sub Total
1,044,000.00
870,000.00
Sub Total
1,044,000.00
99,000.00
9,900.00
10,890.00
105,600.00
1,125.00
810.00
10,753.50
11,828.85
TITIK LAMPU
Lampu TLD 2x36 W COVER ACR
Bahan :
-TBS 318 236 IC M2
-TLD 36 Watt
Tenaga Kerja:
Pekerja
1.10
2.00
Bh
Bh
40,000.00
95,000.00
5.00
234,000.00
1.10
2.00
Bh
Bh
40,000.00
65,000.00
5.00
174,000.00
1.10
2.00
Bh
Bh
40,000.00
65,000.00
5.00
174,000.00
44,000.00
190,000.00
44,000.00
130,000.00
44,000.00
130,000.00
URAIAN PEKERJAAN
Lampu Down Light 1x14 W
Bahan :
FBH 058 114 I
PLC 14 Watt
Tenaga:
Pekerja
VOL
SAT
HRG. SAT
(Rp)
1.10
1.00
Bh
Bh
60,000.00
75,000.00
5.00
141,000.00
1.10
1.00
Bh
Bh
60,000.00
110,000.00
5.00
176,000.00
1.10
Bh
50,000.00
5.00
55,000.00
1.10
Bh
150,000.00
5.00
165,000.00
119.00
78.70
96.00
1,920.00
m'
kg
bh
cm
15,000.00
18,095.00
2,500.00
1,316.00
1.10
Bh
250,000.00
5.00
275,000.00
2.00
2.00
Bh
Bh
75,000.00
60,000.00
5.00
270,000.00
MATERIAL
LABOUR
TOTAL
(Rp)
66,000.00
75,000.00
705,000.00
Sub Total
846,000.00
880,000.00
Sub Total
1,056,000.00
275,000.00
Sub Total
330,000.00
825,000.00
Sub Total
990,000.00
Sub Total
5,975,796.50
1,375,000.00
Sub Total
1,650,000.00
1,350,000.00
Sub Total
1,620,000.00
11,666.67
16,500.00
14,100.00
Sub Total
582,266.67
66,000.00
110,000.00
55,000.00
165,000.00
1,785,000.00
1,424,076.50
240,000.00
2,526,720.00
275,000.00
150,000.00
120,000.00
TITIK INSTALASI
Titik Instalasi Daya AC
Bahan :
Kabel, NYM 3 x 2,5 mm2
Pipa Conduit
Isolasi ban
Tenaga Kerja :
Mandor
Tukang listrik
Pembantu tukang listrik
25.00
25.00
1.00
m'
m'
bh
14,000.00
7,500.00
2,500.00
0.17
0.30
0.30
OH
OH
OH
70,000.00
55,000.00
47,000.00
350,000.00
187,500.00
2,500.00
URAIAN PEKERJAAN
Titik Instalasi Exhaust Fan
Bahan :
Kabel, NYM 3 x 2,5 mm2
Pipa Conduit
Isolasi ban
Tenaga Kerja :
Mandor
Tukang listrik
Pembantu tukang listrik
VOL
SAT
HRG. SAT
(Rp)
8.00
8.00
1.00
m'
m'
bh
14,000.00
7,500.00
2,500.00
0.12
0.30
0.30
OH
OH
OH
70,000.00
55,000.00
47,000.00
10.00
10.00
1.00
2.00
3.00
3.00
2.00
0.25
m
m
Bh
Bh
Bh
Bh
Bh
Bh
14,000.00
7,500.00
750.00
2,500.00
600.00
350.00
300.00
2,500.00
0.17
0.30
0.30
Oh
Oh
Oh
70,000.00
55,000.00
47,000.00
m
m
Bh
Bh
Bh
Bh
Bh
Bh
14,000.00
7,500.00
750.00
2,500.00
600.00
350.00
300.00
2,500.00
Oh
Oh
Oh
70,000.00
55,000.00
47,000.00
4,500.00
7,500.00
750.00
2,500.00
600.00
350.00
300.00
2,500.00
70,000.00
55,000.00
47,000.00
MATERIAL
LABOUR
TOTAL
(Rp)
112,000.00
60,000.00
2,500.00
8,400.00
16,500.00
14,100.00
Sub Total
213,500.00
11,666.67
16,500.00
14,100.00
Sub Total
267,091.67
11,666.67
16,500.00
14,100.00
Sub Total
803,591.67
11,666.67
16,500.00
14,100.00
Sub Total
471,091.67
140,000.00
75,000.00
750.00
5,000.00
1,800.00
1,050.00
600.00
625.00
490,000.00
262,500.00
2,250.00
2,500.00
1,800.00
1,050.00
600.00
625.00
157,500.00
262,500.00
2,250.00
2,500.00
1,800.00
1,050.00
600.00
625.00
URAIAN PEKERJAAN
VOL
SAT
HRG. SAT
(Rp)
m
m
Bh
Bh
Bh
Bh
Bh
Bh
14,000.00
7,500.00
750.00
2,500.00
600.00
350.00
300.00
2,500.00
Oh
Oh
Oh
70,000.00
55,000.00
47,000.00
m
m
Bh
Bh
Bh
Bh
Bh
Bh
40,000.00
7,500.00
750.00
2,500.00
600.00
350.00
300.00
2,500.00
Oh
Oh
Oh
70,000.00
55,000.00
47,000.00
15.00
15.00
1.00
2.00
3.00
3.00
0.25
m
m
Bh
Bh
Bh
Bh
Bh
30,000.00
7,500.00
750.00
2,500.00
600.00
350.00
2,500.00
0.17
0.30
0.30
Oh
Oh
Oh
70,000.00
55,000.00
47,000.00
20.00
20.00
1.00
2.00
3.00
3.00
0.25
m
m
Bh
Bh
Bh
Bh
Bh
7,500.00
7,500.00
750.00
2,500.00
600.00
350.00
2,500.00
0.17
0.30
0.30
Oh
Oh
Oh
70,000.00
55,000.00
47,000.00
MATERIAL
LABOUR
TOTAL
(Rp)
210,000.00
112,500.00
750.00
5,000.00
1,800.00
1,050.00
600.00
625.00
11,666.67
16,500.00
14,100.00
Sub total
374,591.67
11,666.67
16,500.00
14,100.00
Sub total
764,591.67
11,666.67
16,500.00
14,100.00
Sub total
613,991.67
11,666.67
16,500.00
14,100.00
Sub total
351,491.67
600,000.00
112,500.00
750.00
5,000.00
1,800.00
1,050.00
600.00
625.00
450,000.00
112,500.00
750.00
5,000.00
1,800.00
1,050.00
625.00
150,000.00
150,000.00
750.00
5,000.00
1,800.00
1,050.00
625.00
URAIAN PEKERJAAN
Titik Instalasi Fire Alarm
Bahan :
Kabel, NYMHY 2 x 1,5 mm2
Pipa Conduit
Socket Pipa
Tee Doos
Klem Pipa
Fhiser
Isolasi ban
Tenaga Kerja :
Mandor
Tukang listrik
Pembantu tukang listrik
TBT-40 Pairs
Bahan:
-TBT-10 Pairs
-Accessories
Tenaga Kerja :
Tukang listrik
Pembantu tukang listrik
Peralatan
TB-FA. A 20 pairs
Bahan:
-TB-FA. A 20 pairs
-Accessories
Tenaga Kerja:
- Tukang listrik
- Pembantu Tukang Listrik
- Peralatan
VOL
SAT
HRG. SAT
(Rp)
15.00
15.00
1.00
2.00
3.00
3.00
0.25
m
m
Bh
Bh
Bh
Bh
Bh
25,000.00
7,500.00
750.00
2,500.00
600.00
350.00
2,500.00
0.17
0.30
0.30
Oh
Oh
Oh
70,000.00
55,000.00
47,000.00
15.00
15.00
1.00
2.00
3.00
3.00
0.25
m
m
Bh
Bh
Bh
Bh
Bh
3,000.00
7,500.00
750.00
2,500.00
600.00
350.00
2,500.00
0.17
0.30
0.30
Oh
Oh
Oh
70,000.00
55,000.00
47,000.00
75.00
75.00
75.00
15.00
15.00
0.25
m
m
m
Bh
Bh
Bh
3,500.00
35,000.00
7,500.00
600.00
350.00
2,500.00
0.17
0.30
0.30
Oh
Oh
Oh
70,000.00
55,000.00
47,000.00
1.00
1.00
unit
ls
1,100,000.00
110,000.00
1.73
1.43
1.00
OH
OH
ls
55,000.00
47,000.00
423,500.00
1.00
1.00
unit
ls
120,000.00
12,000.00
2.30
2.53
1.00
OH
OH
ls
55,000.00
47,000.00
46,200.00
MATERIAL
LABOUR
TOTAL
(Rp)
375,000.00
112,500.00
750.00
5,000.00
1,800.00
1,050.00
625.00
11,666.67
16,500.00
14,100.00
Sub total
538,991.67
11,666.67
16,500.00
14,100.00
Sub total
208,991.67
11,666.67
16,500.00
14,100.00
Sub Total
3,507,141.67
95,150.00
67,210.00
423,500.00
Sub total
1,795,860.00
126,665.00
118,863.00
46,200.00
Sub total
423,728.00
45,000.00
112,500.00
750.00
5,000.00
1,800.00
1,050.00
625.00
262,500.00
2,625,000.00
562,500.00
9,000.00
5,250.00
625.00
1,100,000.00
110,000.00
120,000.00
12,000.00
URAIAN PEKERJAAN
TB-TS. SB 20 pairs
Bahan:
TB-TS. SB 20 pairs
-Accessories
Tenaga Kerja:
- Tukang listrik
- Pembantu Tukang Listrik
- Peralatan
VOL
SAT
HRG. SAT
(Rp)
1.00
1.00
unit
ls
3,750,000.00
375,000.00
1.25
2.06
1.00
OH
OH
ls
55,000.00
47,000.00
1,443,750.00
MATERIAL
LABOUR
TOTAL
(Rp)
3,750,000.00
375,000.00
68,750.00
96,585.00
1,443,750.00
Sub total
5,734,085.00
No.
Material
Unit
Harga
Satuan
Harga (Rp)
Kenaikan
Transport
5-8%
1%
5%
Over head/
profit
Total Harga
(Rp.)
Produk/
tipe
1%
DIVISI : MEKANIKAL
I
PIPA
a
1
2
m'
m'
65,000.00
110,000.00
650.00
1,100.00
3,250.00
5,500.00
650.00
1,100.00
69,550.00
117,700.00
b
1
2
3
4
5
6
7
8
9
10
11
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
5,000.00
9,000.00
15,000.00
18,000.00
20,000.00
25,000.00
30,000.00
35,000.00
45,000.00
60,000.00
70,000.00
50.00
90.00
150.00
180.00
200.00
250.00
300.00
350.00
450.00
600.00
700.00
250.00
450.00
750.00
900.00
1,000.00
1,250.00
1,500.00
1,750.00
2,250.00
3,000.00
3,500.00
50.00
90.00
150.00
180.00
200.00
250.00
300.00
350.00
450.00
600.00
700.00
5,350.00
9,630.00
16,050.00
19,260.00
21,400.00
26,750.00
32,100.00
37,450.00
48,150.00
64,200.00
74,900.00
c
1
2
3
4
bh
bh
bh
bh
20,000.00
10,000.00
25,000.00
15,000.00
200.00
100.00
250.00
150.00
1,000.00
500.00
1,250.00
750.00
200.00
100.00
250.00
150.00
21,400.00
10,700.00
26,750.00
16,050.00
II
bh
bh
bh
bh
200,000.00
275,000.00
300,000.00
450,000.00
2,000.00
2,750.00
3,000.00
4,500.00
10,000.00
13,750.00
15,000.00
22,500.00
2,000.00
2,750.00
3,000.00
4,500.00
214,000.00
294,250.00
321,000.00
481,500.00
bh
250,000.00
2,500.00
12,500.00
2,500.00
267,500.00
bh
350,000.00
3,500.00
17,500.00
3,500.00
374,500.00
bh
350,000.00
3,500.00
17,500.00
3,500.00
374,500.00
bh
300,000.00
3,000.00
15,000.00
3,000.00
321,000.00
unit
unit
unit
unit
unit
50,000.00
60,000.00
75,000.00
145,000.00
62,500.00
500.00
600.00
750.00
1,450.00
625.00
2,500.00
3,000.00
3,750.00
7,250.00
3,125.00
500.00
600.00
750.00
1,450.00
625.00
53,500.00
64,200.00
80,250.00
155,150.00
66,875.00
bh
bh
750,000.00
1,250,000.00
7,500.00
12,500.00
37,500.00
62,500.00
7,500.00
12,500.00
802,500.00
1,337,500.00
unit
2,500,000.00
25,000.00
125,000.00
25,000.00
2,675,000.00
III SANITAIR
1 Bahan Stainless Steel
Clean Out, tipe H58-2
Clean Out, tipe H58-3
Clean Out, tipe H58-4
2 Roof Drain Dia. 125 (5")
Roof Drain Dia. 80 (3")
IV FIRE FIGHTING SYSTEM
1 Fire Extinguisher, Dry Chemical
Kapasitas : 3 kg
Kapasitas : 6 kg
IV AIR CONDITIONER
1 AC SPLIT 0,5 PK
Split Wall Mounted
Kapasitas : 0,5 PK
No.
Material
Unit
Harga
Satuan
Harga (Rp)
Kenaikan
Transport
5-8%
1%
5%
Over head/
profit
Total Harga
(Rp.)
Produk/
tipe
1%
2 AC SPLIT 0,75 PK
Split Wall Mounted
Kapasitas : 0,75 PK
unit
3,200,000.00
32,000.00
160,000.00
32,000.00
3,424,000.00
unit
4,000,000.00
40,000.00
200,000.00
40,000.00
4,280,000.00
unit
5,600,000.00
56,000.00
280,000.00
56,000.00
5,992,000.00
unit
4,500,000.00
45,000.00
225,000.00
45,000.00
4,815,000.00
unit
1,400,000.00
14,000.00
70,000.00
14,000.00
1,498,000.00
unit
2,200,000.00
22,000.00
110,000.00
22,000.00
2,354,000.00
unit
3,000,000.00
30,000.00
150,000.00
30,000.00
3,210,000.00
3 AC SPLIT 1 PK
Split Wall Mounted
Kapasitas : 1 PK
5 AC SPLIT 2 PK
Split Wall Mounted
Kapasitas : 2 PK
m
m
m
m
175,000.00
185,000.00
200,000.00
225,000.00
1,750.00
1,850.00
2,000.00
2,250.00
8,750.00
9,250.00
10,000.00
11,250.00
1,750.00
1,850.00
2,000.00
2,250.00
187,250.00
197,950.00
214,000.00
240,750.00
bh
400,000.00
4,000.00
20,000.00
4,000.00
428,000.00
URAIAN PEKERJAAN
I M' PIPA GSP MEDIUM dia. 1"
Bahan :
Pipa PVC GSP Medium dia. 1"
Galian & Urugan tanah
VOLUME
SATUAN
HARGA (Rp)
JUMLAH (Rp)
1.050
0.280
m'
m3
69,550.00
89,597.00
73,027.50
25,087.16
0.020
0.010
0.005
hr
hr
hr
55,000.00
60,000.00
70,000.00
Jumlah
1,100.00
600.00
350.00
100,164.66
100,160.00
Upah :
Tukang pipa
Kepala tukang pipa
Mandor
Rp
Rp
1.050
0.280
m'
m3
117,700.00
89,597.00
123,585.00
25,087.16
0.020
0.010
0.005
hr
hr
hr
55,000.00
60,000.00
70,000.00
Jumlah
1,100.00
600.00
350.00
150,722.16
150,720.00
Upah :
Tukang pipa
Kepala tukang pipa
Mandor
Rp
Rp
1.200
35.000
m'
%
74,900.00
89,880.00
89,880.00
31,458.00
0.081
0.135
0.014
0.004
hr
hr
hr
hr
47,000.00
55,000.00
60,000.00
70,000.00
Jumlah
3,807.00
7,425.00
810.00
287.00
133,667.00
133,660.00
Upah :
Pekerja
Tukang pipa
Kepala tukang pipa
Mandor
Rp
Rp
1.200
35.000
m'
%
64,200.00
77,040.00
77,040.00
26,964.00
0.081
0.135
0.014
0.004
hr
hr
hr
hr
47,000.00
55,000.00
60,000.00
70,000.00
Jumlah
3,807.00
7,425.00
810.00
287.00
116,333.00
116,330.00
Upah :
Pekerja
Tukang pipa
Kepala tukang pipa
Mandor
Rp
Rp
1.200
35.000
m'
%
48,150.00
57,780.00
57,780.00
20,223.00
0.081
0.135
0.014
0.004
hr
hr
hr
hr
47,000.00
55,000.00
60,000.00
70,000.00
Jumlah
3,807.00
7,425.00
810.00
287.00
90,332.00
90,330.00
Upah :
Pekerja
Tukang pipa
Kepala tukang pipa
Mandor
Rp
Rp
No
URAIAN PEKERJAAN
I M' PIPA PVC TYPE AW dia. 3"
Bahan :
Pipa PVC tipe AW dia. 3"
Perlengkapan
VOLUME
SATUAN
HARGA (Rp)
JUMLAH (Rp)
1.200
35.000
m'
%
37,450.00
44,940.00
44,940.00
15,729.00
0.081
0.135
0.014
0.004
hr
hr
hr
hr
47,000.00
55,000.00
60,000.00
70,000.00
Jumlah
3,807.00
7,425.00
810.00
287.00
72,998.00
72,990.00
Upah :
Pekerja
Tukang pipa
Kepala tukang pipa
Mandor
Rp
Rp
1.200
35.000
m'
%
32,100.00
38,520.00
38,520.00
13,482.00
0.036
0.060
0.006
0.004
hr
hr
hr
hr
47,000.00
55,000.00
60,000.00
70,000.00
Jumlah
1,692.00
3,300.00
360.00
287.00
57,641.00
57,640.00
Upah :
Pekerja
Tukang pipa
Kepala tukang pipa
Mandor
Rp
Rp
1.200
35.000
m'
%
26,750.00
32,100.00
32,100.00
11,235.00
0.036
0.060
0.006
0.004
hr
hr
hr
hr
47,000.00
55,000.00
60,000.00
70,000.00
Jumlah
1,692.00
3,300.00
360.00
287.00
48,974.00
48,970.00
Upah :
Pekerja
Tukang pipa
Kepala tukang pipa
Mandor
Rp
Rp
1.200
35.000
m'
%
21,400.00
25,680.00
25,680.00
8,988.00
0.036
0.060
0.006
0.004
hr
hr
hr
hr
47,000.00
55,000.00
60,000.00
70,000.00
Jumlah
1,692.00
3,300.00
360.00
287.00
40,307.00
40,300.00
Upah :
Pekerja
Tukang pipa
Kepala tukang pipa
Mandor
Rp
Rp
1.200
35.000
m'
%
19,260.00
23,112.00
23,112.00
8,089.20
0.036
0.060
0.006
0.004
hr
hr
hr
hr
47,000.00
55,000.00
60,000.00
70,000.00
Jumlah
1,692.00
3,300.00
360.00
287.00
36,840.20
36,840.00
Upah :
Pekerja
Tukang pipa
Kepala tukang pipa
Mandor
Rp
Rp
No
URAIAN PEKERJAAN
I M' PIPA PVC TYPE AW dia. 1 "
Bahan :
Pipa PVC tipe AW dia. 1 "
Perlengkapan
VOLUME
SATUAN
HARGA (Rp)
JUMLAH (Rp)
1.200
35.000
m'
%
16,050.00
19,260.00
19,260.00
6,741.00
0.036
0.060
0.006
0.004
hr
hr
hr
hr
47,000.00
55,000.00
60,000.00
70,000.00
Jumlah
1,692.00
3,300.00
360.00
287.00
31,640.00
31,640.00
Upah :
Pekerja
Tukang pipa
Kepala tukang pipa
Mandor
Rp
Rp
1.200
35.000
m'
%
9,630.00
11,556.00
11,556.00
4,044.60
0.036
0.060
0.006
0.004
hr
hr
hr
hr
47,000.00
55,000.00
60,000.00
70,000.00
Jumlah
1,692.00
3,300.00
360.00
287.00
21,239.60
21,230.00
Upah :
Pekerja
Tukang pipa
Kepala tukang pipa
Mandor
Rp
Rp
1.200
35.000
m'
%
5,350.00
6,420.00
6,420.00
2,247.00
0.036
0.060
0.006
0.004
hr
hr
hr
hr
47,000.00
55,000.00
60,000.00
70,000.00
Jumlah
1,692.00
3,300.00
360.00
287.00
14,306.00
14,300.00
Upah :
Pekerja
Tukang pipa
Kepala tukang pipa
Mandor
Rp
Rp
1.000
1.000
bh
ls
481,500.00
168,525.00
481,500.00
168,525.00
0.300
0.300
0.200
hr
hr
hr
55,000.00
60,000.00
70,000.00
Jumlah
16,500.00
18,000.00
14,000.00
698,525.00
698,520.00
Upah :
Tukang pipa
Kepala tukang pipa
Mandor
Rp
Rp
1.000
1.000
bh
ls
321,000.00
112,350.00
321,000.00
112,350.00
0.200
0.200
0.150
hr
hr
hr
55,000.00
60,000.00
70,000.00
Jumlah
11,000.00
12,000.00
10,500.00
466,850.00
466,850.00
Upah :
Tukang pipa
Kepala tukang pipa
Mandor
Rp
Rp
No
URAIAN PEKERJAAN
Gate Valve 10 Kg dia. 1 1/4"
Bahan :
Gate Valve dia. 1 1/4"
Alat bantu
VOLUME
SATUAN
HARGA (Rp)
JUMLAH (Rp)
1.000
1.000
bh
ls
214,000.00
74,900.00
214,000.00
74,900.00
0.200
0.200
0.150
hr
hr
hr
55,000.00
60,000.00
70,000.00
Jumlah
11,000.00
12,000.00
10,500.00
322,400.00
322,400.00
Upah :
Tukang pipa
Kepala tukang pipa
Mandor
Rp
Rp
1.000
1.000
bh
ls
294,250.00
102,987.50
294,250.00
102,987.50
0.200
0.200
0.150
hr
hr
hr
55,000.00
60,000.00
70,000.00
Jumlah
11,000.00
12,000.00
10,500.00
430,737.50
430,730.00
Upah :
Tukang pipa
Kepala tukang pipa
Mandor
Rp
Rp
1.000
1.000
bh
ls
187,250.00
65,537.50
187,250.00
65,537.50
0.200
0.200
0.150
hr
hr
hr
55,000.00
60,000.00
70,000.00
Jumlah
11,000.00
12,000.00
10,500.00
286,287.50
286,280.00
Upah :
Tukang pipa
Kepala tukang pipa
Mandor
Rp
Rp
1.000
1.000
bh
ls
374,500.00
131,075.00
374,500.00
131,075.00
0.200
0.200
0.150
hr
hr
hr
55,000.00
60,000.00
70,000.00
Jumlah
11,000.00
12,000.00
10,500.00
539,075.00
539,070.00
Upah :
Tukang pipa
Kepala tukang pipa
Mandor
Rp
Rp
1.000
1.000
bh
ls
749,000.00
262,150.00
749,000.00
262,150.00
0.200
0.200
0.150
hr
hr
hr
55,000.00
60,000.00
70,000.00
Jumlah
11,000.00
12,000.00
10,500.00
1,044,650.00
1,044,650.00
Upah :
Tukang pipa
Kepala tukang pipa
Mandor
Rp
Rp
No
URAIAN PEKERJAAN
Flexibel Joint 10 Kg dia. 2"
Bahan :
Foot Valve Strainer dia. 2"
Alat bantu
VOLUME
SATUAN
HARGA (Rp)
JUMLAH (Rp)
1.000
1.000
bh
ls
374,500.00
131,075.00
374,500.00
131,075.00
0.200
0.200
0.150
hr
hr
hr
55,000.00
60,000.00
70,000.00
Jumlah
11,000.00
12,000.00
10,500.00
539,075.00
539,070.00
Upah :
Tukang pipa
Kepala tukang pipa
Mandor
Rp
Rp
1.000
1.000
bh
ls
374,500.00
131,075.00
374,500.00
131,075.00
0.200
0.200
0.150
hr
hr
hr
55,000.00
60,000.00
70,000.00
Jumlah
11,000.00
12,000.00
10,500.00
539,075.00
539,070.00
Upah :
Tukang pipa
Kepala tukang pipa
Mandor
Rp
Rp
1.000
1.000
bh
ls
374,500.00
131,075.00
374,500.00
131,075.00
0.200
0.200
0.150
hr
hr
hr
55,000.00
60,000.00
70,000.00
Jumlah
11,000.00
12,000.00
10,500.00
539,075.00
539,070.00
Upah :
Tukang pipa
Kepala tukang pipa
Mandor
Rp
Rp
1.000
1.000
bh
ls
321,000.00
112,350.00
321,000.00
112,350.00
0.200
0.200
0.150
hr
hr
hr
55,000.00
60,000.00
70,000.00
Jumlah
11,000.00
12,000.00
10,500.00
466,850.00
466,850.00
Upah :
Tukang pipa
Kepala tukang pipa
Mandor
Rp
Rp
1.000
1.000
bh
ls
155,150.00
54,302.50
155,150.00
54,302.50
0.150
0.030
hr
hr
55,000.00
60,000.00
Jumlah
8,250.00
1,800.00
219,502.50
219,500.00
Upah :
Tukang batu
Kepala tukang batu
Rp
Rp
No
URAIAN PEKERJAAN
1 unit ROOF DRAIN Dia. 80 (3")
Bahan :
Roof Drain Dia. 80 (3")
Alat bantu
VOLUME
SATUAN
HARGA (Rp)
JUMLAH (Rp)
1.000
1.000
bh
ls
66,875.00
23,406.25
66,875.00
23,406.25
0.150
0.030
hr
hr
55,000.00
60,000.00
Jumlah
8,250.00
1,800.00
100,331.25
100,330.00
Upah :
Tukang batu
Kepala tukang batu
Rp
Rp
1.000
1.000
bh
ls
2,675,000.00
936,250.00
2,675,000.00
936,250.00
0.750
0.750
0.750
hr
hr
hr
55,000.00
47,000.00
70,000.00
Jumlah
41,250.00
35,250.00
52,500.00
3,740,250.00
3,740,250.00
Upah :
Tukang AC
Pembantu Tukang AC
Mandor
Rp
Rp
1.000
1.000
bh
ls
3,424,000.00
1,198,400.00
3,424,000.00
1,198,400.00
0.750
0.750
0.750
hr
hr
hr
55,000.00
47,000.00
70,000.00
Jumlah
41,250.00
35,250.00
52,500.00
4,751,400.00
4,751,400.00
Upah :
Tukang AC
Pembantu Tukang AC
Mandor
Rp
Rp
1.000
1.000
bh
ls
4,280,000.00
1,498,000.00
4,280,000.00
1,498,000.00
0.750
0.750
0.750
hr
hr
hr
55,000.00
47,000.00
70,000.00
Jumlah
41,250.00
35,250.00
52,500.00
5,907,000.00
5,907,000.00
Upah :
Tukang AC
Pembantu Tukang AC
Mandor
Rp
Rp
1.000
1.000
bh
ls
5,992,000.00
2,097,200.00
5,992,000.00
2,097,200.00
0.750
0.750
0.750
hr
hr
hr
55,000.00
47,000.00
70,000.00
Jumlah
41,250.00
35,250.00
52,500.00
8,218,200.00
8,218,200.00
Upah :
Tukang AC
Pembantu Tukang AC
Mandor
Rp
Rp
No
URAIAN PEKERJAAN
AC CEILLING MOUNTED CASSETTE 22.000 BTU/H
Bahan :
Ceilling Mounted cassette 22.000 Btu/h
Alat bantu
VOLUME
SATUAN
HARGA (Rp)
JUMLAH (Rp)
1.000
1.000
bh
ls
4,815,000.00
1,685,250.00
4,815,000.00
1,685,250.00
1.000
1.000
1.000
hr
hr
hr
55,000.00
47,000.00
70,000.00
Jumlah
55,000.00
47,000.00
70,000.00
6,672,250.00
6,672,250.00
Upah :
Tukang AC
Pembantu Tukang AC
Mandor
Rp
Rp
1.000
1.000
bh
ls
2,354,000.00
823,900.00
2,354,000.00
823,900.00
0.200
0.200
0.200
hr
hr
hr
55,000.00
47,000.00
70,000.00
Jumlah
11,000.00
9,400.00
14,000.00
3,212,300.00
3,212,300.00
Upah :
Tukang AC
Pembantu Tukang AC
Mandor
Rp
Rp
1.000
1.000
bh
ls
1,498,000.00
524,300.00
1,498,000.00
524,300.00
0.200
0.200
0.200
hr
hr
hr
55,000.00
47,000.00
70,000.00
Jumlah
11,000.00
9,400.00
14,000.00
2,056,700.00
2,056,700.00
Upah :
Tukang AC
Pembantu Tukang AC
Mandor
Rp
Rp
1.000
1.000
bh
ls
3,210,000.00
1,123,500.00
3,210,000.00
1,123,500.00
0.200
0.200
0.200
hr
hr
hr
55,000.00
47,000.00
70,000.00
Jumlah
11,000.00
9,400.00
14,000.00
4,367,900.00
4,367,900.00
Upah :
Tukang AC
Pembantu Tukang AC
Mandor
PEMIPAAN DRAIN
Bahan :
Pipa PVC Aw 1"
Isolasi
Fitting
Material Bantu
Rp
Rp
1.000
1.000
1.000
1.000
m'
m'
bh
ls
15,000.00
2,000.00
3,000.00
5,250.00
15,000.00
2,000.00
3,000.00
5,250.00
0.050
0.100
0.100
hr
hr
hr
70,000.00
55,000.00
47,000.00
Jumlah
3,500.00
5,500.00
4,700.00
38,950.00
38,950.00
Upah :
Mandor
Tukang listrik
Pembantu tukang listrik
Rp
Rp
No
URAIAN PEKERJAAN
PEMASANGAN CYCLONE TURBIN
Bahan :
Cyclone Turbine Ventilator
Bahan : Stainless Steel
Bearing : Full Stainless Steel
Diameter : 75 cm (30")
Dimensi : 120 x 100 x 100
Berat : 13,5 Kg s/d 19,5 Kg
Kapasitas Hisap : 117,75 m3 / menit
Upah :
Biaya pemasangan
VOLUME
SATUAN
HARGA (Rp)
1.000
set
450,000.00
35.000
450,000.00
Jumlah
JUMLAH (Rp)
450,000.00
Rp
Rp
157,500.00
607,500.00
607,500.00
NO
SATUAN
HARGA DIPAKAI
Rp.
UPAH PEKERJA
1
Pekerja Terampil
Hr
47,000.00
Tukang kayu
Hr
55,000.00
Tukang Cat
Hr
55,000.00
Tukang batu
Hr
55,000.00
Tukang besi
Hr
55,000.00
Kepala tukang
Hr
60,000.00
Mandor
Hr
70,000.00
70,000.00
Sirtu
m3
Pasir Urug
m3
85,000.00
Pasir Pasang/cor
m3
125,000.00
Tanah Urug
m3
80,000.00
m3
152,500.00
bj
zak
dalam satuan
dalam satuan
408.00
45,900.00
kg
1,147.50
zak
57,375.00
kg
1,147.50
zak
45,900.00
10 Besi Beton
kg
8,262.00
kg
9,690.00
kg
12,750.00
13 Wiremesh M5-150
kg
10,710.00
kg
12,240.00
15 Air
ltr
510.00
MATERIAL CAT
1
kg
28,050.00
Cat besi/kayu
kg
45,900.00
ltr
28,050.00
Minyak bekisting
ltr
7,650.00
Minyak solar
ltr
4,590.00
Minyak pelumas
ltr
5,610.00
Teer
kg
4,590.00
Dempul besi
kg
28,050.00
lbr
3,570.00
lbr
3,060.00
11 Kuas
bh
5,100.00
12 Sealent
klg
4,080.00
m1
30,600.00
Elektroda baja
kg
20,000.00
Kawat las
kg
20,000.00
kg
9,500.00
Besi Profil
kg
9,690.00
Skrup/ ripet
bh
2,500.00
Hollow 4 x 4 cm
m1
9,180.00
kg
9,690.00
kg
9,690.00
kg
9,500.00
bh
10,200.00
bh
15,300.00
bh
20,400.00
m'
153,000.00
m'
178,500.00
m'
204,000.00
m'
306,000.00
m'
408,000.00
URAIAN
NO
SATUAN
HARGA DIPAKAI
Rp.
MATERIAL KAYU
1
m3
3,000,000.00
m3
3,000,000.00
m3
2,000,000.00
m3
3,000,000.00
m3
5,500,000.00
m3
5,000,000.00
m3
5,000,000.00
m3
6,000,000.00
btg
15,300.00
lbr
117,300.00
jm
25,000.00
m1
255,000.00
10 Plywood tebal 9 mm
SEWA PERALATAN
1
HARGA SATUAN
(Rp.)
735,800.00
833,423.00
883,725.00
90,717.00
98,701.00
183,494.00
187,994.00
301,821.00
183,644.00
271,439.00
10,327.00
HARGA SATUAN
(Rp.)
735,800.00
833,423.00
883,725.00
90,717.00
98,701.00
183,494.00
187,994.00
301,821.00
183,644.00
271,439.00
10,327.00
HARGA SATUAN
(Rp.)
735,800.00
833,423.00
883,725.00
90,717.00
98,701.00
183,494.00
187,994.00
301,821.00
183,644.00
271,439.00
10,327.00
HARGA SATUAN
(Rp.)
735,800.00
833,423.00
883,725.00
90,717.00
98,701.00
183,494.00
187,994.00
301,821.00
183,644.00
271,439.00
10,327.00
HARGA SATUAN
(Rp.)
735,800.00
833,423.00
883,725.00
90,717.00
98,701.00
183,494.00
187,994.00
301,821.00
183,644.00
271,439.00
10,327.00
1.00
3.33
133.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
883,725.00
302,390.00
1,373,491.00
2,559,606.00
1.00
3.83
115.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
883,725.00
347,748.50
1,187,605.00
2,419,078.50
1.00
8.00
173.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
883,725.00
789,608.00
1,786,571.00
3,459,904.00
1.00
8.00
192.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
883,725.00
789,608.00
1,982,784.00
3,656,117.00
1.00
6.67
111.32
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
883,725.00
1,223,293.33
1,149,580.80
3,256,599.13
1.00
3.83
115.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
883,725.00
347,748.50
1,187,605.00
2,419,078.50
1.00
6.67
99.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
1.00
10.00
163.00
883,725.00
987,010.00
1,683,301.00
3,554,036.00
1.00
13.33
92.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
1.00
8.00
122.00
89.00
883,725.00
1,467,952.00
1,259,894.00
3,611,571.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
Volume/Satuan
883,725.00
241,912.00
919,103.00
2,044,740.00
Jumlah Harga
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
1.00
10.00
188.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
Volume/Satuan
883,725.00
1,316,013.33
950,084.00
3,149,822.33
1.00
2.67
883,725.00
604,780.00
1,022,373.00
2,510,878.00
01.
BETON POER 150 x 150 x 60 (PC3)
Volume/Satuan
Jumlah Harga
883,725.00
987,010.00
1,941,476.00
3,812,211.00
Jumlah Harga
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
1.00
13.33
145.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
883,725.00
2,446,586.67
1,497,415.00
4,827,726.67
KOMPONEN
HARGA SATUAN
(Rp.)
735,800.00
833,423.00
883,725.00
90,717.00
98,701.00
183,494.00
187,994.00
301,821.00
183,644.00
271,439.00
10,327.00
HARGA SATUAN
(Rp.)
735,800.00
833,423.00
883,725.00
90,717.00
98,701.00
183,494.00
187,994.00
301,821.00
183,644.00
271,439.00
10,327.00
HARGA SATUAN
(Rp.)
735,800.00
833,423.00
883,725.00
90,717.00
98,701.00
183,494.00
187,994.00
301,821.00
183,644.00
271,439.00
10,327.00
HARGA SATUAN
(Rp.)
735,800.00
833,423.00
883,725.00
90,717.00
98,701.00
183,494.00
187,994.00
301,821.00
183,644.00
271,439.00
10,327.00
HARGA SATUAN
(Rp.)
735,800.00
833,423.00
883,725.00
90,717.00
98,701.00
183,494.00
187,994.00
301,821.00
183,644.00
271,439.00
10,327.00
10,710.00
1.00
13.33
170.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
833,423.00
2,446,586.67
1,755,590.00
5,035,599.67
1.00
7.03
224.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
883,725.00
1,321,654.79
2,313,248.00
4,518,627.79
1.00
7.00
191.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
883,725.00
1,315,958.00
1,972,457.00
4,172,140.00
1.00
8.33
117.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
883,725.00
2,515,175.00
1,208,259.00
4,607,159.00
1.00
1.90
53.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
kg
/m3
883,725.00
572,665.08
547,331.00
2,003,721.08
1.00
10.00
178.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
833,423.00
1,834,940.00
1,838,206.00
4,506,569.00
1.00
8.09
160.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
883,725.00
1,520,662.58
1,652,320.00
4,056,707.58
1.00
10.33
111.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
833,423.00
1,942,604.67
1,146,297.00
3,922,324.67
1.00
1.55
111.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
883,725.00
467,579.08
1,146,297.00
2,497,601.08
1.00
20.00
42.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
kg
/m3
Volume/Satuan
883,725.00
3,672,880.00
449,820.00
5,006,425.00
Jumlah Harga
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
1.00
9.33
129.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
883,725.00
1,754,610.67
1,332,183.00
3,970,518.67
1.00
9.33
143.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
833,423.00
1,754,610.67
1,476,761.00
4,064,794.67
1.00
10.00
57.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
/m3
883,725.00
3,018,210.00
588,639.00
4,490,574.00
1.00
2.40
89.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
kg
/m3
883,725.00
724,370.40
919,103.00
2,527,198.40
KOMPONEN
HARGA SATUAN
(Rp.)
735,800.00
833,423.00
883,725.00
90,717.00
98,701.00
183,494.00
187,994.00
301,821.00
183,644.00
271,439.00
10,327.00
10,710.00
HARGA SATUAN
(Rp.)
735,800.00
833,423.00
883,725.00
90,717.00
98,701.00
183,494.00
187,994.00
301,821.00
183,644.00
271,439.00
10,327.00
10,710.00
1.00
1.90
21.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
kg
/m3
883,725.00
572,665.08
224,910.00
1,681,300.08
1.00
1.41
26.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
kg
/m3
833,423.00
426,839.35
278,460.00
1,538,722.35
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
kg
/m3
Volume/Satuan
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
kg
/m3
BETON TANGGA
Volume/Satuan
Jumlah Harga
735,800.00
735,800.00
Jumlah Harga
1.00
8.67
205.00
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
kg
/m3
Volume/Satuan
-
883,725.00
2,353,376.13
2,117,035.00
5,354,136.13
Jumlah Harga
m3
m3
m3
m2
m2
m2
m2
m2
m2
m2
kg
kg
/m3
JENIS PEKERJAAN
SAT. INDEKS
HARGA SAT.
(Rp.)
JUMLAH
(Rp.)
HSPK
PEK. TANAH
1 1 m3 - Galian tanah biasa, 1 meter
A.SNI'08 a. Tenaga :
- Pekerja
- Mandor
OH
OH
0.950
0.055
47,000.00
70,000.00
OH
OH
1.725
0.072
Total HSP
47,000.00
70,000.00
- Pekerja
- Mandor
b. Tenaga :
- Pekerja
- Mandor
m3
1.200
85,000.00
102,000.00
OH
OH
0.525
0.110
47,000.00
70,000.00
24,675.00
7,700.00
Total HSP
Rp 102,000.00
Rp
32,375.00
Rp 134,375.00
84,000.00
Rp
84,000.00
OH
OH
0.545
0.075
47,000.00
70,000.00
25,615.00
5,250.00
Rp
30,865.00
Total HSP
Rp 114,865.00
m3
1.200
80,000.00
96,000.00
Rp
96,000.00
OH
OH
0.552
0.125
47,000.00
70,000.00
25,944.00
8,750.00
Rp
34,694.00
Total HSP
0.250
0.125
47,000.00
70,000.00
OH
OH
0.500
0.125
47,000.00
70,000.00
OH
OH
0.330
0.010
47,000.00
70,000.00
m3 - Pembuangan tanah
Rp 130,694.00
11,750.00
8,750.00
Total HSP
86,115.00
70,000.00
OH
OH
Rp
1.200
m3 - Urugan tanah
6 1 m3 - Urugan tanah kembali
A.SNI'07 a. Tenaga :
- Pekerja
- Mandor
48,500.00
m3
m3 - Urugan sirtu
5 1 m3 - Urugan tanah
T.SNI'07 a. Bahan : - Tanah urug
urug pasir
b. Tenaga :
- Pekerja
- Mandor
Rp
81,075.00
5,040.00
Total HSP
m3 - Urugan pasir
4 1 m3 - Urugan sirtu
A.SNI'08 a. Bahan : - Sirtu
44,650.00
3,850.00
Rp
20,500.00
Rp
32,250.00
Rp
16,210.00
23,500.00
8,750.00
Total HSP
15,510.00
700.00
Total HSP
Pekerja
Tukang batu
Kepala tukang
Mandor
zak
m3
m3
ltr
5.5200
0.6000
0.7000
215.0000
57,375.00
125,000.00
152,500.00
510.00
316,710.00
75,000.00
106,750.00
109,650.00
Rp 608,110.00
OH
OH
OH
OH
1.965
0.455
0.075
0.083
47,000.00
55,000.00
60,000.00
70,000.00
92,355.00
25,025.00
4,500.00
5,810.00
Rp 127,690.00
Total HSP
Rp 735,800.00
NO.
JENIS PEKERJAAN
SAT. INDEKS
Pekerja
Tukang batu
Kepala tukang
Mandor
HARGA SAT.
(Rp.)
b. Tenaga :
Pekerja
Tukang batu
Kepala tukang
Mandor
7.4200
0.5250
0.6500
215.0000
57,375.00
125,000.00
152,500.00
510.00
425,722.50
65,625.00
99,125.00
109,650.00
Rp 700,122.50
OH
OH
OH
OH
1.965
0.557
0.075
0.083
47,000.00
55,000.00
60,000.00
70,000.00
92,355.00
30,635.00
4,500.00
5,810.00
Rp 133,300.00
Total HSP
b. Tenaga :
Pekerja
Tukang batu
Kepala tukang
Mandor
8.2600
0.5150
0.6250
215.0000
57,375.00
125,000.00
152,500.00
510.00
473,917.50
64,375.00
95,312.50
109,650.00
Rp 743,255.00
OH
OH
OH
OH
1.975
0.657
0.095
0.083
47,000.00
55,000.00
60,000.00
70,000.00
92,825.00
36,135.00
5,700.00
5,810.00
Rp 140,470.00
Total HSP
b. Tenaga :
Pekerja
Tukang besi
Kepala tukang
Mandor
10.325
0.535
0.627
215.000
57,375.00
125,000.00
152,500.00
510.00
592,396.88
66,875.00
95,617.50
109,650.00
Rp 864,539.38
OH
OH
OH
OH
1.750
0.545
0.128
0.137
47,000.00
55,000.00
60,000.00
70,000.00
82,250.00
29,975.00
7,680.00
9,590.00
Rp 129,495.00
b. Tenaga :
- Pekerja
b. Tenaga :
Pekerja
Tukang kayu
Kepala tukang
Mandor
8,262.00
12,750.00
8,675.10
191.25
Rp
8,866.35
OH
OH
OH
OH
0.018
0.010
0.0010
0.0004
47,000.00
55,000.00
60,000.00
70,000.00
822.50
550.00
60.00
28.00
Rp
1,460.50
Rp
10,327.00
Total HSP
kg
2.060
10,710.00
22,062.60
Rp
22,062.60
10.000
55,000.00
5,500.00
Rp
5,500.00
Rp
27,563.00
Total HSP
m3
kg
ltr
0.013
0.300
0.100
3,000,000.00
12,240.00
7,650.00
40,000.00
3,672.00
765.00
OH
OH
OH
OH
0.520
0.260
0.026
0.026
55,000.00
55,000.00
60,000.00
70,000.00
28,600.00
14,300.00
1,560.00
1,820.00
Pekerja
Tukang kayu
Kepala tukang
Mandor
Rp 994,034.00
1.050
0.015
m2 - Wiremesh
7 1 m2 - Bekisting poer_3 x Pakai
A.SNI'08 a. Bahan : - Kayu acuan (meranti)
- Paku
- Minyak bekisting
Total HSP
kg
kg
Rp 883,725.00
zak
m3
m3
ltr
Rp 833,423.00
zak
m3
m3
ltr
HSPK
zak
m3
m3
ltr
JUMLAH
(Rp.)
Total HSP
44,437.00
Rp
46,280.00
Rp
90,717.00
m3
kg
ltr
0.015
0.450
0.250
3,000,000.00
12,240.00
7,650.00
45,000.00
5,508.00
1,912.50
Rp
52,420.50
OH
OH
OH
OH
0.520
0.260
0.026
0.026
55,000.00
55,000.00
60,000.00
70,000.00
28,600.00
14,300.00
1,560.00
1,820.00
Rp
46,280.00
Rp
98,701.00
Total HSP
NO.
JENIS PEKERJAAN
SAT. INDEKS
Pekerja
Tukang kayu
Kepala tukang
Mandor
HARGA SAT.
(Rp.)
m3
m3
kg
lbr
ltr
btg
0.020
0.008
0.400
0.175
0.200
1.000
3,000,000.00
3,000,000.00
12,240.00
117,300.00
7,650.00
15,300.00
60,000.00
22,500.00
4,896.00
20,527.50
1,530.00
15,300.00
OH
OH
OH
OH
0.660
0.330
0.033
0.033
55,000.00
55,000.00
60,000.00
70,000.00
36,300.00
18,150.00
1,980.00
2,310.00
Pekerja
Tukang kayu
Kepala tukang
Mandor
Total HSP
m3
m3
kg
lbr
ltr
btg
0.020
0.009
0.400
0.175
0.200
1.000
3,000,000.00
3,000,000.00
12,240.00
117,300.00
7,650.00
15,300.00
60,000.00
27,000.00
4,896.00
20,527.50
1,530.00
15,300.00
OH
OH
OH
OH
0.660
0.330
0.033
0.033
55,000.00
55,000.00
60,000.00
70,000.00
36,300.00
18,150.00
1,980.00
2,310.00
Pekerja
Tukang kayu
Kepala tukang
Mandor
Total HSP
m3
m3
kg
lbr
ltr
btg
0.040
0.015
0.400
0.350
0.200
2.000
3,000,000.00
3,000,000.00
12,240.00
117,300.00
7,650.00
15,300.00
120,000.00
45,000.00
4,896.00
41,055.00
1,530.00
30,600.00
OH
OH
OH
OH
0.660
0.330
0.033
0.033
55,000.00
55,000.00
60,000.00
70,000.00
36,300.00
18,150.00
1,980.00
2,310.00
Pekerja
Tukang kayu
Kepala tukang
Mandor
Total HSP
m3
m3
kg
lbr
ltr
btg
0.015
0.010
0.400
0.175
0.200
1.500
3,000,000.00
3,000,000.00
12,240.00
117,300.00
7,650.00
15,300.00
45,000.00
30,000.00
4,896.00
20,527.50
1,530.00
22,950.00
OH
OH
OH
OH
0.660
0.330
0.033
0.033
55,000.00
55,000.00
60,000.00
70,000.00
36,300.00
18,150.00
1,980.00
2,310.00
Pekerja
Tukang kayu
Kepala tukang
Mandor
JUMLAH
(Rp.)
Total HSP
m3
m3
kg
lbr
ltr
btg
0.030
0.015
0.400
0.350
0.150
2.000
3,000,000.00
3,000,000.00
12,240.00
117,300.00
7,650.00
15,300.00
90,000.00
45,000.00
4,896.00
41,055.00
1,147.50
30,600.00
OH
OH
OH
OH
0.660
0.330
0.033
0.033
55,000.00
55,000.00
60,000.00
70,000.00
36,300.00
18,150.00
1,980.00
2,310.00
m2 - Bekisting tangga
Total HSP
HSPK
124,753.50
Rp
58,740.00
Rp 183,494.00
129,253.50
Rp
58,740.00
Rp 187,994.00
243,081.00
Rp
58,740.00
Rp 301,821.00
124,903.50
Rp
58,740.00
Rp 183,644.00
212,698.50
Rp
58,740.00
Rp 271,439.00
NO.
JENIS PEKERJAAN
SAT. INDEKS
14 1 m1 - Sealent
A.SNI'08 a. Bahan : - Sealent
b. Tenaga :
Pekerja
Tukang batu
Kepala tukang
Mandor
HARGA SAT.
(Rp.)
JUMLAH
(Rp.)
m1
1.050
4,080.00
4,284.00
OH
OH
OH
OH
0.080
0.040
0.004
0.004
55,000.00
55,000.00
60,000.00
70,000.00
4,400.00
2,200.00
240.00
280.00
m1 - Sealent
Total HSP
HSPK
4,284.00
Rp
7,120.00
Rp
11,404.00
Pekerja
Tukang las
Kepala tukang
Mandor
kg
1.150
9,690.00
11,143.50
OH
OH
OH
OH
0.060
0.060
0.006
0.003
55,000.00
55,000.00
60,000.00
70,000.00
3,300.00
3,300.00
360.00
210.00
kg - Besi profil
2 1 kg - Baja WF > 200
A.SNI'08 a. Bahan : - Besi baja WF > 200
b. Tenaga :
Pekerja
Tukang las
Kepala tukang
Mandor
Total HSP
kg
1.150
9,690.00
11,143.50
OH
OH
OH
OH
0.060
0.060
0.006
0.003
55,000.00
55,000.00
60,000.00
70,000.00
3,300.00
3,300.00
360.00
210.00
Pekerja
Tukang las
Kepala tukang
Mandor
Total HSP
kg
1.150
9,690.00
11,143.50
OH
OH
OH
OH
0.060
0.060
0.006
0.003
55,000.00
55,000.00
60,000.00
70,000.00
3,300.00
3,300.00
360.00
210.00
Pekerja
Tukang las
Kepala tukang
Mandor
Total HSP
kg
1.150
9,500.00
10,925.00
OH
OH
OH
OH
0.060
0.060
0.006
0.003
55,000.00
55,000.00
60,000.00
70,000.00
3,300.00
3,300.00
360.00
210.00
OH
OH
OH
OH
0.060
0.060
0.006
0.003
Total HSP
55,000.00
55,000.00
60,000.00
70,000.00
Pekerja
Tukang besi
Kepala tukang
Mandor
Total HSP
7,170.00
Rp
18,314.00
11,143.50
Rp
7,170.00
Rp
18,314.00
11,143.50
Rp
7,170.00
Rp
18,314.00
10,925.00
Rp
7,170.00
Rp
18,095.00
Rp
7,170.00
Rp
7,170.00
1.050
8,262.00
8,675.10
Rp
8,675.10
OH
OH
OH
OH
0.007
0.007
0.0007
0.0004
55,000.00
55,000.00
60,000.00
70,000.00
385.00
385.00
42.00
28.00
Rp
840.00
Rp
9,515.00
Rp
kg
c. Tenaga :
3,300.00
3,300.00
360.00
210.00
11,143.50
OH
OH
OH
Total HSP
0.006
20,000.00
120.00
Rp
120.00
0.021
25,000.00
525.00
Rp
525.00
0.028
0.060
0.002
55,000.00
55,000.00
70,000.00
1,540.00
3,300.00
140.00
Rp
4,980.00
Rp
5,625.00
Total HSP
NO.
JENIS PEKERJAAN
SAT. INDEKS
HARGA SAT.
(Rp.)
1.0200
153,000.00
156,060.00
3.1400
5,000.00
15,700.00
Total HSP
1.0200
178,500.00
182,070.00
3.2708
5,000.00
16,354.00
Total HSP
1.0200
204,000.00
208,080.00
5.8870
5,000.00
29,435.00
Total HSP
1.0200
306,000.00
312,120.00
1.9625
5,000.00
9,812.50
JUMLAH
(Rp.)
Total HSP
1.0200
408,000.00
416,160.00
1.9625
5,000.00
9,812.50
HSPK
Rp 156,060.00
Rp
15,700.00
Rp 171,760.00
Rp 182,070.00
Rp
16,354.00
Rp 198,424.00
Rp 208,080.00
Rp
29,435.00
Rp 237,515.00
Rp 312,120.00
Rp
9,812.50
Rp 321,933.00
Rp 416,160.00
Rp
9,812.50
Total HSP
Rp 425,973.00
10,200.00
HSP
Rp
10,200.00
15,300.00
HSP
Rp
15,300.00
20,400.00
HSP
Rp
20,400.00
Pekerja
Tukang besi
Kepala tukang
Mandor
kg
ltr
ltr
0.040
0.030
0.004
20,000.00
4,590.00
5,610.00
800.00
137.70
22.44
OH
OH
OH
OH
0.0040
0.0020
0.0002
0.0002
55,000.00
55,000.00
60,000.00
70,000.00
220.00
110.00
12.00
14.00
Pekerja
Tukang besi
Kepala tukang
Mandor
Total HSP
kg
bh
0.100
0.010
28,050.00
5,100.00
2,805.00
51.00
OH
OH
OH
OH
0.020
0.200
0.020
0.010
55,000.00
55,000.00
60,000.00
70,000.00
1,100.00
11,000.00
1,200.00
700.00
m2 - Meni besi
Total HSP
960.14
Rp
356.00
Rp
1,316.00
2,856.00
Rp
14,000.00
Rp
16,856.00
BILL OF QUANTITY
Kegiatan
Lokasi
TA.
JENIS PEKERJAAN
NO
II.
#REF!
#REF!
#REF!
VOLUME
SATUAN
HARGA
(Rp)
JUMLAH
(Rp)
PEKERJAAN STRUKTURAL
984.00
m'
200,000.00
196,800,000.00
20.88
2,419,078.50
50,510,359.08
8.10
2,044,740.00
16,562,394.00
36.23
3,459,904.00
125,335,541.39
3.50
3,554,036.00
12,453,342.14
3.33
3,812,211.00
12,694,662.63
6.52
735,800.00
4,795,955.44
26.26
833,423.00
21,884,854.56
9 Kolom 60 cm (K1)
95.92
3,256,599.13
312,362,753.46
2.59
5,035,599.67
13,052,274.34
1.55
5,035,599.67
7,817,768.48
2.23
4,064,794.67
9,070,856.56
49.74
4,518,627.79
224,775,524.41
26.60
4,056,707.58
107,915,520.81
0.42
3,970,518.67
1,667,617.84
2.46
4,064,794.67
10,000,388.72
49.74
4,518,627.79
224,775,524.41
26.26
4,056,707.58
106,546,382.00
77.86
4,607,159.00
358,715,979.75
81.90
4,607,159.00
377,305,258.17
2.66
5,354,136.13
14,242,002.11
---------------------------------2,209,284,960.28
232.55
48,500.00
11,278,766.67
56.32
134,375.00
7,568,403.13
4.83
134,375.00
649,031.25
4.83
134,375.00
649,031.25
69.77
20,500.00
1,430,194.12
162.79
16,210.00
2,638,766.30
---------------------------------24,214,192.71
1,230.00
m'
200,000.00
246,000,000.00
38.02
2,559,606.00
97,305,981.70
2.70
2,044,740.00
5,520,798.00
2.88
2,510,878.00
7,231,328.64
23.08
3,459,904.00
79,837,284.80
21.06
3,554,036.00
74,850,841.39
7.90
735,800.00
5,814,549.13
113.82
833,423.00
94,859,301.60
365.16
2,497,601.08
912,033,489.72
JENIS PEKERJAAN
NO
VOLUME
SATUAN
HARGA
(Rp)
JUMLAH
(Rp)
10 Kolom 60 cm (K1)
83.71
3,256,599.13
272,615,030.63
11 Kolom 30 x 30 cm (K3)
14.67
4,827,726.67
70,822,750.20
6.93
4,506,569.00
31,250,802.73
6.62
4,506,569.00
29,851,513.06
0.64
4,064,794.67
2,615,695.37
3.78
4,064,794.67
15,364,923.84
3.92
4,056,707.58
15,882,010.17
1.22
3,970,518.67
4,860,867.77
20.77
4,056,707.58
84,247,674.62
8.27
3,922,324.67
32,435,663.83
1.24
4,064,794.67
5,048,474.98
1.35
4,056,707.58
5,476,555.23
22.61
4,490,574.00
101,531,339.27
---------------------------------2,195,456,876.67
B
Galian Tanah
843.35
48,500.00
40,902,353.27
233.56
134,375.00
31,384,938.09
7.36
134,375.00
989,268.75
9.88
134,375.00
1,327,651.88
253.00
20,500.00
5,186,587.06
Pembuangan Tanah
590.34
16,210.00
9,569,463.97
---------------------------------89,360,263.02
300.00
m'
200,000.00
60,000,000.00
5.40
2,510,878.00
13,558,741.20
4.35
3,812,211.00
16,583,117.85
2.52
3,149,822.33
7,949,364.11
1.68
735,800.00
1,233,200.80
4.35
833,423.00
3,624,373.27
11.28
2,003,721.08
22,601,492.93
5.90
4,827,726.67
28,502,898.24
9 Kolom 15 x 20 cm (KP2)
1.09
4,506,569.00
4,907,653.64
11.85
5,006,425.00
59,340,772.53
10 Pelat Dinding t: 10 cm
---------------------------------218,301,614.58
B
Galian Tanah
245.64
48,500.00
11,913,313.99
10.60
134,375.00
1,424,315.88
1.08
134,375.00
145,125.00
1.45
134,375.00
194,843.75
24.56
20,500.00
503,552.45
Pembuangan Tanah
221.07
16,210.00
3,583,573.98
---------------------------------17,764,725.04
JENIS PEKERJAAN
NO
C
VOLUME
SATUAN
HARGA
(Rp)
JUMLAH
(Rp)
PEKERJAAN BAJA
1 Baja WF 400.200.8.13
3,960.00
kg
18,314.00
72,523,440.00
2 Baja WF 250.125.6.9
444.50
kg
18,314.00
8,140,573.00
110.11
kg
18,314.00
2,016,600.33
413.60
kg
18,314.00
7,574,613.17
452.16
kg
18,095.00
8,181,835.20
120.00
bh
20,400.00
2,448,000.00
0.10
994,034.00
95,427.26
8 Las, t : 6 mm
224.40
cm'
1,316.00
295,310.40
60.00
m2
16,856.00
1,011,360.00
1,500.00
kg
7,170.00
10,755,000.00
101.00
bh
47,500.00
7 Grouting t.20mm
10
4,797,500.00
---------------------------------117,839,659.36
42.23
833,423.00
35,198,168.71
246.68
2,527,198.40
623,407,532.27
3 Sealend
712.40
m'
11,404.00
8,124,186.79
---------------------------------666,729,887.78
353.49
48,500.00
17,144,178.01
84.47
134,375.00
11,350,188.13
106.05
20,500.00
2,173,952.47
4 Pembuangan Tanah
247.44
16,210.00
4,011,030.68
---------------------------------34,679,349.28
PEKERJAAN BAJA
1
17,619.95
kg
7,170.00
126,335,041.50
31,704,611.40
1,752.12
kg
18,095.00
1,184.00
bh
47,500.00
56,240,000.00
---------------------------------214,279,652.90
2.60
833,423.00
11.60
2,527,198.40
2,170,733.55
29,315,501.44
---------------------------------31,486,234.99
35.87
48,500.00
1,739,678.51
5.21
134,375.00
699,986.25
10.76
20,500.00
220,598.41
4 Pembuangan Tanah
25.11
16,210.00
407,013.03
---------------------------------3,067,276.20
JENIS PEKERJAAN
NO
C
VOLUME
SATUAN
HARGA
(Rp)
JUMLAH
(Rp)
PEKERJAAN BAJA
1
1,000.00
kg
7,170.00
7,170,000.00
5,795,466.60
320.28
kg
18,095.00
136.00
bh
47,500.00
6,460,000.00
---------------------------------19,425,466.60
1.54
833,423.00
2.67
2,003,721.08
1,281,387.86
5,339,916.69
---------------------------------6,621,304.55
18.81
48,500.00
912,042.50
3.08
134,375.00
413,203.13
5.64
20,500.00
115,650.75
13.16
16,210.00
213,380.34
4 Pembuangan Tanah
---------------------------------1,654,276.71
2.7 PEKERJAAN SALURAN
A
7.38
833,423.00
6,147,328.05
24.49
2,003,721.08
49,067,763.08
---------------------------------55,215,091.13
116.69
48,500.00
5,659,383.52
18.44
134,375.00
2,477,875.00
11.67
20,500.00
239,211.06
105.02
16,210.00
1,702,365.90
4 Pembuangan Tanah
---------------------------------10,078,835.48
C
PEKERJAAN BAJA
1 Besi Siku 60.60.5
2,040.05
2 Besi D16-50
kg
18,314.00
37,361,439.07
40,364,153.51
3,908.60
kg
10,327.00
3 Las, t : 6 mm
407.33
cm'
1,316.00
536,045.45
107.48
m2
16,856.00
1,811,755.55
---------------------------------80,073,393.58
721.95
m'
171,760.00
124,002,132.00
1,052.76
m'
171,760.00
180,822,057.60
854.72
m'
198,424.00
169,597,754.98
---------------------------------474,421,944.58
4,831.20
m'
171,760.00
829,806,912.00
1,778.30
m'
198,424.00
352,857,399.20
889.15
m'
237,515.00
211,186,462.25
---------------------------------1,393,850,773.45
JENIS PEKERJAAN
NO
C
VOLUME
SATUAN
HARGA
(Rp)
JUMLAH
(Rp)
297.95
m'
321,933.00
95,918,649.62
383.10
m'
425,973.00
163,191,534.22
---------------------------------259,110,183.84
800.79
kg
18,095.00
14,490,216.63
576.00
bh
75,500.00
43,488,000.00
1,080.91
cm'
1,316.00
3 Sambungan Las
1,422,481.90
---------------------------------59,400,698.53
9.87
833,423.00
8,226,641.34
47.38
2,003,721.08
94,937,018.26
8.53
1,538,722.35
13,122,938.30
---------------------------------116,286,597.90
138.19
48,500.00
6,702,346.19
26.32
134,375.00
3,537,075.19
13.82
20,500.00
283,295.05
124.37
16,210.00
2,016,093.37
4 Pembuangan Tanah
---------------------------------12,538,809.80
BALOK
No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Balok
Balok 30/55 (B1) elv.+ 3,45 m
Balok 30/55 (B1) elv.+ 6.95 m
Balok 25/45 (B2) elv.+ 3,45 m
Balok 25/45 (B2) elv.+ 6,95 m
Balok 25/45 (B2) elv.+ 5,65 m
Balok 25/45 (B2) elv.+ 6,55 m
Balok 25/45 (B2) elv.+ 13,75 m
Balok 20/30 (B3) elv.+ 3,45 m
Balok 20/30 (B3) elv.+ 5,65 m
Balok 30/60 (B4) elv.+ 6,55 m
Balok 15/20 (B5) elv.+ 6,55 m
Balok 15/15 (BL1) elv.+ 2,90 m
Balok 15/15 (BL1) elv.+ 6,40 m
Balok 15/15 (BL1) elv.+ 3,50 m
Balok 15/15 (BL1) elv.+ 5,54 m
Balok 15/15 (B6) elv.+ 6,55 m
JUMLAH
Vol Beton
BQ (m3)
Vol Beton
Gbr (m3)
49.74
51.05
49.74
51.05
26.60
27.79
26.26
28.13
3.92
3.92
20.77
24.92
1.35
1.35
0.42
0.42
1.22
1.22
5.62
8.27
8.42
2.23
2.23
2.46
2.46
0.64
0.64
3.78
3.78
1.24
1.24
198.66
214.23
jumlah dalam lonjor
D 22
2,698
2,698
225
9,389
782
6,639
553
628
628
492
486
72
384
25
36
106
-
2,859
238
3,692
3,692
D 22
2,768
1,259
1,243
185
983
64
2,338
2,366
329
2,097
114
13
36
7,384
615
679
244
270
70
414
136
5,548
462
625
49
4
116
31
34
9
52
17
259
22
2,768
231
10,260
855
7,244
604
644
644
514
521
72
461
25
36
106
65
3,090
257
3,789
3,789
1,315
1,331
185
1,179
64
13
36
7,578
631
285
691
244
270
70
414
136
6,186
515
49
4
118
31
34
9
52
17
261
22
dikonversi
SUMBER
TYPE
HARGA
UPAH KERJA
1
2
3
4
5
6
7
8
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
1
2
3
4
5
6
7
8
9
10
11
12
13
Pekerja Terampil
Tukang kayu
Tukang Cat
Tukang batu
Tukang besi
Kepala tukang
Mandor
Upah pasang Plafond rangka metal furing
MATERIAL PENUTUP LANTAI DAN DINING
Homogenous 60/60
Homogenous 40/40
Homogenous 30/30
Cove 10/20
Keramik 40x40
Keramik 30x30
Keramik 20x25
Keramik 20x20
Cove 10/20 ROMAN
Granit Import ex./type
Vynil merk GERFLOR
HPL
Lem Vynil
Serat fibre
Waterprofing
MATERIAL PLAFOND DAN PARTISI
Rangka Metal Stud
Gypsum tebal 12 mm
Gypsum tebal 9 mm JAYABOARD
dalam satuan
Moistureshield board 9 mm EX. GRESIK
dalam satuan
Paku Sekrup
Metal Furing
C Channel
Angle Section
Saddle Clip
Suspension Bracket
Threaded Rod
Sffit Cleat
Jointing Coumpound
Joint Tape
Screw
Glasswool tebal 5 cm ( 1,2 x 15 meter )
dalam satuan
MATERIAL
Sirtu
Pasir Urug
Pasir Pasang/cor
Batu Pecah Mesin/Stenslah 1/2
Batu Merah klas 1
Portland Cement (PC) @ 40 kg
dalam satuan
Semen berwarna
Besi Beton
Besi Plat Strip
Besi Hollow
Kawat Beton/ Bendrat
Paku kayu 2-5"
Paku Gypsum
Paku Sekrup
Sekrup Galvalum
MATERIAL CAT
Wood filler
Wood Stain
Shanding
Thinnner A
Thinnner B
Compound
Clear Gloss
Cat meni kayu/besi
Cat besi/kayu EMCO
Cat Tembok Dulux Weathershield
Cat Tembok CATYLAC
Plamir tembok
Plamir kayu
dalam satuan
Hr
Hr
Hr
Hr
Hr
Hr
Hr
m2
47,000.00
55,000.00
55,000.00
55,000.00
55,000.00
60,000.00
70,000.00
15,000.00
m2
m2
m2
bh
m2
m2
m2
m2
bh
m2
m2
m2
kg
m2
m2
178,500.00
168,300.00
147,900.00
7,650.00
71,400.00
56,100.00
66,300.00
56,100.00
12,240.00
510,000.00
91,800.00
66,300.00
15,300.00
3,570.00
25,500.00
m2
lembar
lembar
m2
lembar
m2
bh.
m'.
m'.
m'.
pcs
pcs
pcs
pcs
kg
m'.
pcs
gulung
m2
45,900.00
88,740.00
66,300.00
23,460.00
163,200.00
57,120.00
153.00
7,650.00
7,650.00
3,570.00
765.00
459.00
4,590.00
663.00
3,060.00
255.00
153.00
275,400.00
15,300.00
m3
m3
m3
m3
bj
zak
kg
kg
kg
kg
m'
kg
kg
kg
pak
bh
68,850.00
81,600.00
117,300.00
153,000.00
408.00
45,900.00
1,147.50
6,120.00
8,262.00
9,690.00
8,160.00
12,750.00
12,240.00
12,240.00
112,200.00
153.00
kg
kg
kg
ltr
ltr
kaleng
kg
kg
kg
kg
kg
kg
kg
45,900.00
45,900.00
66,300.00
10,200.00
10,200.00
45,900.00
45,900.00
28,050.00
45,900.00
66,300.00
48,450.00
7,650.00
7,650.00
SUMBER
TYPE
HARGA
ltr
ltr
ltr
kg
kg
lbr
lbr
kg
28,050.00
10,200.00
7,650.00
4,590.00
28,050.00
3,570.00
5,100.00
76,500.00
m2
m2
m2
18,360.00
25,500.00
5,100.00
m2
ls
2,550,000.00
510,000.00
m2
m2
117,300.00
7,140.00
lbr
lbr
lbr
lbr
lbr
lbr
lbr
m2
kg
m'
45,900.00
117,300.00
66,300.00
178,500.00
127,500.00
96,900.00
183,600.00
63,750.00
15,300.00
15,300.00
m2
bh
m2
m2
bh
m2
m2
m2
117,300.00
459.00
117,300.00
459,000.00
4,080.00
14,280.00
102,000.00
91,800.00
m2
m1
96,900.00
17,340.00
m2
m2
m2
m2
m2
unit
unit
unit
unit
unit
unit
unit
76,500.00
86,700.00
112,200.00
127,500.00
142,800.00
178,500.00
178,500.00
255,000.00
663,000.00
127,500.00
122,400.00
102,000.00
kg
kg
jm
kg
m1
m2
m2
m2
m1
bh
m1
20,000.00
20,000.00
25,000.00
9,500.00
55,000.00
450,000.00
400,000.00
350,000.00
55,000.00
2,500.00
8,000.00
m3
m3
m3
m3
m3
m3
m3
3,000,000.00
3,000,000.00
3,000,000.00
5,500,000.00
5,000,000.00
5,000,000.00
6,000,000.00
PENGGANTUNG/PENGUNCI
Engsel Pintu 4" SOLID EK 08
Engsel Pintu 3" PALOMA EB 028
Lockcase griff 2202,A4R
Clinder Griff 3301,70N
BODY SWING PALOMA BD 038 SS
Handle on Roses(HRE) PALOMA HP 403
BODY SLIDING DEKKSON 85100+DC60 SN
Handle Sliding PALOMA CM 010
Rel pintu dorong, merk SOLID
Spring Knife GRADINO 950 SN
Pull Handle PALOMA 083 600mm
Hak Angin 951 GRADINO
Grendel Biasa SES
Floor Hinges SOLID FH 84
GLASS LOCK SOLID 702 CHR
Casement SOLID 701 20"
Patch Fitting SOLID 20
Patch Fitting SOLID 21
Patch Fitting SOLID 30
Patch Fitting SOLID 40
Door Closer DEKKSON 500
Handle Jendela Stainless Steel, PALOMA
MATERIAL SANITAIR
Urinoir
Kloset Duduk TOTO
Wastafel besar ex. INA
Bak cuci stainlessteel EX. Visa tebal
Water drain + asesories
Floor drain
KRAN Single Lever Shower Set
Kran Air 1/2" ; sink tap
Kran Air 1/2" , Sink Tap with Hose Coupling
Kran Leher Angsa SINK
Karan PANAS DINGIN
Wash let Closet
bak mandi Fibreglass volume 0,3 m air
SUMBER
TYPE
HARGA
set
set
bh
bh
set
set
set
set
bh
bh
set
set
bh
set
set
set
set
set
set
set
set
bh
40,800.00
35,700.00
127,500.00
127,500.00
102,000.00
255,000.00
255,000.00
102,000.00
255,000.00
25,500.00
204,000.00
25,500.00
15,300.00
255,000.00
76,500.00
153,000.00
25,500.00
27,540.00
30,600.00
35,700.00
255,000.00
102,000.00
set
set
set
set
set
set
set
set
set
set
set
set
set
1,300,000.00
1,700,000.00
1,200,000.00
400,000.00
200,000.00
75,000.00
150,000.00
75,000.00
100,000.00
75,000.00
150,000.00
150,000.00
500,000.00
Vol
Vol Cek
Sat
8.85
3.36
1.31
2.00
1.00
2.00
6.72
m'
m2
m2
set
bh
set
m2
9.50
3.36
1.31
2.00
1.00
2.00
6.72
55,000.00
408,057.00
94,058.00
663,000.00
102,000.00
243,630.00
99,400.00
Dibulatkan
9.50
3.36
1.31
3.00
1.00
2.00
2.00
6.72
8.95
3.36
1.31
3.00
1.00
2.00
2.00
6.72
m'
m2
m2
set
bh
set
bh
m2
55,000.00
408,057.00
94,058.00
50,708.00
102,000.00
243,630.00
294,630.00
99,400.00
Dibulatkan
7.50
1.89
0.72
3.00
1.00
1.00
1.00
3.78
7.10
1.89
0.72
3.00
1.00
1.00
1.00
3.78
m'
m2
m2
set
bh
set
bh
m2
55,000.00
408,057.00
94,058.00
50,708.00
102,000.00
243,630.00
294,630.00
99,400.00
Dibulatkan
5.25
1.00
1.50
1.00
5.25
1.00
1.50
1.00
m'
unit
set
bh
55,000.00
250,000.00
50,708.00
294,630.00
Dibulatkan
0.90
4.00
1.00
1.00
4.00
1.80
1.00
0.81
4.00
1.00
1.00
1.00
1.62
1.00
m2
m'
unit
unit
bh
m2
unit
1,000,000.00
275,000.00
200,000.00
150,000.00
30,000.00
99,400.00
450,000.00
Dibulatkan
0.90
4.00
1.00
1.00
4.00
1.80
1.00
0.81
4.00
1.00
1.00
1.00
1.62
1.00
m2
m'
unit
unit
bh
m2
unit
1,000,000.00
275,000.00
200,000.00
150,000.00
30,000.00
99,400.00
450,000.00
Dibulatkan
5.25
1.00
1.50
1.00
5.25
1.00
1.50
1.00
m'
unit
set
bh
55,000.00
250,000.00
50,708.00
294,630.00
Dibulatkan
24.80
1.00
22.53
1.00
m2
LS
2,550,000.00
510,000.00
Dibulatkan
2.50
1.73
10.80
32.68
2.50
1.73
10.80
32.68
m2
m2
m2
m'
252,662.00
252,662.00
94,058.00
55,000.00
Dibulatkan
3.53
9.97
22.59
3.53
9.97
22.59
m2
m2
m'
252,662.00
94,058.00
55,000.00
Dibulatkan
1.23
3.52
14.07
1.23
3.51
14.05
m2
m2
m'
252,662.00
94,058.00
55,000.00
Dibulatkan
1.13
7.56
19.80
1.12
7.56
19.80
m2
m2
m'
350,000.00
94,058.00
55,000.00
Dibulatkan
1.23
1.76
7.35
1.23
1.34
6.88
m2
m2
m'
252,662.00
94,058.00
55,000.00
Dibulatkan
28.22
6.72
6.56
4.00
4.00
8.00
2.00
4.00
4.00
25.98
7.14
6.55
4.00
4.00
8.00
2.00
4.00
4.00
m'
m2
m2
set
set
bh
set
daun
daun
55,000.00
127,500.00
94,058.00
663,000.00
243,630.00
35,700.00
76,500.00
175,000.00
102,000.00
Dibulatkan
34.96
3.36
5.09
3.00
1.00
2.00
2.00
6.72
35.76
3.36
9.16
3.00
1.00
2.00
2.00
6.72
m'
m2
m2
set
bh
set
bh
m2
55,000.00
127,500.00
94,058.00
50,708.00
102,000.00
243,630.00
294,630.00
99,400.00
Dibulatkan
18.92
3.36
4.83
3.00
1.00
2.00
2.00
6.72
17.16
3.36
5.41
3.00
1.00
2.00
2.00
6.72
m'
m2
m2
set
bh
set
bh
m2
55,000.00
127,500.00
94,058.00
50,708.00
102,000.00
243,630.00
294,630.00
99,400.00
Dibulatkan
288,750.00
250,000.00
76,062.00
294,630.00
909,442.00
909,442.00
63,250,200.00
510,000.00
63,760,200.00
63,760,200.00
630,644.35
436,599.94
1,015,826.40
1,797,400.00
3,880,470.69
3,880,470.00
892,604.31
937,899.35
1,242,450.00
3,072,953.66
3,072,953.00
311,279.58
330,754.96
773,850.00
1,415,884.54
1,415,884.00
393,750.00
711,078.48
1,089,000.00
2,193,828.48
2,193,828.00
311,279.58
165,071.79
404,250.00
880,601.37
880,601.00
1,552,100.00
856,800.00
616,832.36
2,652,000.00
974,520.00
285,600.00
153,000.00
700,000.00
408,000.00
8,198,852.36
8,198,852.00
1,922,800.00
428,400.00
478,284.93
152,124.00
102,000.00
487,260.00
589,260.00
667,968.00
4,828,096.93
4,828,096.00
1,040,600.00
428,400.00
453,923.91
152,124.00
102,000.00
487,260.00
589,260.00
667,968.00
3,921,535.91
3,921,535.00
PERSIAPAN
1 m1 - Bouwplank
a. Bahan :- Kayu hutan balok MERANTI
- Paku
- Kayu hutan papan MERANTI
m3
kg
m3
0.012
0.020
0.007
3,000,000.00
12,240.00
3,000,000.00
36,000.00
244.80
21,000.00
Rp
57,244.80
b. Tenaga :-
OH
OH
OH
OH
0.100
0.100
0.010
0.005
47,000.00
55,000.00
60,000.00
70,000.00
4,700.00
5,500.00
600.00
350.00
Rp
11,150.00
Rp
Rp
68,395.00
68,300.00
Rp
8,200.00
Rp
37,000.00
Pekerja
Tukang kayu
Kepala tukang
Mandor
m1 - Bouwplank
1 m2 - Pembersihan
a. Tenaga :- Pekerja
- Mandor
OH
OH
Total HSP
di bulatkan
0.100
0.050
47,000.00
70,000.00
m2 - Pembersihan
1 m3 - Galian tanah biasa, 1 meter
a. Tenaga :- Pekerja
- Mandor
OH
OH
4,700.00
3,500.00
Total HSP
0.750
0.025
47,000.00
70,000.00
35,250.00
1,750.00
Total HSP
1 m3 - Urugan pasir
a. Bahan :- Pasir urug
m3
1.200
81,600.00
97,920.00
Rp
97,920.00
b. Tenaga :- Pekerja
- Mandor
OH
OH
0.300
0.010
47,000.00
70,000.00
14,100.00
700.00
Rp
14,800.00
Rp
112,720.00
Rp
12,310.00
m3 - Urugan pasir
1 m3 - Urugan tanah kembali
a. Tenaga :- Pekerja
- Mandor
OH
OH
Total HSP
0.250
0.008
47,000.00
70,000.00
11,750.00
560.00
Total HSP
1 m3 - Urugan sirtu
a. Bahan :- Sirtu
m3
1.200
68,850.00
82,620.00
Rp
82,620.00
b. Tenaga :- Pekerja
- Mandor
OH
OH
0.250
0.025
47,000.00
70,000.00
11,750.00
1,750.00
Rp
13,500.00
Rp
96,120.00
Rp
315,659.00
Rp
336,659.00
Rp
13,249.00
m3 - Urugan sirtu
1 m3 - Pembongkaran dinding bata merah
a. Tenaga :- Pekerja
- Mandor
OH
OH
Total HSP
6.667
0.033
47,000.00
70,000.00
OH
OH
6.667
0.333
Total HSP
47,000.00
70,000.00
OH
OH
0.267
0.010
313,349.00
2,310.00
313,349.00
23,310.00
Total HSP
47,000.00
70,000.00
12,549.00
700.00
Total HSP
Catatan : Untuk Pembongkaran Keramik , Plafond , Partisi, pakai analisa yang sama
PASANGAN BATA
1 m2 - Bata merah, 1 PC : 3 PP (tebal 1/2 BT)
a. Bahan :- Bata merah 5 x 11 x 22 cm
- Semen portland
- Pasir pasang
Bh
Kg
M
70.000
14.370
0.040
408.00
1,147.50
117,300.00
28,560.00
16,489.58
4,692.00
Rp
49,741.58
b. Tenaga :-
OH
OH
OH
OH
0.300
0.100
0.010
0.015
47,000.00
55,000.00
60,000.00
70,000.00
14,100.00
5,500.00
600.00
1,050.00
Rp
21,250.00
Rp
70,992.00
Pekerja
Tukang batu
Kepala tukang
Mandor
Total HSP
Bh
Kg
M
70.000
9.680
0.045
408.00
1,147.50
117,300.00
28,560.00
11,107.80
5,278.50
Rp
44,946.30
b. Tenaga :-
OH
OH
OH
OH
0.300
0.100
0.010
0.015
47,000.00
55,000.00
60,000.00
70,000.00
14,100.00
5,500.00
600.00
1,050.00
Rp
21,250.00
Rp
66,196.00
Pekerja
Tukang batu
Kepala tukang
Mandor
Pekerja
Tukang batu
Kepala tukang
Mandor
OH
OH
OH
OH
Total HSP
140.000
22.200
0.102
408.00
1,147.50
117,300.00
57,120.00
25,474.50
11,964.60
Rp
94,559.10
0.600
0.200
0.020
0.030
47,000.00
55,000.00
60,000.00
70,000.00
28,200.00
11,000.00
1,200.00
2,100.00
Rp
42,500.00
Rp
137,059.00
Total HSP
PLESTERAN-ACIAN-BENANGAN
1 m2 - Plesteran, 1 PC : 3 PP (t= 15 mm)
a. Bahan :- Semen / PC (40 kg)
- Pasir pasang
zak
m3
0.194
0.023
45,900.00
117,300.00
8,904.60
2,697.90
Rp
11,602.50
b. Tenaga :-
OH
OH
OH
OH
0.300
0.150
0.015
0.015
47,000.00
55,000.00
60,000.00
70,000.00
14,100.00
8,250.00
900.00
1,050.00
Rp
24,300.00
Rp
35,903.00
Pekerja
Tukang batu
Kepala tukang
Mandor
Total HSP
zak
m3
0.130
0.026
45,900.00
117,300.00
5,967.00
3,049.80
Rp
9,016.80
b. Tenaga :-
OH
OH
OH
OH
0.300
0.150
0.015
0.015
47,000.00
55,000.00
60,000.00
70,000.00
14,100.00
8,250.00
900.00
1,050.00
Rp
24,300.00
Rp
33,317.00
Pekerja
Tukang batu
Kepala tukang
Mandor
Total HSP
1 m2 - Acian
a. Bahan :- Semen / PC (40 kg)
zak
0.081
45,900.00
3,717.90
b. Tenaga :-
OH
OH
OH
OH
0.200
0.100
0.010
0.010
47,000.00
55,000.00
60,000.00
70,000.00
9,400.00
5,500.00
600.00
700.00
Pekerja
Tukang batu
Kepala tukang
Mandor
m2 - Acian
Total HSP
3,717.90
Rp
16,200.00
Rp
19,918.00
zak
m3
0.013
0.013
45,900.00
117,300.00
596.70
1,524.90
Rp
2,121.60
b. Tenaga :-
OH
OH
OH
OH
0.075
0.050
0.005
0.004
47,000.00
55,000.00
60,000.00
70,000.00
3,525.00
2,750.00
300.00
280.00
Rp
6,855.00
Rp
8,977.00
Pekerja
Tukang batu
Kepala tukang
Mandor
Total HSP
Pekerja
Tukang batu
Kepala tukang
Mandor
OH
OH
OH
OH
0.700
0.350
0.035
0.035
168,300.00
1,147.50
117,300.00
6,120.00
185,130.00
11,934.00
5,278.50
9,914.40
Rp
212,256.90
47,000.00
55,000.00
60,000.00
70,000.00
32,900.00
19,250.00
2,100.00
2,450.00
Rp
56,700.00
Rp
Rp
268,957.00
268,900.00
Rp
189,816.90
Rp
56,700.00
Rp
Rp
246,517.00
246,500.00
Pekerja
Tukang batu
Kepala tukang
Mandor
OH
OH
OH
OH
0.700
0.350
0.035
0.035
47,000.00
55,000.00
60,000.00
70,000.00
32,900.00
19,250.00
2,100.00
2,450.00
Pekerja
Tukang besi
Kepala tukang
Mandor
OH
OH
OH
OH
0.080
0.800
0.080
0.004
47,000.00
55,000.00
60,000.00
70,000.00
65,280.00
3,760.00
44,000.00
4,800.00
280.00
Rp
52,840.00
Rp
Rp
118,120.00
118,100.00
m2
Kg
M
Kg
1.100
10.400
0.045
1.620
56,100.00
1,147.50
117,300.00
6,120.00
61,710.00
11,934.00
5,278.50
9,914.40
Rp
88,836.90
b. Tenaga :-
OH
OH
OH
OH
0.700
0.350
0.035
0.035
47,000.00
55,000.00
60,000.00
70,000.00
32,900.00
19,250.00
2,100.00
2,450.00
Rp
56,700.00
Rp
Rp
145,537.00
145,500.00
Pekerja
Tukang batu
Kepala tukang
Mandor
Total HSP
di bulatkan
m2
Kg
M
Kg
1.100
10.400
0.045
1.620
66,300.00
1,147.50
117,300.00
6,120.00
72,930.00
11,934.00
5,278.50
9,914.40
Rp
100,056.90
b. Tenaga :-
OH
OH
OH
OH
0.700
0.350
0.035
0.035
47,000.00
55,000.00
60,000.00
70,000.00
32,900.00
19,250.00
2,100.00
2,450.00
Rp
56,700.00
Rp
Rp
156,757.00
156,700.00
Pekerja
Tukang batu
Kepala tukang
Mandor
Total HSP
di bulatkan
bh
Kg
M
Kg
5.300
1.140
0.003
0.025
12,240.00
1,147.50
117,300.00
6,120.00
64,872.00
1,308.15
351.90
153.00
Rp
66,685.05
b. Tenaga :-
OH
OH
OH
OH
0.090
0.090
0.009
0.005
47,000.00
55,000.00
60,000.00
70,000.00
4,230.00
4,950.00
540.00
350.00
Rp
10,070.00
Rp
Rp
76,755.00
76,700.00
Pekerja
Tukang batu
Kepala tukang
Mandor
Total HSP
di bulatkan
LANTAI VYNIL
1 m2 - pasangan Vynil 30/30 dengan Perekat
a. Bahan
:- Vynil Karet
- Lem Vynil
b. Tenaga :-
Pekerja
Tukang batu
Kepala tukang
Mandor
m2
Kg
1.100
0.350
91,800.00
15,300.00
100,980.00
5,355.00
OH
OH
OH
OH
0.150
0.150
0.015
0.008
47,000.00
55,000.00
60,000.00
70,000.00
7,050.00
8,250.00
900.00
560.00
106,335.00
Rp
16,760.00
Total HSP
di bulatkan
Rp
Rp
123,095.00
123,000.00
20,196.00
25,500.00
5,100.00
Total HSP
di bulatkan
Rp
Rp
50,796.00
50,700.00
PENGECATAN
1 1 M2 MENGECAT/PLAMUR TEMBOK (3 lapis penutup) Mowilec (DINDING LUAR)
a. Bahan
:- Plamur
- Cat dinding
- Cat dasar
b. Tenaga :-
Pekerja
Tukang CAT
Kepala tukang
Mandor
Kg
Kg
Kg
0.100
0.260
0.100
7,650.00
66,300.00
48,450.00
765.00
17,238.00
4,845.00
Rp
22,848.00
OH
OH
OH
OH
0.020
0.063
0.006
0.025
47,000.00
55,000.00
60,000.00
70,000.00
940.00
3,465.00
378.00
1,750.00
Rp
6,533.00
29,381.00
29,300.00
:- Plamur
- Cat dinding
- Cat dasar
b. Tenaga :-
Pekerja
Tukang CAT
Kepala tukang
Mandor
Kg
Kg
Kg
0.100
0.260
0.100
7,650.00
48,450.00
48,450.00
765.00
12,597.00
4,845.00
Rp
18,207.00
OH
OH
OH
OH
0.020
0.063
0.006
0.025
47,000.00
55,000.00
60,000.00
70,000.00
940.00
3,465.00
378.00
1,750.00
Rp
6,533.00
24,740.00
24,700.00
:-
Wood Filler
Pewarna
Kertas Gosok no 150
Kertas Gosok no 200
Shanding
Clear Doof
Thinner A
Coumpound
kg
sachet
lembar
lembar
kg
kg
liter
kaleng
0.200
0.500
1.000
1.000
0.500
0.200
0.837
0.200
45,900.00
5,000.00
3,060.00
3,570.00
66,300.00
45,900.00
10,200.00
45,900.00
9,180.00
2,500.00
3,060.00
3,570.00
33,150.00
9,180.00
8,537.40
9,180.00
Pekerja
Tukang CAT
Kepala tukang
Mandor
OH
OH
OH
OH
0.075
0.090
0.009
0.025
47,000.00
55,000.00
60,000.00
70,000.00
3,525.00
4,950.00
540.00
1,750.00
Rp
10,765.00
set
jam
1.000
0.625
1,000.00
15,000.00
1,000.00
9,375.00
Rp
10,375.00
Rp
Rp
99,497.00
99,400.00
Total HSP
di bulatkan
78,357.40
Pekerja
Tukang besi
Kepala tukang
Mandor
4.400
0.270
55,000.00
76,500.00
4,080.00
242,000.00
1,101.60
OH
OH
OH
OH
0.085
0.085
0.009
0.005
47,000.00
55,000.00
60,000.00
70,000.00
3,995.00
4,675.00
540.00
350.00
243,101.60
Rp
9,560.00
Rp
252,662.00
m2
1.100
76,500.00
84,150.00
Rp
b. Tenaga :-
OH
OH
OH
OH
0.015
0.150
0.015
0.00075
47,000.00
55,000.00
60,000.00
70,000.00
705.00
8,250.00
900.00
52.50
Rp
9,907.50
Rp
94,058.00
Pekerja
Tukang kayu
Kepala tukang
Mandor
Total HSP
84,150.00
m2
1.100
86,700.00
95,370.00
Rp
95,370.00
b. Tenaga :-
OH
OH
OH
OH
0.015
0.150
0.015
0.00075
47,000.00
55,000.00
60,000.00
70,000.00
705.00
8,250.00
900.00
52.50
Rp
9,907.50
Rp
105,278.00
Pekerja
Tukang kayu
Kepala tukang
Mandor
Total HSP
Pekerja
Tukang kayu
Kepala tukang
Mandor
m3
kg
kg
lbr
0.025
0.030
0.300
1.000
6,000,000.00
12,240.00
15,300.00
66,300.00
150,000.00
367.20
4,590.00
66,300.00
Rp
221,257.20
OH
OH
OH
OH
0.800
2.400
0.240
0.040
47,000.00
55,000.00
60,000.00
70,000.00
37,600.00
132,000.00
14,400.00
2,800.00
Rp
186,800.00
Rp
408,057.00
0.030
0.300
1.000
6,000,000.00
12,240.00
15,300.00
66,300.00
367.20
4,590.00
66,300.00
Rp
71,257.20
OH
OH
OH
OH
0.800
2.400
0.240
0.040
47,000.00
55,000.00
60,000.00
70,000.00
37,600.00
132,000.00
14,400.00
2,800.00
Rp
186,800.00
258,057.00
Pekerja
Tukang kayu
Kepala tukang
Mandor
Total HSP
Pekerja
Tukang kayu
Kepala tukang
Mandor
OH
OH
OH
OH
Kayu Kamper
0.025
0.030
0.800
1.000
0.500
6,000,000.00
12,240.00
15,300.00
66,300.00
178,500.00
150,000.00
367.20
12,240.00
66,300.00
89,250.00
Rp
318,157.20
0.850
2.550
0.255
0.043
47,000.00
55,000.00
60,000.00
70,000.00
39,950.00
140,250.00
15,300.00
3,010.00
Rp
198,510.00
Rp
516,667.00
set
1.000
40,800.00
40,800.00
Rp
40,800.00
OH
OH
OH
OH
0.015
0.150
0.015
0.00075
47,000.00
55,000.00
60,000.00
70,000.00
705.00
8,250.00
900.00
52.50
Rp
9,907.50
Rp
50,708.00
Total HSP
set
1.000
35,700.00
35,700.00
Rp
35,700.00
OH
OH
OH
OH
0.010
0.100
0.010
0.0005
47,000.00
55,000.00
60,000.00
70,000.00
470.00
5,500.00
600.00
35.00
Rp
6,605.00
Rp
42,305.00
Total HSP
set
1.000
204,000.00
204,000.00
Rp
OH
OH
OH
OH
0.060
0.600
0.060
0.003
47,000.00
55,000.00
60,000.00
70,000.00
2,820.00
33,000.00
3,600.00
210.00
Rp
39,630.00
Rp
243,630.00
Total HSP
Inc.Clynder
bh
1.000
102,000.00
102,000.00
Rp
102,000.00
OH
OH
OH
OH
0.060
0.600
0.060
0.003
47,000.00
55,000.00
60,000.00
70,000.00
2,820.00
33,000.00
3,600.00
210.00
Rp
39,630.00
Rp
141,630.00
204,000.00
Total HSP
HRE )
bh
1.000
255,000.00
255,000.00
Rp
255,000.00
OH
OH
OH
OH
0.060
0.600
0.060
0.003
47,000.00
55,000.00
60,000.00
70,000.00
2,820.00
33,000.00
3,600.00
210.00
Rp
39,630.00
Rp
294,630.00
Total HSP
Inc.Clynder
bh
1.000
255,000.00
255,000.00
Rp
255,000.00
OH
OH
OH
OH
0.060
0.600
0.060
0.003
47,000.00
55,000.00
60,000.00
70,000.00
2,820.00
33,000.00
3,600.00
210.00
Rp
39,630.00
Rp
294,630.00
Total HSP
bh
1.000
102,000.00
102,000.00
Rp
102,000.00
OH
OH
OH
OH
0.060
0.600
0.060
0.003
47,000.00
55,000.00
60,000.00
70,000.00
2,820.00
33,000.00
3,600.00
210.00
Rp
39,630.00
Rp
141,630.00
Total HSP
bh
1.000
255,000.00
255,000.00
Rp
255,000.00
b. Tenaga :-
OH
OH
OH
OH
0.060
0.600
0.060
0.0030
47,000.00
55,000.00
60,000.00
70,000.00
2,820.00
33,000.00
3,600.00
210.00
Rp
39,630.00
Rp
294,630.00
Pekerja
Tukang kayu
Kepala tukang
Mandor
Total HSP
set
1.000
153,000.00
153,000.00
Rp
153,000.00
b. Tenaga :-
OH
OH
OH
OH
0.060
0.600
0.060
0.0030
47,000.00
55,000.00
60,000.00
70,000.00
2,820.00
33,000.00
3,600.00
210.00
Rp
39,630.00
Rp
192,630.00
Pekerja
Tukang kayu
Kepala tukang
Mandor
Total HSP
1 set-Door Closer
a. Bahan :- Door Closer DEKKSON 500
set
1.000
255,000.00
255,000.00
Rp
255,000.00
b. Tenaga :-
OH
OH
OH
OH
0.060
0.600
0.060
0.0030
47,000.00
55,000.00
60,000.00
70,000.00
2,820.00
33,000.00
3,600.00
210.00
Rp
39,630.00
Rp
294,630.00
Pekerja
Tukang kayu
Kepala tukang
Mandor
set-Door Closer
Total HSP
set
1.000
25,500.00
25,500.00
Rp
b. Tenaga :-
OH
OH
OH
OH
0.015
0.150
0.015
0.00075
47,000.00
55,000.00
60,000.00
70,000.00
705.00
8,250.00
900.00
52.50
Rp
9,907.50
Rp
35,408.00
Pekerja
Tukang kayu
Kepala tukang
Mandor
Total HSP
25,500.00
1 bh - Grendel biasa
a. Bahan :- Spring Knife GRADINO 950 SN
bh
1.000
25,500.00
25,500.00
Rp
25,500.00
b. Tenaga :-
OH
OH
OH
OH
0.020
0.200
0.020
0.001
47,000.00
55,000.00
60,000.00
70,000.00
940.00
11,000.00
1,200.00
70.00
Rp
13,210.00
Rp
38,710.00
Pekerja
Tukang kayu
Kepala tukang
Mandor
bh - Grendel biasa
Total HSP
set
1.000
102,000.00
102,000.00
Rp
102,000.00
b. Tenaga :-
OH
OH
OH
OH
0.050
0.500
0.050
0.0025
47,000.00
55,000.00
60,000.00
70,000.00
2,350.00
27,500.00
3,000.00
175.00
Rp
33,025.00
Rp
135,025.00
Rp
35,801.39
Rp
39,750.00
Rp
23,250.00
Rp
Rp
98,801.00
98,800.00
Rp
20,396.12
Rp
39,750.00
Rp
23,250.00
Rp
Rp
83,396.00
83,300.00
Pekerja
Tukang kayu
Kepala tukang
Mandor
Total HSP
b. Tenaga :-
m3
lembar
bh.
Pekerja
Tukang kayu
Kepala tukang
Mandor
OH
OH
OH
OH
0.015
0.347
28.000
0.150
0.450
0.045
0.075
45,900.00
88,740.00
153.00
47,000.00
55,000.00
60,000.00
70,000.00
706.86
30,810.53
4,284.00
7,050.00
24,750.00
2,700.00
5,250.00
- Penambahan GlassWool
m2
1.000
15,300.00
15,300.00
( lapisan Kedap Suara )
m2 - Pasangan Partisi Gypsum 12 mm , rangka Metal Stud___(
Total 2HSP
sisi )
di bulatkan
b. Tenaga :-
Pekerja
Tukang kayu
Kepala tukang
Mandor
m3
lembar
bh.
OH
OH
OH
OH
0.015
0.174
28.000
0.150
0.450
0.045
0.075
45,900.00
88,740.00
153.00
47,000.00
55,000.00
60,000.00
70,000.00
706.86
15,405.26
4,284.00
7,050.00
24,750.00
2,700.00
5,250.00
- Penambahan GlassWool
m2
1.000
15,300.00
15,300.00
( lapisan Kedap Suara )
m2 - Pasangan Partisi Gypsum 12 mm , rangka Metal Stud___(
Total 1HSP
sisi )
di bulatkan
400 mm
1200 mm
1200 mm
:- Plasterboard 9 mm
- Metal Furing
C Channel
Angle Section
Saddle Clip
Suspension Bracket
Threaded Rod
Sffit Cleat
Jointing Coumpound
Joint Tape
Screw
b. Tenaga :- Pekerja
m2
m'.
m'.
m'.
pcs
pcs
pcs
pcs
kg
m'.
pcs
1.000
2.400
0.800
0.400
1.920
0.640
0.640
0.640
0.300
0.840
11.200
23,460.00
7,650.00
7,650.00
3,570.00
765.00
459.00
4,590.00
663.00
3,060.00
255.00
153.00
23,460.00
18,360.00
6,120.00
1,428.00
1,468.80
293.76
2,937.60
424.32
918.00
214.20
1,713.60
57,338.28
LOT
1.000
12,000.00
12,000.00
12,000.00
Rp
Rp
69,338.00
69,300.00
400 mm
1200 mm
1200 mm
:- KALSI board 9 mm
- Metal Furing
C Channel
Angle Section
Saddle Clip
Suspension Bracket
Threaded Rod
Sffit Cleat
Jointing Coumpound
Joint Tape
Screw
b. Tenaga :- Pekerja
m2
m'.
m'.
m'.
pcs
pcs
pcs
pcs
kg
m'.
pcs
1.000
2.400
0.800
0.400
1.920
0.640
0.640
0.640
0.300
0.840
11.200
57,120.00
7,650.00
7,650.00
3,570.00
765.00
459.00
4,590.00
663.00
3,060.00
255.00
153.00
57,120.00
18,360.00
6,120.00
1,428.00
1,468.80
293.76
2,937.60
424.32
918.00
214.20
1,713.60
90,998.28
LOT
1.000
12,000.00
12,000.00
12,000.00
Rp
Rp
102,998.00
102,900.00
m1
kg
1.050
0.010
15,300.00
12,240.00
16,065.00
122.40
Rp
16,187.40
b. Tenaga :-
OH
OH
OH
OH
0.060
0.060
0.006
0.003
47,000.00
55,000.00
60,000.00
70,000.00
2,820.00
3,300.00
360.00
210.00
Rp
6,690.00
Rp
Rp
22,877.00
22,800.00
Rp
155,528.67
Rp
Rp
39,750.00
195,278.67
Rp
Rp
Rp
99,400.00
294,678.67
294,600.00
Pekerja
Tukang kayu
Kepala tukang
Mandor
Total HSP
di bulatkan
:-
b. Tenaga :-
m3
lembar
lembar
kg.
Pekerja
Tukang kayu
Kepala tukang
Mandor
OH
OH
OH
OH
0.015
0.347
0.347
0.050
0.150
0.450
0.045
0.075
5,000,000.00
96,900.00
127,500.00
12,240.00
47,000.00
55,000.00
60,000.00
70,000.00
77,000.00
33,645.83
44,270.83
612.00
7,050.00
24,750.00
2,700.00
5,250.00
SubTotal 1
SubTotal 2
1 m2 Pemasangan Dinding Sketsel ( Double Teakwood rangka
TotalKamper
HSP )
di bulatkan
WATERPROOFING
1 m2 - Pelapisan Waterprofing
a. Bahan
:- Waterprofing
- Serat Fiber
b. Tenaga :-
Pekerja
Tukang Cat
Kepala tukang
Mandor
Kg
m2
0.350
1.000
25,500.00
3,570.00
8,925.00
3,570.00
Rp
12,495.00
OH
OH
OH
OH
0.050
0.075
0.008
0.003
47,000.00
55,000.00
60,000.00
70,000.00
2,350.00
4,125.00
450.00
175.00
Rp
7,100.00
Rp
Rp
19,595.00
19,500.00
Rp
Rp
142,621.50
142,600.00
m2 - Pelapisan Waterprofing
Total HSP
di bulatkan
Pekerja
Tukang batu
Tukang kayu
Tukang besi
Kepala tukang
Mandor
OH
OH
OH
OH
OH
OH
5.300
0.275
1.300
1.050
0.262
0.265
3,000,000.00
12,240.00
8,262.00
12,750.00
45,900.00
117,300.00
153,000.00
7,650.00
600,000.00
18,360.00
1,301,265.00
28,687.50
385,560.00
63,342.00
123,930.00
3,060.00
47,000.00
55,000.00
55,000.00
55,000.00
60,000.00
70,000.00
249,100.00
15,125.00
71,500.00
57,750.00
15,720.00
18,550.00
Total HSP
2,524,204.50
Rp
427,745.00
Rp
2,951,950.00
kg
ljr
kg
8.730
0.500
1.200
8,262.00
330,000.00
20,000.00
72,127.26
165,000.00
24,000.00
Rp
261,127.26
b. Tenaga :-
OH
OH
OH
OH
1.670
1.670
0.167
0.083
47,000.00
55,000.00
60,000.00
70,000.00
78,490.00
91,850.00
10,020.00
5,810.00
Rp
186,170.00
Rp
447,297.00
Pekerja
Tukang besi
Kepala tukang
Mandor
m2 - Pagar besi
Total HSP
PEKERJAAN LANSEKAP
1 m1 - Kansteen beton
a. Bahan :- Kansteen beton
- Semen / PC (40 kg)
- Pasir pasang
m1
zak
m3
1.000
0.131
0.018
17,340.00
45,900.00
117,300.00
17,340.00
6,012.90
2,111.40
Rp
25,464.30
b. Tenaga :-
OH
OH
OH
OH
0.300
0.100
0.010
0.015
47,000.00
55,000.00
60,000.00
70,000.00
14,100.00
5,500.00
600.00
1,050.00
Rp
21,250.00
Rp
46,714.00
Pekerja
Tukang batu
Kepala tukang
Mandor
m1 - Kansteen beton
Total HSP
1 m2 - Paving beton
a. Bahan :- Paving beton
- Pasir urug
m2
m3
1.000
0.100
96,900.00
81,600.00
96,900.00
8,160.00
Rp
105,060.00
b. Tenaga :-
OH
OH
OH
OH
0.300
0.100
0.010
0.015
47,000.00
55,000.00
60,000.00
70,000.00
14,100.00
5,500.00
600.00
1,050.00
Rp
21,250.00
Rp
126,310.00
Pekerja
Tukang batu
Kepala tukang
Mandor
m2 - Paving beton
Total HSP
m2
m3
7.400
0.100
35,000.00
81,600.00
259,000.00
8,160.00
Rp
267,160.00
b. Tenaga :-
OH
OH
OH
OH
0.300
0.100
0.010
0.015
47,000.00
55,000.00
60,000.00
70,000.00
14,100.00
5,500.00
600.00
1,050.00
Rp
21,250.00
Rp
288,410.00
Pekerja
Tukang batu
Kepala tukang
Mandor
Total HSP
m3
1.200
70,000.00
84,000.00
Rp
84,000.00
b. Tenaga :- Pekerja
- Mandor
OH
OH
0.300
0.010
47,000.00
70,000.00
14,100.00
700.00
Rp
14,800.00
Rp
98,800.00
Total HSP
ATAP CMS
ATAP CMS
1 m2 - Penutup atap CMS
a. Bahan :- CMS tebal 4,5 mm
- alat bantu
m2
%
1.1000
15.0000
117,300.00
129,030.00
129,030.00
19,354.50
ls
1.0000
7,000.00
7,000.00
Total HSP
di bulatkan
Rp
Rp
148,384.50
7,000.00
Rp
Rp
155,384.50
155,300.00
Rp
261,127.26
Rp
186,170.00
Rp
447,297.00
Rp
Rp
456,297.00
456,000.00
kg
ljr
kg
8.730
0.500
1.200
8,262.00
330,000.00
20,000.00
72,127.26
165,000.00
24,000.00
b. Tenaga :-
OH
OH
OH
OH
1.670
1.670
0.167
0.083
47,000.00
55,000.00
60,000.00
70,000.00
78,490.00
91,850.00
10,020.00
5,810.00
1.000
9,000.00
Pekerja
Tukang kayu
Kepala tukang
Mandor
PENGECATAN
m1 - RELLING TANGGA
m2
Total HSP
9,000.00
Total HSP
di bulatkan
TALANG BJLS 30
1 m1 - Talang seng BJLS 30
a. Bahan :- Seng plat
- Paku
- Kayu hutan papan
lbr
kg
m3
1.050
0.015
0.019
60,000.00
12,240.00
3,000,000.00
63,000.00
183.60
57,000.00
Rp
120,183.60
b. Tenaga :-
OH
OH
OH
OH
0.200
0.400
0.025
0.010
47,000.00
55,000.00
60,000.00
70,000.00
9,400.00
22,000.00
1,500.00
700.00
Rp
33,600.00
Rp
153,784.00
Pekerja
Tukang
Kepala tukang
Mandor
Total HSP
SANITAIR
PEKERJAAN SANITAIR
6.1 Memasang 1 buah kloset duduk / Duoblok
6,1,1
Bahan
Kloset duduk / monoblok
Perlengkapan
Tenaga
Pekerja
Tukang Pipa
Kepala tukang
Mandor
a.
b.
Pekerja
Tukang besi
Kepala tukang
Mandor
Bh
1.0000
6% Harga kloset
Org
Org
Org
Org
3.3000
1.1000
0.0010
0.1600
Bh
1.0000
12% Harga kloset
Kg
6.0000
M
0.0100
OH
OH
OH
OH
1.2000
1.4500
0.1500
0.1000
Rp
Rp
1,700,000.00
1,700,000.00
47,000.00
55,000.00
60,000.00
70,000.00
1,700,000.00
1,700,000.00
Jumlah (1)
Rp
3,400,000.00
155,100.00
60,500.00
60.00
11,200.00
Jumlah (2)
Jumlah (1) + (2)
Dibulatkan
Rp
Rp
Rp
226,860.00
3,626,860.00
3,626,860.00
1,200,000.00
1,200,000.00
6,120.00
117,300.00
1,200,000.00
1,200,000.00
36,720.00
1,173.00
47,000.00
55,000.00
60,000.00
70,000.00
56,400.00
79,750.00
9,000.00
7,000.00
Total HSP
Dibulatkan
a.
b.
Pekerja
Tukang besi
Kepala tukang
Mandor
1.00
1.00
Bh
Set
OH
OH
OH
OH
0.3000
0.0300
400,000.00
200,000.00
400,000.00
200,000.00
47,000.00
55,000.00
60,000.00
70,000.00
16,500.00
1,800.00
Total HSP
Dibulatkan
2,437,893.00
Rp
152,150.00
Rp
Rp
2,590,043.00
2,590,040.00
600,000.00
Rp
18,300.00
Rp
Rp
618,300.00
618,300.00
a.
b.
1.00
Bh
10% Harga urinoir
6.00
Kg
0.01
M
Pekerja
Tukang besi
Kepala tukang
Mandor
OH
OH
OH
OH
1.0000
1.0000
0.1000
0.1000
1,300,000.00
1,300,000.00
1,147.50
117,300.00
1,300,000.00
130,000.00
6,885.00
1,173.00
47,000.00
55,000.00
60,000.00
70,000.00
47,000.00
55,000.00
6,000.00
7,000.00
Total HSP
Dibulatkan
a.
b.
Pekerja
Tukang besi
Kepala tukang
Mandor
Bh
%
1.0000
10.0000
350,000.00
350,000.00
350,000.00
35,000.00
OH
OH
OH
OH
0.1000
0.0100
47,000.00
55,000.00
60,000.00
70,000.00
5,500.00
600.00
Total HSP
Dibulatkan
a.
b.
Pekerja
Tukang besi
Kepala tukang
Mandor
Bh
Bh
1.0000
0.0250
75,000.00
2,500.00
75,000.00
2,500.00
OH
OH
OH
OH
0.1000
0.0100
47,000.00
55,000.00
60,000.00
70,000.00
5,500.00
600.00
Total HSP
Dibulatkan
1 Memasang 1 bh kran diameter " atau " PANAS DINGIN termasuk SHOWER
a.
Bahan :- Kran air
Bh
1.0000
150,000.00
Seal tape
Bh
0.0250
2,500.00
b.
Tenaga :-
Pekerja
Tukang besi
Kepala tukang
Mandor
OH
OH
OH
OH
0.1000
0.0100
47,000.00
55,000.00
60,000.00
70,000.00
b.
Pekerja
Tukang besi
Kepala tukang
Mandor
OH
OH
OH
OH
5,500.00
600.00
-
1.0000
0.0250
75,000.00
2,500.00
75,000.00
2,500.00
0.1000
0.0100
47,000.00
55,000.00
60,000.00
70,000.00
5,500.00
600.00
Total HSP
Dibulatkan
a.
b.
Pekerja
Tukang besi
Kepala tukang
Mandor
Bh
1.0000
75,000.00
75,000.00
OH
OH
OH
OH
0.1000
0.0100
47,000.00
55,000.00
60,000.00
70,000.00
5,500.00
600.00
Total HSP
Dibulatkan
a.
b.
Pekerja
Tukang besi
Kepala tukang
Mandor
Bh
1.0000
12% Harga kloset
Kg
6.0000
M
0.0100
OH
OH
OH
OH
1.2000
1.4500
0.1500
0.1000
Rp
115,000.00
Rp
Rp
1,553,058.00
1,553,050.00
385,000.00
Rp
6,100.00
Rp
Rp
391,100.00
391,100.00
77,500.00
Rp
6,100.00
Rp
Rp
83,600.00
83,600.00
150,000.00
2,500.00
Total HSP
Dibulatkan
a.
1,438,058.00
400,000.00
400,000.00
6,120.00
117,300.00
400,000.00
400,000.00
36,720.00
1,173.00
47,000.00
55,000.00
60,000.00
70,000.00
56,400.00
79,750.00
9,000.00
7,000.00
Total HSP
Dibulatkan
152,500.00
Rp
6,100.00
Rp
Rp
158,600.00
158,600.00
77,500.00
Rp
6,100.00
Rp
Rp
83,600.00
83,600.00
75,000.00
Rp
6,100.00
Rp
Rp
81,100.00
81,100.00
837,893.00
Rp
152,150.00
Rp
Rp
990,043.00
990,040.00
a.
b.
Pekerja
Tukang besi
Kepala tukang
Mandor
Bh
Bh
1.0000
0.0250
150,000.00
2,500.00
150,000.00
2,500.00
OH
OH
OH
OH
0.1000
0.0100
47,000.00
55,000.00
60,000.00
70,000.00
5,500.00
600.00
Total HSP
Dibulatkan
152,500.00
Rp
6,100.00
Rp
Rp
158,600.00
158,600.00
NO
JENIS PEKERJAAN
VOLUME
SATUAN
HARGA
JUMLAH
(Rp)
(Rp)
PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi
5.94
m2
8,200.00
48,708.00
-------------------------------48,708.00
PEKERJAAN TANAH
1 Galian
1.84
m3
37,000.00
67,932.00
-------------------------------67,932.00
PEKERJAAN PONDASI
1 Batu Putih
1.84
m3
405,035.40
743,644.99
-------------------------------743,644.99
PEKERJAAN BETON
1 Kolom Praktis 15X15
0.33
m3
1,500,000.00
502,132.50
0.23
m3
1,500,000.00
344,250.00
0.23
m3
1,500,000.00
344,250.00
0.18
m3
1,500,000.00
264,000.00
5 Sloof 15X20
0.31
m3
1,500,000.00
459,000.00
-------------------------------1,913,632.50
PEKERJAAN PASANGAN
1 Batu merah 1/2 bata 1 : 5
28.20
m2
50,234.00
1,416,689.22
-------------------------------1,416,689.22
PEKERJAAN PLESTERAN
1 Plesteran bata 1:4
60.80
m2
18,217.00
1,107,593.60
2 Acian
60.80
m2
15,934.40
968,811.52
109.34
m'
5,786.23
3 Benangan/tali air
632,677.96
-------------------------------2,709,083.08
5.94
m2
58,118.05
7.52
m2
61,317.89
345,221.21
461,110.52
-------------------------------806,331.72
0.05
m3
2,424,012.00
109,080.54
1.68
m2
198,994.46
334,310.70
2.00
unit
326,040.80
652,081.60
4 Jendela Nako
0.69
m2
131,771.20
90,922.13
-------------------------------1,186,394.97
NO
JENIS PEKERJAAN
VOLUME
SATUAN
HARGA
JUMLAH
(Rp)
(Rp)
PEKERJAAN PLAFOND
1 Plafond Eternit
3 List Plafond
5.94
m2
47,410.22
10.20
m'
3,093.25
281,616.73
31,551.15
-------------------------------313,167.88
PEKERJAAN ATAP
1 Penutup Atap Esbes Gelombang Kecil
9.66
m2
26,795.00
258,839.70
0.05
m3
2,578,268.00
128,088.35
13.00
m'
23,186.00
3 Lisplank
301,418.00
-------------------------------688,346.05
60.80
m2
9,547.00
2 Cat Plafond
5.94
m2
7,637.60
580,491.97
45,367.34
-------------------------------625,859.31
PEKERJAAN ELEKTRIKAL
1 Pasang Lampu Fitting 11 watt
5.00
ttk
156,120.00
780,600.00
2.00
ttk
23,556.24
47,112.48
1.00
ttk
23,364.24
23,364.24
-------------------------------851,076.72
Total
11,370,866.45