Anda di halaman 1dari 1

Minutes of 6th Session on ISO-14001 (EMS) & 18001 (OHSAS) Certification work for JMT Auto Ltd held

on 22.11.12
Observations/instructions
1. Heat Treatment OCPs as discussed and modified in the last session in thorough discussion with Mr. Sengupta, HT and his team to make these technically valid and practical from implementation point of view could not be reviewed for finalisation due to non-availability of the same after review by Mr.Sengupta. These would be checked by Mr.Sengupta at earliest so that these can be reviewed and finalised in next session. As final disposal method for some of the critical hazardous waste e.g. Nitriding bath sludge, Washing solution from nitride parts etc. could not be decided in the meeting, it was decided that Mr. Sengupta would talk to the concerned persons and explore ways for suitable disposal method meeting applicable legal/statutory environmental requirement. All other OCPs redrafted based on the modifications suggested. All these OCPs would also be reviewed in the next session for finalisation. Rest of the other reference Standards of ISO-14001/ISO18001 to be procured as suggested. Aspect-Impact study for the Stores area was discussed and drafted. WI prepared for safe handling, storage and use of the purchased hazardous material was reviewed and found ok for implementation. It was decided that only 2 types of empty drums e.g. Plastic drum and Steel sheet drum would be considered for storage & disposal control directly from the earmarked storage area Mr.Giri /Mr.Satnam Singh to prepare the Environmental legal requirement compliance register as per format given to them and show in the next session. A generically prepared guideline document for Emergency preparedness response plan (EPRP) for Fire was given to Mr. Maharana for drafting EPRP for JMT on the basis of the EPRP document prepared by him. This is to be shown in next session. Aspect-impact study for common processes would be discussed after all these are finalised.

JMTs comments/status
Got the OCP checked by Mr. Sengupta and the same may be finalised in the next session.

2.

Had talks on the subject at length. Mr. Sengupta would come up with ideas for the same after having discussed with his concerned colleagues in the meeting.

3.

Duly modified at our end. Further to be reviewed in the meeting. To be taken care by Sr. G.M.-QA & MR

4.

5.

W.Is. on the subject have been prepared and ready to be reviewed in the next session.

6.

OCPs were modified accordingly.

7.

The said register has been made ready for perusal.

8.

The same has been made ready for perusal.

9.

10. Next Session points for discussion/review : (a) Review and finalise all the OCPs prepared so far. (b) EPRP for Fire to be prepared by Mr. Maharana (c) Review Legal compliance register (d) Implementation status of OCPs/Waste inventory register in the shop-floor (e) Storage, Transfer & Final disposal systems being followed for shop-floor environmental waste management including empty drums. (f) OCP implementation in HT. (g) Practising status of Hazardous purchased material as per WI prepared by Mr.Ghosh