PERHITUNGAN VOLUME

I.
PEKERJAAN PERSIAPAN
1. Pembersihan Lahan
Panjang lahan = 65 m
Lebar lahan = 38 m
Volume
= 65 x 38
= 2470 m
Pagar Keamanan
Keliling lapangan
= ( 65 + 38 ) x 2
= 206 m
3. Direksi Kit
Luas = Panjang x lebar
=4mx4m
= 16 m
Bauplank
Keliling bangunan
= 126,28 m
II.
PEKERJAAN TANAH
1. Galian Tanah Pondasi Lajur
Panjang
Luas

1 66

Volume

160

= 216 m
= ( 1,66 + 0,80) x x 1,6
= 1,986 m
= 1,986 x 216
= 425,088 m

80

2. Galian Tanah Pondasi Foot Plat ( 40 Titik )


Panjang
Luas

2 82

Volume

20 0

17 5

Volume Tot

= 2,8 m
= ( 1,75 + 2,82 ) x x 2
= 4,57 m
= 2,8 x 4,57
= 12,79 m
= 12,79 x 40
= 511,84 m

3. Galian Tanah Pondasi Rollag


Rollag Trap
Panjang
Luas
100

1 2 0 ,2 7

Volume

85

Rollag Pengikat
Panjang
3 0 ,5 8

30

= 9m
= ( 0,85 + 1,2) x x 1
= 1,025 m
= 1,025 x 9
= 9,225 m

20

= 84,8 m

Luas
Volume

= ( 0,2 + 0,3 ) x x 0,3


= 0,075 m
= 0,075 x 84,8
= 6,36 m

TOTAL PEKERJAAN GALIAN TANAH = 425,088 +511,84 + 9,225 + 6,36


= 952,513 m

10

III.
PEKERJAAN PASANGAN PONDASI
1. Urugan Pasir
Pondasi Lajur
Panjang
= 216
Luas
= 0,8 x 0,1
= 0,08 m
Volume
= 0,08 x 216
= 17,28 m
Pondasi Foot Plat
Volume
= 0,1 x 1,75 x 2,8
= 0,49 m
Volume tot = 0,49 x 40
= 19,6 m
Pondasi Rollag Trap
Volume
= 0,3 x 0,1 x 9
= 0,27 m
Volume tot = 0,27 x 6
=1,62 m
Pondasi Rollag Pengikat
Volume
= 0,25 x 0,1 x 84,8
= 2,12 m
8
0

1
0

1
7
5

10

30

10

25

Urugan pasir bawah lantai


Luas
= 643,45 m
Volume
= 643,45 x 0,1
= 64,345 m
VOLUME TOTAL URUGAN PASIR
= 17,28 + 19,6 + 1,62 + 2,12 + 64,345
= 104,965 m
2. Pasangan Batu Belah
Panjang
= 216 m
Luas
= ( 0,25 + 0,8 ) x x 0,9
= 0,47 m
Volume
= 0,47 x 216
= 102,06 m
3. Pasangan Anstamping
Volume
= 0,2 x 1 x 216
= 43,2 m
90

80

20

100

IV.
PEKERJAAN BETON BERTULANG
1. Foot Plat
Type A ( 20 Bh)
Volume di bagi menjadi 2 bagian :
V1
= 1,65 x 1,62 x 0,3
= 0,80 m
V2
= {(3,14x0,25x0,25) + (1,65x1,62) x x 0,2
= 0,28 m
Vol tot/ bh
= 0,8 + 0,28
= 1,08 m / bh
Vol total
= 1,08 x 20
= 36 m
Pembesian
D 19 15. 2 = 2x ( 100/15 x 2,230 x 1,65 x 1,62 )
= 79,47 kg / unit
Berat / m
= 79,47 / 1,08
= 73,58 kg / m ~ 74 kg / m
Type B ( 6 Bh )
0.50

1.62

19 - 15

19 - 15

50
16 5

0 .4 0

V1

= 1,65x1,62x0,3
= 0,80 m
V2
= {( 0,4x0,4) + ( 1,65x1,62) x x 0,2
= 0,28 m
V tot / bh
= 0,8 + 0,2
= 1m

1.62

19 - 1 5

19 - 15

4 0
1 65

V total = 1 x 6
=6m
Pembesian
19 15
= 2{( 100/15x2,230) x ( 1,65 x 1,62)
= 79,47
Berat / m
= 79,47 / 1
= 79,47 kg / m ~ 79 kg / m
Type C ( 4 bh)
V1
= 1,65x1,62x0,3
= 0,80
V2
= {( 3,14x0,2x0,2)+(1,65x1,62)x1/2x0,2
= 1,1 m
V tot / bh
= 0,80 + 1,1
= 1,91 m / bh
Vol tot = 1,91 x 4
= 7,67 m
Pembesian
19 15
= 2{( 100/15x2,230) x ( 1,65 x 1,62)
= 79,47
Berat / m
= 79,47 / 1,91
= 41,60 kg / m ~ 42 kg / m
Type D ( 6 bh )
V1
= 1,5 x1,5x0,25
= 0,56 m
V2
= { ( 0,3 x 0,3)+ ( 1,5x1,5)} x x 0,15
= 0,015 m
0 .4 0

1 .6 2

19 - 1 5

1 9 - 15

40
165

1.5 0

19 - 15

19 - 15

19 - 15

30
150

V tot / bh

= 0,015 + 0,56
= 0,57 m
V tot = 0,57 x 8
= 4,6 m
Pembesian
19 15

= 2{( 100/15x2,230) x ( 1,5 x 1,5 )


= 66,9
= 66,9 / 0,57 = 117,36 kg / m ~ 117 kg / m

Berat / m

Type E ( 2 bh )
V1
1.50
1 9 - 15

19 - 15

19 - 1 5

30
150

Pembesian
19 15

= 1,5 x 1,5 x 0,25


= 0,56
V2
= {( 3,14x0,15x0,15)+(1,5x1,5)} x x 0,15
= 0,174
Vol tot / unit = 0,56 + 0,174
= 0,7
Vol Total
= 0,7 x 2
= 1,4 m

= 2{( 100/15x2,230) x ( 1,5 x 1,5 )


= 66,9
= 66,9 / 0,7 = 95,57 kg / m ~ 96 kg / m

Berat / m
2. Sloof
Type S1
TUMPUAN
Panjang
= 34,4 m
Volume
= 34,4 x 0,6 x 0,25
= 5,16 m
Pembesian
5 D 22 x 2
= 5 x 2,980 x 2
2 12
= 2 x 0,888
10 10
= 100 / 10 x 0,617 x 1,7

= 29,8 kg / m
= 1,776 kg / m
= 10,48 kg / m
= 42,06 kg / m

Berat / m
Bekisting
Luas / m

= 42,06 / 0,15
= 280,4 kg / m
= ( 2 x 0,6 ) + 0,25
= 1,45
= 1,45 / 0,15
= 9,66 m / m

LAPANGAN
Panjang
= 51,6 m
Volume
= 51,6 x 0,6 x 0,25
= 7,74 m
Pembesian
6 D 22 x 2
= 6 x 2,980 x 2
2 12
= 2 x 0,888
10 15
= 100 / 15 x 0,617 x 1,7

= 35,76 kg / m
= 1,776 kg / m
= 6,98 kg / m
= 44,516 kg / m

Berat / m

Type S2
TUMPUAN
Panjang
Volume

Pembesian
4 D 22 x 2
2 12
10 10

= 44,516 / 0,15
= 296,77 kg / m
= 58,2 m
= 58,2 x 0,4 x 0,25
= 5,82 m

= 4 x 2,980 x 2
= 2 x 0,888
= 100 / 10 x 0,617 x 1,3

= 23,84 kg / m
= 1,776 kg / m
= 8,021 kg / m
= 33,63 kg / m

Berat / m

= 33,63 / 0,1
=336,37 kg / m

LAPANGAN
Panjang
=87,3 m
Volume
= 87,3 x 0,4 x 0,25
= 8,73 m
Pembesian
4 D 22 x 2
= 4 x 2,980 x 2
2 12
= 2 x 0,888
10 15
= 100 / 15 x 0,617 x 1,3

= 23,84 kg / m
= 1,776 kg / m
= 5,34 kg / m
= 30,96 kg / m

Berat / m
Bekisting
Luas / m

Type S3
TUMPUAN
Panjang
Volume
Pembesian
6 D 22 x 2
2 12
10 10

= 30,96 / 0,1
= 309,6 kg
= ( 2 x 0,4 ) + 0,25
= 1,05 m
= 1,05 / 0,1
= 10,5 m / m
= 16,8 m
= 16,8 x 0,3 x 0,6
= 3,024 m
= 6 x 2,980 x 2
= 2 x 0,888
= 100 / 10 x 0,617 x 1,8

= 35,76 kg / m
= 1,776 kg / m
= 11,1 kg / m
= 48,64 kg / m

Berat / m

= 48,64 / 0,18
= 270,2 kg /m

LAPANGAN
Panjang
= 25,2
Volume
= 25,2 x 0,6 x 0,3
= 4,536 m

Pembesian
6 D 22 x 2
2 12
10 15

= 6 x 2,980 x 2
= 2 x 0,888
= 100 / 15 x 0,617 x 1,8

= 35,76 kg / m
= 1,776 kg / m
= 7,40 kg / m
= 44,9 kg / m

Berat / m
Bekisting
Luas /m

= 44,9 / 0,18
= 249 , 4 kg / m
= ( 2 x 0,6 ) + 0,3
= 1,5 m
= 1,5 / 0,18
= 8,33 m / m

3. Kolom
K1
Tinggi = 7,4 m
Jumlah= 20 bh
Vol
= 7,4 x 3,14 x 0,25 x 0,25 x 20
= 29,04 m
Pembesian
15 19
= 15x2,230
8 10
=100 / 10 x 0,395 ( 3,14 x 0,5)

= 33, 45 kg / m
= 6,2 kg / m
= 39,65 kg / m

Berat / m
Bekisting
Luas / m

= 39,65 / 0,195
= 202,29 kg / m
= ( 3,14 x 0,5) x 1
= 1,57 m
= 1,57 / ( 3,14 x 0,25 x 0,25
= 8,26 m / m

K2
Tinggi = 4,2 m
Jumlah = 4 bh
Vol
= 4,2 x 3,14 x 0,2 x 0,2 x 4
= 2,1 m
Pembesian
10 19= 10 x2,230
8 10
=100 / 10 x 0,395 ( 3,14 x 0,4)

= 22,3 kg / m
= 4,96 kg / m
= 27,26 kg / m

Berat / m
Bekisting
Luas / m

= 27,26 / 0,125
= 218,08 kg / m
= ( 3,14 x 0,4) x 1
= 1,26 m
= 1,26 / 0,125
= 10 m / m

K3
Tinggi = 4,2 m

Jumlah = 2 bh
Vol
= 4,2 x 3,14 x 0,15 x 0,15 x 2
= 0,593 m
Pembesian
8 19
= 8 x2,230
8 10
=100 / 10 x 0,395 ( 3,14 x 0,3)

= 17,84 kg / m
= 3,72 kg / m
= 21,56 kg / m

Berat / m
Bekisting
Luas / m

= 21,56 / 0,07
= 308 kg / m
= ( 3,14 x 0,3 ) x 1
= 0,942 m
= 0,942 / 0,07
= 13,45 m / m

K4
Tinggi = 7,4 m
Jumlah = 6 bh
Vol
= 7,4 x 0,4 x 0,4 x 6
= 7,104 m
Pembesian
16 19
= 16 x2,230
= 35,68 kg / m
8 10
=100 / 10 x 0,395 { ( 0,4 + 0,4) x2) = 6,32 kg / m
= 42 kg / m
Berat / m
Bekisting
Luas / m

= 42 / 0,16
= 262,5 kg / m
= ( 2 x ( 0,4 x 0,4 ) ) x 1
= 1,6 m
= 1,6 / 0,16
= 10 m / m

K5
Tinggi = 7,4 m
Jumlah = 8 bh
Vol
= 7,4 x 0,3 x 0,3 x 8
= 5,328 m
Pembesian
8 19
= 8 x2,230
= 17,84 kg / m
8 10
=100 / 10 x 0,395 { ( 0,3 + 0,3) x2) = 4,74 kg / m
= 22,58 kg / m
Berat / m
Bekisting
Luas / m

= 22,58 / 0,09
= 250 kg / m
= ( 2 x ( 0,3 x 0,3 ) ) x 1
= 1,2 m
= 1,2 / 0,09
= 13,3 m / m

4. Balok
B1
TUMPUAN
Panjang = 4,8 m
Volume = 4,8 x 0,8 x 0,4
= 1,536 m
Pembesian
2x 10 19
= 10 x2,230
8 10
=100 / 10 x 0,395 x 2,4

= 44,6 kg / m
= 9,48 kg / m
= 54,08 kg / m

Berat / m
Bekisting
Luas / m

= 54,08 / ( 0,8 x 0,4 )


= 169 kg / m
= ( 0,8 x 2 ) + 0,4
=2m
= 2 / ( 0,8 x 0,4 )
= 6,25 m / m

LAPANGAN
Panjang
= 7,2 m
Volume
= 7,2 x 0,8 x 0,4
= 2,304 m
Pembesian
10 19
= 10 x2,230
8 15
=100 / 15 x 0,395 x 2,4
7 19
= 7 x 2,230
4 19
= 4 x 2,230

= 22,3 kg / m
= 6,31 kg / m
= 15,61 kg / m
= 8,92 kg / m
=53, 14kg / m

Berat / m

= 53,14 / ( 0,8 x 0,4 )


= 166 kg / m
B2-1

TUMPUAN
Panjang = 14,4 m
Volume = 7,2 x 0,7 x 0,3
= 3,024 m
Pembesian
8 19
= 8 x2,230
8 10
=100 / 10 x 0,395 x 2
4 19
= 4 x 2,230
2 8
= 2 x 0,395

= 17,84 kg / m
= 7,9 kg / m
= 8,92 kg / m
= 0,79 kg / m
=35,45 kg / m

Berat / m

= 35,45 / 0,21
=168,8 kg / m

LAPANGAN
Panjang = 21,6 m
Volume = 21,6 x 0,7x 0,3
= 4,536 m

Pembesian
4 19 x 2
8 15
2 8

= 4 x2,230 x 2
=100 / 15 x 0,395 x 2
= 2 x 0,395

= 17,84 kg / m
= 5,26 kg / m
= 0,79 kg / m
=23,89 kg / m

Berat / m
Bekisting
Luas / m

TUMPUAN
Panjang
Volume
Pembesian
7 19
8 10
3 19
2 8

= 23,89 / 0,21
=113,79 kg / m
= ( 0,7 x 2 ) + 0,3
= 1,7 m
= 1,7 / ( 0,7 x 0,3 )
= 8,09 m / m
B2 -2
=6m
= 6 x 0,7 x 0,3
= 1,26 m
= 7 x2,230
=100 / 10 x 0,395 x 2
= 3 x 2,230
= 2 x 0,395

= 15,61 kg / m
= 7,9 kg / m
= 6,69 kg / m
= 0,79 kg / m
=30,99 kg / m

Berat / m
Bekisting
Luas / m

= 30,99 / 0,21
= 147,57 kg / m
= ( 0,7 x 2 ) + 0,3
= 1,7
= 1,7 / 0,21
= 8,09 m /m

LAPANGAN
Panjang
=9m
Volume
= 9 x 0,7x 0,3
= 1,89 m
Pembesian
4 19
= 4 x2,230
8 15
=100 / 15 x 0,395 x 2
5 19
= 5 x 2,230
2 8
= 2 x 0,395

= 8,920 kg / m
= 5,26 kg / m
= 11,15 kg / m
= 0,79 kg / m
=26,12 kg / m

Berat / m

TUMPUAN
Panjang
Volume

= 26,12 / 0,21
= 124,38 kg / m
B3-1
= 56 m
= 56 x 0,5 x 0,25
=7m

Pembesian
6 19
8 10
3 19
2 8

= 6 x2,230
=100 / 10 x 0,395 x 1,5
= 3 x 2,230
= 2 x 0,395

= 13,38 kg / m
= 5,925 kg / m
= 6,69 kg / m
= 0,79 kg / m
=26,78 kg / m

Berat / m
Bekisting
Luas / m

= 26,78 / 0,5 x 0,25


= 214,24 kg / m
= ( 0,5 x 2 ) + 0,25
= 1,25 m
= 1,25 / 0,5 x 0,25
= 10 m / m

LAPANGAN
Panjang
= 96 m
Volume
= 96 x 0,5 x 0,25
= 12 m
Pembesian
3 19
= 3 x2,230
8 15
=100 / 15 x 0,395 x 1,5
4 19
= 4 x 2,230
2 8
= 2 x 0,395

= 6,69 kg / m
= 3,94 kg / m
= 8,92 kg / m
= 0,79 kg / m
=16,79 kg / m

Berat / m

B3-2
TUMPUAN
Panjang
Volume
Pembesian
5 19
8 10
2 19
2 8

= 16 ,79 / 0,5x 0,25


= 134,32 kg / m
= 12 m
= 12 x 0,5 x 0,25
= 1,5 m
= 5 x2,230
=100 / 10 x 0,395 x 1,5
= 2 x 2,230
= 2 x 0,395

= 11,15 kg / m
= 5,925 kg / m
= 4,46 kg / m
= 0,79 kg / m
=22,325 kg / m

Berat / m

= 22,325 / 0,5x0,25
= 178,6 kg / m

LAPANGAN
Panjang
= 18 m
Volume
= 18 x 0,5 x 0,25 = 2,25 m
Pembesian
2 19
= 2 x2,230
8 15
=100 / 15 x 0,395 x 1,5
3 19
= 2 x 2,230
2 8
= 2 x 0,395

= 4,46 kg / m
= 3,94 kg / m
= 6,69 kg / m
= 0,79 kg / m
=15,88 kg / m

Berat / m

B4-1
TUMPUAN
Panjang
Volume
Pembesian
5 19
8 10
2 19

= 15,88/ 0,5 x 0,25


= 127,04 kg / m

= 70,8 m
= 70,8 x 0,4 x 0,25
= 7,08
= 5 x2,230
=100 / 10 x 0,395 x 1,3
= 2 x 2,230

= 11,15 kg / m
= 3,42 kg / m
= 4,46 kg / m
=19,38 kg / m

Berat / m
Bekisting
Luas / m

= 19,38 / 0,4x0,25
=193,8 kg / m
= ( 0,4 x 2 ) + 0,25
= 1,05
= 1,05 / 0,4 x 0,25
= 1,05 m / m

LAPANGAN
Panjang
= 106,2 m
Volume
= 106,2 x 0,4 x 0,25
= 10,62 m
Pembesian
2 19
= 2 x2,230
8 15
=100 / 15 x 0,395 x 1,3
3 19
= 2 x 2,230

= 4,46 kg / m
= 3,42 kg / m
= 6,69 kg / m
=14,57 kg / m

Berat / m

B4-2
TUMPUAN
Panjang
Volume
Pembesian
4 19
8 10
2 19

= 14,57/ 0,4x0,25
= 145,7 kg / m
= 27,6 m
= 27,6 x 0,4 x 0,25
= 2,76 m
= 4 x2,230
=100 / 10 x 0,395 x 1,3
= 2 x 2,230

= 8,920 kg / m
= 3,42 kg / m
= 4,46 kg / m
=16,8 kg / m

Berat / m

= 16,8 / 0,4 x 0,25


= 168 kg / m

LAPANGAN
Panjang
= 41,4 m
Volume
= 41,4 x 0,4 x 0,25
= 4,14 m
Pembesian
2 19
= 2 x2,230

= 4,46 kg / m

8 15
3 19

=100 / 15 x 0,395 x 1,3


= 2 x 2,230

= 3,42 kg / m
= 6,69 kg / m
=14,57 kg / m

Berat / m

B5-1
TUMPUAN
Panjang
Volume
Pembesian
5 16
8 10
2 16

= 14,57/ 0,4x0,25
= 145,7 kg / m
= 16,8 m
= 16,8 x 0,4 x 0,2
= 1,344 m
= 5 x1,58
=100 / 10 x 0,395 x 1,2
= 2 x 1,58

= 7,9 kg / m
= 4,74 kg / m
= 3,16 kg / m
=15,8 kg / m

Berat / m
Bekisting
Luas / m

= 15,8 / 0,08
= 197,5 kg / m
= ( 0,4 x 2 ) + 0,2
=1
= 1 / 0,08
= 12,5 m / m

LAPANGAN
Panjang
= 25,2 m
Volume
= 25,2 x 0,4 x 0,2
= 2,016
Pembesian
3 16
= 3 x1,58
8 15
=100 / 15 x 0,395 x 1,2
4 16
=4 x 1,58

= 4,74kg / m
= 3,15 kg / m
= 6,32 kg / m
=14,21 kg / m

Berat / m

B5-2
TUMPUAN
Panjang
Volume
Pembesian
4 16
8 10
2 16

= 14,21 / 0,08
= 177,625 kg / m
= 3,6 m
= 3,6 x 0,4 x 0,2
= 0,288 m
= 4 x1,58
=100 / 10 x 0,395 x 1,2
= 2 x 1,58

= 6,32kg / m
= 4,74 kg / m
= 3,16 kg / m
=14,2 kg / m

Berat / m

= 14,2 / 0,08
= 177,5 kg / m

LAPANGAN
Panjang
= 5,4 m
Volume
= 5,4 x 0,4 x 0,2
= 0,432 m
Pembesian
3 16
= 3 x1,58
8 15
=100 / 15 x 0,395 x 1,2
2 16
= 2 x 1,58

= 4,74kg / m
= 3,15 kg / m
= 3,16 kg / m
=11,05 kg / m

Berat / m

B6
TUMPUAN
Panjang
Volume
Pembesian
3 14
8 15
2 14

= 11,05 / 0,08
= 138,125 kg / m
= 9,6 m
= 9,6 x 0,3 x 0,25
= 0,72 m
= 3 x1,23
=100 / 15 x 0,395 x 1,1
= 2 x 1,23

= 3,69 kg / m
= 2,89 kg / m
= 2,46 kg / m
=9,04 kg / m

Berat / m

= 9,04 / 0,075
= 120,53 kg / m

LAPANGAN
Panjang
= 14,4
Volume
= 14,4 x 0,3 x 0,25
= 1,08 m
Pembesian
3 16
= 3 x1,58
8 20
=100 / 20 x 0,395 x 1,1
2 14
= 2 x 1,23

= 4,74 kg / m
= 2,17 kg / m
= 2,46 kg / m
=9,37 kg / m

Berat / m
Bekisting
Luas / m

B7
TUMPUAN
Panjang
Volume
Pembesian
6 19
8 10

= 9,37 / 0,075
= 124,9 kg / m
= ( 0,3 x 2 ) + 0,25
= 0,85 m
= 0,85 / 0,075
= 11,3 m / m

= 4,8 m
= 4,8 x 0,6 x 0,25
= 0,72 m
= 6 x2,230
=100 / 10 x 0,395 x 1,7

= 13,38kg / m
= 6,715 kg / m

3 19
2 8

=3 x 2,230
= 2 x 0,395

= 6,69kg / m
= 0,79kg / m
=27,57 kg / m

Berat / m
= 27,57 / 0,15 = 183,8 kg /m
LAPANGAN
Panjang
= 7,2 m
Volume
= 7,2 x 0,6 x 0,25
Pembesian
4 19
= 4 x2,230
8 10
=100 / 15 x 0,395 x 1,7
3 19
=3 x 2,230
2 8
= 2 x 0,395

= 8,92kg / m
= 4,47 kg / m
= 6,69kg / m
= 0,79kg / m
=20,87 kg / m

Berat / m
Bekisting
Luas /m

= 20,87 / 0,15
= 139,17 kg /m
= ( 0,6 x2 ) + 0,25
= 1,45
= 1,45 / 0,15
=9,66 m /m

5. RING BALK
TUMPUAN
Panjang
= 75,8 m
Volume
= 75,8 x 0,4 x 0,25
= 7,58 m
Pembesian
4 19
= 4 x2,230
8 10
=100 / 10 x 0,395 x 1,3
2 19
=2 x 2,230

= 8,92kg / m
= 5,135 kg / m
= 4,46 kg / m
=18,515 kg / m

Berat / m
Bekisting
Luas / m

= 18,515 / 0,1
= 185,15 kg /m
= ( 0,4 x 2 ) + 0,25
= 1,05
= 1,05 / 0,1
= 10,5 m / m

LAPANGAN
Panjang
= 96,1 m
Volume
= 96,1 x 0,4 x 0,25
= 9,61 m
Pembesian
3 19
= 3 x2,230
8 15
=100 / 15 x 0,395 x 1,3
2 19
=2 x 2,230

= 6,69 kg / m
= 3,42 kg / m
= 4,46 kg / m
=14,57 kg / m

Berat / m

= 14,57 / 0,1 = 145,7 kg /m

6. PLAT LANTAI
Luas lantai
= 573 m
Tebal
= 0,12
Volume
= 0,12 x 474,1
= 67,772 m
Pembesian
10 40
= 1,48 kg
Berat / m
= 1,48 / 0,12 x 1
= 12,34 kg / m
7. TANGGA
V.

PEKERJAAN PASANGAN DINDING


1. Pasangan Batu Trasram 1 : 3
Dinding lantai 1
Panjang
= 157,75 50,69
= 107,06 m
Volume
= 107,06 x 0,3 x 0,15
= 4,8117 m

Trasram KM / WC LT 1 dan Lt 2
Tinggi trasram
= 1,5 m
Panjang
= 50,4 8,2
= 42,2 m
Volume
= 42,2 x 1,5 x 0,15
= 9,495 m
2. Pasangan Batu bata 1 : 3 : 10

Dinding Lantai 1
Tinggi dinding
= 3,7 m
Panjang
= 157,75 m
Luas
= ( panjang dinding x tinggi ) bukaan
= ( 157,75 x 3,7 ) 142,69
= 583,675 142,69
= 440,985 m
Volume
= 440,985 x 0,15
= 66,14 m
Dinding Km / Wc lantai 1
Tinggi dinding
= 2,25 m
Panjang
= 27 m
Luas
= ( 27 x 2,25 ) 23,066
= 60,75 23,066
= 37,684 m
Volume
= 37,684 x 0,15
= 5,65 m
Dinding Lantai 2
Tinggi
= 3,2 m
Panjang
= 153,75
Luas
= ( 153,75 x 3,2 ) 116,25
= 492 116,25
= 375,75 m

Volume

VI.

VII.

= 375,75 x 0,15
= 56,36 m

Dinding Km Lt 2
Tinggi
= 1,45 m
Panjang
= 26,6
Luas
= ( 26,2 x 1,45 ) 5,28
= 33,29 m
Volume
= 33,29 x 0,15
= 4,99 m
PEKERJAAN PLESTERAN
1. Dinding trasram ( 1 : 8 ) tebal 15 mm
Dinding LT 1
Panjang
= 107,06
Tinggi
= 0,3
Volume
= 107,06 x 0,3 x 2
= 64,23 m
Dinding Km / Wc
Panjang
= 42,2
Tinggi
= 1,75
Volume
= 42,2 x 1,75 x 2
= 147,7 m
2. Dinding bata ( 1: 3 ) tebal 15 mm
Dinding Lt 1
Volume = 440,985 x 2
= 881,97 m
Dinding KM / wc Lt1
Volume = 37,684 x 2
= 75,368 m
Dinding Lt 2
Volume = 375,75 x 2
= 751 ,5 m
Dinding Km / Wc Lt2
Volume = 33,29 x 2
= 66,58
PEKERJAAN KUSEN
1. Type PJ1 ( 1 Bh )
Kusen
= Alumunium 6 / 10
Panjang
= 29,61 m
Kaca Mati
Volume
=12,284 m
2. Type PJ2 ( 1 bh )
Kusen
= Alumunium
Panjang = 21,29 m
Pintu Panil Kyu
Luas
= 3,15 m

Jendela Berbingkai
Luas
= 3,342 m

Kaca Mati
Luas
= 1,135 m

3. Type PJ3 ( 2 Bh )
Kusen
= Alumunium
Panjang = 15,55 x 2
= 31,1 m
Pintu Panil Kyu
Luas
= 1,68 m
Volume = 1,68 x 2
= 3,36 m

Jendela Berbingkai
Luas
= 1,43 m
Volume = 1,43 x 2
= 2,86 m
4. Type PTS ( 1 Bh )
Kusen
= Alumunium
Panjang = 16,5 m
Pintu Panil Kyu
Luas
= 1,68 m
Kaca Mati
Luas
= 2,62 m
5. Type P1 ( 4 Bh )
Kusen
= Alumunium
Panjang = 9,05 m
Volume = 9,05 x 4
= 36,2 m
Pintu Panil Kayu
Luas
= 2,73 m
Volume = 2,73 x 4
= 10,92 m
Kaca Mati
Luas
= 3,65 m
Volume = 3,65 x 4
= 14,6 m
6. Type P2 ( 7 Bh )
Kusen
= Alumunium
Panjang = 7,5 m
Volume = 7,5 x 7
= 52,5 m
Pintu Panil Kayu
Luas
= 1,68 m
Volume = 1,68 x 7
= 11,76 m
Kaca Mati
Luas
= 0,52 m
Volume = 0,52 x 7
= 3,64 m
7. Type P3 ( 2 Bh )
Kusen
= Alumunium

Panjang
Volume

= 10,4 m
= 10,4 x 2
= 20,8 m

Pintu Kaca
Luas
= 2,28 m
Volume = 2,28 x 2
= 4,56 m
Kaca Mati
Luas
= 1,1 m
Volume = 1,1 x 2
= 2,2 m
8. Type P4 ( 10 Bh )
Kusen
= Alumunium
Panjang = 5,12 m
Volume = 5,12 x 10
= 51,2 m
Pintu PVC
Luas
= 1,57 m
Volume = 1,57 x 10
= 15,7 m
9. Type J1 ( 10 Bh )
Kusen
= Alumunium
Panjang = 17,2 m
Volume = 17,2 x 10
= 172 m
Daun Jendela
Luas
= 2,37 m
Volume = 2,37 x 10
= 23,7 m
Kaca Mati
Luas
= 1,7 m
Volume = 1,7 x 10
= 17 m
10. Type J2 ( 19 Bh )
Kusen
= Alumunium
Panjang = 11,8 m
Volume = 11,8 x 19
= 224,2 m
Daun Jendela
Luas
= 2,37 m
Volume = 2,37 x 19
= 45,03 m
Kaca Mati
Luas
= 0,85m
Volume = 0,85 x 19
= 16,15 m
11. Type J3 ( 4 Bh )
Kusen
= Alumunium 6 / 10

Panjang
Volume

= 14,08 m
= 14,08 x 4
= 56,32 m

Kaca Mati
Luas
= 3,852 m
Volume = 3,85 x 4
= 15,4 m
12. Type J4 ( 2 Bh )
Kusen
= Alumunium
Panjang = 9,9 m
Volume = 9,9 x 2
= 19,8 m
Daun Jendela
Luas
= 1,18 m
Volume = 1,18 x 2
= 2,37 m
Kaca Mati
Luas
= 0,85m
Volume = 0,85 x 2
= 1,7 m
13. Type J5 ( 2 Bh )
Kusen
= Alumunium 6 / 10
Panjang = 13,14 m
Volume = 13,14 x 2
= 26,28 m
Kaca Mati
Luas
= 2,772m
Volume = 2,772 x 2
= 5,54 m
14. Type J6 ( 1 Bh )
Kusen
= Alumunium 6 / 10
Panjang = 20,6 m
Kaca Mati
Luas
= 3,68 m
15. Type V1 (2 Bh )
Kusen
= Alumunium
Panjang = 5,35 m
Volume = 5,35 x 2
= 10,7 m
Daun Jendela
Luas
= 0,91 m
Volume = 0,91 x 2
= 1,82 m
16. Type V2 ( 9 Bh )
Kusen
= Alumunium
Panjang = 3,1 m

Volume

VIII.

IX.

X.

= 3,1 x 9
= 27,9 m
Daun Jendela
Luas
= 0,455 m
Volume = 0,455 x 9
= 4,095 m
PEKERJAAN LANTAI
1. Garaito 40 x 40 ( Polos )
Luas
= 157,5 + 13,5 + 9 + 4,25
= 184,25 m
Volume
= 184,25 4,8
= 179,45 m
2. Keramik Glasur 40 x 40
Luas
= 24,4 m
3. Keramik 30 x 30 ( Putih )
Luas
= 684,5 m
4. Keramik 30 x 30 ( abu abu )
Luas
= 323,23 m
5. Keramik 20 x 20
Luas
= 38 m
6. Keramik Dinding 20 x 25
Panjang
=51,9
Tinggi
= 1,5 m
Luas
= 51,9 x 1,5
= 77,85 m
PEKERJAAN LANGIT LANGIT
1. Pemasanga Rangka Metal Furring
Luas
= 1542,34 m
2. Pemesangan gypsum Board
Luas
= 723,09 m
3. Pemasangan Kalsiboard
Luas
= 819,25 m
PEKERJAAN ATAP
1. Pekerjaan Kuda Kuda Baja
Kuda Kuda 1
Profile 60.60 . 6
Panjang = 55,22 m
Berat kg / m = 5,42
Berat total = 55,22 x 5,42
= 299,2
Profile 80.80.8
Panjang = 51,24 m
Barat kg / m
= 8,72
Berat total = 51,24 x 8,72
= 446,8
BERAT TOTAL KUDA KUDA TYPE 1

Kuda Kuda 2
Profile 60.60.6
Panjang = 73,69

= 446,8 + 299,2
= 746,01

Berat Total = 73,69 x 5,42


= 399,41
Profile 80.80.8
Panjang = 28,44 m
Berat total = 28,44 x 8,72
= 247,4
BERAT KUDA KUDA TYPE 2

Kuda Kuda 3
Profile 60.60.6
Panjang = 18,16 m
Berat total = 18,16 x 5,42
= 98,42
Profile 80.80.8
Panjang = 25,78 m
Berat total = 25,78 x 8,72
= 224,8
BERAT KUDA KUDA TYPE 3

2. Gording 8 / 12
Panjang
= 633,33 m
Volume
= 0,08 x x 633,33
3. Usuk dan reng
Luas atap
= 870,454 m
Nok
Panjang

= 48,75 m

Bubungan
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
XII.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.

Panjang
= 48,75 m
XI.
PEKERJAAN SANITASI
Jumlah Kloset Duduk = 7 bh
Jumlah Wastafel = 9 bh
Jumlah floor drain = 8 bh
Jumlah kran
= 9 bh
Pasang Bak cuci stainlestil = 1 bh
Pasang bak mandi
= 7 bh
Panjang Pipa air kotor padat = 29,73 m
Panjang pipa air kotor cair = 48,63 m
Pasang pipa beton
= 195,65 m
Pasang pipa air bersih
= 99,13 m
PEKERJAAN ISTALASI LISTRIK
exhous fan
= 5 bh
Ac split
= 21 bh
Pane listrik = 2 bh
Lampu Rml = 11 bh
Lampu TKI = 5 bh
Lampu RML = 53 bh
Dwont light = 64 bh
Stop Kontak = 2 bh
Saklar ganda = 11 bh
Saklar hotel = 26 bh

= 50,6 m

= 399,41 + 247,4
= 646,838

= 98,42 + 224 ,8
= 323,22

11.

Lampu gantung = 1 bh