BSM Cluster F 7 September 2010, Tuesday, 10am to 11am BSM Boardroom th 36 Street, University Park, Bonifacio Global City, 1634 Taguig, Metro Manila Construction Coordination Meeting Nr 15 BSM, DLS PM, DLS QS, AMCON, Rchitects, Sy^2, Phil-Sundt
Purpose: Attendees:
Item
Topic
Action
1 2
All All
Page 1
3 September 2010
MINUTES Project: Date / Time: Location: The British School Manila Cluster F 31 August 2010 ; 10am 11am BSM Board Room, The British School Manila 36th Street University Park, Bonifacio Global City Taguig Metro Manila, 1634 Weekly Site Coordination Meeting Nr 14 Name Nicole Tanjangco (NT) Tom C Keator (TCK) Johnny S Sicatin (JSS) Alexander R Gatila (ARG) Joel N Arda (JNA) Jen E Silva (JES) Annie T Oseda (ATO) Dave Marr (DM) James Clyde (JC) Robin Salenga (RS) Avelino de Leon (ADL) Organisation British School Manila Davis Langdon & Seah Davis Langdon & Seah Davis Langdon & Seah AMCON & Company, Inc. AMCON & Company, Inc. Rchitects, Inc. Phil-Sundt Const. & Devt. Phil-Sundt Const. & Devt. Phil-Sundt Const. & Devt. Phil-Sundt Const. & Devt. Role Owner / Administration Manager Senior Development Manager Project Manager QS Team Leader CM CM Architect/ Lead Consultant President Contractor, Area Manager Contractor, Senior QS Contractor, Project Engineer Development Governor/ President Owner / Operations Manager QS Team Leader Contractor, Project-InCharge
Purpose: Attendees:
Apologies:
Alan P Hearn(APH) Diana Cristobal (DC) Ricardo G Lozano II (RGL) Rayvi Cruz (RC)
British School Manila / Davis Langdon & Seah British School Manila Davis Langdon & Seah Phil-Sundt Const. & Devt. Corp.
Distribution:
Item
Description
Meeting was presided by JSS.
Action By
MINUTES OF PREVIOUS MEETING The minutes of the Weekly Site Meeting Nr 13 were reviewed and approved with the team. The pending and resolved items discussed were:
If there are any discrepancies or corrections in the understanding of the above meeting documentation, please notify DLS within 48 hours in writing.
U:\Dev Management\E - Projects\E - DMP10002 British School - Cluster F\E - Meetings\Weekly Construction Meeting\Minutes\Minutes of Weekly Site Coordination Meeting Nr 14.doc Page 1
Item
1.1 1.1.1
Description
Pending Issues Contractor Design
Action By
1.1.1.1
PS to submit complete FCD from grids F to J and 1 to 2 (existing changing rooms) for review and approval by Rchitects. ATO required PS to provide cross-section, elevations and perspective.
Phil-Sundt/ Rchitects
1.1.1.2
PS to confirm Cluster F total power requirement and total KVA for back-up power.
Phil-Sundt
1.1.1.3
Phil-Sundt
1.1.2 1.1.2.1
Construction Issues Construction Programme Update (as per updated 16 August 2010) As of 27 August 2010: Commencement Date : Targeted Completion Date : Actual : Target : Remarks : 17 May 2010 17 December 2010 23% 31% 17 days behind schedule CM to update every meeting
1.1.2.2
JC informed the Team that by end of September 2010, the Project would be on-schedule.
Phil-Sundt
1.1.2.3
The Project Team agreed that all finishes (interior and exterior) shall be APPROVED by mid of September.
All
15 Sep. 2010
1.1.2.4
Phil-Sundt
On-going
1.1.2.5
American Standard Representative to meet BSM Facilities to discuss various operational problems/concerns particularly of Cluster E.
Done 2 Sept.
If there are any discrepancies or corrections in the understanding of the above meeting documentation, please notify DLS within 48 hours in writing.
U:\Dev Management\E - Projects\E - DMP10002 British School - Cluster F\E - Meetings\Weekly Construction Meeting\Minutes\Minutes of Weekly Site Coordination Meeting Nr 14.doc Page 2
Item
1.1.2.6
Description
PS has started work for the re-routing of existing drainage system at Level 1. Schedule of completing remaining works to be finalized by PS.
Action By
Phil-Sundt
1.1.2.7
AMCON will maintain submittal log, update and highlights pending items for prompt action.
AMCON
7 Sept. 2010
1.1.3 1.1.3.1
1.1.3.2
Reconciliation of PS claims is proceeding. PS Claims are on: School Bell System Drinking Fountain rough-ins Smoke and Heat Detector Control Room Wi-Fi Port Hot Water System (as per PS Letter re: Additional Works dd. 6 August 2010)
Coordination drawings (item 1.1.1.3) for these works was done, and it has to be implemented
1.1.3.3
7 Sept. 2010
1.1.4 1.1.4.1
OSM Issues Kitchen Design PS to coordinate with the winning Supplier to finalize lay-out, stub-outs, equipment list, power requirement, supply and exhaust systems, and data/cabling requirements. BSM, Kitchen Supplier, and BSM IT Consultant
Pending
1.1.4.2
BSM/ DLS QS
Note
1.1.5 1.1.5.1
Owner Issues NT/DC informed the Team that starting 26 November 2010, BSM needs to use the Changing Rooms. PS to confirm next meeting if this target Partial Occupancy is achievable or not. BSM Note
Phil-Sundt
7 Sept. 2010
If there are any discrepancies or corrections in the understanding of the above meeting documentation, please notify DLS within 48 hours in writing.
U:\Dev Management\E - Projects\E - DMP10002 British School - Cluster F\E - Meetings\Weekly Construction Meeting\Minutes\Minutes of Weekly Site Coordination Meeting Nr 14.doc Page 3
Item
1.1.5.2
Description
Relative to 1.1.5.1, PS shall comply with all authorities requirements for the Partial Occupancy (for using the Changing Rooms before Completion Date)
Action By
Phil-Sundt
1.1.5.3
PS to submit Safety Implementation Plan starting School Days opening on 16 Aug as per instruction from APH for approval.
Phil-Sundt
1.1.5.4
PS to name all its Sub-Contractors and Suppliers to the Insurance company or insurer. A document shall be furnished to DLS QS for review and endorsement to BSM.
Phil-Sundt
1.1.6 1.1.6.1
Others Inconsistencies in GFA applied by BSM discovered by BESC. PS to coordinate with BESC to gather pertinent data, Rchitects to assist in the determination of the GFAs. Target resolution is before Occupancy Permit Application for Cluster F. Phil-Sundt, Rchitects, BSM
Meeting with BESC confirmed on 7 Sept. 2010 ,1.30pm at BESC
1.1.6.2
Diana/ DLS QS
1.1.6.3
On-going
1.2 1.2.1
RESOLVED ISSUE Sy^2 have reviewed the latest FCD Structural Drawings of PS dated 11 August. Included in is the 1.20meter deep basement beam for implementation. Sy^2 Reviewed drawings transmitted to PS 27 August
Meeting adjourned at 11am. Next meeting will be on 7 September 2010, 10.00am, at BSM Boardroom. CLOSE
If there are any discrepancies or corrections in the understanding of the above meeting documentation, please notify DLS within 48 hours in writing.
U:\Dev Management\E - Projects\E - DMP10002 British School - Cluster F\E - Meetings\Weekly Construction Meeting\Minutes\Minutes of Weekly Site Coordination Meeting Nr 14.doc Page 4