Anda di halaman 1dari 74

Grid Connection of Solar PV Technical and Economical Assessment of Net-Metering in Kenya

Authors Georg Hille et al. Michael Franz (ed.) December 2011 Editor Deutsche Gesellschaft fr Internationale Zusammenarbeit (GIZ) GmbH On behalf of the German Federal Ministry of Economics and Technology (BMWi) Contact Deutsche Gesellschaft fr Internationale Zusammenarbeit (GIZ) GmbH Potsdamer Platz 10, 10785 Berlin, Germany Fax: +49 (0)30 408 190 22 253 Email: pep-ostafrika@giz.de Web: www.gtz.de/projektentwicklungsprogramm Web: www.exportinitiative.bmwi.de

This report is part of the Project Development Programme (PDP) East Africa. PDP East Africa is implemented by the Deutsche Gesellschaft fr Internationale Zusammenarbeit (GIZ) on behalf of the German Federal Ministry of Economics and Technology (BMWi) under the Export Initiative Renewable Energies. More information about the PDP and about renewable energy markets in East Africa: www.gtz.de/projektentwicklungsprogramm

This publication, including all its information, is protected by copyright. GIZ cannot be liable for any material or immaterial damages caused directly indirectly by the use or disuse of parts. Any use that is not expressly permitted under copyright legislation requires the prior consent of GIZ. All contents were created with the utmost care and in good faith. GIZ assumes no responsibility for the accuracy, timeliness, completeness or quality of the information provided.

Technical and Economical Assessment of Net-Metering in Kenya

Content
I. NET METERING IN KENYA OUR RESULTS AT A GLANCE 1 2 6 8 8

II. RECOMMENDATIONS III. METHODOLOGY PART I: ANALYSIS OF THE ECONOMICS OF SOLAR PV IN KENYA 1. BACKGROUND AND CONTEXT
a.

The Kenyan context 9 i. The Solar Resource .................................................................................................................................... 9 ii. Status of the Kenyan Solar Market ......................................................................................................... 10 iii. Existing grid-connected PV plants .......................................................................................................... 11 iv. The Kenyan Electricity Market - relevant customer tariff categories .................................................. 13 What is Net Metering Net Metering or Feed-in-Tariffs Solar PV system price development 17 19 20

b. c. d.

2. ECONOMIC EVALUATION
a. Introduction

23
23

b. Reference case and input data 25 i. Reference case assumptions ................................................................................................................... 25 ii. PV generation cost assumptions ............................................................................................................. 26 c. i. ii. d. e. f. g. Consumer perspective: economic viability of PV power generation 30 Investment today ....................................................................................................................................... 30 Investment in future / Investment based on future cost ....................................................................... 32 Economic implications at system level Optional compensation through net-metering-fee a theoretical model Other economic implications A possible market development for grid connected PV 36 38 40 41

Technical and Economical Assessment of Net-Metering in Kenya

3. INTERNATIONAL EXPERIENCES IN NET-METERING


a. b. c. d. e. f. United States Denmark Mexico Brazil Morocco Best practices

42
42 43 44 45 45 46

PART II: TECHNICAL ISSUES OF SOLAR PV GRID INTERCONNECTION 1. INTRODUCTION 2. COMPATIBILITY WITH THE KENYA GRID CODE 3. SOLAR PV AND THE GERMAN/EUROPEAN ELECTRICITY SUPPLY NETWORK 4. RELEVANT TECHNICAL ISSUES OF DISTRIBUTED PV GENERATION 5. APPLICABLE ASPECTS OF THE GERMAN LV GUIDELINE 6. FUTURE OPTIONS REFERENCES

47 47 48 51 53 56 61 63

Technical and Economical Assessment of Net-Metering in Kenya

List of Tables
Table 1: Table 2: Table 3: Table 4: Table 5: Table 6: Table 7: Table 9: Table 10: Table 11: Table 12: Table 13: Table 15: Table 16: Table 17: Table 18: Table 19: Table 20: Table 8: Kenya Solar Market: > 1.2 MWp/a [16] ...................................................................................... 10 Current tariff structure ................................................................................................................ 13 Examples for impact of level of consumption on energy charge payment ................................. 14 Electricity tariff charges and levies ............................................................................................. 15 Relevant tariff groups and actual end-user prices ...................................................................... 16 Characteristics, strengths and weaknesses of net-metering versus Feed-in Tariffs FIT ............ 20 Prices for PV in Germany and Kenya in 10/2011 ....................................................................... 21 Definition of the most relevant consumer cases for net metering, ............................................. 26 PV input data and possible variations ........................................................................................ 27 Economic input data and possible variations ............................................................................. 28 Possible scenarios and input data variations ............................................................................. 30 Current costs for PV Left side for Nairobi radiation conditions (Kisumu) versus average of recent electricity tariff (10/2011) ............................................................................... 31 Profit or losses by net-metering at system level ......................................................................... 37 Avoided cost at system level in a mature PV market under net-metering .................................. 37 Example how to calculate the surcharge/additional fee on the annual consumers bill .............. 39 Cost/benefit of Net Metering for the GoK ................................................................................... 40 Customers per relevant KPLC tariff groups ................................................................................ 41 Assessment of possible PV market development ...................................................................... 42 Set values and reaction time of protection relays ....................................................................... 60

List of Figures
Figure 1: Global Horizontal Solar Radiation in Kenya ................................................................................. 9 Figure 2: Electricity production and real production for the 60 kWp system for September 2011 (www.sma.de) ................................................................................................. 12 Figure 3: Principle of PV electricity production and daily demand ............................................................. 17 Figure 4: PV system price decrease in Germany ...................................................................................... 21 Figure 5: Learning Curve for PV and future cost development projection ................................................. 22 Figure 11: Sensitivity analysis of a small grid-connected PV plant ............................................................. 25 Figure 12: Comparison of PV cost with increasing tariffs for Nairobi .......................................................... 31 Figure 13: Comparison of PV cost with increasing tariffs for Kisumu .......................................................... 32 Figure 14: Comparison and analysis of LCOE for a) customer categories, b) sites/ irradiation regimes, c) exchange rates ........................................................................................................ 36 Figure 6: Development of PV installations in Germany 2000 2010 ........................................................ 47 Figure 7: Principle scheme of current flow over LV transformer and voltage gradient at distributed generation. ................................................................................................................ 53 Figure 8: Active power reduction of renewable-based generating units in the case of over-frequency (from [12]) ................................................................................................................................... 58 Figure 9: Example of a cos (P)-characteristic. This is the recommended default curve. ....................... 59 Figure 10: Operation voltage-time bands for DG on the MV grid. ............................................................... 61

Technical and Economical Assessment of Net-Metering in Kenya

Currency
1 EUR = 133 KES / 120 KES

Measurement
W kW MW GW Watt Kilowatt Megawatt Gigawatt Wp kWp MWp GWp Watt peak Kilowatt peak Megawatt peak Gigawatt peak Wh kWh MWh GWh Watt hour Kilowatt hour Megawatt hour Gigawatt hour

Technical and Economical Assessment of Net-Metering in Kenya

List of Acronyms
BMZ ENTSOE EIRR PIRR EPC ERC ESCO FIT FNN GDP GoK IFI IPP IRR KES KPLC Bundesministerium fr wirtschaftliche Zusammenarbeit und Entwicklung European common control area Euro Equity internal rate of return Project internal rate of return equipment purchase contract Energy Regulatory Commission energy services company Feed-in-Tariffs Forum network technology / network operation in the Association of Electrical, Electronic and Information Technologies VDE, Germany gross domestic product BIP Government of Kenya International Financing Institutions independent power producer internal rate of return Kenyan Shilling Kenya Power and Lighting Company Limited

PPI
LCOE LCP LEAP MoE REAP O&M SPV WASP

power project implementation


Levelised costs of electricity least cost planning the Long range Energy Alternatives Planning System Ministry of Energy of Kenya Regional energy advisory platform East Africa operation and maintenance Special purpose vehicles The Wien Automatic Simulation Planning Package

Technical and Economical Assessment of Net-Metering in Kenya

I.

Net Metering in Kenya Our Results at a Glance

1 1 1.5 2 2 2.2 3.5 50 200

year is the duration for formulating and implementing a net-metering regulation, assuming fast and well-informed Government of Kenya (GoK) decision until end 2011, the first 30,000 MWh could be fed-in by end of year 2012! EURO / Wp prices have meanwhile been reached in EU sales for high end modules in 2011-Q4, down from about 1,4 /Wp in early 2011. This sharp decline makes PV in Kenya competitive! The medium term estimates for further cost reductions is 10% p.a.! times better than Germany: the yield (harvested energy fed into the grid per installed nameplate power of generator) is about 1.5 times higher than Germany and about 1.1 times higher than that of the sunniest EU FIT markets. years maximum until net metering will become the cheapest solution based on LCOE comparison - for the consumer classes DC (> 1500 kWh/month), SC and CI1. GoK should pave the way for net metering now, so that these projects can gear up. recently installed lighting projects (UNEP and SOS Childrens Village) prove that grid-connected PV works and performs well in Kenya, if it is planned and installed properly with high-end components. The quality standards for products and services of these two projects are equivalent to those recommended in the technical and economical analysis presented here. billion KES p.a. avoided fuel cost and a correspondingly lower fuel cost charge could be realized if 100 MWp of solar PV would be installed. This estimate is based on the assumption that PV under net-metering would replace the energy & fuel charges paid to the three most expensive thermal power plants KES/kWh could be the maximum for a net-metering fee to compensate additional administration expenditures for the utility Kenya Power. This fee should be paid once with the annual bill. However, net metering will not reduce KPLC profit! Hz can be technically controlled and actively supported by modern inverters. Modern solar PV technology can play an active role in voltage control and should not to be seen longer as an additive power resource. With improving weather forecast, PV becomes a dispatchable power resource with a very low default rate. MWp installed solar PV under net-metering is realistically feasible within a relatively short timeframe, assuming that only a small fraction of the consumers in the relevant consumer classes (DC, SC, CI1) of between 1% and 3% invest in solar PV under netmetering. However, we recommend starting with 75MWpas soon as possible, and then scale up quickly to allow benchmarking of development partner interventions, international PV manufacturer costs and system performance in Africa. EURO investment costs per kWp are attainable today for 50 kWp plants with highend components. Total turnkey PV generator costs of 2/Wp are possible for Q1 2013 in Kenya, due to the oversupply and resulting drop in EPC prices worldwide. possible PV investors are clients to KPLC in the tariff groups DC (with more than 1500 kWh/consumption), SC and CI1. They are willing to invest. The potential is 210 MWp and above. GoK should balance upfront costs with benefits such as saving the hydro reserves, bringing the national energy mix closer to the efficient frontier of optimal risk-return combinations, creating national employment, abating greenhouse gases, and improving the LV grid, in particular in cities and at the end of weak lines.

2,500 300,000

Technical and Economical Assessment of Net-Metering in Kenya

II.

Recommendations

This report is about the potential for net metering to help support the electric grid and to help grow the solar electric (PV) market in Kenya. Net metering is an incentive policy practice which allows owners of small electric renewable energy systems (i.e. solar, wind, biogas, etc) to feed excess power produced by their energy systems into the grid. Consumers, who purchase energy systems themselves, receive credit from the utility at a retail rate for the portion of electricity they feed on to the grid. At the end of a billing period, they are able to deduct this retail credit from their overall bill. As a policy practice, net metering has been widely used in the US, Canada, Europe and Australia to provide a low cost and unbureaucratic incentive for consumers who desire solar PV systems. A net metering policy would be a low cost and low risk way to introduce grid connected solar PV (as well as small scale wind and biogas) into Kenya. It would allow residential, commercial and industrial consumers to invest in small renewable energy systems on a competitive, free-market based approach that would be administered by parastatals such as the ERC and KPLC. Such a policy would allow Kenya to continue its leadership of East Africas commercial solar energy development. The team makes the following recommendations for the development of net-metering in Kenya: A. Policy aspects A1. PV is only financially competitive today (10/2011) under specific circumstances, due to the high costs of financing for both equity and debt capital, and due to the adverse development of the exchange rate. In addition, PV could contribute to greening the power sector, and to improved grid stability. With further price drops being a certainty, GoK should pave the way now for net metering to prepare the market within the very near future. A2. Currently PV is exempted from VAT (16%). We recommend maintaining the current situation for at least 2 years until a net metering market is established. A3. GoK could start with a 1000 roof-program, by installing a second meter on the PV plant and herewith monitoring the system performance to gain experiences. A4. Policy should encourage owners of suitable existing off-grid systems to connect their systems to the grid under net-metering, once the grid reaches their area and a net-metering policy is in place. B1. Allow all customer classes to do net metering B2. Allow all renewable energy sources to be tapped through net metering B3. Do not arbitrarily limit net metering as a percent of the utilitys peak demand.

B. General regulatory aspects

Technical and Economical Assessment of Net-Metering in Kenya

C. Economic aspects

C1. Allow KPLC an annual net-metering fee depending from the size of the PV system to cover the lost profits (i.e. annual payment to KPLC corresponding with the total amount of net-metered electricity) C2. Allow monthly carryover of excess electricity at the utilitys full retail rate but prevent annual payments of the utility to the consumer C3. Set fair fees that are proportional to a projects size. D1. In order to ensure quality and safety of PV systems connected to the grid under net-metering, a qualified and competent entity should be in charge of approving and inspecting all installed systems through a standardized, transparent and efficient procedure. Preferably, this entity could be KPLC, under supervision of ERC. D2. Ensure that policies are transparent, uniform, detailed and public; and that regulation sets out the required minimum without over-regulating the market D3. The approval process for net-metering projects should also be fully transparent and fully standardized D4. Applications should be processed quickly, decisions should occur within a few days D5. Customer / investor documentation must be comprehensive and accessible. It is therefore recommended that the documentation for net-metering projects is fully standardized D6. Categorize applications by degree of complexity and adopt plug-andplay rules for residential- scale systems and expedited procedures for larger systems. D7. A problem reported in a US-study1 was the billing systems and a lack of proper documentation from the customer. The billing needs to accommodate net-metered customers and adjustments may be required. D8. Ideal procedure to commission a PV plant on net metering (equivalent to German procedure) Up to a certain rated power no permission or LV grid affirmation from KPLC is required Either KPLC or a technician with a certificate from KPLC may exclusively commission the plant The investor / tariff consumer has to prepare a proper documented commissioning protocol provided by ERC KPLC will consider this consumer as net metering consumer once the ERC commissioning protocol is given

D. Procedural aspects

[14]

Technical and Economical Assessment of Net-Metering in Kenya

E.

Technical aspects

E1. Kenya could adapt to standards recently set up in Germany. The report doesnt want to copy solutions; however other European countries are now harmonizing their PV-guidelines according to the German standards described here. E2. We suggest adding a section to the Kenyan Grid Code for inverter based generators, or generators connected to the LV grid. This would clarify the requirements for potential Independent Power Producers. E3. Modern inverters comply with the Kenyan Grid Code. These PV inverters - meeting the 2012 German requirements - can perform active filtering by injecting compensating current harmonics, reactive power control, voltage level control, phase symmetry control, reduce losses at the transmission and the distribution grid, support the grid during disturbances (Fault-Ride-Through Capability), balance of nonsymmetric loads. We recommend allowing only PV inverters to the Kenyan grid fulfilling all these requirements. E4. In the short term, respectively for low PV capacities, PV can be directly used through net metering without any adverse impact on the power system. On mid-term basis settings for frequency bands and over frequency behaviour should be adapted to the general network settings such as 45 Hz for disconnection. E5. Prohibit requirements for extraneous devices, such as redundant disconnect switches, and do not require additional insurance. E6. Apply existing technical standards, tapping international experience2

F.

Capacity development aspects

F1. Key personnel responsible for distribution networks should be trained to be aware of grid supporting potential of the new inverters and to use it for the benefit in their specific grid situation. F2. A developing PV market requires strong available capacity for services. Therefore, capacity building of technicians on design and installation of grid-connected PV systems is strongly recommended. G1. In order to guarantee economic returns for investors, power generation as projected for the utility and minimal grid stability hazards, it is of utmost importance to proscribe high quality installation and service standards for the grid-connected PV systems.

G. Technical risk mitigation

It is worth noting that about 315,000 PV plants larger than 100 kWp will be upgraded In Germany in 2012 to the new technical requirements. In the vast majority of cases, the installer only has to update the software or change the parameter settings of the solar inverters. This means, that even later re-adjustment of technical standards does not automatically mean a replacement of expensive components of PV systems.

Technical and Economical Assessment of Net-Metering in Kenya

G2. High quality should also extend to comprehensive warranty, quality assurance and after-sale-service mechanisms. G3. The quality control of the installed systems should be ensured through a procedure as described above, under supervision of ERC G4. Consumer education should also be factored in, and undertaken by mandated bodies such as the sectoral associations, as an important instrument to achieve good quality in the installed systems and their operation.

Technical and Economical Assessment of Net-Metering in Kenya

III.

Methodology

The objective of this report is to provide quality technical and economical advisory on parameters and feasibility for grid connection of solar photovoltaic systems through net-metering in Kenya. In short, it is designed to answer the question: Is net metering technically, economically and socially feasible as an incentive policy in Kenya? The report is subdivided into an economical and a technical part. All required data has been collected in a fruitful cooperation of the author, GIZ staff and local stakeholders, including Ministry of Energy, Kenya Power (KPLC) and ERC. Data from the existing power plant structure and electric network as well as future extension plans were provided by KPLC and ERC mainly. While it is desirable to allow investment into renewable energy power generation on the grid, grid stability remains of paramount importance. Furthermore, the economic viability of the grid operations, as well as potential economic implications of investments under a net-metering regime has to be considered. The main questions for the introduction of grid-connected PV are thus:

Do many decentralized small scale PV installations interfere with the grid? Is the (low voltage) grid stability disturbed by the fluctuating generation? Can PV actively contribute to system services and security? Does net metering avoid costs at customer level? What is the impact of net metering on KPLC revenues?

This report aims at utilizing data generated by the aforementioned pilot projects, data obtained from relevant sources in Kenya (e.g. the grid operator), as well as data from other (international sources) to shed light on these issues. In doing so, the assignment is feeding directly into a larger assignment by GoK, with funding support from the World Bank, on a review of regulatory options for Small Scale Power Generation from Renewable Energy Sources. The targeted activities and outcomes of the analysis and assessment included: Data access and collection Discussion with partners from MoE, ERC and KPLC Technical and economical data analysis Provide report and presentation materials Recommendations for intervention

Methodological considerations for the economic analysis comprise: To determine the advisability of a large scale grid connected PV market in Kenya, discounted cash-flows have to be calculated and analyzed. For the (relatively straightforward but somewhat extensive) PV cash-flow modelling (as done regularly for all

Technical and Economical Assessment of Net-Metering in Kenya

types of project finance), three essential elements have to be determined: (i) discount factor, (ii) cost and (iii) benefits. For task iii we chose to largely mirror the calculation performed regularly by the dispatcher, in order to determine the operational benefits of PV. They key to estimating the operational benefits of PV-plants integrated into the Kenyan power system/grid is the optimal, least-cost multi-period commitment and dispatch of available plants both in the absence and the presence of PV-loads, subject to load balances and other operational constraints (spinning reserves, minimum maximum loads, volume of dischargeable water). From this perspective, the PV-benefits to the system amount to avoided costs defined as the difference between system minimum [operational] costs without PV and system minimum [operational] costs in the presence of PV-loads. Accordingly, the specific PV benefits (KES/MWh) are given by the ratio of PV-benefits (KES) to PV-loads (MW) injected. In the LCPDP 2011-2031, the optimum dispatch schedule yielding a cost minimum is calculated through the Wien Automatic Simulation Planning Package (WASP). This study could not use this or other software models such as MATHEMATICA (it is a simplexbased de-commitment algorithm) due to time and budget restrictions. To simplify this here we have used the merit order ranking of the existing power plants and defined the incremental fuel costs as the average of the three most expensive power plants.

The report is based on the experiences in the worlds largest PV-market - Germany. It gives recommendations based on the 25 year development of PV in Germany and Europe. Given that net-metering has also been successfully implemented in many other countries around the world, this report includes a chapter on lessons learned from other countries with experience in netmetering, or where net-metering regulation is currently being formulated. While it is evident, that solutions have to be tailored to the Kenyan context, it is still possible to derive lessons and conclusions from abroad. The author firmly believes that the solutions for the German and European context are also suitable for Kenya. The report uses models that the author with his team has developed over 20 years of studying and implementing solar PV projects in European electricity markets.

Technical and Economical Assessment of Net-Metering in Kenya

Part I: Analysis of the Economics of Solar PV in Kenya 1. Background and Context

This chapter looks at the context of solar energy in Kenya, existing electricity tariff and policy structures, the overall concept of net metering (and how it relates to Feed In Tariff incentives), and how net metering programs can positively affect solar electricity prices. Solar electricity is not new to Kenya. The Kenyan power sector is characterized by a rapidly growing demand, large geographical imbalances in power demand and supply, and accelerating private sector involvement. The Government is investing in exploration of geothermal energy. In addition, substantial potential exists for exploiting domestic potential of other renewable energy sources, not least solar power. Interest in solar energy is rapidly increasing. In fact, Kenya and Germany are alike in that they were among the first countries in the world to install hundreds of thousands of solar electric systems for households. The primary difference is that in Kenya, all of the PV systems were off-grid solar home systems (averaging under 50 Wp) while in Germany virtually all of the installed systems were grid-connected (averaging over 4 kWp). Kenya has an active market for solar equipment; however, there has been no systematic effort on the part of the industry or Government to bring solar on to the grid --- which is where over 95% of the global market for PV is today. The experiences of two pilot net-metering systems in Mombasa and Nairobi are explored in this chapter. Thus far, the systems have performed well and there have been no major problems in their interactions with the KPLC grid. Through the detailed study of electricity tariff categories and rate structures, this chapter provides a basis for establishing whether indeed net metering is feasible in Kenya and if it is which consumer categories hold the most promise for net-metering policy arrangements. Finally, this chapter introduces the topic of net metering and the relevant opportunities and difficulties that might arise from its introduction. It explores the difference between net metering and feed in tariff as policy tools and it examines how these policy tools can actively grow solar markets.

Technical and Economical Assessment of Net-Metering in Kenya

a.
i.

The Kenyan context


The Solar Resource

Kenya is located near the equator and has a great potential for solar power. The average radiation is 4-6 kWh/m2/day. However, despite its relatively high solar resources, there are significant local and seasonal variations in solar energy distribution. For example, Nairobi experiences high seasonal fluctuations, with periods of relatively high radiation between December and February and low periods between June and September. On the other hand, Kisumu has a very good solar radiation throughout the year. It is important that solar consumers are aware of solar resources in their area and on the long-term implications of these resources on their purchase. In this report, we have chosen to model Nairobi and Kisumu as two sites representing the conditions in most of the country.

Location Nairobi Mombasa Kisumu

Longitude / Latitude 36.9E / -1.3N 39.6E / -4.0N 34.8E / -0.1N

kWh/m*d 5,01 5,48 6,48

Figure 1:

Global Horizontal Solar Radiation in Kenya3

Source: RETScreen 4, graph from SWERA

Technical and Economical Assessment of Net-Metering in Kenya

ii.

Status of the Kenyan Solar Market

The population is currently 41 Million with an annual growth of 2.5%. The electrification rate ranges between 15-20 % at national level, with a rural electrification rate of only 5-10%. The electricity demand is growing by 5-8% p.a. Off-grid commercial and institutional PV markets play an important role in pre-electrification of areas not reached by the Kenya power grid. PV demand created in this market has created a base market of several MW PV sales per year. However, the potential for PV in grid-connect applications may be much greater than off-grid applications and it offers a dynamic new stage of growth for the solar industry. However, these relatively new markets for larger, commercial on- or off-grid applications are yet to begin to develop. Solar PV Technology Estimated installed capacity >6-8MWp Estimated kWp installed / year (2008) >700kW Degree of Competition Extremely competitive, many players Dominated by wholesaler / agent partnerships Emergent Emergent Emergent

Off-grid HH electrification & small scale commercial Off-grid systems (incl. institutional and pumping) Telecom Tourism On-grid

>1.5MWp

>250kW

>300kWp >50kWp 560 kWp

>100kWp N/A N/A

Table 1: Kenya Solar Market: > 1.2 MWp/a [16] The current market structure is characterized by the following elements: Technicians play a key role in the market, some operating as re-sellers and as sales agents. Established importers (8) represent international PV companies, sell through distributors. Opportunistic importers import PV modules & distribute to retailers of electric goods and shops. Sales agents target geographic and niche markets that they develop on behalf of the wholesaler. High-end niche companies operate in NGO, UN and increasingly tourism and telecommunication markets [16]. While the market for solar home systems mostly comprises over-the-counter trade, the market segment for electrification of social institutions is driven almost exclusively by public procurement.

Technical and Economical Assessment of Net-Metering in Kenya

Recently, through MoE, REA and KPLC, there has been a trend in the face of growing concerns about fuel costs of hybridization of off-grid diesel-based power generation with solar energy Key challenges for the Kenyan PV market include a lack of technical capacity on the planning and installation level to move beyond the traditional market segments, quality issues in terms of products and services in the market, and a relatively weak (however improving) regulatory framework with a view to both quality standards as well as incentives and regulations for private sector investment in solar energy. Specifically with regards to the regulatory framework, it is worth noting that the Government has zero-rated import duty and removed Value Added Tax (VAT) on renewable energy, equipment and accessories, including solar energy. Furthermore, a feed-in tariff for solar energy exists, albeit at a relatively low level. Other than that, no specific incentives or regulatory instruments tailored towards facilitating investment in solar energy are in place.

iii.

Existing grid-connected PV plants

In the course of 2011, two lighthouse projects have been installed by private developers: A. United Nations Environment Programme (UNEP) 515 kW UNEPs rooftop solar plant (515 kWp) was designed to supply power mainly within the UN compound in Nairobi. All the electricity produced by the system is absorbed by the large load of the UN agencies. However, during weekends and on public holidays, there is a potential for feeding excess electricity into the national grid.

Key facts: - 515 kWp installed - Grid connection, but no feeding-in - Commercial procurement by UNEP - Realized by: Energiebau Solarstromsysteme GmbH - Components: o Modules: Schott Solar, Kaneka o Inverters: SMA Solar Systems

Technical and Economical Assessment of Net-Metering in Kenya

B. SOS Childrens Village Mombasa 60 kWp The investment at SOS Childrens village Nairobi aimed at both Greening the SOS Childrens Village as well as at reducing the power bill. The project was designed from the onset in anticipation of a net-metering or similar regime. The system produces a significant amount of excess power during day time peak production. Key facts: - 60 kWp system - Grid connection, feeding-in at peak production - Commercial procurement by SOS CV - Realized by: Asantys Systems GmbH, African Solar Designs (ASD) Ltd. - Components: o Modules: Centrosolar AG, o Inverters SMA Solar Systems

Figure 2:

Electricity production and real production for the 60 kWp system for September 2011 (www.sma.de)

Both systems were installed in 2011. It is therefore not possible to derive strong statements about plant performance, e.g. by comparing actual performance against projected / rated performance. However, the plants have demonstrated so far that from technical point of view, grid connection is absolutely feasible, and that no harmful effects arise. The investors in the two pilot projects, alongside other sector players, have requested the Ministry of Energy and ERC to consider the net-metering option. Against the background of these requests, MoE and ERC in turn requested GIZ to provide technical inputs, which materialized in the shape of this study.

Technical and Economical Assessment of Net-Metering in Kenya

iv.

The Kenyan Electricity Market - relevant customer tariff categories

The tariffs for the electricity supply by Kenya Power and Lighting Company Limited (KPLC) are set by the Energy Regulatory Commission (ERC). The current tariffs have been set in July 2008 and are still valid. Furthermore, ERC regulates taxes, third party levies and other cost items which are charged by KPLC to the consumers. This also includes adjustment formulae which are use to adapt the tariffs to fuel costs and other economic developments. Under net-metering, the effective tariff for investors is the retail tariff rate, since power purchased from the utility is substituted with self-generated electricity. Therefore, this sub-chapter analyses the power tariff structure in Kenya and identifies relevant customer categories.

A. Identification of relevant customer categories The general structure of the electricity tariff is shown in the following table B [18; p. 3 ff]
Tariff DC Type of Customer Domestic Consumers Supply Voltage (V) 240 or 415 Consumption (kWh/month) 0 50 51 1,500 Over 1,500 SC Small Commercial CI1 CI2 CI3 CI4 CI5 IT Interruptible off-peak supplies SL Street Lighting 240 120.00 7.50 Commercial/ Industrial 415, 3 phase 11,000 33,000 / 40,000 66,000 132,000 240 or 415 Up to 15,000 4,200 11,000 240 4.25 4.10 4.85 170 170 Over 15,000 800 2,500 2,900 5.75 4.73 4.49 600 400 200 240 or 415 Up to 15,000 120.00 Fixed Charge (KES/month) 120.00 Energy Charge (KES/kWh) 2.00 8.10 18.57 8.96 Demand Charge (KES/ kVA/ month) -

Table 2: Current tariff structure The benefits of net metering are the avoided incremental energy costs which are related to the consumption of units (kWh). Consequently, the fixed charge, households and small business customers have to pay are not relevant to net metering or energy saving.

Technical and Economical Assessment of Net-Metering in Kenya

The higher the energy charge is, the more attractive is net-metering might be. Tariffs for customers with a very small or a very high consumption (metered by the company at higher voltage) are not relevant for net-metering due to lower energy charges. For the DC tariff, low consumption of 0-50 units per month (2 KES/kWh) or 51-1500 per month (8.1 KES/kWh will not lead to a competitive situation for PV applications. Similarly will the tariffs CI2-5, due to the very low energy charges, not result in economic viability for PV for the foreseeable future. Consequently, in the scenarios presented in chapter 6 this consumer group is not considered. Thus, the following groups are of particular interest, and in the following termed as relevant for the purposes of this analysis: Domestic (DC) for >1500 kWh / month Small Commercial Consumers(SC) Commercial and Industrial Consumers (CI) for supply voltage of 415 V (CI1)

Since the DC tariff group is structured in such a way that the level of consumption greatly impacts on the actual energy charge payment, it has to be analyzed in greater details, using two examples:
DC customer X Electricity consumption per year in kWh Electricity consumption per month in kWh PV-production for a 5 kWp plant per year in kWh Resulting demand customer in kWh Avoided incremental cost (KES/kWh) 26,000 2,142 6,855 13,145 11,15 DC customer Y 100000 8,334 6,855 93,145 16,66

Table 3: Examples for impact of level of consumption on energy charge payment Customer X could, for example, represent a household with air-conditioning. Customer Y would be an extreme case, assuming a very high consumption for a large estate with security lighting, air conditioning and many other electricity appliances. For the following calculations (see chapter 6) an average of 11.15 KES/kWh as the more conservative value was chosen.

Technical and Economical Assessment of Net-Metering in Kenya

B. Analysis of charges and levies In addition to the tariffs set by ERC, all customers have to pay additional taxes and third party levies: Fuel Cost Charge The Fuel Cost Charge reflects the fuel costs for the thermal power plants. It is calculated every month and charged to the customers as an add-on per kWh.4 The Fuel Cost Charge is mainly dependent on following factors: Fraction of the electricity which is produced by thermal power plants. This fraction is mostly dependent on the possibility to use the existing hydro power plants. During drought years there is less generation from hydro power (which has lower variable costs) and more generation from the more expensive thermal power plants and hence the fuel cost charge is higher. Efficiency factor of the thermal power plants in use. Price for fuel for the thermal power plants, i.e. oil and gas price, at a later stage once coal fired power stations are operational this will also include the coal price

Foreign Exchange Rate Fluctuation Adjustment5

A number of factors influencing the cost of power generation are affected by fluctuation in foreign exchange rates, for example loan repayments for some electricity projects which have been financed and need to be paid back by foreign currency. End-user electricity prices are therefore liable to an adjustment factor for foreign exchange rate fluctuation, which reflects the exchange rate of hard currencies against the Kenya Shilling. At the end of every six month period starting from 1st July, 2008, electricity prices may be subject to an inflation adjustment. Consumers have to pay other taxes, levies or duties including: - VAT at 12% charged to the fixed charge, the demand charge, the forex adjustment and to the fuel cost charge. - Rural Electrification Programme (REP) levy at 5% of revenue from Unit sales. - Energy Regulatory Commission (ERC) levy at 3 KES cents/kWh.

Inflation Adjustment Taxes and Levies

Table 4: Electricity tariff charges and levies

The method is describe in detail in the Energy Act No.12 of 2006, page 5 ff

Technical and Economical Assessment of Net-Metering in Kenya

C. Actual end-user prices for relevant tariff groups

The following table 5 shows the relevant (as described above) tariffs and all applicable taxes and levies:
Case 1 Case 2 Case 3

Domestic (DC) > Small Commercial and 1500 kWh/month Commercial (SC) Industrial Customers (CI1) KES/kWh Basic consumption tariff Fuel cost adjustment
5

KES/kWh 8,96 7,30 1,23 0,13 17,62 19,73 0,03 0,45 20,21

KES/kWh 5,75 7,30 1,23 0,13 14,41 16,14 0,03 0,29 16,46

11,15 7,30 1,23 0,13 19,81 22,19 0,03 0,56 22,78

Forex: Foreign exchange adjustments Inflation adjustment Total without ERC and REP Total without ERC and REP incl. VAT (ERC) levy REP levy Total

Table 5: Relevant tariff groups and actual end-user prices For the fuel cost adjustment, this report assumes mean values over 6 months (April September) in 2011 below the values at the time of the compilation of this report, but higher than the minimum observed after good hydrological conditions. While it is the declared objective of the government to reduce the electricity costs, consultation with stakeholders during the compilation of this report revealed that an actual decrease of costs in current prices is not likely. The Least Cost Power Development Plant 2011-2031 states that comparing the future average energy generation cost (11.8USc/kWh in medium scenario) to current average generation cost (9.3USc/kWh) shows that a 27% increase in the generation cost should be anticipated. However the current generation cost is low due to the fact most of the costs had been paid for by the government by the time the current generation tariff to KenGen was determined, therefore the current average generation tariff doesnt represent the actual cost

[23];current data see http://www.kplc.co.ke/index.php?id=104

Technical and Economical Assessment of Net-Metering in Kenya

of generation. The increase can also be attributed to the high reserve margin of 25% adopted by the expansion plan, which should ensure an adequate quality of supply in the future years, provided that the planned power plants are implemented in due time.6 Should there be a delay in power plant implementation, it is likely that the resulting shortfall will continue to be bridged by relatively expensive thermal power generation. We therefore believe that the assumptions of end-user electricity prices as well as the assumed annual tariff increase presented below are realistic.

b.

What is Net Metering

Net-metering, in essence, allows small scale renewable energy power producers to bank or store their electricity in times of over-production (e.g. for solar energy during peak production in the day) in the national grid, and to balance out their grid consumption with this banked or stored electricity during other times (e.g. during night, morning and evening hours).

Load / Production
Excess solar PV Production (stored in the grid)

Grid consumption (of stored solar power 00:00 08:00

Direct solar PV consumption

Grid consumption (of stored solar power) 20:00 24:00

12:00

Time

Figure 3: Principle of PV electricity production and daily demand

Least Cost Power Development Plan 2011-2031, p. 142

Technical and Economical Assessment of Net-Metering in Kenya

In theory, such a system is associated with a range of advantages: Generation of additional power in the national grid, without the need for investment by the utilities or conventional IPPs Promotion of small scale investments, value addition and market development No direct payment by the grid operator (as opposed to a FiT) Consumer savings on power bills Of course there is also a number of open questions, e.g. with regards to Technical feasibility of grid connection and impact on grid stability Revenue loss for the grid operator and potential compensation mechanisms Other direct and indirect benefits for the grid operator A simplified example for net-metering involves a single, 1960s-standard electro-mechanical meter. Now imagine that a residential customer, Charles McSolar, added a rooftop photovoltaic (PV) system (also known as a solar-electric system) to his home, on his side of this meter. Charles wakes up early for his job; on most days, he is out of the house before sunrise. In these dark morning hours, Charles makes his coffee and breakfast while watching the morning news on TV. The electric meter spins forward as Charles is consuming electricity from the grid. Determined not to waste electricity, Charles shuts off all of his appliances as he heads off to work. Charless solar panels now start churning out electricity as the sun riseselectricity Charles sends back to the overstressed grid. His meter now spins in reverse. When Charles returns at night to cook dinner and relax in front of the TV, the meter spins forward again as he consumes more electricity than his system generates. The result? Charless bill will show only his net consumption of electricity from the grid. Whether it is a sunny month or a month in which Charless electricity use is low, any excess electricity his system generates is rolled over to his next bill, just as he might rollover excess cell phone minutes1

Technical and Economical Assessment of Net-Metering in Kenya

c.

Net Metering or Feed-in-Tariffs

The success story of grid connected PV is largely based on Feed-in-Tariffs (FiT). More than 20 countries have opted towards that option. Net-metering is a different regulatory instrument, which will open up a different market segment with different project types and regulatory requirements. Even before FiTs were widely introduced, net-metering was actively practiced by PV installers in many countries including Germany. Net-metering continues to be a driver of emergent PV industries where Governments do not support consumer FiTs (i.e. in many US states). In the following, both instruments are briefly characterized and pros and cons are presented.
Feed-in tariff FIT Key characteristics (best practice) Key elements: - Fixed-price system, i.e. the producer tariff is specified in a legally binding document - Tariff specified over a long timeframe, usually 15-20 years - The tariff should be high enough to deliver return on investment typical to the national market but not too high to devastate local resources, attract free riders, or impose unfair burdens on customers - The tariffs (i.e. the difference costs, which are usually positive due to the higher renewable energy power generation costs) should not come from the national budget but come as a surcharge from all electricity consumers. - Standardized and simplified procedure for investors to access the FiT - Regular review of the FiT levels - May include annual legally fixed decrease of the FIT-levels, depending on the technology learning curve Optional / best practice elements: - Fixed tariff contains an inflation factor (in case of countries with general inflation rates above 2% p.a.) Strengths - Strong security of investment, both for project developers as well as for financiers - Everyone can invest, including the utilities themselves - Can be tailored and refined in order to channel investment into desired subsectors and project types Very easy to set-up and implement Minimal administrative effort for the utility Can also tap the market segments for power generation below the project sizes suitable to the FiT, and thereby leverage otherwise wasted natural / domestic resources No actual payments by the utility Net metering Key elements - Flexible producer price, i.e. the electricity end-user tariff - No actual payment of grid operator to the investor investors collect their revenue through substituting power purchase from the utility with self-generated power - No difference cost apply, thus no need to finance from end-users or taxpayers - Commissioning procedure is very similar to that of a FiT-project (e.g. in terms of grid access / connection)

Technical and Economical Assessment of Net-Metering in Kenya

and little risk of deceptive practices. Weaknesses - Perception of FiT as a subsidy, even if it designed as a surcharge to all consumers - Extra metering is required, which should be registered by remote sensing monthly (otherwise there must be monthly downpayments and annual control) - Relatively complex regulatory instrument, requiring close management in order to effectively leverage investment while avoiding market distortions Not fair to all consumer classes higher incentive and economic attractiveness for consumers with higher tariffs Does not provide very strong security of investment due to the (at least theoretical) possibility of fluctuating end-user tariffs

Table 6: Characteristics, strengths and weaknesses of net-metering versus Feed-in Tariffs FIT

d.

Solar PV system price development

PV is the renewable technology with the most dynamic development in the last years. The mass production of its key component the module is the driving force. The module costs are causing up to 70% of the total system costs in large green-field installations, on roof-tops the share differs depending from size and system design7. It is strongly advised for any study to update costs of PV and related prices frequently. PV prices have to be updated very recently as the costs are decreasing rapidly. 2011 is a year of tremendous price decreases in the 2nd half. The following figure shows that system prices in Germany have halved over the last 5 years. The German market accounts for approx. 40% of the worlds grid-connected market. Moreover, Germany is a well established competitive market with well established legal boundary conditions and a dense network of craftsmen, installers, wholesalers and manufacturers. Therefore, prices for grid connected plan are lower than in most other PV markets in the world.

Historically, PV prices in Kenya have been much higher than European prices because they are off-grid and include battery storage. The prices shown above are for grid-connected PV systems and do not include battery storage at all. It is important to note that PV prices have been dropping dramatically, while battery prices have remained stable.

Technical and Economical Assessment of Net-Metering in Kenya

Figure 4: PV system price decrease in Germany8 For Kenya pricing and investment cost information have been verified with the solar companies who are collaborating with GIZ on this issue. The following table shows a comparison of Germany and Kenya.
PV size in kWp DE: spec. price in /kWp Spec. price in KES/kWp Spec. price in Ken incl. VAT
10 9

5 2.450 2.700 3.132

50 2.300 2.530 2.935

500 2.150 2.100 2.436

Table 7: Prices for PV in Germany and Kenya in 10/2011 The continuous increase of manufacturing capacities for wafers, cells, and modules will continue the pressure on the worldwide market. PV remains still a buyer and not a seller market.

[25] This price for a full installed turnkey system reflects the authors own and direct experience in project development. 10 Same as before, however including VAT.
9

Technical and Economical Assessment of Net-Metering in Kenya

Figure 5: Learning Curve for PV and future cost development projection11 Note that the 2011-2012Q2 price developments are NOT learning curve effects but a market adjustment due to the recent burst of the EU FIT bubble. Knowing this (and the actual production costs of PV manufacturers) helps to pick the right time to start net metering in Kenya!12 However, as a project developer with 12 operational solar parks in Germany, the author denies the argument often used to wait until a certain cost threshold of cost is achieved. A lesson learned is that long-term learning curves do not reflect local prices at any time. The author decides any investment based on current prices and market conditions.

11 12

Roland Berger: Adolescence of an Industry (INSERT PROPER SOURCE) [24]

Technical and Economical Assessment of Net-Metering in Kenya

2.

Economic evaluation

The Kenyan Government is focused on increasing energy access to larger segments of the population. Because of relatively low incomes, increased access requires that all introduced energy systems are economically viable and do not add a burden to electricity ratepayers, who already are forced to pay high prices for electricity. As such, new technology investments, including solar, must in the long term reduce the burden on the rate payer. Thus cost is the major issue in introduction of electricity generation technologies. This chapter analyses the economic viability of net metered PV systems for three categories of electricity consumers and in two different solar regimes (Nairobi and Kisumu). It examines investment in PV systems from the consumer perspective --- identifying lifetime cost issues that are important to commercial and individual consumers. The chapter also examines the implications of wide-spread net metering on KPLC, and whether net-metering would impact on KPLC financial performance. It also explores potential fee structures that KPLC might use to cover the extra costs incurred by a net metering program. In summary, the analysis finds that, with current trends, net metering will be economically attractive by 2014, especially in sunnier parts of the country. (The recent fluctuations in the Kenya shilling against the Euro could make net metering profitable even sooner). The analysis also finds that, with the foreseeable PV market of up to 100 MWp, the cash flow implications for KPLC are not significant, and that there are likely to be overall economic benefits, including carbon trading and reduction of fuel use by generators, which could lead to financial gains by the company.

a.

Introduction

PV power plants are in essence front-loaded investments with no fuel cost and therefore insignificant O&M costs. To determine the advisability of a scale PV plant in Kenya, discounted cash flows have to be calculated and analyzed. For the (relatively straightforward but somewhat extensive) PV cash flow modelling (as done regularly for all types of project finance), three essential elements have to be determined: (i) discount factor, (ii) cost and (iii) benefits. For task i and ii above, the teams experience is combined with several standard methods and software. To achieve realistic modelling, the key is to choose parameters that fit the Kenyan case well. For task iii the determination of PV benefits a multitude of publications exists which provide murky calculations and questionable quantifications. We have therefore chosen a different route, mirroring largely the calculation performed regularly by the dispatcher, in order to determine the operational benefits of PV. Therefore, the levelised costs of electricity (LCOE) of solar PV are

Technical and Economical Assessment of Net-Metering in Kenya

compared to the most expensive power plants in Kenya according to KPLCs merit-order ranking. The formula below ilustrates how to calculate the LCOE:

I0 At i Mel n t

initial Investment total annual costs in the year t real interest rate in % electricity produced in the year t years of lifetime current year

In many reports the Annuity Method and the Net Present Value (NPV) are used for economic evaluation. In case of feasibility studies for a single project cash-flow profiles are used, i.e. the Internal Rate of Return IRR either expressed as Equity Internal Rate of Return (EIRR) or as Project Internal Rate of Return (PIRR). In addition, the Cost Benefit Ratio over the project lifetime can be used to assess the profitability of an investment. It is expressed as

Levelised revenues of the PV plant during the life time of the PV plant (The annuity cost of the PV investment + the levelised annual costs over the lifetime)

Any calculation should consider possible failures in the parameter settings. Consequently a sensitivity analysis spotlights the relevant and the less important parameters or in other words it advises the author to focus on the most important input parameters. The following figure shows the impact of a deviation of one and each simulation only one - input parameter and the resulting deviation of the outcome, here the specific cost (in Euro/kWh) of a PV plant. One example: a decrease of the yield (yellow line by 20% would result into a cost increase from 0.33(as reference case) to 0.42 /kWh. This sensitivity analysis is carried out for the input initial investment, lifetime, yield, O&M cost and weighted average cost of capital. The stronger the deviation is the stronger is the influence of this parameter. For PV the case is clear: Assessment of the electricity yield is the determining factor for the profitability, with the assumed investment costs as second.

Technical and Economical Assessment of Net-Metering in Kenya

Figure 6: Sensitivity analysis of a small grid-connected PV plant Initial investment price/cost Lifetime Yield O&M costs (operation & maintenance) Weighted Average Cost of Capital

b.

Reference case and input data

For net-metering, the anticipated project types in a developed net-metering market will not comprise one or few large scale PV plants but thousands of dispersed plants, varying in scale, site, efficiency and technology. Therefore, we choose a reference case for each appropriate tariff group with various parameters (see the following table C and G)

i.

Reference case assumptions

The reference cases represent the most relevant electricity consumer groups and corresponding PV sizes. The table C (see chapter 4.1) describes them in detail, and breaks down the electricity costs as per regulation & KPLC billing method:

Technical and Economical Assessment of Net-Metering in Kenya

Case 1

Case 2

Case 3

Domestic (DC) > Small Commercial and 1500 kWh/month Commercial (SC) Industrial Customers (CI1) KES/kWh Basic consumption tariff Fuel cost adjustment Forex: Foreign exchange adjustments Inflation adjustment Total without ERC and REP Total without ERC and REP incl. VAT (ERC) levy REP levy Total 11,15 7,30 1,23 0,13 19,81 22,19 0,03 0,56 22,78 KES/kWh 8,96 7,30 1,23 0,13 17,62 19,73 0,03 0,45 20,21 KES/kWh 5,75 7,30 1,23 0,13 14,41 16,14 0,03 0,29 16,46

Table 8: Definition of the most relevant consumer cases for net metering,

ii.

PV generation cost assumptions

The costs for PV electricity generation depend on two categories of parameters: the technical assumptions, and the economic / financing assumptions: Technical assumptions

Under net-metering, PV system size and corresponding solar electricity generation - cannot be larger than the annual electricity consumption in each tariff class (as explained in chapter 4.3). Otherwise net payments at the annual bill from the customer / PV investor to KPLC would occur, or power would be fed into the grid without compensation. . Thus, we are calculating here three examples representing the three aforementioned, relevant customer categories: 5 kW for domestic > 1500 kWh / month, 50 kW for SC, 250 kW for CI1. The size of the PV systems reflects the expected area available on the roofs and the equity required.

Technical and Economical Assessment of Net-Metering in Kenya

PV system parameters Case 1 Domestic (DC) > 1500 kWh/month PV size in kWp Delivered kWh/kW and year resp. capacity factor Specific Investment costs in Euro/kW Maintenance costs (% of investment) Expected cost reduction rate for PV 2011-2020 per year 5 1371 15,7% 2698 2%

PV-system size Case 2 Small Commercial (SC) 50 1389 15,9% 2526 2% 10% / 15 % Case 3 Commercial and Industrial Customers (CI1) 250 1389 15,9% 2100 2%

Table 9: PV input data and possible variations We recommend allowance of monthly carryovers of excess electricity at the utilitys full retail rate, this requires a change in billing an administration structures (for more details see chapter 2). Of the three solar radiation examples presented in chapter 4.1.1, Nairobi represents a site with lower yields than many parts of Kenya - if net metering is profitable in Nairobi it is likely to be profitable in most other locations! For Kisumu the values would be 1750 kWh/kW year delivered for a 5 kWp plant resp.1774 kWh/kW year delivered for 50 / 250 kWp plant. This variation is due to the fact that the capacity factor reflecting electricity delivered differs. Small PV systems (<20 kW) have a lower overall efficiency. Therefore, the performance ratio (PR) of the system larger 50kWp will be at least 1% better. Costs for PV are related to Kenya with high-end components in particular for the modules and inverters. Lower quality modules are 10-15 % less expensive. However, unbranded products have less track record in fulfilling warranty commitments or in maintaining long-term output. From a project developers point of view with a project horizon also under net-metering of 20 years, quality and warranty reliability for products and services is crucial. Therefore all information given is related to quality components. Currently PV is exempted from VAT (16%). We refer to and recommend maintaining - the current situation. For operation and maintenance of PV systems we assume about 2% of investment as annual operation cost in Kenya, which is slightly higher than in the EU due to higher insurance costs. As explained in chapter 4.4 the rate of cost reduction for PV 2011-2020 is expected to be between 10-15% annually.

Technical and Economical Assessment of Net-Metering in Kenya

Economic / financial assumptions

The following assumptions were identified based on literature13 and stakeholder consultation:
Economic parameter Average life time PV-system interest rate equity for EIRR equity share interest rate debt debt share levelised interest rate for PIRR inflation rate maintenance cost Assumed annual power tariff increase Exchange rate (KES / EUR) 20 years 10% 50% 10% 50% 10,0% 5% 5% 133 120 15% Possible Scenarios

Table 10: Economic input data and possible variations The parameters outlined above require further elaboration: The interest rate on equity for EIRR is equivalent to PIRR for private consumers for the cases 2 and 3. For small systems, the private investor will compare the current costs of his electricity bill with the PV annuity costs. He will not take any future tariff increase into his consideration. Assuming a positive result for PV, he will invest if he has the money (willingness-to-pay).The commercial investor (class CI1) of a 250 kWp PV plant acts in a different way: he will decide between various investment options (e.g. solar plant or government bonds) and will decide according to the best EIRR. We assume his EIRR expectation will be 5% higher than the IRR for debt capital (Case 4b). Consequently, the PIRR increases from 10 to 12.5%. For the equity/ debt share, we have chosen a conservative value of 50% / 50%for project financing, meaning that the project here the PV investment is the only guarantee. The interest rate for debt are below the local market rates and assume that debt financing will have a foreign component, either through project development partnerships or through involvement of GoK or development partners with a view to promoting renewable energy. The inflation rate for maintenance costs is based on literature14.

13

[21][22]

Technical and Economical Assessment of Net-Metering in Kenya

Power tariff escalation rate: according to the LCPDP 2011-203115, current average costs on the Kenyan national grid are 9.3USc/kWh (p.142). Depending on the scenario a cost increase up to min 11.8 and max 15.6USc/kWh (p.141) in 2031 is anticipated. These values are expressed in 2011 prices with the assumption of 90$/bbl oil. This is a price increase of 27% or 68% respectively over a 20 year period. These increased costs will need to be reflected in the end-user prices, which will essentially lead to an increase of the basic tariffs. However, this is the optimal scenario assuming that all projects are realized as scheduled in the LCPDP. Should any delays materialize, or the oil price increase further than assumed, the real increase might be even higher. Assuming that the values above would materialize at a level of approx. 50% price increase over 20 years, this would be equivalent to an annual increase of 2%. In addition, inflation has to be considered. Inflation influences upcoming power projects, both in construction as well as in operating costs. The higher the share of generation capacity with high operating costs will be, the higher the influence of inflation. It is important to note that renewable energy projects, including solar, with their very low operating costs, are less affected by inflation. For the above prices, considering historic values for US$ inflation rate, it is therefore realistic to assume a 3% annual inflation rate. On this basis, the assumed annual power tariff increase is assumed here at 5% p.a.

PV components (modules, inverter) are imported and have to be paid in US$ or . Therefore the exchange is of outstanding importance to the economic evaluation. At the date of editing this report the exchange rate is at a critical level: 133 KES/. While it is difficult to forecast the development, we are using one alternative scenario of 120 KES/16. Any further improvement would improve PV competitiveness accordingly.

The following table summarizes all the values identified above, with 96 possible variations.
Variable 3 Tariff cases and PV sizes Equity Interest rate EIRR Exchange rate Site (PV production): Nairobi / Kisumu Expected degression of PV costs Expected increase of tariffs Value 1 DC > 1500, 5 kWp 10% 132 KES/ 1371 or 1750 10% 5% Value 2 SC, 50 kWp 10% 120 KES/ 1389 or 1774 15% 1389 or 1774 Value 3 CI1, 250 kWp 10% or 15%

14 15

[21] [26] 16 Economist Intelligence Unit

Technical and Economical Assessment of Net-Metering in Kenya

Table 11: Possible scenarios and input data variations In the following chapters 6.3 and 6.4 we will present results of the most relevant scenarios. Prepaid Metering: Prepaid meters are mainly used in the DC class for low consumption (< 1500 kWh/unit). The few meters, which might be also used by those DC consumers able to invest in PV, the metering must be exchanged to more advanced electronic ones. The estimated cost for the new meters should be below 3% of the total PV investment

c.

Consumer perspective: economic viability of PV power generation

A consumer willing to invest in PV will make his calculation based on the annuity cost of the PV investment plus the levelised annual costs over the lifetime. In our calculations the PV lifetime is limited to 20 years even though practical experiences in Germany show duration up to 30 years are possible. However, the existing FIT (for hydro and biomass) in Kenya as well the FIT in Germany for PV - is given for 20 years only. From the consumer / investor perspective, a longer lifetime is thus an add-on to the profit (as the annuity factor for 30 instead of 20 years is 9.5% lower). In a first step he compares the current tariff with this annuity cost. i. Investment today

Due to the aforementioned parameters (in particular the financing costs for equity and debt, as well as the exchange rate) grid-connected PV under net-metering is not cheaper for the consumer than the average tariff level throughout 2011. It is important to note that this statement does not consider any component of diesel power generation at the end-user level that could be substituted by solar PV, e.g. a diesel-based backup system. Many users may want to consider a solar-battery system as their primary backup. Such systems could be designed to supply both backup power, as well as substitute grid power under net-metering. However, this implies modifications to the plant design, which will have a price implication. While this may be a very interesting perspective for many investors, it has not been considered here due to the additional variables. The investment into PV for the systems assumed here is calculated on the basis of annuity costs. The consumer electricity bill (see table. C in chapter 4.1.4) includes basic consumption tariff + fuel costs + forex adjustments + inflation adjustment + ERC and REP levy and VAT. The parameters set out above for solar PV electricity costs as well as for the grid prices are summarized in the following table:

Technical and Economical Assessment of Net-Metering in Kenya

PV in KES/kWh Nairobi / (Kisumu), LCOE 1 EUR = 133 KES DC, 5 kWp SC, 50 kWp CI1, 250 kWp 38.6 (30.2) 35.6 (27.9) 33.6 (26.3) 1 EUR = 120 KES 34.8 (27.3) 32.1 (25.2) 30.3 (23.7)

Corresponding tariff class / electricity tariff, KES / KWh 22,78 20,21 16,46

Table 12: Current costs for PV Left side for Nairobi radiation conditions (Kisumu) versus average of recent electricity tariff (10/2011) However, the picture changes completely once future increases in tariffs are taken into consideration, i.e. if PV-annuity costs are compared with future tariffs. PV power plants are in essence front-loaded investments with no fuel cost and therefore almost insignificant O&M costs. Under net-metering, where the income is generated through the substitution of power consumption from the grid with own generation in a net-metered PV plant, the assumed increase of the electricity tariff determines the year of break-even. In terms of todays monetary values, an annual tariff increase can be expected (dotted lines in the following figures 12 a,b), assumed here as outlined above at 5% p.a. The following figures12a,b show the thee cases identified previously. The investment into PV (Solid lines: on the basis of LCOE for PV) compared with the current tariff (dotted lines) are shown.

Exchange rate 133 KES / EUR

Exchange rate 120 KES / EUR

Figure 7: Comparison of PV cost with increasing tariffs for Nairobi

Technical and Economical Assessment of Net-Metering in Kenya

Exchange rate 133 KES / EUR

Exchange rate 120 KES / EUR

Figure 8: Comparison of PV cost with increasing tariffs for Kisumu Dashed lines: current consumer tariffs with increase rate of 5% annually for all tariff groups Annuity costs of the related PV plant, dotted line: Case 1: domestic consumer (DC), >1500 kW/month, 5 kWp plant Case 2: Small Commercial (SC), 50 kWp plant, Case 3: Commercial/Industrial (CI), 250 kWp plant

Solid lines: Black: Red: Blue:

The break-even of the LCOE of an investment into PV undertaken today with current electricity prices (not the levelised tariffs during the lifetime of the PV system!) or grid parity at present prices will be reached within the next four years in Nairobi for the Small Consumers (black lines)respectively for three years in Kisumu. The better insolation conditions in Kisumu will improve the cost competitiveness by at least two years to the break-even. In conclusion, consumers are willing to pay for PV within the next 3-7 years on the basis of current prices for electricity from the grid. The break-even depends on the site (i.e. the radiation conditions) and on the consumer tariff development. ii. Investment based on future cost

From an investors point of view, it is however prudent not only to consider present prices, but also the development of future prices. As described in chapter 4.4, the costs of PV are continuously decreasing. At the same time, grid electricity prices can be expected to increase further. This improves the cost- competitiveness of solar PV. For a PV cash-flow modelling (as done regularly for all types of project finance) the levelised costs of PV as done before are compared with the levelised increase of consumer tariff. This

Technical and Economical Assessment of Net-Metering in Kenya

method of calculation expresses all future cost components, and allows to compare the future cost of energy from solar PV (including technology as well as financing costs, i.e. already including returns on investment) with future costs grid electricity. For solar PV electricity generation, the levelised costs thus include all the parameters listed in 6.1.2, projected over a lifetime of 20 years. For the grid electricity cost, they show the estimated cost of grid power with an annual escalation of 5%. As explained previously, the 5 % are an approximated value accounting for both inflation as well as increased cost of power generation as per LCPDP 2011-2031. Should the cost of grid electricity increase further than this value, the conditions for PV through net-metering are more favourable, and break-even is achieved earlier! Where the graphs for PV costs intersect with the graphs for grid cost / avoided cost electricity demand, the investment in PV under net-metering is commercially viable for the respective customer groups. The graphs thus show clearly when commercial break-even including all relevant costs i.e. including as well the profit margin of investors expressed in the discount rate on equity is reached.

Technical and Economical Assessment of Net-Metering in Kenya

133 KES / EUR

120 KES / EUR

Nairobi, DC > 1500 kWh / month, 5 kWp

Viable without net-metering-fee in 2012 Viable with net-metering-fee in 2013

Viable without net-metering-fee in 2011 Viable with net-metering-fee in 2012

Nairobi, SC > 3000 kWh / month, 50 kWp

Viable without net-metering-fee in 2012 Viable with net-metering-fee in 2013

Viable without net-metering-fee in 2011 Viable with net-metering-fee in 2012

Nairobi, CI1, 250 kWp

Viable without net-metering-fee in 2012 Viable without net-metering-fee, but with higher EIRR in 2013 Viable with higher EIRR and net-meteringfee in 2014

Viable without net-metering-fee in 2011 Viable without net-metering-fee, but with higher EIRR in 2012 Viable with higher EIRR and net-meteringfee in 2013

Technical and Economical Assessment of Net-Metering in Kenya

133 KES / EUR

120 KES / EUR

Kisumu, DC > 1500 kWh / month, 5 kWp

Viable ex-/including net-metering fee now

Viable ex-/including net-metering fee now

Kisumu, SC > 3000 kWh / month, 50 kWp

Viable (without net-metering-fee) now Viable with net-metering-fee in 2012

Viable ex-/including net-metering fee now

Kisumu, CI1, 250 kWp

Viable without net-metering-fee now Viable without net-metering-fee, but with higher EIRR in 2011 Viable with higher EIRR and net-meteringfee in 2012

Viable without net-metering-fee in now Viable without net-metering-fee, but with higher EIRR now Viable with higher EIRR and net-meteringfee in 2012

Technical and Economical Assessment of Net-Metering in Kenya

Figure 9: Comparison and analysis of LCOE for a) customer categories, b) sites/ irradiation regimes, c) exchange rates It is evident that the viability strongly depends on the solar radiation regime, which is much better in Kisumu than in Nairobi. It is equally clear that another crucial determining factor is the exchange rate, since a return (i.e. the avoided cost for electricity demand) in KES is compared with an investment in EUR. We have used exchange rates of 133 and 120 KES / EUR respectively. While it was not possible to include this value in the models, it is important to note that as of December 2011, the exchange rate has reached 113 KES / EUR again. It should therefore be kept in mind that any decrease below the levels considered in the models here directly and substantially improves economic competitiveness of solar PV under net-metering in Kenya! In addition, our assumptions of the rate of return expected by investors might not necessarily apply to all investors. Any investor with additional, non-commercial motives (e.g. CSR) for investment in PV which would effectively reduce the return expectations could invest immediately, once the regulatory instruments are in place. In conclusion, within 2 years, net-metering will become the cheapest solution based on LCOE comparison - for all the relevant consumer classes. In order to tap this potential, GoK should pave the way for net-metering today by putting in place the required regulatory framework.

d.

Economic implications at system level

This report argues that the adoption of net-metering and subsequent connection of dispersed solar PV systems to the grid may reduce overall system costs, and contribute to reducing power costs for the end-users accordingly. As defined in the PPA between KPLC and the IPP delivering power and energy, KPLC has to pay a capacity cost converted to energy at contractual load charge independent if energy and power is demanded. This capacity charge cannot be avoided through electricity produced under netmetering, since it is contractually guaranteed irrespective of actual power offtake. The avoided costs could thus be constructed as the average of the incremental cost of production of the most expensive power plants, plus other applicable costs. For this calculation, we have taken into consideration the one year average of the three most expensive fossil fuelled power plants according to the KPLC merit order situation. Due to confidential nature of this information, this report cannot reveal the calculation method in greater detail. We are therefore working with the assumption of incremental fuel costs of 15.78 KES / kWh in average for these three most expensive thermal power sources.

Technical and Economical Assessment of Net-Metering in Kenya

In addition, 1.12 kWh must be produced to deliver one kWh to a customer as losses on the LV level and the HV level must be considered17. Furthermore, other incremental costs incurred by KPLC apply. On this basis the total avoided KPLC costs can be calculated to 18.73 KES/kWh. Under net-metering, this power is generated by the investors / consumers themselves, and it thus does not have to be purchased by Kenya Power these costs are avoided.
Incremental Fuel costs Incremental KPLC costs avoided technical grid losses (LV & HV) Total avoided cost without taxes 15,78 0,68 12% 18,73

Table 13: Profit or losses by net-metering at system level The following table shows an example calculation of the annual avoided cost at system level, if the three most expensive plants in the power mix could be substituted with the load freed up by net-metering. We have based this example calculation on a total market penetration of 100 MWp installed capacity under net-metering, with most of the investment in the SC group.
Total Installation of MWp = 100 Share of consumer in each class investing into PV Share of total investment from different 18 customer-classes Installed PV-capacity MWp Electricity production in kWh/kWp *a Electricity production in MWh/a Avoided fuel costs in KES Avoided total costs at system level in KES Case 2 DC> 1500 1.0% 4.3% 4.3 1,389 5,989 94,506,420 112,164,968 Case 3 SC 3.0% 89.7% 89.7 1,389 124,672 1,967,324,160 2,334,968,971 Case 4 CI1 2.0% 6.0% 6.0 1,389 8,267 130,453,260 154,836,503 100 4,168 138,928 2,192,283,840 2,601,970.442 Total

Table 14: Avoided cost at system level in a mature PV market under net-metering

17 18

See [15] table 14 at p. 41 This is proportional to share of the respective customer category of the total electricity consumption

Technical and Economical Assessment of Net-Metering in Kenya

Note that the avoided fuel costs would directly translate into a cost reduction for the end-users through a reduced fuel cost charge. The future development of this result is mainly dependent on The price-development of fuel for the power plant. If the prices will go up, the benefits of the PV-Plants will rise accordingly; The fraction of electricity produced by fossil fuels. If the fraction is rising, the installation of PV-plants will be more beneficial It is important to consider that this calculation does not consider any potential other direct or indirect benefits from dispersed production of solar PV in the Kenyan grid, e.g. through improved grid stability (as a result of modern inverter application), reduced system losses, or other aggregate benefits. It also does not consider potential carbon credit revenues.

e.

Optional compensation through net-metering-fee a theoretical model

As any utility, Kenya Power (KPLC) will evaluate the perspective of net-metering based on the implications for its business. When consumers are investing into solar PV to substitute their grid power consumption through net-metering, thereby reducing their own power bill payable to KPLC, KPLC is losing turnover. The investment into new PV-plants will reduce the purchase of electricity of KPLC from KenGen or IPPs. The power fed-into the grid from the solar PV plants under net-metering, however, can obviously be sold to other customers or, in other words, the power not consumed by the investor in PV can be sold elsewhere. Under the assumption that the power made available through net-metering could be sold elsewhere, Kenya Power would not suffer losses. Nevertheless, this assumption might not materialize. Furthermore, it could be argued from the perspective of Kenya Power that the additional administration costs for registration and billing of the net metering PV systems need to be considered. Following this logic, Kenya Power could make a position towards introducing a net-metering fee to compensate for this loss. To assess net-metering fee, we are working with an average KPLC yield of 6.12 KES/kWh (figure provided by KPLC). From this value, system losses and incremental cost of KPLC (see table 15) have to be deducted. If the remainder would be covered through a net-metering fee, KPLCs overall position would not only be neutral, but rather positive since incremental costs plus the profit margin would be covered. On the basis of the data available, i.e. yield of 6.12 KES 0.68 KES incremental KPLC costs 12% system losses, such a net-metering fee could be determined at about 3.5 KES/kWh. For ease of calculation and implementation, this figure is independent from the consumer classes, and would be claimed by KPLC.

Technical and Economical Assessment of Net-Metering in Kenya

To keep all administrative actions as low as possible a separate metering system for the PV plant should not be required. With plant commissioning KPLC could calculate in the following way the expected yield of the PV plant and the net-metering-fee. This table should be extended to max 4 different insolation regions here given for Nairobi as the worst and Kisumu as the best case.
Site Nairobi PV size in kWp delivered kWh/kWp *year total kWh PV delivered KPLC in KES/kWh Annual "Net Metering" fee to KPLC in KES 5 1,371 6,855 3.5 23,992.5 50 1,389.28 69,464 3.5 243,124,0 Site Kisumu PV size in kWp delivered kWh/kWp *year total kWh PV delivered KPLC in KES/kWh Annual "Net Metering" fee to KPLC in KES 5 1,750 8,751 3.5 30,629.3 50 1,774 88,679 3.5 310,377.3 250 1,797 449,230 3.5 1,572,306.1 250 1,389.28 347,320 3.5 1,215,620,0

Table 15: Example how to calculate the surcharge / additional fee on the annual consumer bill If this net-metering-fee should be allowed to KPLC, we recommend to ERC to design it as a single down-payment put on the annual consumers bill. For consideration of the implications of this additional fee on the consumers investment decision, please compare the graphs in chapter 6.3. We have added this net-metering-fee on the current tariff of the customer CI1. It is evident that the break-even is only shifted by a few months this would not influence the consumers decision pros/cons PV considerably. However, it is important to consider that any such fee would effectively amount to a disincentive from the perspective of investors. It should therefore be considered carefully, whether the introduction of this construct is actually necessary and adding value. Furthermore, as an additional option to play a more direct role in the net-metering market, KPLC could act as a facilitator between the consumers / PV investors and financing institutions with regards to financing the PV systems. Under this approach, PV investors could pay back the PV systems through their power bill. A similar approach is being implemented by the utility in Tunisia for financing of solar water heaters. This would not only greatly reduce transaction costs and thus expedite PV market development under net-metering; it would also ease bundling of and monitoring of the individual PV installations and thus pave the way for tapping carbon revenues.

Technical and Economical Assessment of Net-Metering in Kenya

f.
-

Other economic implications


Lost revenue through statutory levies

Other economic implications refer to the statutory levies of GoK on the power bill, notably ERC and REP levy as well as taxes. Equivalent to the turnover of Kenya Power lost from net-metering, these revenues are lost for GoK. As indicated in the following table G there are losses for the ERC fee, the REP fee and the VAT in the range of 2-2.97 KES/kWh.
Case 1 VAT ERC levy REP levy Total per kWh 2,38 0,03 0,56 2,97 Case 2 2,11 0,03 0,45 2,59 Case 3 1.73 0,03 0,29 2,05

Table 16: Cost/benefit of Net Metering for the GoK GoK should balance these lost revenues with the following benefits of PV. Avoided costs for the consumers

The avoided cost calculation illustrated above translates into direct cost reductions for the power customers (assuming that thermal generation capacity would be displaced). Since the investment costs for the net-metering projects are borne by private investors, and since fuel costs are passed through to consumers as fuel cost charge, this would imply lower power bills for the end-users. Other operational benefits of PV

The key to estimating the operational benefits of PV-plants integrated into the Kenyan power system/grid is the optimal, least-cost multi-period commitment and dispatch of available plant both in the absence and the presence of PV-loads, subject to load balances and other operational constraints (spinning reserves, minimum maximum loads, and volume of dischargeable water). From this perspective, the PV-benefits to the system amount to avoided costs defined as the difference between system minimum [operational] costs without PV and system minimum [operational] costs in the presence of PV-loads. Accordingly, the specific PV benefits (KES/MWh) are given by the ratio of PV-benefits (KES) to PV-loads (MW) injected. In the present contest, the optimum dispatch schedule yielding a cost minimum is calculated for the LCDP 2011 through The Wien Automatic Simulation Planning Package (WASP). This study could not use this or other software models such as MATHEMATICA (a simplex-based decommitment algorithm). To simplify this here we have used the merit order ranking of the existing power plants and defined the incremental fuel costs as the average of the three most expensive power plants. The results have informed the above analysis of economic implications for KPLC.

Technical and Economical Assessment of Net-Metering in Kenya

Additional benefits (not yet quantified) are - Combination of PV with hydropower to increase availability of this least-cost resource - National energy mix closer to the efficient frontier of optimal risk-return combinations - PV will help reduce the economic and political cost of probable future blackouts - PV will stabilize the LV grid, especially in weak parts of it and in centres such as Nairobi - PV fed in a LV level will reduce overall system losses - PV can create national employment - PV will abate greenhouse gases

g.

A possible market development for grid connected PV

According to KPLC data the No. of consumers for the tariff groups are shown below. Based on this as well as on parameters analyzed above, a potential market development can be assessed:
Number of customers DC DC/IT Out of this DC with > 1500 SC CI1 Total 1,525,047 182,044 126,322 2,513 1,767,929

Table 17: Customers per relevant KPLC tariff groups

No. of consumers for the tariff groups DC DC/IT DC with > 1500 SC CI1 Total 1,525,047 182,044 126,322 2,513 310,879

Est. share of PV investors of total tariff group 0% 1% 3% 2% 5,660

average size of PV plant (kWp)

assumed market installed PV (kWp)

electricity produced in kWh/kWp (Nairobi)

total electricity produced in MWh

5 50 250

9,102 189,483 12,565 211,150

1,371 1,389 1,408 4,168

12,479 263,245 17,686 293,410

Technical and Economical Assessment of Net-Metering in Kenya

Table 18: Assessment of possible PV market development It is obvious that this market of 211 MWp will not be realised within one year. Germany as worldwide leading market has shown similar developments today 1million PV systems are installed by approx. 30 million households- this is a share of 3%.The diffusion of 1-5% of PV on the targeted tariff groups (DC with more than 1500units, SC and CI1) could be realised in a time frame of 2-5 years, mainly depending from the economic development and the administration burdens GoK will put on net metering. The PV plants in the SC tariff group are the backbone of this development. Even assuming a market penetration of 1% only for each class, this would result in a total installed capacity of 78.5 MWp, mainly installed in the cities such as Nairobi, Kisumu and/or Mombasa with more than 90% feeding into the LV grid. This report cannot consider regional impacts; however, we assume that feeding into the LV grid in Nairobi will improve the grid quality if the technical standards recommended in part II are fulfilled.

3.

International experiences in Net-metering

In 2010, PV installations reached the one million mark, thanks to small residential installations to a large extent. The rapid growth of the residential sector in Germany accounted for much of reaching this target (EPIA, 2011) but other countries have as well been successful in the implementation of decentralized generation connected to the low voltage grid. The aim of this chapter is to show case international experiences in small-scale grid-connected PV, in particular with a net-metering framework. The USA, Denmark and Mexico have already run net-metering for solar PV for several years. Brazil and Morocco have been chosen as cases of governments actively pursuing a net-metering framework. In the following, a brief overview of each of these countries is given, focusing on regulation and technical aspects.

a.

United States

Depending on the size of the solar installation, different policy strategies apply. For systems below 1 MW which is the large majority of PV installations in the USA (outside California) netmetering is applicable19.

19

[27]

Technical and Economical Assessment of Net-Metering in Kenya

Regulatory aspects

In the U.S.A., as part of the Energy Policy Act of 2005, state utility regulatory commissions must consider requiring the public electric utilities under their jurisdiction to make net metering available to their customers upon request20. Specific regulation therefore varies from state to state. Several bills are pending in Congress to institute a federal framework. Currently as of May 2010, 46 US states have a net-metering policy21. Regarding capacity limits, several states impose a subscriber limit as a percentage of the utilitys peak load (typically ranging from 1 to 5%). However, already twenty states plus Washington D.C. impose no limit on the number of subscribers using net metering. Technical aspects

As is the case in Europe, the USA has implemented specific regulation concerning the connection to the low voltage grid. The market access requirements for PV equipment are segmented in two main areas - safety and performance - that are integral to each other in the overall construction. The focus of the UL standards (UL, 2011) is in providing requirements for materials, construction and the evaluation of the potential electrical shock and fire safety hazards. The focus of the IEC requirements is in terms and symbols, testing, design qualification and type approval. UL certifies that PV equipment complies with the safety, environmental and other performance requirements of the appropriate standards. UL supports manufacturers with the compliance to both the UL and the IEC requirements utilizing a combined project or if needed, as individual evaluations. The only norms that contain information towards grid connection are UL 1741 and IEEE 1547 (Stadler, 2011).

b.

Denmark

Even if there is no feed-in tariff for solar PV in Denmark, high electricity prices virtually the highest in Europe22 provide the rationale for net-metering. Regulatory aspects

The "Guidelines for net settlement of auto producers"23 were approved by the Danish Energy Authority in 2005.

20 21

[28] [29] 22 [30]

Technical and Economical Assessment of Net-Metering in Kenya

Solar PV systems below 50kWp are eligible for net-metering and are automatically registered for net-metering. Larger systems could also benefit from net-metering, but must address an application to the utility24. Technical aspects

At the time of writing (December 2011), Energinet.dk has only made available the Technical regulation 3.2.1 for electricity-generating facilities of 16 A pr. phase or lower. This technical regulation comprises provisions for electricity-generating facilities connected to the Danish public electricity supply network which have a maximum output current of 16 A per phase. The regulation includes provisions regarding the properties which the electricity-generating facilities must have and continue to have throughout their service life. As an attachment to this regulation, a list of solar inverters that comply with this regulation and are thus approved for use is provided.

c.

Mexico

Net-metering for solar PV installations is possible throughout the country since June 200725. Although the government has not set specific targets for solar energy generation, insolation conditions in Mexico and a legal framework for grid access encourage optimistic forecasts. Regulatory aspects

The net-metering regulation makes a difference between small-scale generators (connected to the grid at voltage below 1kV) and medium-scale generators (connected to the grid at voltage between 1kW and 69kV). The specific capacity limits that apply are respectively 30kW and 500kW. In both cases, no generation permit is required. In order to access the electrical grid, a contract for distributed generation is signed with the Comisin Federal de Electricidad (CFE), which is only an annex to the normal electricity supply contract). Technical aspects

Specific technical requirements concerning the connection to the low voltage grid are available on the website of the Comisin Reguladora de Energa. These cover all technical requirements for inverter-based generators.

23 24

[31] [32] 25 [33]

Technical and Economical Assessment of Net-Metering in Kenya

d.

Brazil

The government of Brazil is set to promulgate market-enabling legislation that will finally permit broad grid connections for solar installations by the end of 201126. This new opportunity is expected to catalyze growth in the solar PV sector. Regulatory aspects

No official documentation is available at the time of writing (December 2011). The Deutsche Gesellschaft fr Internationale Zusammenarbeit (GIZ) is actively working with local governmental institutions and relevant stakeholders to push forward the net-metering policy. For this purpose, a thorough study by German lawyers was completed in August 2011 to provide the Brazilian Electricity Regulatory Agency (ANEEL) with information on the legal procedures for the connection of small and decentralized distributed generation plants up to 1 Megawatt to low voltage grids27.

e.

Morocco

The Deutsche Gesellschaft fr Internationale Zusammenarbeit (GIZ) is completing a study to prove the potential of grid-connected solar PV to the low voltage grid 28. According to the outputs of this study, grid parity will be achieved by electricity consumers of all tariff categories by latest 2013. As part of the efforts to promote such regulation, a proposal of 1 million roofs program is being developed. Such program would have to rely on a net-metering framework. Regulatory aspects

There is no specific regulation for net-metering at the moment of writing (December 2011). However, a law published in 2010 (Dahir n 1-10-16 du 11 fvrier 2010, publie au Bulletin officiel n 5822 le 18 mars 2010) expresses the right to produce electricity from renewable energy sources for own consumption in grid-connected applications in medium and high voltage. This law is in line with the philosophy of net-metering and represents starting point for the development of specific regulation.

26 27

[34] [35] 28 [36]

Technical and Economical Assessment of Net-Metering in Kenya

f.

Best practices

Interesting lessons can be derived from each the previous examples. The practices listed below could set examples worthwhile to consider: Several states in the USA, including Washington D.C. impose no limit on the number of subscribers using net metering The national utility in Denmark makes available a list of solar inverters that comply with its regulation for connection to the low voltage grid Administrative procedures for net-metering are kept very simple in most of the cases listed above. In the case of Mexico, the contract is just an annex to the normal energy supply contract with the utility. Brazil conducted a thorough study on the legal procedures for the connection of small and decentralized distributed generation plants to low voltage grids with the aim of collecting the best practices from around the world. Moroccos proposal of a 1 million roofs program might be too ambitious, but a thousand roof program would be a great example of an achievable target that would pave the way for the growth of decentralized small-scale solar PV.

Technical and Economical Assessment of Net-Metering in Kenya

Part II: Technical Issues of Solar PV Grid Interconnection 1. Introduction

This chapter is intended to examine the technical feasibility of grid integration of solar Distributed Generation (DG) with PV in Kenya. As Kenya has up to now no country-specific experiences in this area, we are basing our analysis on the circumstances of the German market, in combination with parameters and information derived from the available documentation of the Kenyan electricity market, e.g. the grid code as well as other information obtained from stakeholders. Technical requirements in other countries having implemented net-metering have also been reviewed for reference and have been included in chapter 7. By 2011, approx. 1,000,000 grid-connected PV systems were operating in Germany with a total rated power of 17,200 MW installed capacity, of which 7,200 were added in 2010 only. 98% of these systems are feeding into the LV grid. As a result, the technical issues of distributed generation (DG) are of paramount importance with respect to the German grid operation and stability. In this chapter, we discuss the newly developed, advanced guidelines for grid interconnection of DG. These guidelines were recently changed in a significant way and are now ready for future growth of the share of distributed electric power generation. The changes became necessary because earlier technical rules were not suitable to accommodate for the tremendous growth of DG in Germany. Instead, they were a threat to the stability of the European electricity supply, the synchronous area, ENTSOE. Thus, the new guidelines reflect the impact of DG on the distribution grid level on the transmission and generation system.

Figure 10: Development of PV installations in Germany 2000 2010

Technical and Economical Assessment of Net-Metering in Kenya

The report therefore will not simply copy the German solution to Kenya without considering the implications of transfer and proper adaption. However, the new German guidelines for gridconnected PV are based on the general guidelines of the European High Voltage (HV) network. Furthermore, European countries are now harmonizing their PV-guidelines according to the German regulations. We therefore also recommend for Kenya to switch to these very advanced guidelines for PV. This chapter addresses technical issues of connection to the LV distribution grid with respect to the whole electricity supply system. It is intended to give guidance on preparations for a growing rate of distributed generation. The report primarily addresses the low voltage LV connection of DG systems. However, the technical issues are similar for medium voltage MV connection.

2.

Compatibility with the Kenya Grid Code

This assessment is based on an evaluation of the /Kenya Electricity Grid Code of 200829 . It considers only technical and not procedural and administrative requirements. The grid code focuses on large electricity production plants which are typically connected to higher voltage levels than Low Voltage (LV). Therefore a literal employment for PV systems would not be appropriate. PV systems that would be installed under net metering would be much smaller and would require much simpler procedures as those outlined in code section 3 and 6. We noticed several technical requirements with respect to the transmission network. No specific requirements for LV had been noticed. Thus the following discussion is based on the rules for the High Voltage (HV) network. We recommend adding a section to the Kenyan Grid Code for inverter based generators, or generators connected to the LV grid. This would clarify the requirements for potential Independent Power Producers. Frequency behaviour The Code says in section S3.1.3: A network service provider shall ensure that within the power system frequency range 45.0 to 52.0 Hz all of his power system equipment will remain in service unless that equipment is required to be switched to give effect to load shedding in accordance with clause S3.1.10, or is required by the System Operator to be switched for operational

29

[20]

Technical and Economical Assessment of Net-Metering in Kenya

purposes. Plant shall not be required to operate in a sustained manner outside the range of the normal operating frequency excursion band but should remain in service for shortterm operation in the range of 45.0 Hz to 52 Hz. . In section S3.2.6.4 it states: Overall response of a generator for system frequency excursions shall be settable and be capable of achieving.a reduction in the generator's active power output of 2% per 0.1 Hz increase in system frequency provided the latter does not require operation below technical minimum. For initial outputs above 85% of rated output response capability shall be able to achieve a linear reduction in response down to zero response at rated output. The basic functionality to abide by these requirements is implemented in modern inverters. However, the frequency range is wider than in Europe, thus inverters with European settings might switch off more often than necessary. Default frequency range in Europe is 47.5 Hz to 51.5 Hz. Once a significant generation capacity with PV is available, the switching-off threshold at lower frequency becomes crucial. A premature disconnection of inverters would actually reduce generation power, when it is badly needed, during a lack of generation. Therefore, on a long term basis inverters threshold for disconnection should be set to 45 Hz during commissioning. As grid voltage in Kenya is above the German standard, the inverter operational bands have to be adapted. This is technically feasible.

Voltage behaviour and Fault-Ride-Through (FRT) Section S3.1.4 states: . control of voltage such that the minimum steady state voltage magnitude on the transmission network will be 90% of nominal voltage and the maximum steady state voltage magnitude will be 110% of nominal voltage. . Short-time variations (of several minutes duration) within 5% of the intended values shall be considered in the design of plant by Code Participants. And sectionS3.2.5.3 on Generator response to disturbances in the power system connection point to drop to zero for up to 0.175 seconds in any one phase or combination of phases, followed by a period of ten seconds where voltage may vary in the range 80-110%.

Technical and Economical Assessment of Net-Metering in Kenya

The voltage band from 90 % to 110 % of nominal voltage (Un) is already implemented as default into European inverters. No change is necessary. FRT capability in Europe is not requested on the LV grid, but only on higher grid voltage levels, however many inverters are prepared for this feature, since they may be employed in PV systems connected to the MV grid. The Kenyan requirement for FRT for 0.175 s duration is slightly higher than in Europe (0.150 s). It should be clarified whether FRT will be requested also for generators connected to the LV grid. Reactive power capability According to the code power factor (PF) limits are 0.85 inductive and 0.95 capacitive. (Code S3.2.5.1). Modern inverters can typically deliver PF >= 0.95 (Pn<= 13.8 kVA) or PF >= 0.90 (Pn<= 13.8kVA). This is a sub band of the code requirement. It is only minor constraint, not impeding application of PV technology. Typically most systems are set to a PF of 1. Voltage quality (harmonics, dips, swells, phase unbalance) These topics are stated in Code section S3.1.6. The code refers to requirements according to the IEC 61000 standard series. The same standards are required in Europe, too. In short, modern inverters fully comply with the Kenyan Grid Code. From the inverter side, no serious obstacles can be expected.

Technical and Economical Assessment of Net-Metering in Kenya

3.

Solar PV and the German/European Electricity Supply Network

The German electricity supply network is part of the European common control area, ENTSOE. It includes generation and transmission system with typical 220 kV and 380 kV system voltages. For cities and short distances 110 kV is used for transmission as well as distribution. Regional distribution is done over 10 kV and 20 kV 3-phase, 3-wire system. Local distribution uses a 400 V, 3-phase, 4-wire system with a neutral centre wire. Nominal voltage between phases and neutral is 230 V. Generally, buildings are connected to this 3-phase system. Internal 1-phase loads are distributed over the three phases. Voltage regulation is regularly performed at the HV/MV transformer by means of a tap changer. In residential areas in Germany the network regularly comprises a transformer with a nominal power of Sn = 400 kVA. This transformer feeds several feeders of 150 mm Al cables. These cables can carry about 180 kVA continuously /PV Upscale - Utilities Experience [1]/. Currently in Europe a substantial change in electrical power generation and distribution is taking place. The structure is shifting from a central, top-down structured generation and distribution to a combined central and decentralised generation. With fast growing penetration especially of photovoltaic power systems (PV) mainly in the low-voltage grid the impact of PV on the whole electricity supply network has been re-assessed. It is very important to consider that the utilities view of the role of PV has completely changed: PV in Germany is now a power source with a significant generation capacity and a big impact on the European electricity supply system. New PV systems therefore are requested to actively contribute to system services and security. Grid stability is of paramount importance. Therefore fault-ride-through capabilities are an important feature for PV systems including small ones, due to their large number. Even with little PV capacity on the grid potential effects of future large inverter capacities should be taken into account, since the amount of DG capacity will steadily increase and these inverters will operate for the next 10- 15 years.

Technical and Economical Assessment of Net-Metering in Kenya

Retrofitting of PV systems (in Germany) to solve 50.2 Hz problemplanned Press Release from the German the Association of Electrical, Electronic and Information Technologies VDE,September 2011 A joint initiative of grid operators and the solar industry is recommending that the German Government take measures to ensure supply security in the German and European power grid. According to a scientific study, a retrofitting of some solar power systems is necessary to solve the so-called 50.2-hertz problem. The technical guidelines for operating decentralized power generating systems were established at a time when these systems played only a minor role. For this reason, the forum network technology (FNN) has now revised the guidelines for new systems. The objective is to achieve a "gentle" disconnect of systems from the grid when overfrequencies occur. Since the large number of already installed systems has a significant influence on network stability in the German and European electricity grids, there must be a regulation of retrofitting. In Germany, these modifications are recommended for all photovoltaic systems that became operational after 1 September 2005 and that have a capacity of over 10 kWp peak power. Technical implementation is to be carried out between 2012 and 2014 on around 315,000 mid- to large-sized solar power systems that are connected to the low-voltage grid. This means that small roof-mounted systems on single-family homes would not be required to undergo retrofitting. Although solar inverters were always installed and set up properly and according to current guidelines, necessary progress in shutdown specifications requires that changes be made to existing systems. According to experts, the retrofit recommendation is the simplest and most cost-efficient solution. In the vast majority of cases, the installer must only update the software or change the parameter settings of the solar inverter.

Technical and Economical Assessment of Net-Metering in Kenya

4.

Relevant technical issues of distributed PV generation

This section summarizes concerns of utilities with regards to distributed generation. These individual aspects relevant to this presented in the following are based on two studies undertaken by a team of experts on this issue3031 : Maximum capacity for distributed PV generation in LV networks

The acceptable capacity depends strongly on the assumptions for a tolerable voltage rise. A study by IEA32 found a difference by a factor of four when comparing the limits of 2 % as given in the former VDEW Guideline and the 10 % tolerance level regulated in the European Standard for voltage quality, EN 50160. /EN 50160:200833 . As a rule of thumb PV capacity in an LV grid segment should not cause any problems, if power is limited to 70 % of the rated power of the feeding transformer34. Voltage level rise along feeder

g rid

20 kV

0,4 kV G

G G

V/Vn [% ]

110 105 100 95 90

Figure 11: Principle scheme of current flow over LV transformer and voltage gradient at distributed generation. Due to PV power generation, the voltage drop across the branch can change its sign.

30 31

[1] [2] 32 [3] 33 [12] 34 [2]

Technical and Economical Assessment of Net-Metering in Kenya

Adding generation capacity on a feeder formerly used only to supply loads may cause a reverse power flow in that feeder along with a voltage rise due to voltage drops on the power line to the transformer. Figure 7 shows the basic scheme. The low voltage grid is often designed with a so called after diversity maximum (ADMD) load for each domestic customer of 1 to 1.1 kVA. If PV systems are connected with a nominal power of several kWs at each customers installation, problems with the actual voltage level and capacity of the LV cable can occur. From one of the aforementioned studies35, it can be assumed that this effect is noticed; however, in stiff grids it is not critical. It may become critical in rural areas with higher impedance networks.

Component loading

A recent study for German networks36 showed that under the assumption of an even distribution of PV capacity - each customer has a PV system (!) - at the LV level, the first limitation for higher PV capacity arises from the voltage rise towards the end of the feeder. Thermal overload of equipment is not noticed until even higher PV power, in the worst case of suburban networks 6 kWp per household (household is equal to connection point). In stiffer network areas 10 kWp - 30 kWp per consumer can be connected. Note that these values are depending on the topology of the grids. Certain numbers for Kenya should be assessed in a more detailed investigation however 100% PV penetration in a market has not yet been achieved in the world (see chapter 6.2 for the market scenario).

Harmonics from inverters

Harmonic currents and DC from inverters are no problem with modern inverters, which comply with generic standards of the IEC 61000 series. Also analysis of high population real estates with PV showed that in general no detrimental effect on power quality was noticed. Flicker problems were not noticed37.

External manual disconnect

External disconnects were for a long time in many countries seen as a very important measure to ensure staff safety during maintenance work. However, with soaring numbers of systems manually disconnecting all DG systems seems no longer feasible. Thus, for systems up to 30 kW the external disconnect requirement had been dismissed, if grid connection is done through a safety interface according to the German standard VDE 0126-1-1: 2007.

35 36

[2] [7] 37 [2]

Technical and Economical Assessment of Net-Metering in Kenya

Unintentional islanding

The possible occurrence of unintentional islanding in networks with distributed generation had been one of the major issues. However, investigations have shown that likelihood and risk of personal injury or death from islanding are below other risks accepted by society (such as smoking, driving cars or passing a highway). This topic has been discussed in detail38. . Accordingly, unintentional islanding and its risks should not be seen as a barrier or limiting factor for the further development of Distributed Generation.

Short-circuits in the distribution system

In urban areas employing underground cable networks the currents from PV systems are small compared to the high short circuit current of the network. Therefore no adverse effect on fault clearance is expected. However, under high penetration of PV-DG and if faults occur at the end of lines with high impedance, currents from PV systems might hamper fault detection and clearance. To avoid reduced stability of the electricity supply system due to massive disconnection of generation capacity, short faults with voltage breakdown must not lead to disconnection of PV systems from the grid (see box Retrofitting of PV systems (in Germany) to solve 50.2 Hz problem).

Network stability

Grid stability is of prime importance. Therefore fault-ride-through capabilities are an important feature for PV systems including small ones, due to their large number. Even with little PV capacity on the grid potential effects of large inverter capacities should be taken into account, since the amount of DG capacity will steadily increase and these inverters will operate for the next 10 15 years. Therefore, in Germany, due to the large PV capacity of some 17 GVA (2010) on the grid, PV inverters are now required to provide fault-ride-through capability like central power stations39 (more details in section 5.4 New Guidelines). For systems on the LV grid the necessity of this feature is being discussed, but not implemented.

38 39

[8] [9]

Technical and Economical Assessment of Net-Metering in Kenya

Output power control

The current feed-in law (EEG 201140) requires for systems of 30 kW and above means for remotely controllable output power. In case of overload, DNOs may reduce the actual power of a system. Output power control allows a coordinated reduction in power delivery from generation systems. This reduction is used to ensure abidance with admissible voltage bands. The method would allow a higher capacity than could be tolerated on the basis of fixed rules for voltage rise. However, this option requires a reliable communication channel and an appropriate control scheme implementation into network operation. It is thus suitable only for larger systems.

Reactive power supply

Drawing reactive power while supplying real power is an option for voltage level control widely used in transmission networks. It is essentially an option for PV inverters, too. Currently, it is not (yet) used in small inverters, but by 2012 new .inverters have to be prepared to activate such an option. Ideally this control should operate automatically, using some static control characteristics. This option can be implemented in cable networks, though it is more effective in overhead lines. This capability is required in the new German LV guidelines41.

5.

Applicable aspects of the German LV Guideline

In Germany a new guideline for connecting and operating distributed generation systems on the medium voltage grid has been published in August 201142.This guideline considers DG as part of the larger electricity network as described before, and imposes some concepts from the transmission system level (transmission code 200743) to the LV grid. This section gives a summary of the main requirements discussed in that paper. The new LV guideline requests a contribution to grid security and stability from DG. DG systems have to remain connected and feed into the grid using much wider voltage and frequency bands than in former editions of this guideline. DG systems have to o contribute to static voltage control, i.e. aid in maintaining voltage level under varying loads

40 41

[5] [10] 42 [10] 43 [11]

Technical and Economical Assessment of Net-Metering in Kenya

o o

contribute to dynamic grid support during grid disturbances This includes a defined fault-ride-through capability and the option to deliver reactive current for voltage support must operate with a defined over-frequency regime

Admissible voltage changes

The connection point between grid and DG Systems as well as the power factor of the DG system have to be selected that the voltage change of the sum of all DG systems at full power is limited to 3 %.This measure shall ensure that voltage limits defined by respective standards are well kept. Asymmetric loading

Generally, symmetric 3-phase generation is required. Maximum tolerable difference between phases is 4.6 kVA. Active power limitation

An additional requirement regards the option for the DNO to actively reduce the power output of DG systems in critical situations. This requirement is also defined in the governing EEG law for system sized above 30 kWp. A paper by the Association of Network Operators (VDN) suggests use of a variable power reduction scheme with several reduction levels, at least: 0 %, 30 %, 60 %, and 100 % with respect to nominal system power. Automatic power reduction at over frequency

All renewable-based generating units must reduce, while in operation, at a frequency of more than 50.2 Hz the instantaneous active power with a gradient of 40 % of the generators instantaneously available capacity per Hertz (Figure 7).

Technical and Economical Assessment of Net-Metering in Kenya

Figure 12:

Active power reduction of renewable-based generating units in the case of over-frequency (from [12])

For maintenance work transformers may be switched off and power supply on the LV level is assured by mobile gensets. Typically, emergency power units are operated for a short while in parallel to the public grid. To avoid disturbing interactions of distributed generators and emergency generators the frequency of the emergency generator is shortly increased above the cut-off threshold of DG units, e.g. 52 Hz. After all DG has disconnected, the frequency is reduced and kept slightly above the reconnection frequency.

Reactive power control

DG systems need some means for reactive power control. Sn< 3.68 kVA: PF <= 0,95 3.68 kVA: <Sn<= 13,8 kVA: PF <= 0,95; control curve by DNO 13,8 kVA <Sn : PF <= 0,90; control curve by DNO Power limits are somewhat arbitrary and influenced by European standards. The control curve can be a fixed displacement factor cos , or fixed reactive power Q in MVAr, or a variable displacement factor as function of real power cos (P), or a variable reactive power Q as function of voltage, Q (V). Dynamic functions shall respond within 10 s (for cos (P)) up to 1 minute (for Q (V)).

Technical and Economical Assessment of Net-Metering in Kenya

Figure 13: Example of a cos (P)-characteristic. This is the recommended default curve.

Protective relays

The MV Guideline44 states: Protection equipment is of considerable importance for secure and reliable operation of networks, connection facilities and generating plants. According to DIN VDE 0101, automatic installations must be provided for short-circuit clearing in electric facilities. The plant operator is responsible himself for the reliable protection of his plants (e.g. short-circuit, earth fault and overload protection, protection from electric shock, etc.). To this end, the plant operator must install an adequate amount of protection equipment... The protective relay works on the transfer switch, which eventually connects the DG unit to the grid. The following functions of the protective disconnection equipment shall be realized for LV systems, with set values and reaction time given in the following table F.

44

[9]

Technical and Economical Assessment of Net-Metering in Kenya

Protective function under-voltage protection U< over-voltage protection U> over-voltage protection U>> under-frequency protection f< over-frequency protection f> islanding detection

Set value 0.8 Un 1.1 Un 1.15 Un 47.5 Hz 51.5 Hz n.a.

Reaction time 200 ms 200 ms 200 ms 200 ms 200 ms 5s

Table 19: Set values and reaction time of protection relays Over-voltage protection employs a 10 min sliding average measurement. Thus it is compatible with the voltage quality standard EN 50 16045. The other voltage deviation protection relies on fast, half-cycle, rms measurements. At a frequency below 47.5 Hz or above 51.5 Hz the DG system shall disconnect immediately. Between 47.5 Hz and 51.5 Hz the DG unit must not disconnect, but shall deliver a frequency dependent power as shown in section 5.4.4 Islanding detection can be realised by an active method like frequency shift or by 3-ph voltage monitoring (only 1-ph inverters and electrical machines). Verification of the electrical properties

Every generating unit requires a type-specific unit certificate which specifies the electrical properties of the generating unit in order to confirm the conformity of the generating unit with the requirements of the guideline. A second type certificate is required which confirms the proper function and settings of the protective relays including the Testing specifications for conformity assessment are currently under development in the German standardisation committee DKE K261 and are expected to be published in 2013.

45

[12]

Technical and Economical Assessment of Net-Metering in Kenya

6.

Future options

Modern inverters can perform additional functions such as: active filtering by injecting compensating current harmonics, reactive power control, voltage level control, phase symmetry control / P. Kremer and M. Fruehauf46. In combination with energy storage more options are possible, for example: intended islanding, extended voltage control, peak shaving. Such solutions are of particular interest to consumers that currently rely on generator sets and battery back-ups. Potential benefits are generally acknowledged, but currently have little market value in European grids. To employ these options a regulatory framework including financial incentives FIT surplus or down-payment for installation - needs to be developed. In future, theses benefits may become features of a smart grid.

Grid support during disturbances (Fault-Ride-Through Capability)

The MV guideline requests that DG plants contribute to grid security and stability. DG systems have to remain connected and feed into the grid using much wider voltage and frequency bands than in former editions of this guideline. The same operating areas as for HV equipments are employed (see Figure 10).
V/Vn V/Vn limit curve 1 limit curve 1 limit curve 2 limit curve 2 lower limit of voltage lower limit % Vn band = 90 of voltage band = 90 % Vn

below blue curve - disconnection not regulated below blue curve - disconnection not regulated time [ms] time [ms] begin of disturbance begin of disturbance
source: source: Technische Richtlinie Erzeugungsanlagen am Technische Richtlinie Erzeugungsanlagen am Mittelspannungsnetz (Technical guideline for generation systems Mittelspannungsnetz (Technical guideline for generation in the Medium Voltage grid), BDEW, Ausgabe Juni 2008 systems in the Medium Voltage grid), BDEW, Ausgabe Juni 2008

Figure 14: Operation voltage-time bands for DG on the MV grid.

46

[13]

Technical and Economical Assessment of Net-Metering in Kenya

Disconnection within the first 150 ms of a disturbance is not permitted even when the voltage completely collapses. Above limit curve1 all PV systems have to remain connected to the grid, between curve 1 and curve 2 short time disconnections (< = 2 s) are allowed, but preferably the system should stay connected. Active filtering

Inverters can be operated as active harmonic filters. In grid sections with a high distortion this may cause violations of harmonic current limits given in EMC standards like IEC 61000 3-2. Here is a gap in conventional standards and this condition could be addressed in utilities guidelines to take advantage of the new opportunities from modern inverters. If active filtering is employed and ripple control is used, inverters shall be adjusted not to compensate the frequency of the ripple control voltage. Active symmetry control

Unbalanced loads and generation lead to voltage unbalance and generate a negative sequence component. This component causes additional losses mainly in rotating machines. Properly designed and connected inverters are capable of sensing the voltage unbalance and adjust their feed-in control in a such a way that the phase with the lowest voltage receives the highest feed-in power47.Consequently, such systems can improve the grid quality at the low voltage level.

47

[13]

Technical and Economical Assessment of Net-Metering in Kenya

References
[1] PV Upscale - Utilities Experience and Perception of PV Distributed Generation, http://www.pvupscale.org/IMG/pdf/WP4_D4-2_Utilities-Experience-PVDG_v5.pdf, (July 2008) PV Upscale - Impact of PV Generation on Power Quality in Urban Areas with High PV Population, http://www.pvupscale.org/IMG/pdf/WP4_D4-3_public_v1c.pdf, (July 2008) IEA-PVPVS-Task 5, Impacts of Power Penetration from Photovoltaic Power Systems in Distribution Networks, Report IEA-PVPS T5-10: 2002, February 2002 PV Upscale - Recommendations for Utilities, http://www.pvupscale.org/IMG/pdf/WP4_D4-4_recommendations_V6.pdf: EEG 2011, Erneuerbare-Energien-Gesetz EEG) http://www.erneuerbare-energien.de/inhalt/47585/4596/ an English Version of the preceding version of this law is found here: http://www.erneuerbare-energien.de/inhalt/42934/ (August 2011) IEA-PVPVS-Task 5, Impacts of Power Penetration from Photovoltaic Power Systems in Distribution Networks, Report IEA-PVPS T5-10: 2002, February 2002 Kerber, G.; Witzmann, R.: Aufnahmefhigkeit der Verteilnetze fr Strom aus Photovoltaik, EW Jg. 106 (2007), Heft 4, (Capacity of distribution networks for electric power from PV) IEA-PVPVS-Task 5, Risk Analysis of Islanding of Photovoltaic Power Systems within low voltage Distribution Network, Task V Report IEA PVPS T5-08: 2002, March 2002 Technische Richtlinie Erzeugungsanlagen am Mittelspannungsnetz (Richtlinie fr Anschluss und Parallelbetrieb von Erzeugungsanlagen am Mittelspannungsnetz), Ausgabe Juni 2008, (Guideline for Interconnection and operation of electric generation systems in parallel to the Medium Voltage grid), BDEW (Bundesverband der Energie- und Wasserwirtschaft Federal Association of Energy and Water Industries), issued June 2008 english version available - http://www.vde.com/en/fnn/documents/rl_ea-am-msnetz_bdew2008-06_engl.pdf

[2] [3] [4] [5]

[6] [7]

[8] [9]

[10] VDE-AR-N 4105 - Anforderungen an Erzeugungsanlagen am Niederspannnungsnetz), Ausgabe September 2011 (Technical minimum requirements for distributed generation for the connection to and parallel operation with low-voltage distribution networks; September 2011; http://www.vde.com/de/infocenter/seiten/details.aspx?eslshopitemid=0d65ed5e-83c94d84-af92-356f06b66f8b [11] Transmission Code 2007, Network and System Rules of the German Transmission System Operators, August 2007; http://www.bdew.de/bdew.nsf/id/DE_7B6ERD_NetzCodes_und_Richtlinien/$file/Trans missionCode%202007_GB_end.pdf, (August 2008)

Technical and Economical Assessment of Net-Metering in Kenya

[12] EN 50160:2008; Voltage characteristics of electricity supplied by public distribution networks; German version of EN 50160:2007 [13] P. Kremer and M. Fruehauf, PV grid power unlimited Multi MW Power Conditioner units Sinvert Solar, 21st European Photovoltaic Solar Energy Conference, September 2006, Dresden, Germany [14] Freeing the Grid: Best Practices in State Net Metering Policies and Interconnection Procedures, www.newenergychoices.org, 2010 [15] MoE: Least cost power development plan LCDP, study period 2010-2030 [16] Business Guide Erneuerbare Energien, Projektentwicklungsprogramm Ostafrika: Kenia; www.exportinitiative.bmwi.de; 2009 [17] Solar PV in Kenya Potentials, Market, and Opportunity Portfolio, Michael Franz GIZ Solar Technology Forum, Nairobi; 04.07.2011 [18] ERC: Gazette Notice No. The energy act (No.12 of 2006) [19] Konstantin, Panos, Praxisbuch Energiewirtschaft: Energieumwandlung, -transport und -beschaffung im liberalisierten Markt, Springer, Berlin; 2009 [20] Kenya Electricity Grid Code; ERC; 2008 [21] Dual metering for solar PV systems - discussion paper for investors and consumers; Michael Franz GIZ, Kenya; 10/2011 [22] Kenya Country Report, Economist Intelligence Unit; United Kingdom; 9/2011 [23] http://www.kplc.co.ke/index.php?id=104 [24] Adolescence of an Industry, Dr. Michael Alexander, Roland Berger Consultant, at Bird & Bird Solar Conference 2010; Investments in the Solar Industry: opportunities and pitfalls in a challenging environment, 26 November 2009 [25] German Solar Industry Association (BSW-Solar), BSW Statistic data on the German, solar power (photovoltaic) industry, BSW http://www.solarwirtschaft.de/fileadmin/content_files/factsheet_pv_engl.pdf June 2011 [26] Least Cost Power Development Plant 2011-2031, http://www.erc.go.ke/erc/LCPDP%202011%20-%202030.pdf [27] EPIA, European Photovoltaic Industry Association, 2011. Global Market Outlook for Photovoltaics until 2015. [28] EERE, U.S. Department of Energy, Energy Efficiency and Renewable Energy, 2011. http://www.eere.energy.gov [29] DSIRE, Database of State Incentives for Renewables & Efficiency, 2011. http://www.dsireusa.org [30] Europes Energy Portal, 2011. http://www.energy.eu [31] Energinet.dk, 2010. Technical Regulation 3.2.1 for electricity-generation plants of 11kW or lower [32] Energinet.dk, 2011. Official website. http://energinet.dk

Technical and Economical Assessment of Net-Metering in Kenya

[33] CRE, Comisin Reguladora de Energa, Gobierno Federal de Mexico, 2011. http://www.cre.gob.mx [34] PV Magazine, July 14th 2011.Brazil readies grid connection law. [35] STADLER, Ingo. 2011. Study about International Standards for the connection of Small Distributed Generators to the power grid. Cologne University of Applied Science. [36] GIZ, Deutsche Gesellschaft fr Internationale Zusammenarbet, 2011. Lnergie solaire photovoltaque au Marocet la basse tension.

Technical and Economical Assessment of Net-Metering in Kenya

Our team
Georg Hille is a senior PV expert with over 26 years in hands-on experience in the financial analysis, technical and project design, acquisition and operation of utility scale PV power plants across Europe (focus Germany EEG) with a total power of >60 MWp. He is CEO of twelve PV SPVs and responsible for the highly successful Ecovision PV business which has outperformed IRR predictions in all SPVs they have brought to the market to date. He has more than ten years of specific LCR renewable energy sector experience. Dieter Seifried is an internationally recognized energy economist with more than thirty years of specific work experience. He has carried Germanys most successful contracting projects with limited partners participations and is a least cost planning expert from the beginning. Hermann Laukamp is an electrical engineer and an international recognized PV specialist with about 25 years of work experience. For the last two decades he works with Fraunhofer Institute for Solar Energy Systems ISE, Europes largest research institute for solar energy, lately with an emphasis on standardization of grid connected PV in Germany and Europe, working with Governments, leading donors and top tier PV companies. Eberhard Rssler is one of the most experienced PV installers worldwide with more than 28 years in hands-on experience in planning, installing and monitoring of small up to utility scale PV power plants across Europe (focus Germany EEG). He is managing director of the installation company ARES and freelancer to the Fraunhofer Institute for Solar Energy Systems ISE in monitoring. Kilian Reiche is an internationally recognized expert in the fields of renewable energy (RE) and energy access, with eighteen years of specific work experience. He is lead advisor to several RE funds and managing director of iidevelopment, a small firm specialized on RE equity placements and PPI in developing countries. He has led transactions and funds totalling >$500M, is a co-founder of fosera ltd and teaches at TU Darmstadt. Since 1999, he has been working continuously for the World Bank Group, first as a staff member and recently as a senior consultant. He has more than ten years of specific energy sector experience in Latin America.

Anda mungkin juga menyukai