JORGE BASADRE
GERENCIA DE DESARROLLO
URBANO E INFRAESTRUCTURA
: INSTALACION DEL ALBERGUE PARA EL ADULTO MAYOR EN EL DISTRITO DE HUANUARA - CANDARAVE - TACNA"
INICIO OBRA
UBICACIN
DIAS EJECUTADOS
ITEM
01
DESCRIPCION DE LA ACTIVIDAD
UND
PRESUPUESTO
METR.
P.U.
ACTUAL
Parcial
Metrado
Monto
424,391.35
01.01
TRABAJOS PRELIMINARES
01.01.01
und
1.00
846.70
846.70
2,200.00
259.83%
01.01.02
m2
40.00
82.27
3,290.80
4,500.00
136.74%
01.01.03
30.00
51.57
1,547.10
1,125.99
72.78%
01.01.04
GLB
1.00
25,000.00
25,000.00
3,892.10
15.57%
01.01.05
m2
210.00
2.50
525.00
800.00
152.38%
01.01.06
m2
262.50
6.17
1,619.63
1,500.00
92.61%
01.01.07
m2
525.00
6.73
3,533.25
7,600.00
215.10%
01.02
36,362.48
21,105.44
MOVIMIENTO DE TIERRAS
21,618.09
18,647.04
01.02.01
m3
101.47
51.07
5,182.07
2,480.00
47.86%
01.02.02
m2
94.22
12.05
1,135.35
14,832.00
1306.38%
01.02.03
m2
196.50
12.05
2,367.83
1,335.04
56.38%
01.02.04
m3
47.94
60.71
2,910.44
01.02.05
m2
196.50
31.38
6,166.17
01.02.06
m3
69.60
31.31
2,179.18
01.02.07
m3
69.60
16.73
01.03
1,164.41
36,911.75
9,314.36
01.03.01
m2
65.24
36.97
2,411.92
448.45
18.59%
01.03.02
m3
27.44
324.69
8,909.49
4,668.00
52.39%
01.03.03
m3
8.96
538.90
4,828.54
2,006.47
41.55%
01.03.04
m2
115.61
44.68
5,165.45
01.03.05
m2
155.40
64.75
10,062.15
01.03.06
m2
41.10
91.24
3,749.96
01.03.07
m2
196.50
9.08
2,191.44
122.82%
01.04
01.04.01
1,784.22
131,883.80
895.89
18,754.64
ZAPATAS
01.04.01.01
m3
26.10
532.73
13,904.25
178.75
1.29%
01.04.01.02
kg
625.05
7.76
4,850.39
717.13
14.79%
01.04.02
42,437.53
COLUMNAS
01.04.02.01
m3
12.87
731.22
9,410.80
0.00
0.00%
01.04.02.02
m2
172.57
58.82
10,150.57
0.00
0.00%
01.04.02.03
kg
2,855.95
8.01
22,876.16
0.00
0.00%
01.04.03
35,807.38
VIGAS
01.04.03.01
m3
12.83
585.86
7,516.58
0.00
0.00%
01.04.03.02
m2
144.95
51.57
7,475.07
0.00
0.00%
01.04.03.03
kg
1,586.30
8.01
12,706.26
0.00
0.00%
01.04.03.04
Solaqueo de Estructuras
m2
317.52
25.54
8,109.46
0.00
0.00%
01.04.04
LOSA ALIGERADA
01.04.04.01
m3
26.12
546.86
14,283.98
01.04.04.02
m2
149.25
15.39
2,296.96
0.00
0.00%
01.04.04.03
kg
768.32
8.42
6,469.25
0.00
0.00%
01.04.04.04
und
1,194.00
3.92
4,680.48
0.00
0.00%
01.04.04.05
m2
149.25
9.08
1,355.19
0.00
0.00%
0.00
0.00%
0.00
0.00%
01.04.05
29,085.87
5,798.38
01.04.05.01
m3
2.58
620.07
1,599.78
01.04.05.02
m2
30.53
60.08
1,834.24
01.04.05.03
kg
236.00
8.01
1,890.36
01.04.05.04
m2
7.66
61.88
01.05
MAMPOSTERIA DE LADRILLO
01.05.01
m2
284.40
120.05
01.05.02
m2
10.66
61.13
01.06
474.00
34,793.87
34,142.22
651.65
18,709.60
01.06.01
m2
312.84
30.16
9,435.25
01.06.02
m2
312.84
25.25
7,899.21
01.06.03
123.00
11.18
01.07
0.00
1,375.14
20,027.42
0.00
01.07.01
Contrapiso de e=5cm
m2
172.40
35.75
6,163.30
01.07.02
m2
41.10
31.85
1,309.04
0.00
MUNICIPALIDAD PROVINCIAL
JORGE BASADRE
GERENCIA DE DESARROLLO
URBANO E INFRAESTRUCTURA
: INSTALACION DEL ALBERGUE PARA EL ADULTO MAYOR EN EL DISTRITO DE HUANUARA - CANDARAVE - TACNA"
INICIO OBRA
UBICACIN
DIAS EJECUTADOS
ITEM
DESCRIPCION DE LA ACTIVIDAD
UND
PRESUPUESTO
METR.
P.U.
ACTUAL
Parcial
Metrado
01.07.03
m2
39.80
64.96
2,585.41
01.07.04
m2
40.80
214.99
8,771.59
01.07.05
m2
16.00
74.88
1,198.08
01.08
Monto
3,296.31
ZOCALOS Y CONTRAZOCALOS
01.08.01
32.80
34.25
1,123.40
0.00
0.00%
01.08.02
m2
33.45
64.96
2,172.91
0.00
0.00%
0.00
0.00%
01.09
10,251.22
CARPINTERIA DE MADERA
01.09.01
m2
11.24
541.53
6,086.80
01.09.02
m2
3.96
243.08
962.60
01.09.03
Meson de Madera
und
1.00
546.94
546.94
01.09.04
m2
12.29
216.02
2,654.89
01.10
CARPINTERIA METALICA
01.10.01
m2
4.86
710.83
01.11
3,454.63
3,454.63
1,884.00
CERRAJERIA
01.11.01
pza
12.00
27.17
326.04
01.11.02
pza
12.00
19.17
230.04
01.11.03
und
18.00
26.62
479.16
01.11.04
pza
3.00
135.84
407.52
01.11.05
pza
4.00
110.31
01.12
441.24
7,039.31
PINTURA
01.12.01
m2
391.05
8.11
3,171.42
01.12.02
m2
391.05
6.60
2,580.93
01.12.03
m2
22.48
43.59
979.90
01.12.04
m2
7.92
38.77
307.06
01.13
668.03
VARIOS
01.13.01
m2
5.50
73.92
01.13.02
m3
5.50
47.54
01.14
406.56
261.47
1,211.17
01.14.01
20.00
11.60
232.00
01.14.02
20.00
2.55
51.00
01.14.03
20.00
3.48
69.60
01.14.04
20.00
6.26
125.20
01.14.05
pto
3.00
14.34
43.02
01.14.06
25.00
6.84
171.00
01.14.07
und
4.00
11.97
47.88
01.14.08
pza
1.00
38.52
38.52
01.14.09
pza
4.00
24.02
96.08
01.14.10
und
12.00
12.67
152.04
01.14.11
und
4.00
12.56
50.24
01.14.12
Caja de Paso
und
1.00
65.84
65.84
01.14.13
Prueba hidrulica
25.00
2.75
01.15
68.75
2,976.47
DESAGUE Y VENTILACION
01.15.01
20.00
18.25
365.00
01.15.02
20.00
2.55
51.00
01.15.03
20.00
3.48
69.60
01.15.04
20.00
6.26
125.20
01.15.05
pza
2.00
155.84
311.68
01.15.06
und
2.00
278.68
557.36
01.15.07
20.00
12.68
253.60
01.15.08
12.00
7.11
85.32
01.15.09
pza
6.00
20.61
123.66
01.15.10
pza
2.00
30.33
60.66
01.15.11
pza
7.00
23.84
166.88
01.15.12
pza
6.00
12.99
77.94
01.15.13
pza
3.00
12.99
38.97
01.15.14
und
4.00
25.29
101.16
01.15.15
und
3.00
81.80
245.40
01.15.16
und
3.00
47.34
142.02
01.15.17
Prueba hidrulica
20.00
2.75
55.00
01.15.18
pza
1.00
146.02
146.02
MUNICIPALIDAD PROVINCIAL
JORGE BASADRE
GERENCIA DE DESARROLLO
URBANO E INFRAESTRUCTURA
: INSTALACION DEL ALBERGUE PARA EL ADULTO MAYOR EN EL DISTRITO DE HUANUARA - CANDARAVE - TACNA"
INICIO OBRA
UBICACIN
DIAS EJECUTADOS
ITEM
01.16
01.16.01
01.16.01.01
01.16.02
DESCRIPCION DE LA ACTIVIDAD
UND
PRESUPUESTO
METR.
P.U.
Metrado
m2
10
6.17
m3
1.13
36.48
m3
1.13
60.71
68.60
01.16.02.03
m3
5.00
31.31
156.55
01.16.02.04
und
2.00
311.23
622.46
2,578.96
CONDUCTORES
Conductor NYY 2x1x6mm2
30.00
14.04
01.16.03.02
170.00
4.13
702.10
01.16.03.03
240.00
4.83
1,159.20
01.16.03.04
und
1.00
296.46
421.20
296.46
5,219.82
ARTEFACTOS DE ILUMINACION
01.16.04.01
und
15.00
282.98
4,244.70
01.16.04.02
und
4.00
97.98
391.92
01.16.04.03
und
4.00
116.40
465.60
01.16.04.04
und
3.00
39.20
117.60
und
16.00
44.38
01.16.05.01
710.08
TOMACORRIENTES
Tomacorriente Doble c/puesta a tierra
710.08
01.16.06
INTERRUPTORES
01.16.06.01
Interruptor Simple
und
6.00
29.92
179.52
01.16.06.02
Interruptor Doble
und
8.00
35.92
287.36
01.16.06.03
Interruptor Triple
und
3.00
42.92
128.76
und
1.00
754.78
01.16.07
01.16.07.01
01.16.08
595.64
754.78
754.78
5,132.13
ACCESORIOS Y TUBERIAS
01.16.08.01
95.00
11.21
1,064.95
01.16.08.02
155.00
11.16
1,729.80
01.16.08.03
pto
26.00
34.92
907.92
01.16.08.04
pto
16.00
34.92
558.72
01.16.08.05
pto
17.00
51.22
01.16.09
870.74
1,346.70
01.16.09.01
pza
7.00
51.60
361.20
01.16.09.02
pza
2.00
66.60
133.20
01.16.09.03
pza
2.00
76.95
153.90
01.16.09.04
und
2.00
349.20
01.16.10
01.16.10.01
01.17
01.17.01
01.18
glb
1.00
2,503.74
2,503.74
36,590.00
MOBILIARIO Y EQUIPAMIENTO
Mobiliario
698.40
2,503.74
und
1.00
36,590.00
36,590.00
22,433.47
MURO DE CONTENCION
01.18.01
m3
19.11
63.84
1,219.98
01.18.02
m3
25.48
12.05
307.03
01.18.03
m3
18.59
31.31
582.05
01.18.04
m3
18.59
16.73
311.01
01.18.05
m2
18.85
36.97
696.88
01.18.06
m3
13.75
619.63
8,519.91
01.18.07
m2
57.20
69.81
3,993.13
01.18.08
kg
732.62
8.01
5,868.29
01.18.09
Curado de Estructuras
m2
68.64
3.53
242.30
01.18.10
18.00
3.59
64.62
01.18.11
m2
31.46
19.97
628.26
glb
1.00
10,000.00
glb
1.00
5,000.00
01.19
01.19.01
01.20
01.20.01
02
02.01
02.01.01
10,000.00
CAPACITACION
Capacitacion
10,000.00
5,000.00
0.00%
41.22
01.16.03.01
01.16.05
0.00
61.70
888.83
MOVIMIENTO DE TIERRAS
01.16.02.02
01.16.04
61.70
TRABAJOS PRELIMINARES
01.16.02.01
01.16.03
Monto
19,792.38
INSTALACIONES ELECTRICAS
ACTUAL
Parcial
5,000.00
203,211.03
75,602.06
COLUMNAS
33,344.14
MUNICIPALIDAD PROVINCIAL
JORGE BASADRE
GERENCIA DE DESARROLLO
URBANO E INFRAESTRUCTURA
: INSTALACION DEL ALBERGUE PARA EL ADULTO MAYOR EN EL DISTRITO DE HUANUARA - CANDARAVE - TACNA"
INICIO OBRA
UBICACIN
DIAS EJECUTADOS
ITEM
DESCRIPCION DE LA ACTIVIDAD
UND
02.01.01.01
m3
02.01.01.02
02.01.01.03
02.01.02
PRESUPUESTO
METR.
P.U.
ACTUAL
Parcial
Metrado
10.26
731.22
m3
130.39
58.82
7,669.54
kg
2,268.70
8.01
18,172.29
m3
9.74
585.86
5,706.28
02.01.02.02
m2
108.27
51.57
5,583.48
02.01.02.03
kg
1,212.42
8.01
9,711.48
02.01.02.04
Solaqueo de Estructuras
m2
238.65
25.54
02.01.03
COBERTURA LIGERA
Tijerales Principales de Rollizo
und
14.00
239.01
3,346.14
02.01.03.02
Correas de Rollizo
106.60
50.76
5,411.02
02.01.03.03
m2
65.00
86.47
5,620.55
02.01.03.04
m2
13.80
56.80
02.02
MAMPOSTERIA DE LADRILLO
Muro Hercules II (12x24x9) de soga con cemento - arena
m2
309.24
120.05
37,124.26
20,150.74
m2
340.16
30.16
10,259.23
02.03.02
m2
340.16
25.25
8,589.04
02.03.03
116.50
11.18
1,302.47
28,510.56
02.04.01
Contrapiso de e=5cm
m2
152.00
35.75
02.04.02
m2
64.00
64.96
4,157.44
02.04.03
m2
88.00
214.99
18,919.12
02.05
5,434.00
2,630.47
ZOCALOS Y CONTRAZOCALOS
02.05.01
m2
32.80
34.25
02.05.02
m2
23.20
64.96
02.06
1,123.40
1,507.07
10,096.10
CARPINTERIA DE MADERA
02.06.01
m2
11.80
541.53
02.06.02
m2
3.96
243.08
962.60
02.06.03
m2
12.70
216.02
2,743.45
02.07
CARPINTERIA METALICA
02.07.01
m2
18.00
264.01
02.08
6,390.05
4,752.18
4,752.18
1,396.74
CERRAJERIA
02.08.01
pza
12.00
27.17
326.04
02.08.02
pza
9.00
19.17
172.53
02.08.03
und
6.00
26.62
159.72
02.08.04
pza
3.00
135.84
407.52
02.08.05
pza
3.00
110.31
02.09
330.93
7,597.45
PINTURA
02.09.01
m2
425.20
8.11
3,448.37
02.09.02
m2
425.20
6.60
2,806.32
02.09.03
m2
23.76
43.59
1,035.70
02.09.04
m2
7.92
38.77
307.06
02.10
412.26
02.10.01
pto
3.00
14.34
43.02
02.10.02
10.00
6.84
68.40
02.10.03
und
3.00
11.97
35.91
02.10.04
pza
2.00
24.02
48.04
02.10.05
und
9.00
12.67
114.03
02.10.06
und
6.00
12.56
75.36
02.10.07
Prueba hidrulica
10.00
2.75
02.11
0.00%
783.84
37,124.26
02.03.01
02.04
0.00
6,095.12
15,161.55
02.01.03.01
02.03
27,096.37
VIGAS
02.01.02.01
02.02.01
Monto
7,502.32
27.50
970.39
DESAGUE Y VENTILACION
02.11.01
pza
1.00
155.84
155.84
02.11.02
und
1.00
278.68
278.68
02.11.03
6.00
12.68
76.08
02.11.04
12.00
7.11
85.32
02.11.05
pza
4.00
20.61
82.44
02.11.06
pza
1.00
23.84
23.84
02.11.07
pza
3.00
12.99
38.97
02.11.08
und
2.00
25.29
50.58
MUNICIPALIDAD PROVINCIAL
JORGE BASADRE
GERENCIA DE DESARROLLO
URBANO E INFRAESTRUCTURA
: INSTALACION DEL ALBERGUE PARA EL ADULTO MAYOR EN EL DISTRITO DE HUANUARA - CANDARAVE - TACNA"
INICIO OBRA
UBICACIN
DIAS EJECUTADOS
ITEM
DESCRIPCION DE LA ACTIVIDAD
02.11.09
02.11.10
02.11.11
Prueba hidrulica
02.12
02.12.01
UND
und
PRESUPUESTO
METR.
P.U.
ACTUAL
Parcial
Metrado
Monto
2,503.74
0.00
0.00%
2,503.74
0.00
0.00%
1.00
81.80
81.80
1.00
47.34
47.34
18.00
2.75
49.50
13,967.82
INSTALACIONES ELECTRICAS
1,689.10
CONDUCTORES
02.12.01.01
140.00
4.13
578.20
02.12.01.02
230.00
4.83
1,110.90
02.12.02
ARTEFACTOS DE ILUMINACION
4,222.74
02.12.02.01
und
13.00
282.98
3,678.74
02.12.02.02
02.12.02.03
und
und
4.00
2.00
116.40
39.20
465.60
78.40
und
10.00
44.38
02.12.03
02.12.03.01
443.80
TOMACORRIENTES
Tomacorriente Doble c/puesta a tierra
02.12.04
INTERRUPTORES
02.12.04.01
Interruptor Simple
und
6.00
29.92
02.12.04.02
Interruptor Triple
und
3.00
42.92
02.12.05
443.80
308.28
179.52
128.76
4,101.01
ACCESORIOS Y TUBERIAS
02.12.05.01
95.00
11.21
1,064.95
02.12.05.02
140.00
11.16
1,562.40
02.12.05.03
pto
19.00
34.92
663.48
02.12.05.04
pto
10.00
34.92
349.20
02.12.05.05
pto
9.00
51.22
460.98
02.12.06
699.15
02.12.06.01
pza
4.00
51.60
206.40
02.12.06.02
pza
1.00
66.60
66.60
02.12.06.03
pza
1.00
76.95
76.95
02.12.06.04
und
1.00
349.20
349.20
glb
1.00
2,503.74
02.12.07
02.12.07.01
COSTO DIRECTO
GASTOS GENERALES
COSTO DE OBRA
15.00%
627,602.37
94,140.36
S/. 721,742.73
50,475.38
7,571.31
S/. 58,046.68
8.04%
: INSTALACION DEL ALBERGUE PARA EL ADULTO MAYOR EN EL DISTRITO DE HUANUARA - CANDARAVE - TACNA"
01 de Setiembre al 30 de Setiembre del 2012
FECHA : SABADO,01 DE SETIEMBRE DEL 2012
ITEMS
01.00.00
01.02.00
01.02.01
DESCRIPCION DE PARTIDA
MEJORAMIENTO DE LA INFRAESTRUCTURA 1ER PISO
MOVIMIENTO DE TIERRAS
EXCAVACION ZAPATAS Y CIMIENTOS HASTA 1.5m DE PROF.
UND
N
VECES
M3
1.00
MEDIDAS
LARGO
ANCHO
ALTO
----------------------------------------------------
DESCRIPCION DE PARTIDA
INFRAESTRUCTURA URBANA
CERCO PROVISIONAL DE ESTERAS
CASETA DE ALMACEN Y GUARDIANIA
UND
N
VECES
ML
GLB
1.00
0.30
MEDIDAS
LARGO
ANCHO
ALTO
40.00
DESCRIPCION DE PARTIDA
INFRAESTRUCTURA URBANA
CERCO PROVISIONAL DE ESTERAS
CASETA DE ALMACEN Y GUARDIANIA
UND
N
VECES
ML
GLB
1.00
0.30
MEDIDAS
LARGO
ANCHO
ALTO
40.00
DESCRIPCION DE PARTIDA
UND
N
VECES
INFRAESTRUCTURA URBANA
CERCO PROVISIONAL DE ESTERAS
CASETA DE ALMACEN Y GUARDIANIA
SERVICIO HIGIENICO PARA EL PERSONAL DE OBRA
ML
GLB
GLB
1.00
0.10
0.50
MEDIDAS
LARGO
ANCHO
ALTO
40.00
DESCRIPCION DE PARTIDA
UND
INFRAESTRUCTURA URBANA
SERVICIO HIGIENICO PARA EL PERSONAL DE OBRA
LIMPIEZA DEL TERRENO EN FORMA MANUAL
GLB
M2
N
VECES
MEDIDAS
LARGO
ANCHO
Area:
400.00
ALTO
0.50
DESCRIPCION DE PARTIDA
INFRAESTRUCTURA URBANA
LIMPIEZA DEL TERRENO EN FORMA MANUAL
UND
M2
N
VECES
MEDIDAS
LARGO
ANCHO
Area:
400.00
ALTO
: INSTALACION DEL ALBERGUE PARA EL ADULTO MAYOR EN EL DISTRITO DE HUANUARA - CANDARAVE - TACNA"
01 de Setiembre al 30 de Setiembre del 2012
FECHA : LUNES,12 DE MARZO DEL 2012
ITEMS
01.00.00
01.02.01
01.02.02
01.02.03
DESCRIPCION DE PARTIDA
INFRAESTRUCTURA URBANA
TRAZO NIVELES Y REPLANTEO
LIMPIEZA DEL TERRENO EN FORMA MANUAL
ELIMINACIN DE DESMONTE EXISTENTE
UND
N
VECES
M2
M2
M3
MEDIDAS
LARGO
ANCHO
Area:
Area:
Vol:
300.00
400.00
40.00
ALTO
DESCRIPCION DE PARTIDA
INFRAESTRUCTURA URBANA
AGUA PARA LA OBRA
TRAZO NIVELES Y REPLANTEO
LIMPIEZA DEL TERRENO EN FORMA MANUAL
ELIMINACIN DE DESMONTE EXISTENTE
UND
GLB
M2
M2
M3
N
VECES
MEDIDAS
LARGO
ANCHO
Area:
Area:
Vol:
300.00
400.00
40.00
ALTO
0.30
DESCRIPCION DE PARTIDA
INFRAESTRUCTURA URBANA
AGUA PARA LA OBRA
TRAZO NIVELES Y REPLANTEO
UND
GLB
M2
N
VECES
MEDIDAS
LARGO
ANCHO
Area:
300.00
ALTO
0.30
DESCRIPCION DE PARTIDA
INFRAESTRUCTURA URBANA
AGUA PARA LA OBRA
TRAZO NIVELES Y REPLANTEO
ELIMINACIN DE DESMONTE EXISTENTE
UND
GLB
M2
M3
N
VECES
MEDIDAS
LARGO
ANCHO
Area:
Vol:
400.00
32.00
ALTO
0.40
DESCRIPCION DE PARTIDA
INFRAESTRUCTURA URBANA
MOVILIZACION Y DESMOVILIZACION DE MAQUINARIAS Y EQUIPOS
CORTE Y EXCAVACION EN TERRENO SUELTO C/MAQUINARIA
UND
GLB
M3
N
VECES
MEDIDAS
LARGO
ANCHO
Vol:
65.00
ALTO
0.50
DESCRIPCION DE PARTIDA
INFRAESTRUCTURA URBANA
CORTE Y EXCAVACION EN TERRENO SUELTO C/MAQUINARIA
ACARREO DE MATERIAL EXCEDENTE D=40 M
UND
M3
M3
N
VECES
MEDIDAS
LARGO
ANCHO
Vol:
Vol:
48.82
35.00
ALTO
: INSTALACION DEL ALBERGUE PARA EL ADULTO MAYOR EN EL DISTRITO DE HUANUARA - CANDARAVE - TACNA"
01 de Setiembre al 30 de Setiembre del 2012
FECHA : LUNES,19 DE MARZO DEL 2012
ITEMS
01.00.00
01.01.04
01.01.07
01.03.02
01.03.03
DESCRIPCION DE PARTIDA
INFRAESTRUCTURA URBANA
MOVILIZACION Y DESMOVILIZACION DE MAQUINARIAS Y EQUIPOS
TRANSPORTE DE MATERIALES DE TACNA A LOCUMBA
RELLENO CON MATERIAL DE PRESTAMO C/MAQUINARIA
ACARREO DE MATERIAL EXCEDENTE D=40 M
UND
GLB
GLB
M3
M3
N
VECES
MEDIDAS
LARGO
ANCHO
Vol:
Vol:
10.00
40.00
ALTO
0.20
0.20
DESCRIPCION DE PARTIDA
INFRAESTRUCTURA URBANA
TRANSPORTE DE MATERIALES DE TACNA A LOCUMBA
RELLENO CON MATERIAL DE PRESTAMO C/MAQUINARIA
ACARREO DE MATERIAL EXCEDENTE D=40 M
UND
GLB
M3
M3
N
VECES
MEDIDAS
LARGO
ANCHO
Vol:
Vol:
10.00
40.00
ALTO
0.30
DESCRIPCION DE PARTIDA
INFRAESTRUCTURA URBANA
CARTEL DE IDENTIFICACION DE LA OBRA DE 2.40X3.60 M.
RELLENO CON MATERIAL DE PRESTAMO C/MAQUINARIA
ACARREO DE MATERIAL EXCEDENTE D=40 M
ELIMINACION DE MATERIAL EXCEDENTE C/EQUIPO D=5 KM.
UND
UND
M3
M3
M3
N
VECES
MEDIDAS
LARGO
ANCHO
Vol:
Vol:
Vol:
10.00
40.00
147.97
ALTO
1.00
DESCRIPCION DE PARTIDA
INFRAESTRUCTURA URBANA
MOVILIZACION Y DESMOVILIZACION DE MAQUINARIAS Y EQUIPOS
RELLENO CON MATERIAL DE PRESTAMO C/MAQUINARIA
Habilitacion de Madera para encofrado
Habilitacion de Acero para jardineras
UND
GLB
M3
N
VECES
MEDIDAS
LARGO
ANCHO
Vol:
15.00
ALTO
0.30
DESCRIPCION DE PARTIDA
INFRAESTRUCTURA URBANA
RELLENO CON MATERIAL DE PRESTAMO C/MAQUINARIA
Habilitacion de Madera para encofrado
Habilitacion de Acero para jardineras
UND
N
VECES
M3
MEDIDAS
LARGO
ANCHO
Vol:
15.00
ALTO
DESCRIPCION DE PARTIDA
INFRAESTRUCTURA URBANA
RELLENO CON MATERIAL DE PRESTAMO C/MAQUINARIA
EXCAVACION EN TERRENO SUELTO EN FORMA MANUAL
UND
M3
M3
MEDIDAS
N
VECES
LARGO
ANCHO
ALTO
2.00
Vol:
30.53
5.00
Area:
0.03
: INSTALACION DEL ALBERGUE PARA EL ADULTO MAYOR EN EL DISTRITO DE HUANUARA - CANDARAVE - TACNA"
01 de Setiembre al 30 de Setiembre del 2012
FECHA : LUNES,26 DE MARZO DEL 2012
ITEMS
01.00.00
01.03.02
01.04.04.03.02
DESCRIPCION DE PARTIDA
INFRAESTRUCTURA URBANA
RELLENO CON MATERIAL DE PRESTAMO C/MAQUINARIA
SARDINEL PERALTADO: ENCOFRADO Y DESENCOFRADO NORMAL
UND
M3
M2
MEDIDAS
N
VECES
LARGO
ANCHO
1.00
2.00
2.00
Vol:
30.53
30.53
15.00
ALTO
0.30
0.20
18.32
12.21
DESCRIPCION DE PARTIDA
01.00.00
01.03.02
01.04.01.01
01.04.01.02
INFRAESTRUCTURA URBANA
RELLENO CON MATERIAL DE PRESTAMO C/MAQUINARIA
EXCAVACION EN TERRENO SUELTO EN FORMA MANUAL
NIVELACION Y COMPACTACION DE TERRENO P/PISOS C/EQUIPO LIVIANO
Vereda perimetral contigua calle 2
Habilitacion de Madera para encofrado
MEDIDAS
UND
N
VECES
LARGO
ANCHO
ALTO
M3
M3
1.00
2.00
Vol:
32.18
15.00
Area:
0.03
Area:
83.95
M2
DESCRIPCION DE PARTIDA
01.00.00
01.03.02
01.04.01.01
01.04.01.02
INFRAESTRUCTURA URBANA
RELLENO CON MATERIAL DE PRESTAMO C/MAQUINARIA
EXCAVACION EN TERRENO SUELTO EN FORMA MANUAL
NIVELACION Y COMPACTACION DE TERRENO P/PISOS C/EQUIPO LIVIANO
Vereda perimetral contigua calle 6
Habilitacion de Acero para jardineras
MEDIDAS
UND
N
VECES
LARGO
ANCHO
ALTO
M3
M3
1.00
2.00
Vol:
35.27
15.00
Area:
0.03
Area:
81.70
M2
DESCRIPCION DE PARTIDA
INFRAESTRUCTURA URBANA
RELLENO CON MATERIAL DE PRESTAMO C/MAQUINARIA
SARDINEL PERALTADO: CONCRETO F'C= 140 KG/CM2
MEDIDAS
UND
N
VECES
LARGO
ANCHO
M3
1.00
Vol:
5.00
1.00
1.00
30.53
30.53
Area:
Area:
0.045
0.030
ALTO
1.374
0.916
DESCRIPCION DE PARTIDA
INFRAESTRUCTURA URBANA
RELLENO CON MATERIAL DE PRESTAMO C/MAQUINARIA
EXCAVACION EN TERRENO SUELTO EN FORMA MANUAL
Vereda perimetral contigua calle 1
SARDINEL PERALTADO: ENCOFRADO Y DESENCOFRADO NORMAL
Vereda perimetral contigua calle 6
Habilitacion de Madera para encofrado
Corte de Terreno en zona de calle 1
MEDIDAS
UND
N
VECES
LARGO
ANCHO
ALTO
M3
M3
1.00
2.00
Vol:
35.27
5.00
Area:
0.03
M2
1.00
35.27
0.30
10.58
: INSTALACION DEL ALBERGUE PARA EL ADULTO MAYOR EN EL DISTRITO DE HUANUARA - CANDARAVE - TACNA"
01 de Setiembre al 30 de Setiembre del 2012
FECHA : SABADO,31 DE MARZO DEL 2012
ITEMS
01.00.00
01.04.04.03.02
01.01.07
DESCRIPCION DE PARTIDA
INFRAESTRUCTURA URBANA
SARDINEL PERALTADO: ENCOFRADO Y DESENCOFRADO NORMAL
Vereda perimetral contigua calle 6
Habilitacion de Madera para encofrado
TRANSPORTE DE MATERIALES DE TACNA A LOCUMBA
MEDIDAS
UND
N
VECES
LARGO
M2
2.00
35.27
GLB
0.50
ANCHO
ALTO
0.30
21.16
0.00
1.00
40.00
0.30
40.00
0.30
40.00
0.10
0.50
0.50
400.00
400.00
300.00
400.00
40.00
0.30
300.00
400.00
40.00
0.30
300.00
0.40
400.00
32.00
0.50
65.00
48.82
35.00
0.20
0.20
10.00
40.00
0.30
10.00
40.00
1.00
10.00
32.97
147.97
0.30
15.00
15.00
5.00
1.83
15.00
30.53
15.00
1.93
83.95
15.00
2.12
81.70
5.00
2.29
5.00
2.12
10.58
21.16
0.50
: INSTALACION DEL ALBERGUE PARA EL ADULTO MAYOR EN EL DISTRITO DE HUANUARA - CANDARAVE - TACNA"
PARTIDA
01
DESCRIPCION DE PARTIDA
UND
METRADO
M
06
M
07
J
08
01.01
TRABAJOS PRELIMINARES
Cartel de obra de 3.60 x 2.40 m
und
1.00
40.0
40.0
40.0
40.0
01.01.02
m2
40.00
0.3
0.3
0.3
0.1
01.01.03
30.00
01.01.04
GLB
01.01.05
m2
210.00
01.01.06
m2
262.50
01.01.07
m2
525.00
101.47
m3
01.02.02
m2
94.22
01.02.03
m2
196.50
01.02.04
m3
47.94
01.02.05
m2
196.50
01.02.06
m3
69.60
01.02.07
m3
69.60
m2
01.03.02
m3
01.03.03
m3
8.96
01.03.04
m2
115.61
01.03.05
m2
155.40
01.03.06
m2
41.10
01.03.07
m2
196.50
65.24
V
16
S
17
D
18
L
19
M
20
M
21
J
22
V
23
S
24
D
25
L
26
M
27
M
28
J
29
V
30
S
31
AVANCE
ACUMULADO
SALDO
160.00
1.00
1.00
1.00
1.00
1.00
1.00
160.0
1.0
1.0
1.0
1.0
1.0
1.0
-159.0
39.0
29.0
0.0
209.0
261.5
524.0
1,600.00
1,600.00
112.00
0.00
1,600.0
1,600.0
112.0
0.0
-1,498.5
-1,505.8
84.5
47.9
113.82
120.00
147.97
147.97
113.8
120.0
148.0
148.0
-44.2
-50.4
-148.0
-82.7
5.88
165.62
0.00
0.00
0.00
5.9
165.6
0.0
0.0
0.0
109.7
-10.2
41.1
196.5
0.0
0.00
0.00
0.00
0.0
0.0
0.0
26.1
625.1
0.0
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
172.6
2,856.0
0.0
12.8
145.0
1,586.3
317.5
0.0
26.1
149.3
0.00
0.00
0.00
0.00
0.0
0.0
0.0
0.0
149.3
0.0
2.6
30.5
0.00
0.00
0.0
0.0
7.7
0.0
2.3
62.3
0.0
0.0
0.0
8.4
-62.3
312.8
312.8
123.0
AVANCE
MAYO
1.0
0.5
0.5
0.2
0.3
0.5
0.3
0.3
0.4
300.0
300.0
600.0
400.0
400.0
400.0
40.0
40.0
0.2
0.3
0.5
400.0
400.0
32.0
65.0
48.82
10.0
10.0
40.0
40.0
10.0
15.0
15.0
5.0
15.0
15.0
15.0
5.0
5.0
33.0
148.0
1.83
1.93
84.0
2.1
81.7
ZAPATAS
Concreto f'c=210 kg/cm2, en zapatas
m3
26.10
kg
625.05
01.04.02.01
m3
12.87
01.04.02.02
m2
172.57
01.04.02.03
COLUMNAS
kg
2,855.95
01.04.03.01
m3
12.83
01.04.03.02
m2
144.95
01.04.03.03
kg
1,586.30
01.04.03.04
Solaqueo de Estructuras
m2
317.52
VIGAS
01.04.04
LOSA ALIGERADA
01.04.04.01
m3
26.12
01.04.04.02
m2
149.25
01.04.04.03
kg
768.32
01.04.04.04
und
1,194.00
01.04.04.05
m2
149.25
2.58
01.04.05
J
15
01.04.01.02
01.04.03
M
14
27.44
01.04.01.01
01.04.02
M
13
35.0
01.03.01
01.04
L
12
MOVIMIENTO DE TIERRAS
Excavacin Zapatas y Cimientos Hasta 1.5m de Prof.
01.04.01
D
11
1.00
01.02.01
01.03
S
10
01.01.01
01.02
V
09
01.04.05.01
m3
01.04.05.02
m2
30.53
01.04.05.03
kg
236.00
01.04.05.04
m2
7.66
01.05
MAMPOSTERIA DE LADRILLO
284.40
01.05.01
m2
01.05.02
2.29
123.00
2.29
62.27
0.00
0.00
0.00
01.07.01
Contrapiso de e=5cm
m2
172.40
0.00
0.0
172.4
01.07.02
m2
41.10
01.07.03
m2
39.80
0.00
0.0
39.8
01.07.04
m2
40.80
01.07.05
m2
16.00
0.00
0.00
0.00
0.00
0.0
0.0
0.0
0.0
16.0
0.0
32.8
33.5
0.00
0.0
4.0
0.00
0.00
0.00
0.00
0.0
0.0
0.0
0.0
12.3
0.0
4.9
0.0
0.00
0.0
12.0
0.00
0.00
0.00
0.0
0.0
0.0
3.0
4.0
0.0
0.00
0.00
0.0
0.0
391.1
22.5
0.00
0.0
5.5
0.00
0.00
0.00
0.0
0.0
0.0
0.0
20.0
20.0
0.00
0.0
20.0
m2
10.66
01.06.01
m2
312.84
01.06.02
m2
312.84
01.06.03
01.06
01.07
01.08
30.53
ZOCALOS Y CONTRAZOCALOS
Contrazocalo de cermico de 10x40 cm
32.80
01.08.02
m2
33.45
01.09.01
m2
11.24
01.09.02
m2
01.09.03
Meson de Madera
und
1.00
01.09.04
m2
12.29
01.10
CARPINTERIA METALICA
01.10.01
CARPINTERIA DE MADERA
m2
4.86
pza
12.00
01.11.02
pza
12.00
01.11.03
und
18.00
01.11.04
pza
3.00
01.11.05
pza
4.00
01.12
3.96
01.11.01
01.11
CERRAJERIA
PINTURA
01.12.01
m2
391.05
01.12.02
m2
391.05
01.12.03
m2
22.48
01.12.04
m2
7.92
01.13
VARIOS
01.13.01
m2
01.13.02
5.50
m3
5.50
01.14.01
20.00
01.14.02
20.00
01.14.03
20.00
01.14.04
20.00
01.14
21.16
01.08.01
01.09
10.58
01.14.05
pto
3.00
01.14.06
25.00
01.14.07
und
4.00
01.14.08
pza
1.00
01.14.09
pza
4.00
01.14.10
und
12.00
01.14.11
und
4.00
01.14.12
Caja de Paso
und
1.00
01.14.13
Prueba hidrulica
25.00
01.15.01
20.00
01.15.02
20.00
01.15.03
20.00
01.15.04
20.00
01.15.05
pza
2.00
01.15.06
und
2.00
01.15.07
20.00
01.15.08
12.00
01.15.09
pza
6.00
01.15.10
pza
2.00
01.15.11
pza
7.00
01.15.12
pza
6.00
01.15.13
pza
3.00
01.15.14
und
4.00
01.15.15
und
01.15.16
und
01.15.17
Prueba hidrulica
01.15.18
pza
1.00
m2
10
01.15
01.16
01.16.01
01.16.01.01
3.00
3.00
20.00
TRABAJOS PRELIMINARES
Trazo, niveles y replanteo preliminar
01.16.02.01
m3
1.13
01.16.02.02
m3
1.13
01.16.02.03
m3
01.16.02.04
und
5.00
30.00
01.16.03.02
170.00
01.16.03.03
240.00
01.16.03.04
und
1.00
01.16.04.01
und
15.00
01.16.04.02
und
4.00
01.16.04.03
und
4.00
01.16.04.04
und
3.00
und
16.00
01.16.05.01
01.16.06
ARTEFACTOS DE ILUMINACION
TOMACORRIENTES
Tomacorriente Doble c/puesta a tierra
INTERRUPTORES
01.16.06.01
Interruptor Simple
und
6.00
01.16.06.02
Interruptor Doble
und
8.00
01.16.06.03
Interruptor Triple
und
3.00
01.16.07
01.16.07.01
01.16.08
und
1.00
ACCESORIOS Y TUBERIAS
01.16.08.01
95.00
01.16.08.02
155.00
01.16.08.03
pto
26.00
01.16.08.04
pto
16.00
01.16.08.05
pto
17.00
01.16.09
pza
7.00
01.16.09.02
pza
2.00
01.16.09.03
pza
2.00
01.16.09.04
und
2.00
glb
1.00
01.16.10
01.17
01.17.01
01.18
und
1.00
MURO DE CONTENCION
01.18.01
m3
19.11
01.18.02
m3
25.48
01.18.03
m3
18.59
01.18.04
m3
18.59
01.18.05
m2
18.85
01.18.06
m3
01.18.07
m2
57.20
01.18.08
kg
732.62
01.18.09
Curado de Estructuras
m2
68.64
01.18.10
18.00
01.18.11
m2
31.46
glb
1.00
glb
1.00
01.19
01.19.01
01.20
01.20.01
02
02.01
02.01.01
12.0
4.0
1.0
0.00
0.0
20.0
0.00
0.00
0.00
0.00
0.00
0.0
0.0
0.0
0.0
0.0
20.0
20.0
2.0
2.0
20.0
0.00
0.0
6.0
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
7.0
6.0
3.0
4.0
3.0
3.0
20.0
1.0
0.00
0.00
0.00
0.00
0.00
0.00
0.0
0.0
0.0
0.0
0.0
0.0
0.0
10.0
0.0
1.1
1.1
5.0
0.00
0.00
0.00
0.0
0.0
0.0
0.0
30.0
170.0
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
15.0
4.0
4.0
3.0
0.0
16.0
0.0
6.0
8.0
3.0
0.0
1.0
0.0
95.0
155.0
26.0
16.0
17.0
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
7.0
2.0
2.0
2.0
0.0
1.0
0.0
1.0
0.0
19.1
25.5
18.6
18.6
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
57.2
732.6
68.6
18.0
31.5
0.0
1.0
0.0
1.0
0.0
0.0
0.0
10.3
130.4
2,268.7
0.0
9.7
108.3
1,212.4
238.7
0.0
13.75
CAPACITACION
Capacitacion
EVALUACION DEL IMPACTO AMBIENTAL
IMPACTO AMBIENTAL.
MEJORAMIENTO DE LA INFRAESTRUCTURA 2DO PISO
OBRAS DE CONCRETO ARMADO
COLUMNAS
02.01.01.01
m3
02.01.01.02
m3
130.39
02.01.01.03
kg
2,268.70
02.01.02
0.0
0.0
0.0
01.16.09.01
01.16.10.01
0.00
0.00
0.00
2.00
CONDUCTORES
01.16.03.01
01.16.05
25.0
4.0
1.0
INSTALACIONES ELECTRICAS
MOVIMIENTO DE TIERRAS
01.16.04
0.0
0.0
0.0
DESAGUE Y VENTILACION
01.16.02
01.16.03
0.00
0.00
0.00
10.26
VIGAS
02.01.02.01
m3
02.01.02.02
m2
108.27
02.01.02.03
kg
1,212.42
9.74
02.01.02.04
Solaqueo de Estructuras
m2
238.65
02.01.03
COBERTURA LIGERA
02.01.03.01
und
02.01.03.02
Correas de Rollizo
106.60
02.01.03.03
m2
65.00
02.01.03.04
m2
13.80
02.02
02.02.01
14.00
m2
309.24
m2
340.16
02.03.02
m2
340.16
02.03.03
116.50
02.04
Contrapiso de e=5cm
m2
152.00
m2
64.00
02.04.03
m2
88.00
m2
32.80
02.05.02
m2
23.20
11.80
m2
02.06.02
m2
3.96
02.06.03
m2
12.70
02.07
CARPINTERIA METALICA
02.07.01
m2
18.00
02.08.01
pza
12.00
02.08.02
pza
9.00
02.08.03
und
6.00
02.08.04
pza
3.00
02.08.05
pza
3.00
m2
425.20
02.09.02
m2
425.20
02.09.03
m2
23.76
02.09.04
m2
7.92
02.10
02.10.01
pto
3.00
02.10.02
10.00
02.10.03
und
3.00
02.10.04
pza
2.00
02.10.05
und
02.10.06
und
02.10.07
Prueba hidrulica
9.00
6.00
10.00
DESAGUE Y VENTILACION
02.11.01
pza
1.00
02.11.02
und
1.00
02.11.03
6.00
02.11.04
12.00
02.11.05
pza
4.00
02.11.06
pza
1.00
02.11.07
pza
3.00
02.11.08
und
2.00
02.11.09
und
02.11.10
02.11.11
Prueba hidrulica
02.12
0.0
1.0
1.0
6.0
12.0
4.0
1.0
3.0
2.0
1.0
1.0
18.0
0.0
0.0
140.0
230.0
0.0
PINTURA
Pintura vinilica en muros exteriores 2 manos
02.12.01
9.0
6.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
CERRAJERIA
02.09.01
02.11
0.0
0.0
CARPINTERIA DE MADERA
02.06.01
02.09
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
ZOCALOS Y CONTRAZOCALOS
02.05.01
02.08
0.00
0.00
02.04.02
02.06
14.0
02.04.01
02.05
0.0
MAMPOSTERIA DE LADRILLO
02.03.01
02.03
0.00
1.00
1.00
18.00
INSTALACIONES ELECTRICAS
CONDUCTORES
02.12.01.01
140.00
02.12.01.02
230.00
02.12.02
ARTEFACTOS DE ILUMINACION
02.12.02.01
und
13.00
02.12.02.02
und
4.00
02.12.02.03
und
2.00
0.00
0.0
2.0
und
10.00
0.00
0.00
0.00
0.00
0.00
0.0
0.0
0.0
0.0
0.0
10.0
0.0
6.0
3.0
0.0
0.00
0.00
0.00
0.0
0.0
0.0
140.0
19.0
10.0
0.00
0.00
0.00
0.00
0.00
0.00
0.0
0.0
0.0
0.0
0.0
0.0
0.0
4.0
1.0
1.0
1.0
0.0
02.12.03
02.12.03.01
02.12.04
TOMACORRIENTES
Tomacorriente Doble c/puesta a tierra
INTERRUPTORES
02.12.04.01
Interruptor Simple
und
02.12.04.02
Interruptor Triple
und
02.12.05
6.00
3.00
ACCESORIOS Y TUBERIAS
02.12.05.01
95.00
02.12.05.02
140.00
02.12.05.03
pto
19.00
02.12.05.04
pto
10.00
02.12.05.05
pto
9.00
02.12.06
02.12.06.01
pza
4.00
02.12.06.02
pza
1.00
02.12.06.03
pza
1.00
02.12.06.04
und
1.00
glb
1.00
02.12.07
02.12.07.01
MUNICIPALIDAD PROVINCIAL
JORGE BASADRE
GERENCIA DE DESARROLLO
URBANO E INFRAESTRUCTURA
: INSTALACION DEL ALBERGUE PARA EL ADULTO MAYOR EN EL DISTRITO DE HUANUARA - CANDARAVE - TACNA"
UBICACIN
ITEM
01
DESCRIPCION DE LA ACTIVIDAD
UND
FECHA :
3/5/2012
3/31/2012
PRESUPUESTO
METR.
P.U.
ANTERIOR
Parcial
Metrado
INICIO OBRA
DIAS EJECUTADOS
: 27 DIAS CALENDARIO
ACTUAL
ACUMULADO
SALDO
Monto
Metrado
Monto
Metrado
Monto
Metrado
Monto
424,391.35
01.01
TRABAJOS PRELIMINARES
01.01.01
und
1.00
846.70
846.70
0.00
0.00%
160.00
135,472.00
16000.00%
160.00
135,472.00
16000.00%
-159.00
-134,625.30
01.01.02
m2
40.00
82.27
3,290.80
0.00
0.00%
1.00
82.27
2.50%
1.00
82.27
2.50%
39.00
3,208.53
01.01.03
30.00
51.57
1,547.10
0.00
0.00%
1.00
51.57
3.33%
1.00
51.57
3.33%
29.00
1,495.53
01.01.04
GLB
1.00 25,000.00
25,000.00
0.00
0.00%
1.00
25,000.00
100.00%
1.00
25,000.00
100.00%
0.00
0.00
01.01.05
m2
210.00
2.50
525.00
0.00
0.00%
1.00
2.50
0.48%
1.00
2.50
0.48%
209.00
522.50
01.01.06
m2
262.50
6.17
1,619.63
0.00
0.00%
1.00
6.17
0.38%
1.00
6.17
0.38%
261.50
1,613.46
01.01.07
m2
525.00
6.73
3,533.25
0.00
0.00%
1.00
6.73
0.19%
1.00
6.73
0.19%
524.00
3,526.52
01.02
36,362.48
21,105.44
MOVIMIENTO DE TIERRAS
01.02.01
m3
101.47
51.07
5,182.07
0.00
0.00%
1,600.00
81,712.00
1576.82%
1,600.00
81,712.00
1576.82%
-1,498.53
-76,529.93
01.02.02
m2
94.22
12.05
1,135.35
0.00
0.00%
1,600.00
19,280.00
1698.15%
1,600.00
19,280.00
1698.15%
-1,505.78
-18,144.65
01.02.03
m2
196.50
12.05
2,367.83
0.00
0.00%
112.00
1,349.60
57.00%
112.00
1,349.60
57.00%
84.50
1,018.23
01.02.04
m3
47.94
60.71
2,910.44
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
47.94
2,910.44
01.02.05
m2
196.50
31.38
6,166.17
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
196.50
6,166.17
01.02.06
m3
69.60
31.31
2,179.18
0.00
0.00%
112.00
3,506.72
160.92%
112.00
3,506.72
160.92%
-42.40
-1,327.54
01.02.07
m3
69.60
16.73
1,164.41
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
69.60
1,164.41
01.03
36,911.75
01.03.01
m2
65.24
36.97
2,411.92
0.00
0.00%
113.82
4,207.93
174.46%
113.82
4,207.93
174.46%
-48.58
-1,796.00
01.03.02
m3
27.44
324.69
8,909.49
0.00
0.00%
120.00
38,962.80
437.32%
120.00
38,962.80
437.32%
-92.56
-30,053.31
01.03.03
m3
8.96
538.90
4,828.54
0.00
0.00%
147.97
79,741.03
1651.45%
147.97
79,741.03
1651.45%
-139.01
-74,912.49
01.03.04
m2
115.61
44.68
5,165.45
0.00
0.00%
147.97
6,611.30
127.99%
147.97
6,611.30
127.99%
-32.36
-1,445.84
01.03.05
m2
155.40
64.75
10,062.15
0.00
0.00%
120.00
7,770.00
77.22%
120.00
7,770.00
77.22%
35.40
2,292.15
01.03.06
m2
41.10
91.24
3,749.96
0.00
0.00%
147.97
13,500.78
360.02%
147.97
13,500.78
360.02%
-106.87
-9,750.82
01.03.07
m2
196.50
9.08
1,784.22
0.00
0.00%
147.97
1,343.57
75.30%
147.97
1,343.57
75.30%
48.53
440.65
01.04
01.04.01
131,883.80
18,754.64
ZAPATAS
01.04.01.01
m3
26.10
532.73
13,904.25
0.00
0.00%
5.88
3,132.45
22.53%
5.88
3,132.45
22.53%
20.22
10,771.80
01.04.01.02
kg
625.05
7.76
4,850.39
0.00
0.00%
165.62
1,285.21
26.50%
165.62
1,285.21
26.50%
459.43
3,565.18
01.04.02
42,437.53
COLUMNAS
01.04.02.01
m3
12.87
731.22
9,410.80
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
12.87
9,410.80
01.04.02.02
m2
172.57
58.82
10,150.57
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
172.57
10,150.57
01.04.02.03
kg
2,855.95
8.01
22,876.16
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
2,855.95
22,876.16
7,516.58
01.04.03
35,807.38
VIGAS
01.04.03.01
m3
12.83
585.86
7,516.58
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
12.83
01.04.03.02
m2
144.95
51.57
7,475.07
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
144.95
7,475.07
01.04.03.03
kg
1,586.30
8.01
12,706.26
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
1,586.30
12,706.26
01.04.03.04
Solaqueo de Estructuras
m2
317.52
25.54
8,109.46
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
317.52
8,109.46
01.04.04
LOSA ALIGERADA
01.04.04.01
m3
26.12
546.86
14,283.98
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
26.12
14,283.98
01.04.04.02
m2
149.25
15.39
2,296.96
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
149.25
2,296.96
01.04.04.03
kg
768.32
8.42
6,469.25
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
768.32
6,469.25
01.04.04.04
und
1,194.00
3.92
4,680.48
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
1,194.00
4,680.48
01.04.04.05
m2
149.25
9.08
1,355.19
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
149.25
1,355.19
01.04.05
29,085.87
5,798.38
01.04.05.01
m3
2.58
620.07
1,599.78
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
2.58
1,599.78
01.04.05.02
m2
30.53
60.08
1,834.24
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
30.53
1,834.24
MUNICIPALIDAD PROVINCIAL
JORGE BASADRE
GERENCIA DE DESARROLLO
URBANO E INFRAESTRUCTURA
: INSTALACION DEL ALBERGUE PARA EL ADULTO MAYOR EN EL DISTRITO DE HUANUARA - CANDARAVE - TACNA"
UBICACIN
ITEM
DESCRIPCION DE LA ACTIVIDAD
UND
FECHA :
3/5/2012
3/31/2012
PRESUPUESTO
METR.
P.U.
01.04.05.03
kg
236.00
8.01
01.04.05.04
m2
7.66
61.88
01.05
MAMPOSTERIA DE LADRILLO
ANTERIOR
Parcial
Metrado
INICIO OBRA
DIAS EJECUTADOS
: 27 DIAS CALENDARIO
ACTUAL
ACUMULADO
SALDO
Monto
Metrado
Monto
Metrado
Monto
Metrado
Monto
1,890.36
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
236.00
1,890.36
474.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
7.66
474.00
34,793.87
01.05.01
m2
284.40
120.05
34,142.22
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
284.40
34,142.22
01.05.02
m2
10.66
61.13
651.65
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
10.66
651.65
01.06
18,709.60
01.06.01
m2
312.84
30.16
9,435.25
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
312.84
9,435.25
01.06.02
m2
312.84
25.25
7,899.21
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
312.84
7,899.21
01.06.03
123.00
11.18
1,375.14
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
123.00
1,375.14
01.07
20,027.42
01.07.01
Contrapiso de e=5cm
m2
172.40
35.75
6,163.30
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
172.40
6,163.30
01.07.02
m2
41.10
31.85
1,309.04
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
41.10
1,309.04
01.07.03
m2
39.80
64.96
2,585.41
01.07.04
m2
40.80
214.99
8,771.59
0.00
0.00%
2.29
492.33
5.61%
2.29
492.33
5.61%
38.51
8,279.26
01.07.05
m2
16.00
74.88
1,198.08
0.00
0.00%
62.27
4,662.78
389.19%
62.27
4,662.78
389.19%
-46.27
-3,464.70
01.08
3,296.31
ZOCALOS Y CONTRAZOCALOS
01.08.01
32.80
34.25
1,123.40
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
32.80
1,123.40
01.08.02
m2
33.45
64.96
2,172.91
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
33.45
2,172.91
01.09
10,251.22
CARPINTERIA DE MADERA
01.09.01
m2
11.24
541.53
6,086.80
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
11.24
6,086.80
01.09.02
m2
3.96
243.08
962.60
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
3.96
962.60
01.09.03
Meson de Madera
und
1.00
546.94
546.94
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
546.94
01.09.04
m2
12.29
216.02
2,654.89
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
12.29
2,654.89
01.10
CARPINTERIA METALICA
01.10.01
m2
4.86
710.83
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
4.86
3,454.63
01.11
3,454.63
3,454.63
1,884.00
CERRAJERIA
01.11.01
pza
12.00
27.17
326.04
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
12.00
326.04
01.11.02
pza
12.00
19.17
230.04
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
12.00
230.04
01.11.03
und
18.00
26.62
479.16
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
18.00
479.16
01.11.04
pza
3.00
135.84
407.52
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
3.00
407.52
01.11.05
pza
4.00
110.31
441.24
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
4.00
441.24
01.12
7,039.31
PINTURA
01.12.01
m2
391.05
8.11
3,171.42
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
391.05
3,171.42
01.12.02
m2
391.05
6.60
2,580.93
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
391.05
2,580.93
01.12.03
m2
22.48
43.59
979.90
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
22.48
979.90
01.12.04
m2
7.92
38.77
307.06
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
7.92
307.06
01.13
668.03
VARIOS
01.13.01
m2
5.50
73.92
406.56
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
5.50
406.56
01.13.02
m3
5.50
47.54
261.47
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
5.50
261.47
01.14
1,211.17
01.14.01
20.00
11.60
232.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
20.00
232.00
01.14.02
20.00
2.55
51.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
20.00
51.00
01.14.03
20.00
3.48
69.60
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
20.00
69.60
01.14.04
20.00
6.26
125.20
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
20.00
125.20
01.14.05
pto
3.00
14.34
43.02
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
3.00
43.02
01.14.06
25.00
6.84
171.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
25.00
171.00
01.14.07
und
4.00
11.97
47.88
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
4.00
47.88
01.14.08
pza
1.00
38.52
38.52
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
38.52
MUNICIPALIDAD PROVINCIAL
JORGE BASADRE
GERENCIA DE DESARROLLO
URBANO E INFRAESTRUCTURA
: INSTALACION DEL ALBERGUE PARA EL ADULTO MAYOR EN EL DISTRITO DE HUANUARA - CANDARAVE - TACNA"
UBICACIN
ITEM
DESCRIPCION DE LA ACTIVIDAD
UND
FECHA :
3/5/2012
3/31/2012
PRESUPUESTO
METR.
P.U.
ANTERIOR
Parcial
Metrado
INICIO OBRA
DIAS EJECUTADOS
: 27 DIAS CALENDARIO
ACTUAL
ACUMULADO
SALDO
Monto
Metrado
Monto
Metrado
Monto
Metrado
Monto
01.14.09
pza
4.00
24.02
96.08
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
4.00
96.08
01.14.10
und
12.00
12.67
152.04
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
12.00
152.04
01.14.11
und
4.00
12.56
50.24
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
4.00
50.24
01.14.12
Caja de Paso
und
1.00
65.84
65.84
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
65.84
01.14.13
Prueba hidrulica
25.00
2.75
68.75
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
25.00
68.75
01.15
2,976.47
DESAGUE Y VENTILACION
01.15.01
20.00
18.25
365.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
20.00
365.00
01.15.02
20.00
2.55
51.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
20.00
51.00
01.15.03
20.00
3.48
69.60
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
20.00
69.60
01.15.04
20.00
6.26
125.20
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
20.00
125.20
01.15.05
pza
2.00
155.84
311.68
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
2.00
311.68
01.15.06
und
2.00
278.68
557.36
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
2.00
557.36
01.15.07
20.00
12.68
253.60
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
20.00
253.60
01.15.08
12.00
7.11
85.32
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
12.00
85.32
01.15.09
pza
6.00
20.61
123.66
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
6.00
123.66
01.15.10
pza
2.00
30.33
60.66
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
2.00
60.66
01.15.11
pza
7.00
23.84
166.88
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
7.00
166.88
01.15.12
pza
6.00
12.99
77.94
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
6.00
77.94
01.15.13
pza
3.00
12.99
38.97
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
3.00
38.97
01.15.14
und
4.00
25.29
101.16
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
4.00
101.16
01.15.15
und
3.00
81.80
245.40
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
3.00
245.40
01.15.16
und
3.00
47.34
142.02
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
3.00
142.02
01.15.17
Prueba hidrulica
20.00
2.75
55.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
20.00
55.00
01.15.18
pza
1.00
146.02
146.02
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
146.02
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
10.00
61.70
41.22
01.16
01.16.01
01.16.01.01
01.16.02
19,792.38
INSTALACIONES ELECTRICAS
61.70
TRABAJOS PRELIMINARES
Trazo, niveles y replanteo preliminar
m2
10
6.17
61.70
888.83
MOVIMIENTO DE TIERRAS
01.16.02.01
m3
1.13
36.48
41.22
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
1.13
01.16.02.02
m3
1.13
60.71
68.60
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
1.13
68.60
01.16.02.03
m3
5.00
31.31
156.55
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
5.00
156.55
01.16.02.04
und
2.00
311.23
622.46
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
2.00
622.46
421.20
01.16.03
2,578.96
CONDUCTORES
01.16.03.01
30.00
14.04
421.20
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
30.00
01.16.03.02
170.00
4.13
702.10
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
170.00
702.10
01.16.03.03
240.00
4.83
1,159.20
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
240.00
1,159.20
01.16.03.04
und
1.00
296.46
296.46
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
296.46
01.16.04
5,219.82
ARTEFACTOS DE ILUMINACION
01.16.04.01
und
15.00
282.98
4,244.70
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
15.00
4,244.70
01.16.04.02
und
4.00
97.98
391.92
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
4.00
391.92
01.16.04.03
und
4.00
116.40
465.60
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
4.00
465.60
01.16.04.04
und
3.00
39.20
117.60
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
3.00
117.60
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
16.00
710.08
01.16.05
01.16.05.01
710.08
TOMACORRIENTES
Tomacorriente Doble c/puesta a tierra
und
16.00
44.38
710.08
01.16.06
INTERRUPTORES
595.64
01.16.06.01
Interruptor Simple
und
6.00
29.92
179.52
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
6.00
179.52
01.16.06.02
Interruptor Doble
und
8.00
35.92
287.36
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
8.00
287.36
01.16.06.03
Interruptor Triple
und
3.00
42.92
128.76
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
3.00
128.76
MUNICIPALIDAD PROVINCIAL
JORGE BASADRE
GERENCIA DE DESARROLLO
URBANO E INFRAESTRUCTURA
: INSTALACION DEL ALBERGUE PARA EL ADULTO MAYOR EN EL DISTRITO DE HUANUARA - CANDARAVE - TACNA"
UBICACIN
ITEM
01.16.07
01.16.07.01
01.16.08
DESCRIPCION DE LA ACTIVIDAD
UND
3/5/2012
3/31/2012
PRESUPUESTO
METR.
P.U.
ANTERIOR
Parcial
Metrado
INICIO OBRA
DIAS EJECUTADOS
: 27 DIAS CALENDARIO
ACTUAL
ACUMULADO
SALDO
Monto
Metrado
Monto
Metrado
Monto
Metrado
Monto
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
754.78
754.78
FECHA :
und
1.00
754.78
754.78
5,132.13
ACCESORIOS Y TUBERIAS
01.16.08.01
95.00
11.21
1,064.95
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
95.00
1,064.95
01.16.08.02
155.00
11.16
1,729.80
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
155.00
1,729.80
01.16.08.03
pto
26.00
34.92
907.92
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
26.00
907.92
01.16.08.04
pto
16.00
34.92
558.72
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
16.00
558.72
01.16.08.05
pto
17.00
51.22
870.74
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
17.00
870.74
01.16.09
1,346.70
01.16.09.01
pza
7.00
51.60
361.20
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
7.00
361.20
01.16.09.02
pza
2.00
66.60
133.20
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
2.00
133.20
01.16.09.03
pza
2.00
76.95
153.90
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
2.00
153.90
01.16.09.04
und
2.00
349.20
698.40
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
2.00
698.40
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
2,503.74
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
36,590.00
01.16.10
01.16.10.01
01.17
01.17.01
01.18
2,503.74
glb
1.00
2,503.74
Mobiliario
2,503.74
36,590.00
MOBILIARIO Y EQUIPAMIENTO
und
1.00 36,590.00
36,590.00
22,433.47
MURO DE CONTENCION
01.18.01
m3
19.11
63.84
1,219.98
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
19.11
1,219.98
01.18.02
m3
25.48
12.05
307.03
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
25.48
307.03
01.18.03
m3
18.59
31.31
582.05
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
18.59
582.05
01.18.04
m3
18.59
16.73
311.01
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
18.59
311.01
01.18.05
m2
18.85
36.97
696.88
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
18.85
696.88
01.18.06
m3
13.75
619.63
8,519.91
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
13.75
8,519.91
01.18.07
m2
57.20
69.81
3,993.13
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
57.20
3,993.13
01.18.08
kg
732.62
8.01
5,868.29
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
732.62
5,868.29
01.18.09
Curado de Estructuras
m2
68.64
3.53
242.30
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
68.64
242.30
01.18.10
18.00
3.59
64.62
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
18.00
64.62
01.18.11
m2
31.46
19.97
628.26
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
31.46
628.26
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
10,000.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
5,000.00
7,502.32
01.19
01.19.01
01.20
01.20.01
02
02.01
02.01.01
10,000.00
CAPACITACION
Capacitacion
glb
1.00 10,000.00
IMPACTO AMBIENTAL.
10,000.00
5,000.00
glb
1.00
5,000.00
5,000.00
203,211.03
75,602.06
33,344.14
COLUMNAS
02.01.01.01
m3
10.26
731.22
7,502.32
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
10.26
02.01.01.02
m3
130.39
58.82
7,669.54
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
130.39
7,669.54
02.01.01.03
kg
2,268.70
8.01
18,172.29
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
2,268.70
18,172.29
02.01.02
27,096.37
VIGAS
02.01.02.01
m3
9.74
585.86
5,706.28
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
9.74
5,706.28
02.01.02.02
m2
108.27
51.57
5,583.48
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
108.27
5,583.48
02.01.02.03
kg
1,212.42
8.01
9,711.48
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
1,212.42
9,711.48
02.01.02.04
Solaqueo de Estructuras
m2
238.65
25.54
6,095.12
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
238.65
6,095.12
02.01.03
COBERTURA LIGERA
15,161.55
02.01.03.01
und
14.00
239.01
3,346.14
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
14.00
3,346.14
02.01.03.02
Correas de Rollizo
106.60
50.76
5,411.02
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
106.60
5,411.02
02.01.03.03
m2
65.00
86.47
5,620.55
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
65.00
5,620.55
MUNICIPALIDAD PROVINCIAL
JORGE BASADRE
GERENCIA DE DESARROLLO
URBANO E INFRAESTRUCTURA
: INSTALACION DEL ALBERGUE PARA EL ADULTO MAYOR EN EL DISTRITO DE HUANUARA - CANDARAVE - TACNA"
UBICACIN
ITEM
DESCRIPCION DE LA ACTIVIDAD
02.01.03.04
02.02
MAMPOSTERIA DE LADRILLO
02.02.01
02.03
UND
m2
FECHA :
3/5/2012
3/31/2012
PRESUPUESTO
METR.
13.80
P.U.
56.80
ANTERIOR
Parcial
Metrado
783.84
INICIO OBRA
DIAS EJECUTADOS
: 27 DIAS CALENDARIO
ACTUAL
ACUMULADO
SALDO
Monto
Metrado
Monto
Metrado
Monto
Metrado
Monto
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
13.80
783.84
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
309.24
37,124.26
37,124.26
m2
309.24
120.05
37,124.26
20,150.74
02.03.01
m2
340.16
30.16
10,259.23
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
340.16
10,259.23
02.03.02
m2
340.16
25.25
8,589.04
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
340.16
8,589.04
02.03.03
116.50
11.18
1,302.47
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
116.50
1,302.47
5,434.00
02.04
28,510.56
02.04.01
Contrapiso de e=5cm
m2
152.00
35.75
5,434.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
152.00
02.04.02
m2
64.00
64.96
4,157.44
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
64.00
4,157.44
02.04.03
m2
88.00
214.99
18,919.12
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
88.00
18,919.12
02.05
2,630.47
ZOCALOS Y CONTRAZOCALOS
02.05.01
m2
32.80
34.25
1,123.40
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
32.80
1,123.40
02.05.02
m2
23.20
64.96
1,507.07
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
23.20
1,507.07
6,390.05
02.06
10,096.10
CARPINTERIA DE MADERA
02.06.01
m2
11.80
541.53
6,390.05
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
11.80
02.06.02
m2
3.96
243.08
962.60
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
3.96
962.60
02.06.03
m2
12.70
216.02
2,743.45
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
12.70
2,743.45
02.07
CARPINTERIA METALICA
02.07.01
m2
18.00
264.01
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
18.00
4,752.18
02.08
4,752.18
4,752.18
1,396.74
CERRAJERIA
02.08.01
pza
12.00
27.17
326.04
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
12.00
326.04
02.08.02
pza
9.00
19.17
172.53
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
9.00
172.53
02.08.03
und
6.00
26.62
159.72
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
6.00
159.72
02.08.04
pza
3.00
135.84
407.52
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
3.00
407.52
02.08.05
pza
3.00
110.31
330.93
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
3.00
330.93
02.09
7,597.45
PINTURA
02.09.01
m2
425.20
8.11
3,448.37
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
425.20
3,448.37
02.09.02
m2
425.20
6.60
2,806.32
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
425.20
2,806.32
02.09.03
m2
23.76
43.59
1,035.70
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
23.76
1,035.70
02.09.04
m2
7.92
38.77
307.06
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
7.92
307.06
02.10
412.26
02.10.01
pto
3.00
14.34
43.02
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
3.00
43.02
02.10.02
10.00
6.84
68.40
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
10.00
68.40
02.10.03
und
3.00
11.97
35.91
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
3.00
35.91
02.10.04
pza
2.00
24.02
48.04
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
2.00
48.04
02.10.05
und
9.00
12.67
114.03
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
9.00
114.03
02.10.06
und
6.00
12.56
75.36
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
6.00
75.36
02.10.07
Prueba hidrulica
10.00
2.75
27.50
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
10.00
27.50
02.11
970.39
DESAGUE Y VENTILACION
02.11.01
pza
1.00
155.84
155.84
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
155.84
02.11.02
und
1.00
278.68
278.68
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
278.68
02.11.03
6.00
12.68
76.08
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
6.00
76.08
02.11.04
12.00
7.11
85.32
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
12.00
85.32
02.11.05
pza
4.00
20.61
82.44
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
4.00
82.44
02.11.06
pza
1.00
23.84
23.84
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
23.84
02.11.07
pza
3.00
12.99
38.97
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
3.00
38.97
02.11.08
und
2.00
25.29
50.58
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
2.00
50.58
MUNICIPALIDAD PROVINCIAL
JORGE BASADRE
GERENCIA DE DESARROLLO
URBANO E INFRAESTRUCTURA
: INSTALACION DEL ALBERGUE PARA EL ADULTO MAYOR EN EL DISTRITO DE HUANUARA - CANDARAVE - TACNA"
UBICACIN
ITEM
DESCRIPCION DE LA ACTIVIDAD
02.11.09
02.11.10
02.11.11
Prueba hidrulica
02.12
02.12.01
UND
und
FECHA :
3/5/2012
3/31/2012
PRESUPUESTO
METR.
P.U.
ANTERIOR
Parcial
Metrado
INICIO OBRA
DIAS EJECUTADOS
: 27 DIAS CALENDARIO
ACTUAL
ACUMULADO
SALDO
Monto
Metrado
Monto
Metrado
Monto
Metrado
Monto
1.00
81.80
81.80
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
81.80
1.00
47.34
47.34
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
47.34
18.00
2.75
49.50
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
18.00
49.50
13,967.82
INSTALACIONES ELECTRICAS
1,689.10
CONDUCTORES
02.12.01.01
140.00
4.13
578.20
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
140.00
578.20
02.12.01.02
230.00
4.83
1,110.90
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
230.00
1,110.90
02.12.02
ARTEFACTOS DE ILUMINACION
4,222.74
02.12.02.01
und
13.00
282.98
3,678.74
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
13.00
3,678.74
02.12.02.02
und
4.00
116.40
465.60
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
4.00
465.60
02.12.02.03
und
2.00
39.20
78.40
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
2.00
78.40
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
10.00
443.80
02.12.03
02.12.03.01
443.80
TOMACORRIENTES
und
10.00
44.38
443.80
02.12.04
INTERRUPTORES
02.12.04.01
Interruptor Simple
und
6.00
29.92
179.52
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
6.00
179.52
02.12.04.02
Interruptor Triple
und
3.00
42.92
128.76
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
3.00
128.76
02.12.05
308.28
4,101.01
ACCESORIOS Y TUBERIAS
02.12.05.01
95.00
11.21
1,064.95
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
95.00
1,064.95
02.12.05.02
140.00
11.16
1,562.40
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
140.00
1,562.40
02.12.05.03
pto
19.00
34.92
663.48
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
19.00
663.48
02.12.05.04
pto
10.00
34.92
349.20
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
10.00
349.20
02.12.05.05
pto
9.00
51.22
460.98
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
9.00
460.98
02.12.06
699.15
02.12.06.01
pza
4.00
51.60
206.40
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
4.00
206.40
02.12.06.02
pza
1.00
66.60
66.60
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
66.60
02.12.06.03
pza
1.00
76.95
76.95
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
76.95
02.12.06.04
und
1.00
349.20
349.20
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
349.20
glb
1.00
2,503.74
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
2,503.74
02.12.07
02.12.07.01
2,503.74
COSTO DIRECTO
GASTOS GENERALES
COSTO DE OBRA
15.00%
2,503.74
627,602.37
94,140.36
S/. 721,742.73
0.00
0.00
S/. 0.00
0.00%
428,179.74
64,226.96
S/. 492,406.70
68.22%
428,179.74
64,226.96
S/. 492,406.70
68.22%
196,837.23
29,525.58
S/. 226,362.81
MUNICIPALIDAD PROVINCIAL
JORGE BASADRE
GERENCIA DE DESARROLLO
URBANO E INFRAESTRUCTURA
SALDO
%
-15900.00%
97.50%
96.67%
0.00%
99.52%
99.62%
99.81%
-1476.82%
-1598.15%
43.00%
100.00%
100.00%
-60.92%
100.00%
-74.46%
-337.32%
-1551.45%
-27.99%
22.78%
-260.02%
24.70%
77.47%
73.50%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
MUNICIPALIDAD PROVINCIAL
JORGE BASADRE
GERENCIA DE DESARROLLO
URBANO E INFRAESTRUCTURA
SALDO
%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
94.39%
-289.19%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
MUNICIPALIDAD PROVINCIAL
JORGE BASADRE
GERENCIA DE DESARROLLO
URBANO E INFRAESTRUCTURA
SALDO
%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
MUNICIPALIDAD PROVINCIAL
JORGE BASADRE
GERENCIA DE DESARROLLO
URBANO E INFRAESTRUCTURA
SALDO
%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
MUNICIPALIDAD PROVINCIAL
JORGE BASADRE
GERENCIA DE DESARROLLO
URBANO E INFRAESTRUCTURA
SALDO
%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
MUNICIPALIDAD PROVINCIAL
JORGE BASADRE
GERENCIA DE DESARROLLO
URBANO E INFRAESTRUCTURA
SALDO
%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
31.36%
: INSTALACION DEL ALBERGUE PARA EL ADULTO MAYOR EN EL DISTRITO DE HUANUARA - CANDARAVE - TACNA"
: ANEXO DE PIAPA, DISTRITO LOCUMNA, PROVINCIA JORGE BASADRE, REGION TACNA.
: ING. ANTONY RONCAL CAI
:60 DIAS CALENDARIO
N DE DIAS
N DE MES
MES
27
33
MES 01
MES 02
MARZO
ABRIL
PROGRAMADO
199,341.51
246,830.62
AVANCE FISICO
% PROGRAMADO
EJECUTADO
492,406.70
44.68%
0.00
55.32%
S/. 446,172.13
100.00%
% EJECUTADO
110.36%
0.00%
PROGRAMADO
199,341.51
246,830.62
110.36%
S/. 446,172.13
S/. 492,406.70
AVANCE FISICO
PROGRAMADO VS EJECUTADO
S/. 101,696.78
0.00
55.32%
MES 02
246,830.62
MES 02
110.36%
44.68%
MES 01
20.00%
40.00%
60.00%
80.00%
PORCENTAJE VALORIZADO
100.00%
120.00%
% EJECUTADO
% PROGRAMADO
PLAZO DE EJECUCION
PLAZO DE EJECUCION
100.00%
AVANCE FINANCIERO
PROGRAMADO VS EJECUTADO
0.00%
0.00%
AVANCE FINACIERO
% PROGRAMADO
EJECUTADO
101,696.78
44.68%
0.00
55.32%
101,696.78
199,341.51
MES 01
0.00
50,000.00
100,000.00
150,000.00
MONTO VALORIZADO
200,000.00
250,000.00
EJECUTADO
PROGRAMADO
AVANCE FINACIERO
% EJECUTADO
22.79%
0.00%
22.79%
246,830.62
EJECUTADO
PROGRAMADO
: INSTALACION DEL ALBERGUE PARA EL ADULTO MAYOR EN EL DISTRITO DE HUANUARA - CANDARAVE - TACNA"
: ANEXO DE PIAPA, DISTRITO LOCUMNA, PROVINCIA JORGE BASADRE, REGION TACNA.
: ING. ANTONY RONCAL CAI
:60 DIAS CALENDARIO
N DE DIAS
N DE MES
MES
27
33
INICIO
MES 01
MES 02
MARZO
ABRIL
S/. 446,172.13
ACUMULADO PROGRAMADO
MONTO
PORCENTAJE %
0
0
199,341.51
44.68%
446,172.13
100.00%
100.00%
S/. 492,406.70
ACUMULADO EJECUTADO
MONTO
0
492,406.70
0.00
110.36%
VALORIZACION
PROGRAMADO VS EJECUTADO
120.00%
110.36%
100.00%
% VALORIZADO ACUMULADO
OBRA
UBICACIN
RESIDENTE DE OBRA
PLAZO DE EJECUCION
100.00%
80.00%
60.00%
44.68%
40.00%
20.00%
0.00%
00
INICIO
MES 01
PLAZO DE EJECUCION
MES 02
ACUMULADO PROGRAMADO
ACUMULADO EJECUTADO
ACUMULADO EJECUTADO
PORCENTAJE %
0
110.36%
0.00%
Construccin de Plaza Cvica, en el Asentamiento Humano Piapa, Distrito de Locumba, Provincia Jorge
140547
S/. 388,358.36
01: reas Verdes , 02: Equipamiento y Mobiliario Urbano,03: Infraestructura
R.A. N 746-2011-A/MPJB - 14/12/2011
S/. 494,669.09
60 Dias Calendario
Ejecucin Presupuestaria Directa
Anexo Piapa, Distrito Locumba, Provincia Jorge Basadre
05 de febrero del 2012
03 de mayo del 2012
Ing. Jaime Villa Casapino
Ing. Antony Roncal Cai
Bach. Arq. Elmer Pablo Navarro Pari
Sr. Hugo Joel Tintaya Ramos
AVANCE FISICO
Presupuesto Base
N de Adicional
Resolucin que
Aprueba
Monto Aprobado
S/. 721,742.73
S/. 721,742.73
S/. 492,406.70
68.22%
Adicional N001
en tramite
S/. 66,914.99
Adicional n002
en tramite
S/. 14,566.48
S/. 81,481.47
Mes
Ao Anterior
0.00
0.00
0.00
N de Deductivos
Resolucin que
Aprueba
Monto Aprobado
Marzo
S/. 492,406.70
68.22%
44.68%
Deductivo N001
en tramite
S/. 34,027.18
Abril
Deductivo N002
Total Sumatoria de Deductivos
Mayo
S/. 34,027.18
Junio
492,406.70
68.22%
44.68%
AVANCE FINANCIERO
Presupuesto Base
S/. 721,742.73
S/. 101,696.78
N de Ampliacin de
plazo
Resolucin que
Aprueba
Das Aprobados
en tramite
30
30
Detalles
Montos (s/.)
Ao anterior
0.00
0.00
0.00
Marzo
S/. 101,696.78
22.79%
44.68%
Abril
Mayo
Junio
101,696.78
22.79%
44.68%
OBSERVACIONES
Se esta consignando en la ficha, los montos de los adicionales, deductivos y las ampliaciones de plazo, como informacion, pero no esta sumando en los cuadros de resumen de avance fisico - financiero
dichos expedientes estan en tramite para revision, los cuales han sido presentados el 04/04/2012 y el 09/04/2012
Se indica que los retrazos son por causa del retiro y reubicacion de bienes de otra obra que se encontraban en el area de influencia del proyecto, asi mismo se ha tenido que replantear todos los niveles, y
que estos estaban referenciados erroneamente e cuando se proyectaba la via de transito vehicular las veredas perimetrales quedaban 0.50 por encima y en algunos casos 0.20 por debajo de esta.
Otra de las razones del retrazo es que a causa de este replanteao se ha presentado mayores metrados en movimiento de tierras, lo que ha generado mas tiempo en ejecutar estar partidas.
Tambien se ha tenido que deducir partidas que tenian rendimientos demasiado altos para la zona y se realizado partidas nuevas acorde al rendimiento de la zona.
2012
a, Provincia Jorge
DEDUCTIVOS
Causales
Partidas Nuevas
Mayores Metrados
S/. 81,481.47
Causales
S/. 34,027.18
Causales
Por Adicionales
30
Observaciones
en tramite
en tramite