Anda di halaman 1dari 208

Chapter 1 Overview of Hardware Installation ............................................... 1.1 Introduction to the Chapter ..................................................................... 1.2 MSOFTX3000 Hardware System ...........................................................

1.2.1 OSTA Platform ............................................................................... 1.2.2 Overall Hardware Structure ........................................................... 1.3 Procedure of Hardware Installation ........................................................ 1.4 Prerequisites .......................................................................................... Chapter 2 Installation Preparations ............................................................... 2.1 Introduction to the Chapter ..................................................................... 2.2 Engineering Documents ......................................................................... 2.3 Tools and Instruments ............................................................................ 2.4 Installation Conditions ............................................................................ 2.4.1 Construction Conditions ................................................................. 2.4.2 Environment Conditions ................................................................. 2.4.3 Power Supply ................................................................................. 2.4.4 Grounding Conditions .................................................................... 2.4.5 Auxiliary Facilities .......................................................................... 2.4.6 Other Facilities ............................................................................... 2.5 Unpacking .............................................................................................. 2.5.1 Unpacking Requirements............................................................... 2.5.2 Unpacking Wooden Cases ............................................................ 2.5.3 Unpacking Cartons ........................................................................ 2.5.4 Unpacking Boards .......................................................................... Chapter 3 Cabinet Installation ........................................................................ 3.1 Introduction to the Chapter ..................................................................... 3.2 Installing N68-22 Cabinets on the Antistatic Floor ................................. 3.2.1 Introduction to N800 Series Supports ............................................ 3.2.2 Installation Procedure .................................................................... 3.2.3 Determining the Installation Position of Cabinets .......................... 3.2.4 Determining the Installation Position of Supports .......................... 3.2.5 Installing Supports ......................................................................... 3.2.6 Fixing Cabinets .............................................................................. 3.2.7 Testing the Insulation ..................................................................... 3.2.8 Connecting Multiple Cabinets ........................................................ 3.2.9 Restoring the Antistatic Floor ......................................................... 3.3 Installing N68-22 Cabinets on the Cement Floor ................................... 3.3.1 Overview ........................................................................................ 3.3.2 Installation Procedure .................................................................... 3.3.3 Determining the Installation Position of Cabinets ..........................

1-1 1-1 1-1 1-1 1-2 1-3 1-5 2-1 2-1 2-1 2-2 2-3 2-3 2-4 2-4 2-4 2-5 2-5 2-5 2-5 2-6 2-8 2-9 3-1 3-1 3-1 3-2 3-6 3-6 3-7 3-11 3-15 3-17 3-18 3-19 3-21 3-21 3-21 3-22

3.3.4 Fixing Cabinets .............................................................................. 3.3.5 Testing the Insulation ..................................................................... 3.3.6 Connecting Multiple Cabinets ........................................................ Chapter 4 Internal Component Installation ................................................... 4.1 Introduction to the Chapter ..................................................................... 4.2 Precautions ............................................................................................ 4.3 Installation Procedure ............................................................................. 4.3.1 Installing iGWB and BAM Servers ................................................. 4.3.2 Installing Hard Disk Array .............................................................. 4.3.3 Installing LAN Switches: ................................................................ 4.3.4 Installing KVMSs: ........................................................................... 4.3.5 Installing Fan Boxes in Service Subracks ...................................... 4.3.6 Installing Boards in Service Subracks ............................................ Chapter 5 Installation of Protection Ground Cables and Power Cables .... 5.1 Introduction to the Chapter ..................................................................... 5.2 Introduction to Power Supply System and Protection Grounding System ......................................................................................................... 5.2.1 Introduction to Power Supply System ............................................ 5.2.2 Introduction to Protection Grounding System ................................ 5.3 Installation Principles.............................................................................. 5.4 Installation Procedure ............................................................................. 5.4.1 Installing PGND Cables Within Cabinets ....................................... 5.4.2 Installing Power Cables Within Cabinets ....................................... 5.4.3 Installing PGND Cables Between Cabinets ................................... 5.4.4 Installing PGND Cables and Power Cables Between DC Distribution Cabinets and MSOFTX3000 Cabinets................................. 5.4.5 Installing Power Bus Cables Between DC Distribution Cabinets and DC Switchboards ............................................................................. Chapter 6 Signal Cable Installation ................................................................ 6.1 Introduction to the Chapter ..................................................................... 6.2 Introduction to Signal Cables ................................................................. 6.2.1 Signal Cable Types ........................................................................ 6.2.2 Connection of Internal Signal Cables............................................. 6.3 Installation Requirements ....................................................................... 6.3.1 Cabling Requirements ................................................................... 6.3.2 Cabling Modes ............................................................................... 6.4 Installing Internal Signal Cables ............................................................. 6.4.1 Installation Procedure .................................................................... 6.4.2 Installing Straight Through Cables Between LAN Switches ..........

3-26 3-27 3-28 4-1 4-1 4-1 4-1 4-5 4-6 4-6 4-6 4-7 4-7 5-1 5-1 5-1 5-1 5-4 5-5 5-5 5-6 5-8 5-12 5-12 5-17 6-1 6-1 6-1 6-1 6-1 6-5 6-5 6-6 6-8 6-8 6-9

6.4.3 Installing Straight Through Cables Between LAN Switches and iGWB/ BAM Servers ............................................................................... 6.4.4 Installing Straight Through Cables Between LAN Switches and WHSCs ................................................................................................... 6.4.5 Installing Straight Through Cables Between WHSCs and WSIUs ..................................................................................................... 6.4.6 Installing Serial Cables Between iGWB Servers ............................ 6.4.7 Installing Data Cables Between iGWB and Hard Disk Array ......... 6.4.8 Installing Cables Between Servers and KVMS .............................. 6.4.9 Installing PDB Monitoring Serial Cablesserial cable ...................... 6.4.10 Installing Internal Clock Cables .................................................... 6.5 Installing External Signal Cables ............................................................ 6.5.1 Installation Procedure .................................................................... 6.5.2 Installing Clock Cables Between the MSOFTX3000 and BITS Devices ................................................................................................... 6.5.3 Installing Trunk Cables Between the MSOFTX3000 and DDF ...... 6.5.4 Installing External Ethernet Cables ................................................ 6.5.5 Installing Optical Fibers.................................................................. Chapter 7 Cabinet Fittings Installation .......................................................... 7.1 Introduction to the Chapter ..................................................................... 7.2 Cabinet Door Assembly .......................................................................... 7.3 Installation Procedure ............................................................................. 7.4 Installing Side Panels ............................................................................. 7.5 Installing Front and Back Doors ............................................................. 7.6 Installing PGND Cables for Cabinet Doors ............................................ Chapter 8 Peripheral Installation .................................................................... 8.1 Introduction to the Chapter ..................................................................... 8.2 Installation Procedure ............................................................................. 8.3 Installing Terminal Devices .................................................................... 8.4 Installing Alarm Devices ......................................................................... 8.5 Routing Cables for Terminal Devices ..................................................... 8.6 Grounding Requirements of Terminal Devices ...................................... Chapter 9 Hardware Installation Checks ....................................................... 9.1 Introduction to the Chapter ..................................................................... 9.2 Overall Check ......................................................................................... 9.2.1 Checking Cabinets ......................................................................... 9.2.2 Checking Cables ............................................................................ 9.2.3 Checking Connectors and Sockets ................................................ 9.2.4 Checking Labels and Equipment Room Environment ................... 9.3 Electrical Performance Check ................................................................

6-10 6-12 6-13 6-14 6-15 6-16 6-16 6-17 6-19 6-19 6-19 6-20 6-22 6-22 7-1 7-1 7-1 7-3 7-3 7-4 7-6 8-1 8-1 8-1 8-1 8-3 8-4 8-4 9-1 9-1 9-1 9-1 9-1 9-2 9-2 9-2

9.3.1 Checking Power Supply to Cabinets .............................................. 9.3.2 Checking Power Supply to Subracks ............................................. 9.3.3 Checking Working Statuses of Trial Boards .................................. Appendix A Cabling Rack Installation ........................................................... A.1 Introduction to Cabling Rack .................................................................. A.1.1 Specifications ................................................................................ A.1.2 Components .................................................................................. A.2 Installing Process ................................................................................... A.3 Installing Indoor Cabling Rack ............................................................... A.3.1 Ceiling Installing or Floor Installing ................................................ A.3.2 Wall Installing ................................................................................ A.3.3 Over-Cabinet Installing .................................................................. A.4 Connecting Cabling Ladders.................................................................. A.4.1 Assembling Cabling Ladders ......................................................... A.4.2 Turning Cabling Ladder at the Same Level ................................... A.4.3 Turning Cabling Ladder at Different Levels ................................... A.4.4 Connecting Cabling Ladder to the Wall ......................................... A.4.5 Jointing Cabling Ladders ............................................................... A.5 Installing Cabling Trough (Optional) ...................................................... A.5.1 Overview ........................................................................................ A.5.2 Connecting Cabling Troughs ......................................................... A.5.3 Installing Cabling Trough on 200 mm or 400 mm Wide Cabling Ladder ..................................................................................................... A.5.4 Installing Cabling Trough on 600 mm Wide Cabling Ladder ......... A.5.5 Installing Cabling Trough Obliquely ............................................... A.6 Installing Outdoor Cabling Rack ............................................................ A.6.1 Wall Installing ................................................................................ A.6.2 Ground Installing ........................................................................... A.7 Installing Accessories ............................................................................ A.7.1 Overview ........................................................................................ A.7.2 Installing Cable Manager ............................................................... A.7.3 Installing Trough Rim, End Cover and Baffle Ring ........................ Appendix B Core Area Calculation for Power Bus Cables .......................... B.1 Introduction to the Appendix .................................................................. B.2 Computing Core Areas of Power Bus Cables ........................................ B.3 Computing Core Areas of Battery Bus Cables....................................... B.4 Giving an Example ................................................................................. Appendix C Assembly of Cable Connectors ................................................. C.1 Introduction to the Appendix ..................................................................

9-2 9-3 9-3 A-1 A-1 A-1 A-1 A-3 A-4 A-4 A-7 A-9 A-10 A-10 A-11 A-12 A-13 A-13 A-15 A-15 A-15 A-16 A-16 A-17 A-19 A-19 A-20 A-21 A-21 A-22 A-23 B-1 B-1 B-1 B-1 B-2 C-1 C-1

C.2 Mounting Power Cable Connectors ....................................................... C.2.1 Using and Maintaining Crimping Tools.......................................... C.2.2 Mounting Naked Crimping Connectors ......................................... C.3 Mounting RJ-45 Connectors .................................................................. C.4 Mounting SMB Connectors .................................................................... Appendix D Facture of Cable Labels ............................................................. D.1 Introduction to the Appendix .................................................................. D.2 Introduction to Labels ............................................................................ D.2.1 Label Materials and Features ........................................................ D.2.2 Label Types and Structures .......................................................... D.3 Precautions ............................................................................................ D.4 Facture Procedure ................................................................................. D.5 Deciding Label Contents........................................................................ D.5.1 Labels for External Cables of Alarm Box....................................... D.5.2 Labels for Ethernet Cables ............................................................ D.5.3 Labels for Trunk Cables ................................................................ D.5.4 Labels for DC Cables .................................................................... D.5.5 Labels for AC Cables .................................................................... D.5.6 Labels for Optical Fibers ............................................................... D.6 Deciding Information Places on Labels ................................................. D.7 Printing or Writing Labels ....................................................................... D.7.1 Printing Labels ............................................................................... D.7.2 Writing Labels ................................................................................ D.8 Sticking or Binding Labels ..................................................................... D.9 Checking Labels .................................................................................... Appendix E Environment Requirements for Equipment Operation............ E.1 Observed Standards .............................................................................. E.2 Requirements for Equipment Room ....................................................... E.2.1 Site Requirements ......................................................................... E.2.2 Equipment Room Composition ...................................................... E.2.3 Building Requirements .................................................................. E.2.4 Humidity and Temperature Requirements ..................................... E.2.5 Air Cleanness Requirements ......................................................... E.2.6 Erosive Gas Condition Requirements ........................................... E.2.7 Electromagnetic Requirements ..................................................... E.2.8 ESD-Preventive Requirements...................................................... E.2.9 Lightning Protection Requirements ............................................... E.3 Requirements for Power Supply ............................................................ E.3.1 Requirements for AC Power Supply ..............................................

C-1 C-1 C-3 C-8 C-13 D-1 D-1 D-1 D-1 D-2 D-3 D-3 D-4 D-4 D-5 D-7 D-10 D-11 D-12 D-15 D-16 D-16 D-17 D-18 D-20 E-1 E-1 E-1 E-1 E-2 E-3 E-4 E-5 E-5 E-6 E-7 E-7 E-9 E-9

E.3.2 Suggestions on AC Power Supply ................................................. E.3.3 Requirements for DC Power Supply .............................................. E.3.4 Suggestions on DC Power Supply ................................................ Index .................................................................................................................

E-10 E-11 E-12

HUAWEI

HUAWEI MSOFTX3000 Mobile SoftSwitch Center Installation Manual Hardware Installation V100R003

Huawei Technologies Proprietary

HUAWEI MSOFTX3000 Mobile SoftSwitch Center Installation Manual


Volume Manual Version Product Version BOM Hardware Installation T2-030408-20060425-C-3.05 V100R003 31042108

Huawei Technologies Co., Ltd. provides customers with comprehensive technical support and service. Please feel free to contact our local office or company headquarters.

Huawei Technologies Co., Ltd.


Address: Administration Building, Huawei Technologies Co., Ltd., Bantian, Longgang District, Shenzhen, P. R. China Postal Code: 518129 Website: http://www.huawei.com Email: support@huawei.com

Huawei Technologies Proprietary

Copyright 2006 Huawei Technologies Co., Ltd.

All Rights Reserved


No part of this manual may be reproduced or transmitted in any form or by any means without prior written consent of Huawei Technologies Co., Ltd.

Trademarks

, HUAWEI, C&C08, EAST8000, HONET,

, ViewPoint, INtess, ETS, DMC,

TELLIN, InfoLink, Netkey, Quidway, SYNLOCK, Radium, M900/M1800, TELESIGHT, Quidview, Musa, Airbridge, Tellwin, Inmedia, VRP, DOPRA, iTELLIN, HUAWEI OptiX, C&C08 iNET, NETENGINE, OptiX, iSite, U-SYS, iMUSE, OpenEye, Lansway, SmartAX, infoX, TopEng are trademarks of Huawei Technologies Co., Ltd. All other trademarks mentioned in this manual are the property of their respective holders.

Notice
The information in this manual is subject to change without notice. Every effort has been made in the preparation of this manual to ensure accuracy of the contents, but all statements, information, and recommendations in this manual do not constitute the warranty of any kind, express or implied.

Huawei Technologies Proprietary

About This Manual


Release Notes
This manual applies to HUAWEI MSOFTX3000 Mobile SoftSwitch Center V100R003.

Organization
The manual presents the procedure of installing hardware components of the HUAWEI MSOFTX3000 Mobile SoftSwitch Center (hereinafter referred to as the MSOFTX3000), attentions during the installation and hardware installation check. There are nine chapters and five appendixes in the manual. Chapter 1 Overview of Hardware Installation introduces the procedure of installing MSOFTX3000 hardware. Chapter 2 Installation Preparations describes preparations for hardware installation, including preparing installation technical documents, tools, and instruments, as well as checking equipment room conditions. Chapter 3 Cabinet Installation details how to locate, adjust, and fix N68-22 cabinets, and how to combine adjacent cabinets. Chapter 4 Internal Component Installation presents the precautions and methods of installing iGWB servers, BAM servers, LAN Switches, KVMS, and boards in basic and extension subracks. Chapter 5 Installation of Protection Ground Cables and Power Cables describes the connection between DC switchboards, DC distribution cabinets, and power distribution boxes in cabinets, and the cable-routing requirements, as well as protection ground requirements. Chapter 6 Signal Cable Installation describes internal and external signal cables from such aspects as their types, appearances, connection, cable-routing methods, and label sticking methods. Chapter 7 Cabinet Fittings Installation presents the methods and procedures of installing side panels, and front and back doors. Chapter 8 Peripheral Installation describes the methods of installing terminal devices, alarm devices, and auxiliary cables. Chapter 9 Hardware Installation Checks installation. Appendix A Cabling Rack Installation introduces the parts of cable rack and the specific installation methods.
Huawei Technologies Proprietary

introduces overall checks and

electrical checks on the whole hardware, subracks, and boards after hardware

Appendix B Core Area Calculation for Power Bus Cables briefly introduces the method of computing core areas of power bus cables. Appendix C Assembly of Cable Connectors presents the methods of mounting power cable connectors, RJ-45 connectors, and SMB connectors. Appendix D Facture of Cable Labels details materials and specifications of engineering labels on cables, as well as label filling and sticking requirements. Appendix E Environment Requirements for Equipment Operation describes the requirements on the operating environment and power supply system of the equipment.

Intended Audience
The manual is intended for the following audience: Hardware installation engineers Engineering technicians

Conventions
The manual uses the following conventions:

I. General conventions
Convention Arial Arial Narrow Boldface Courier New Description Normal paragraphs are in Arial. Warnings, Cautions, Notes and Tips are in Arial Narrow. Headings are in Boldface. Terminal Display is in Courier New.

II. Symbols
Eye-catching symbols are also used in the manual to highlight the points worthy of special attention during the operation. They are defined as follows:

Caution, Warning, Danger: Means reader be extremely careful during the operation. Note, Means a complementary description.

Huawei Technologies Proprietary

Environmental Protection
This product has been designed to comply with the requirements on environmental protection. For the proper storage, use and disposal of this product, national laws and regulations must be observed.

Huawei Technologies Proprietary

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Table of Contents

Table of Contents
Chapter 1 Overview of Hardware Installation............................................................................. 1-1 1.1 Introduction to the Chapter ................................................................................................ 1-1 1.2 MSOFTX3000 Hardware System ...................................................................................... 1-1 1.2.1 OSTA Platform ........................................................................................................ 1-1 1.2.2 Overall Hardware Structure..................................................................................... 1-2 1.3 Procedure of Hardware Installation ................................................................................... 1-3 1.4 Prerequisites ...................................................................................................................... 1-5 Chapter 2 Installation Preparations............................................................................................. 2-1 2.1 Introduction to the Chapter ................................................................................................ 2-1 2.2 Engineering Documents .................................................................................................... 2-1 2.3 Tools and Instruments ....................................................................................................... 2-2 2.4 Installation Conditions........................................................................................................ 2-3 2.4.1 Construction Conditions .......................................................................................... 2-3 2.4.2 Environment Conditions .......................................................................................... 2-4 2.4.3 Power Supply .......................................................................................................... 2-4 2.4.4 Grounding Conditions ............................................................................................. 2-4 2.4.5 Auxiliary Facilities.................................................................................................... 2-5 2.4.6 Other Facilities ........................................................................................................ 2-5 2.5 Unpacking .......................................................................................................................... 2-5 2.5.1 Unpacking Requirements........................................................................................ 2-5 2.5.2 Unpacking Wooden Cases...................................................................................... 2-6 2.5.3 Unpacking Cartons.................................................................................................. 2-8 2.5.4 Unpacking Boards................................................................................................... 2-9 Chapter 3 Cabinet Installation...................................................................................................... 3-1 3.1 Introduction to the Chapter ................................................................................................ 3-1 3.2 Installing N68-22 Cabinets on the Antistatic Floor............................................................. 3-1 3.2.1 Introduction to N800 Series Supports ..................................................................... 3-2 3.2.2 Installation Procedure ............................................................................................. 3-6 3.2.3 Determining the Installation Position of Cabinets ................................................... 3-6 3.2.4 Determining the Installation Position of Supports ................................................... 3-7 3.2.5 Installing Supports................................................................................................. 3-11 3.2.6 Fixing Cabinets...................................................................................................... 3-15 3.2.7 Testing the Insulation ............................................................................................ 3-17 3.2.8 Connecting Multiple Cabinets ............................................................................... 3-18 3.2.9 Restoring the Antistatic Floor ................................................................................ 3-19 3.3 Installing N68-22 Cabinets on the Cement Floor............................................................. 3-21 3.3.1 Overview ............................................................................................................... 3-21
Huawei Technologies Proprietary i

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Table of Contents

3.3.2 Installation Procedure ........................................................................................... 3-21 3.3.3 Determining the Installation Position of Cabinets ................................................. 3-22 3.3.4 Fixing Cabinets...................................................................................................... 3-26 3.3.5 Testing the Insulation ............................................................................................ 3-27 3.3.6 Connecting Multiple Cabinets ............................................................................... 3-28 Chapter 4 Internal Component Installation................................................................................. 4-1 4.1 Introduction to the Chapter ................................................................................................ 4-1 4.2 Precautions ........................................................................................................................ 4-1 4.3 Installation Procedure ........................................................................................................ 4-1 4.3.1 Installing iGWB and BAM Servers .......................................................................... 4-5 4.3.2 Installing Hard Disk Array........................................................................................ 4-6 4.3.3 Installing LAN Switches:.......................................................................................... 4-6 4.3.4 Installing KVMSs: .................................................................................................... 4-6 4.3.5 Installing Fan Boxes in Service Subracks............................................................... 4-7 4.3.6 Installing Boards in Service Subracks..................................................................... 4-7 Chapter 5 Installation of Protection Ground Cables and Power Cables ................................. 5-1 5.1 Introduction to the Chapter ................................................................................................ 5-1 5.2 Introduction to Power Supply System and Protection Grounding System ........................ 5-1 5.2.1 Introduction to Power Supply System ..................................................................... 5-1 5.2.2 Introduction to Protection Grounding System ......................................................... 5-4 5.3 Installation Principles ......................................................................................................... 5-5 5.4 Installation Procedure ........................................................................................................ 5-5 5.4.1 Installing PGND Cables Within Cabinets ................................................................ 5-6 5.4.2 Installing Power Cables Within Cabinets ................................................................ 5-8 5.4.3 Installing PGND Cables Between Cabinets .......................................................... 5-12 5.4.4 Installing PGND Cables and Power Cables Between DC Distribution Cabinets and MSOFTX3000 Cabinets ................................................................................................. 5-12 5.4.5 Installing Power Bus Cables Between DC Distribution Cabinets and DC Switchboards.................................................................................................................. 5-17 Chapter 6 Signal Cable Installation ............................................................................................. 6-1 6.1 Introduction to the Chapter ................................................................................................ 6-1 6.2 Introduction to Signal Cables............................................................................................. 6-1 6.2.1 Signal Cable Types ................................................................................................. 6-1 6.2.2 Connection of Internal Signal Cables...................................................................... 6-1 6.3 Installation Requirements .................................................................................................. 6-5 6.3.1 Cabling Requirements............................................................................................. 6-5 6.3.2 Cabling Modes ........................................................................................................ 6-6 6.4 Installing Internal Signal Cables ........................................................................................ 6-8 6.4.1 Installation Procedure ............................................................................................. 6-8 6.4.2 Installing Straight Through Cables Between LAN Switches ................................... 6-9 6.4.3 Installing Straight Through Cables Between LAN Switches and iGWB/BAM Servers6-10 6.4.4 Installing Straight Through Cables Between LAN Switches and WHSCs ............ 6-12
Huawei Technologies Proprietary ii

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Table of Contents

6.4.5 Installing Straight Through Cables Between WHSCs and WSIUs........................ 6-13 6.4.6 Installing Serial Cables Between iGWB Servers................................................... 6-14 6.4.7 Installing Data Cables Between iGWB and Hard Disk Array ................................ 6-15 6.4.8 Installing Cables Between Servers and KVMS ..................................................... 6-16 6.4.9 Installing PDB Monitoring Serial Cablesserial cable ............................................. 6-16 6.4.10 Installing Internal Clock Cables........................................................................... 6-17 6.5 Installing External Signal Cables ..................................................................................... 6-19 6.5.1 Installation Procedure ........................................................................................... 6-19 6.5.2 Installing Clock Cables Between the MSOFTX3000 and BITS Devices............... 6-19 6.5.3 Installing Trunk Cables Between the MSOFTX3000 and DDF............................. 6-20 6.5.4 Installing External Ethernet Cables ....................................................................... 6-22 6.5.5 Installing Optical Fibers......................................................................................... 6-22 Chapter 7 Cabinet Fittings Installation........................................................................................ 7-1 7.1 Introduction to the Chapter ................................................................................................ 7-1 7.2 Cabinet Door Assembly ..................................................................................................... 7-1 7.3 Installation Procedure ........................................................................................................ 7-3 7.4 Installing Side Panels ........................................................................................................ 7-3 7.5 Installing Front and Back Doors......................................................................................... 7-4 7.6 Installing PGND Cables for Cabinet Doors........................................................................ 7-6 Chapter 8 Peripheral Installation ................................................................................................. 8-1 8.1 Introduction to the Chapter ................................................................................................ 8-1 8.2 Installation Procedure ........................................................................................................ 8-1 8.3 Installing Terminal Devices................................................................................................ 8-1 8.4 Installing Alarm Devices .................................................................................................... 8-3 8.5 Routing Cables for Terminal Devices ................................................................................ 8-4 8.6 Grounding Requirements of Terminal Devices.................................................................. 8-4 Chapter 9 Hardware Installation Checks .................................................................................... 9-1 9.1 Introduction to the Chapter ................................................................................................ 9-1 9.2 Overall Check .................................................................................................................... 9-1 9.2.1 Checking Cabinets .................................................................................................. 9-1 9.2.2 Checking Cables ..................................................................................................... 9-1 9.2.3 Checking Connectors and Sockets ......................................................................... 9-2 9.2.4 Checking Labels and Equipment Room Environment ............................................ 9-2 9.3 Electrical Performance Check ........................................................................................... 9-2 9.3.1 Checking Power Supply to Cabinets....................................................................... 9-2 9.3.2 Checking Power Supply to Subracks...................................................................... 9-3 9.3.3 Checking Working Statuses of Trial Boards ........................................................... 9-3 Appendix A Cabling Rack Installation.........................................................................................A-1 A.1 Introduction to Cabling Rack .............................................................................................A-1 A.1.1 Specifications..........................................................................................................A-1 A.1.2 Components............................................................................................................A-1

Huawei Technologies Proprietary iii

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Table of Contents

A.2 Installing Process ..............................................................................................................A-3 A.3 Installing Indoor Cabling Rack...........................................................................................A-4 A.3.1 Ceiling Installing or Floor Installing .........................................................................A-4 A.3.2 Wall Installing..........................................................................................................A-7 A.3.3 Over-Cabinet Installing ...........................................................................................A-9 A.4 Connecting Cabling Ladders ...........................................................................................A-10 A.4.1 Assembling Cabling Ladders ................................................................................A-10 A.4.2 Turning Cabling Ladder at the Same Level ..........................................................A-11 A.4.3 Turning Cabling Ladder at Different Levels ..........................................................A-12 A.4.4 Connecting Cabling Ladder to the Wall ................................................................A-13 A.4.5 Jointing Cabling Ladders ......................................................................................A-13 A.5 Installing Cabling Trough (Optional)................................................................................A-15 A.5.1 Overview ...............................................................................................................A-15 A.5.2 Connecting Cabling Troughs ................................................................................A-15 A.5.3 Installing Cabling Trough on 200 mm or 400 mm Wide Cabling Ladder..............A-16 A.5.4 Installing Cabling Trough on 600 mm Wide Cabling Ladder ................................A-16 A.5.5 Installing Cabling Trough Obliquely ......................................................................A-17 A.6 Installing Outdoor Cabling Rack......................................................................................A-19 A.6.1 Wall Installing........................................................................................................A-19 A.6.2 Ground Installing...................................................................................................A-20 A.7 Installing Accessories......................................................................................................A-21 A.7.1 Overview ...............................................................................................................A-21 A.7.2 Installing Cable Manager ......................................................................................A-22 A.7.3 Installing Trough Rim, End Cover and Baffle Ring ...............................................A-23 Appendix B Core Area Calculation for Power Bus Cables .......................................................B-1 B.1 Introduction to the Appendix..............................................................................................B-1 B.2 Computing Core Areas of Power Bus Cables ...................................................................B-1 B.3 Computing Core Areas of Battery Bus Cables..................................................................B-1 B.4 Giving an Example ............................................................................................................B-2 Appendix C Assembly of Cable Connectors ..............................................................................C-1 C.1 Introduction to the Appendix .............................................................................................C-1 C.2 Mounting Power Cable Connectors ..................................................................................C-1 C.2.1 Using and Maintaining Crimping Tools...................................................................C-1 C.2.2 Mounting Naked Crimping Connectors ..................................................................C-3 C.3 Mounting RJ-45 Connectors .............................................................................................C-8 C.4 Mounting SMB Connectors .............................................................................................C-13 Appendix D Facture of Cable Labels...........................................................................................D-1 D.1 Introduction to the Appendix .............................................................................................D-1 D.2 Introduction to Labels........................................................................................................D-1 D.2.1 Label Materials and Features .................................................................................D-1 D.2.2 Label Types and Structures....................................................................................D-2 D.3 Precautions .......................................................................................................................D-3
Huawei Technologies Proprietary iv

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Table of Contents

D.4 Facture Procedure ............................................................................................................D-3 D.5 Deciding Label Contents ...................................................................................................D-4 D.5.1 Labels for External Cables of Alarm Box................................................................D-4 D.5.2 Labels for Ethernet Cables .....................................................................................D-5 D.5.3 Labels for Trunk Cables .........................................................................................D-7 D.5.4 Labels for DC Cables ...........................................................................................D-10 D.5.5 Labels for AC Cables............................................................................................D-11 D.5.6 Labels for Optical Fibers.......................................................................................D-12 D.6 Deciding Information Places on Labels...........................................................................D-15 D.7 Printing or Writing Labels ................................................................................................D-16 D.7.1 Printing Labels ......................................................................................................D-16 D.7.2 Writing Labels .......................................................................................................D-17 D.8 Sticking or Binding Labels...............................................................................................D-18 D.9 Checking Labels..............................................................................................................D-20 Appendix E Environment Requirements for Equipment Operation.........................................E-1 E.1 Observed Standards .........................................................................................................E-1 E.2 Requirements for Equipment Room ..................................................................................E-1 E.2.1 Site Requirements ..................................................................................................E-1 E.2.2 Equipment Room Composition ...............................................................................E-2 E.2.3 Building Requirements............................................................................................E-3 E.2.4 Humidity and Temperature Requirements..............................................................E-4 E.2.5 Air Cleanness Requirements ..................................................................................E-5 E.2.6 Erosive Gas Condition Requirements ....................................................................E-5 E.2.7 Electromagnetic Requirements...............................................................................E-6 E.2.8 ESD-Preventive Requirements...............................................................................E-7 E.2.9 Lightning Protection Requirements.........................................................................E-7 E.3 Requirements for Power Supply........................................................................................E-9 E.3.1 Requirements for AC Power Supply .......................................................................E-9 E.3.2 Suggestions on AC Power Supply........................................................................E-10 E.3.3 Requirements for DC Power Supply.....................................................................E-11 E.3.4 Suggestions on DC Power Supply........................................................................E-12 Index ................................................................................................................................................ i-1

Huawei Technologies Proprietary v

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 1 Overview of Hardware Installation

Chapter 1 Overview of Hardware Installation


1.1 Introduction to the Chapter
Normally, equipment installation sequentially involves the three stages: 1) 2) 3) Hardware installation Software installation System commissioning

This manual tells about the basic procedure of MSOFTX3000 hardware installation.

1.2 MSOFTX3000 Hardware System


1.2.1 OSTA Platform
The MSOFTX3000 adopts open standards telecom architecture (OSTA) platform as its hardware platform. Provided with the following features, the platform is applicable for switching and transmitting variable-length packets of SoftSwitch equipment: Availability of both shared resource and Ethernet buses Good versatility High reliability The OSTA platform uses the structure of a standard subrack that is 19 inches wide and 9 U (1 U = 1.75 inches) high. Boards are inserted into a subrack symmetrically from the front and rear of the subrack, as shown in Figure 1-1.
(2) (3) (2) (1)

(4)

(5)

(6)

(7)
(1) Power boards (4) Back boards (7) Service boards

(8)
(2) Interface boards (5) Backplane (8) System management boards

(7)

(9)

(1)

(3) Ethernet communication boards (6) Front boards (9) Alarm board

Figure 1-1 Overall structure of a service subrack Table 1-1 lists front and back boards in a service subrack.
Huawei Technologies Proprietary 1-1

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 1 Overview of Hardware Installation

Table 1-1 Front and back boards in a service subrack Front board Service board System management board Alarm board Power supply board Back board Interface board Ethernet communication board Power supply board

The symmetric installation mode separates the functions of front boards and back boards, and simplifies board design. In this way, the system benefits a lot: The hardware equipment is simpler. The system is more reliable. Subracks are more versatile. System configuration is more flexible. In the MSOFTX3000, all subracks are versatile in terms of hardware. Each subrack is designed with 21 standard board slots. The configuration of system management boards, Ethernet communication boards, alarm boards, and power boards are fixed. They occupy nine slots. Service boards and interface boards hold the rest 12 slots.

1.2.2 Overall Hardware Structure


Physically, the MSOFTX3000 consists of: Service subracks Core LAN Switches Backend administration module (BAM) iGateway Bill (iGWB) Processing services and managing resources, service subracks compose the host of MSOFTX3000. The BAM and iGWB compose the background, which operates and maintains the equipment, and manages bills. LAN Switches connect the host and background, and provide channels for their communication. Figure 1-2 shows the physical structure of MSOFTX3000.

Huawei Technologies Proprietary 1-2

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 1 Overview of Hardware Installation

FE Subrack 0 FE

FE
Active iGWB To billing center

HUB

FE Subrack 1
LAN Switch in plane 1 Standby iGWB

BAM LAN Switch in plane 0

Subrack 2

Emergency workstation

HUB
To NMS center

Subrack 9 Service proessing subsystem

LMT

LMT

LMT

Maintenance management subsystem

FE: Fast Ethernet

LMT: Local Maintenance Center

Figure 1-2 Physical structure of the MSOFTX3000

1.3 Procedure of Hardware Installation


Correct installation procedure can ensure safe and stable operation of the MSOFTX3000 system. Figure 1-3 shows the general procedure of MSOFTX3000 hardware installation.

Huawei Technologies Proprietary 1-3

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center


Start

Chapter 1 Overview of Hardware Installation

Prepare for hardware installation

Install cabinets

Install internal components

Install protection ground cables and power cables

Install signal cables

Install cabinet fittings

Install peripherals

Check hardware installation

End

Figure 1-3 General procedure of MSOFTX3000 hardware installation 1) Prepare for hardware installation. Read HUAWEI MSOFTX3000 Mobile SoftSwitch Center Technical Manual, HUAWEI MSOFTX3000 Mobile SoftSwitch Center Hardware Description Manual, and this manual. Get familiar with the overall hardware structure of the equipment to be installed and the technical specifications, as well as the prerequisites for equipment installation. Prepare installation tools. Install auxiliary cable racks or cable troughs according to the project design documents and actual conditions of equipment rooms. 2) Install cabinets. Install cabinets in turn and combine adjacent cabinets according to the project design documents.
Huawei Technologies Proprietary 1-4

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 1 Overview of Hardware Installation

3)

Install internal components. a) Install actually-configured devices into correct positions: iGWB server BAM server LAN Switch Keyboard/video/mouse/switcher (KVMS) Cable trough Blank filler panel b) Insert boards into subracks.

4)

Install protection ground (PGND) cables and power cables. After installing cabinets, install PGND cables first to ensure that devices are properly grounded. Thus, you can prevent devices from electrostatic discharge (ESD) damage during subsequent installation. Be sure to power on the system only after the installed power cables pass the hardware installation check and system power-on test.

5)

Install signal cables. Signal cables include: Internal cables: network cables, serial port cables, monitoring cables, and internal clock cables External cables: external clock cables, trunk cables, and external Ethernet cables

6)

Install cabinet fittings. MSOFTX3000 fittings include antistatic floor holder and cabinet door panels.

7)

Install peripherals. Peripherals include a maintenance terminal system, an alarm box, and other network devices.

8)

Check hardware installation. For check lists and criteria, see Chapter 9 "Hardware Installation Checks". Make necessary adjustment until all items comply with criteria.

1.4 Prerequisites
This manual introduces how to install the hardware components and cables of MSOFTX3000. However, the information might not cover all possible site conditions and optional devices in actual installation. You need to use specific methods based on actual site conditions. Before installation, carefully read the Site Survey Report. Thus, you can get clear of: The position and status of the equipment in the network Interface types of line transmission devices Cable lengths
Huawei Technologies Proprietary 1-5

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 1 Overview of Hardware Installation

Charging modes of access devices To install the MSOFTX3000 smoothly, confirm whether the customer requires any great changes on the ordered devices.

Huawei Technologies Proprietary 1-6

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 2 Installation Preparations

Chapter 2 Installation Preparations


2.1 Introduction to the Chapter
This chapter introduces the preparations that should be made before MSOFTX3000 installation, including: Engineering documents Tools and instruments Checking installation conditions Unpacking and checking goods

2.2 Engineering Documents


Table 2-1 lists the engineering documents needed for hardware installation. Table 2-1 List of engineering documents Document type Document name Network Planning Report Equipment Room Layout Detailed Construction Drawing Cable Routing Drawing Installation engineering instructions Site Survey Report Description The customer shall provide the copies of these documents to Huawei before the equipment shipment. Prepared by Huawei site survey engineers. At the request of site engineers, prepared by Huawei network planning engineers based on the configuration of each office. It is shipped with the equipment.

Engineering Design

HUAWEI MSOFTX3000 Hardware Description Manual HUAWEI MSOFTX3000 Technical Manual Product manuals HUAWEI MSOFTX3000 Installation Manual HUAWEI MSOFTX3000 Operation Manual HUAWEI MSOFTX3000 Maintenance Manual Shipped with the equipment.

Huawei Technologies Proprietary 2-1

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 2 Installation Preparations

Document type Other documents

Document name Contract Shipping List

Description Shipped together with the equipment.

2.3 Tools and Instruments


Table 2-2 lists the tools and instruments needed for the installation. Table 2-2 Tools and instruments Long tape and ruler (1 m) General tools Measuring and marking tools Marking pen and marking pin Industrial horizontal ruler Tape and ruler Angle square Ink fountain A percussion drill and matching bits (6, 8, 10, 12, 14 and 16) Drilling tools A vacuum cleaner A terminal block (with three 2-phase sockets and three 3-phase sockets, current capacity volume > 15 A) Three cross screwdrivers (2#, 3#, and 4#) Four straight screwdrivers (100, 150, 200, and 250) Clamping tools Four adjustable wrenches (6', 8', 10', and 12') A set of socket wrenches (10, 13, 16, and 18) A set of double offset ring wrenches (10, 13, 16, and 18) Long-arm wrench Sharp-nose pliers, diagonal pliers, and pliers Hand-held electric drill Pliers File Hand saw Crowbar Rubber hammer

Huawei Technologies Proprietary 2-2

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 2 Installation Preparations

Tweezers Brush Paper knife Auxiliary tools Plumb Electric iron and solder wire A ladder and a forklift Panel lifter Industrial horizontal ruler Optical multimeter Special tools Optical connectors and pig tail fibers Antistatic wrist strap Earth resistance tester Clamp pincers, cable peeler, crimping pliers, and feeder cutter Instruments A multimeter A 500 V meqaohmmeter (for testing insulation resistance)

Note: Huawei engineers provide the tool list and determine the provider of these tools by negotiating with the customer. Meters must be calibrated to ensure accuracy.

2.4 Installation Conditions


The project supervisor and customer representatives shall check installation conditions together. On arriving the installation site, the project supervisor shall: 1) 2) 3) 4) Check the construction conditions based on related specifications. Fill out the Installation Environment Checklist. Sign the Kickoff Agreement with the customer if all conditions are ready. Prepare the Project Installation Plan.

2.4.1 Construction Conditions


Check the items related to the construction of the room, including: Area and height of the room Shock strength Load bearing capacity If any item fails to meet the requirements, ask the customer to improve it.

Huawei Technologies Proprietary 2-3

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 2 Installation Preparations

2.4.2 Environment Conditions


Check the room environment and make sure that: Room illumination meets the requirements for equipment maintenance. Three lighting systems are available, including daily lighting, backup lighting, and emergency lighting. Water supply and drainage systems meet the requirements for normal water supply and fire fighting. Air-conditioning and ventilation systems can ensure the normal temperature and humidity in the room. Effective antistatic measures are applied. Adequate fire-fighting devices are equipped. Lightning protection measures are taken.

2.4.3 Power Supply


Check the power supply of the room and make sure that: AC power supply facilities are complete, and the power specifications meet requirements. In addition to the AC mains, a diesel generator is usually needed for backup purpose. DC power distribution facilities meet the requirements of the equipment, and the power voltage is stable and within the normal range. Batteries provide sufficient capacity to ensure the normal operation of the equipment for a specified period in case of power failure. Lead-out terminals for AC safety ground are available for the purpose of easy connection.

2.4.4 Grounding Conditions


Good grounding is the basis that ensures the stable running of the equipment, and prevents the equipment from lightning and interference. In this case, it is required to carefully check the grounding conditions of the site, and take correct grounding measures.

Note: The grounding impedance for the equipment building must follow the stipulation of the country. It is recommended to be not more than 10.

Huawei Technologies Proprietary 2-4

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 2 Installation Preparations

2.4.5 Auxiliary Facilities


Check that the following transmission facilities are ready: The digital distribution frame (DDF) is installed and expanded. The capacity of the DDF must be figured out according to the requirement of the project. The optical transceiver is installed and tested. Optical fibers or trunk cables are deployed. Trunk cables or the fiber tails from the connection box are clearly labeled. Routing of optical fibers or trunk cables is qualified and tested. The impedance of trunk cables meets requirements. Cabling rack and DDF are installed. The preparation of the interfaces to the IP network is finished. You must install the routers and LAN Switches, and lay the network cables. The building integrated timing supply system (BITS) is installed and accessed into the equipment room when the MSOFTX3000 also serves as signaling gateway to interconnect with SS7 links.

2.4.6 Other Facilities


Other facilities such as computer desks, chairs, power sockets, and a telephone for external communication are needed in the network management room. Check that all necessary items for the installation are ready according to site situation.

2.5 Unpacking
This section introduces how to unpack goods from wooden cases and cartons.

2.5.1 Unpacking Requirements


The project supervisor must unpack and check the goods with customer representatives. Before unpacking goods, check that: The total number of wooden cases and cartons complies with the packing list. The destination of these goods is the installation site. All the wooden cases and cartons are in good condition. No wooden cases or cartons are placed upside down. If there is any package damaged or soaked, or the goods inside is soaked or becomes rusty, stop unpacking and report to the Huawei local office.

Huawei Technologies Proprietary 2-5

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 2 Installation Preparations

Note: To protect the equipment and help find out causes, move the unpacked equipment indoor for proper storage, and take photos to record the storage environment, condition of the rusty or corroded equipment, packing cases, and packaging materials. Keep these photos for later verification and store the packing cases and materials in a proper place.

If the package is in good condition, follow the steps below to unpack the equipment: 1) 2) 3) 4) 5) Unpack the case with the Packing List (a label is on the case containing the Packing List), and take out the Packing List. Check the number of cases according to the Packing List. For any short or wrong shipment, fill out and submit a feedback form. For any equipment damage, fill out and submit a replacement application. Sign the Packing List together with the customer.

Caution: When moving the equipment or its components, Avoid collision with doors, walls, shelves, or other objects. Do not touch the unpainted medal surface of the equipment or its components with sweat soaked or dirty gloves.

2.5.2 Unpacking Wooden Cases

Caution: Do not put wooden cases upside down. Otherwise, the equipment may be damaged.

Wooden cases are used to pack heavy objects like cabinets and batteries. A wooden case is composed of wooden boards, steel edges, tongues, and foamed wrap angles. It is suggested to move wooden cases to or near the equipment room before unpacking. To unpack a wooden case, do as follows:
Huawei Technologies Proprietary 2-6

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 2 Installation Preparations

1)

Insert the spanner into the hole of the tongue and straighten the tongue, as shown in Figure 2-1. Straighten all the tongues fixing the cover in the same way. You can also use a screwdriver or a hammer to straighten the tongue.
(1)

(2)

(3)

(4)

(1) Angle steel

(2) Wooden board

(3) Tongue

(4) Spanner

Figure 2-1 Straightening the tongue 2) Remove the cover, as shown in Figure 2-2.

Figure 2-2 Removing the cover


Huawei Technologies Proprietary 2-7

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 2 Installation Preparations

3)

Remove the side boards in the same way, as shown in Figure 2-3.

Figure 2-3 Removing side boards When moving the cabinet, hold on the solid parts such as backbone frames. Too much force on the parts with poor rigidity (such as cable supports and beams) may cause damage or accidents. Remove the lining plates of the cabinet after it is moved to the installation position. Otherwise, boards and signal cables may be damaged when moving the cabinet.

2.5.3 Unpacking Cartons


Cartons are used to pack circuit boards and terminal devices. To open a carton, do as follows: 1) 2) 3) 4) 5) 6) Check the types and quantity of boards in the carton according to the carton label. Cut the straps using diagonal pliers. Cut the tapes along the seams of the carton cover. Open the carton and take out the foam plate. Check the number of board boxes according to the carton label and take out them. Check the number and type of boards against the Packing List.

Figure 2-4 shows how circuit boards are packed in a carton.

Huawei Technologies Proprietary 2-8

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 2 Installation Preparations

6 5

2 3

1 Pressure-sensitive adhesive tape 4 Cardboard box 7 Board box

2 Strap 5 Foam board 8 ESD-preventive bag

3 Cardboard box label 6 Board label 9 Board

Figure 2-4 Carton containing circuit boards

Caution: Throwing away cartons containing circuit boards may cause troubles. Before unpacking the next one, check each carton to ensure that it is empty.

2.5.4 Unpacking Boards

Warning: Electronic circuits and components are extremely sensitive to electrostatic discharge (ESD). When handling circuit boards, make sure that you wear a securely grounded ESD wrist strap, and only hold the edge of boards during operation.

When unpacking circuit boards, pay attention to the following points:

Huawei Technologies Proprietary 2-9

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 2 Installation Preparations

Boards are shipped in antistatic bags, in which a drying agent is provided to keep it dry inside. Take appropriate antistatic measures when taking the boards out. Note the affect of environment change on circuit boards. When boards are moved from a cold dry place to a hot damp place, wait at least 30 minutes before unpacking. Otherwise, water condensed on the surface may damage the boards. To unpack boards, do as follows: 1) 2) 3) Check that there is no evident damage on the board package. Put on an ESD wrist strap and ground it securely. Open the package and check that the board is intact.

If you are going to install the board right after unpacking, place the board on an antistatic surface to discharge the static electricity. If you are going to install the board at a later time, pack the board using the original materials and place them at a cool dry place without direct sunshine or strong electromagnetic radiation.

Huawei Technologies Proprietary 2-10

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

Chapter 3 Cabinet Installation


3.1 Introduction to the Chapter
The MSOFTX3000 uses standard 19-inch N68-22 cabinets. This chapter describes how to install the N68-22 cabinet on different floors. It consists of the following sections: Installing N68-22 Cabinets on the Antistatic Floor Installing N68-22 Cabinets on the Cement Floor

Caution: Before installing a cabinet, make sure that related installation (such as cabling rack installation and cabling) has been completed. This can prevent some dust and metal bits from falling into the cabinet, so some troubles affecting safe operation of equipment can be avoided. Wear clean gloves when touching the surfaces of cabinets or subracks.

3.2 Installing N68-22 Cabinets on the Antistatic Floor


When installing N68-22 cabinets on the antistatic floor, install N800 supports on the floor and then place the cabinets onto the supports. This section describes how to install N68-22 cabinets on the antistatic floor, which includes the following: Introduction to N800 Series Supports Installation Procedure Determining the Installation Position of Cabinets Determining the Installation Position of Supports Installing Supports Fixing Cabinets Testing the Insulation Connecting Multiple Cabinets Restoring the Antistatic Floor

Huawei Technologies Proprietary 3-1

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

3.2.1 Introduction to N800 Series Supports


An N800 support assembly includes the following components: Support Horizontral Pallet Assembly Side Pallet Assembly

I. Support
Supports are used to lift the cabinet up for the convenience of cabling. The supports are welded by the steel plates. The N800 series supports feature four models. One of them is height-fixed and the others are height-adjustable. Figure 3-1 shows an N800 support.
2 3 4 5

1 Connection hole for the slide rail 4 Height-locking bolt

2 Height mark of the antistatic floor 3 Upper support 5 Lower support 6 Mounting hole to the ground

Figure 3-1 N800 support

Table 3-1 lists the applicable height range of each support type.

Huawei Technologies Proprietary 3-2

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

Table 3-1 Applicable height range of each support type Type I II III IV The height of the applicable antistatic floor (mm) 210255 256345 346525 Customized based on the floor height (minimum: 100 mm)

Note: The floor height refers to the distance between the upper surface of the antistatic floor and the cement floor.

The heights of the N800 series I, II, III supports are steplessly adjustable within their respective ranges by moving the upper and lower supports up and down. N800 series IV supports are in fixed height. They are used when the floor is extremely high or low. The minimum floor height is 100 mm. A cabinet uses two supports with the same height.

II. Horizontral Pallet Assembly


The horizontal pallet assembly includes the following: Slide rail Horizontal pallet Fixing bracket for the pallet Slide rails connect cabinets and supports, pallets support the floor around the cabinet, and fixing brackets secure the pallets. A cabinet uses one horizontal pallet assembly, which includes the following components: Two slide rails Two horizontal pallets Two fixing pallets Figure 3-2 shows the structure of the slide rail.

Huawei Technologies Proprietary 3-3

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

1 Connection hole for the rack 2 Connection hole for the support

Figure 3-2 Structure of the slide rail

Figure 3-3 shows the structure of the horizontal pallet.

1 Connection nut for the side pallet

2 Connection holes for the fixing bracket

Figure 3-3 Structure of the horizontal pallet

Figure 3-4 shows the structure of the fixing bracket.

Huawei Technologies Proprietary 3-4

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center


1

Chapter 3 Cabinet Installation

1 Connection hole for the slide rail

2 Connection hole for the horizontal pallet

Figure 3-4 Structure of the fixing bracket

III. Side Pallet Assembly


Each side pallet assembly includes two side pallets, which support the floor on both sides of the cabinet. Figure 3-5 shows the structure of the side pallet.

1 Connection holes for the horizontral pallet

Figure 3-5 Structure of the side pallet

The number of side pallet assemblies depends on the installation mode: In ordinary installation, a cabinet uses one side pallet assembly. In combined cabinet installation, a row of cabinets use one side pallet assembly.

Huawei Technologies Proprietary 3-5

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

3.2.2 Installation Procedure


Figure 3-6 shows the procedure for installing N68-22 cabinets on the antistatic floor.

Start Determine the installation position of cabinets Determine the installation position of supports Install supports

Install cabinets

Test the insulation

Test pass? Yes Connect multiple cabinets

No

Restore the antistatic floor

End

Figure 3-6 Procedure for installing an N68-22 cabinet on the antistatic floor

3.2.3 Determining the Installation Position of Cabinets


Determine the installation position of cabinets based on the construction engineering drawings. Reserve enough space for maintenance in front and at the back of the cabinet, as shown in Figure 3-7 and Figure 3-8.

Huawei Technologies Proprietary 3-6

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

Caution: Map the installation position on the antistatic floor to the cement floor to help determine the installation position of supports correctly.

3.2.4 Determining the Installation Position of Supports


This part describes how to determine the installation position of supports, which includes the following: Marking Reference Lines Drilling Holes Installing Expansion Bolts

I. Marking Reference Lines


To mark reference lines, do as follows: 1) 2) 3) 4) Determine the positions of supports based on the construction engineering drawings. Determine the mounting holes of supports based on Figure 3-7 and Figure 3-8. Mark the mounting holes. Check the position marks carefully to ensure the correctness.

Figure 3-7 shows the mounting holes of the supports when only one cabinet is installed.

Huawei Technologies Proprietary 3-7

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

800 800

Cabinet contour line 690 4 - 16 Mounting hole 800

354 800 600 800

Figure 3-7 Mounting holes of the supports for one cabinet

Figure 3-8 shows the mounting holes of the supports when several cabinets are installed in a row.

800 800

Cabinet contour line 690 16 Mounting hole 800

354 800 600

354 600

354 600 800

Figure 3-8 Mounting holes of supports for multiple cabinets


Huawei Technologies Proprietary 3-8

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

You can also use the line drawing template to mark the mounting holes of expansion bolts. The procedure is as follows: 1) 2) Place the line drawing template on the floor according to the cabinet layout. Mark the positions for expansion bolts on the floor using the template. (Mark four bolt positions for each cabinet.) Figure 3-9 shows how to mark the mounting holes of expansion bolts using the line drawing template. Note that the half-circle gap on the template indicates the face of the cabinet.

690

800

Mounting hole

354 600

Figure 3-9 Marking mounting holes of expansion bolts using the line drawing template

II. Drilling Holes


M 12 expansion bolts are used to fix the supports onto the ground, so you must use a 16 percussion drill to make holes for the bolts. To drill holes on the floor, do as follows: 1) Keep the drilling bit vertical to the ground and hold tight the drillstock to drill holes 52 mm to 60 mm deep.

Huawei Technologies Proprietary 3-9

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

The depth of the holes must be within 52 mm to 60 mm. Otherwise the expansion bolts cannot be tightened. If the ground is too hard or too smooth to settle the drill bit, use a chisel to punch a pit before drilling. 2) 3) Clean the dust inside the holes using a vacuum cleaner. Measure the depths of the holes to ensure that the depths are the same.

Note: Correct line drawing and hole drilling are essential to quality hardware installation.

III. Installing Expansion Bolts


To install an expansion bolt, do as follows: 1) 2) 3) Check if the dust inside and around the holes are cleaned. Check the hole spacing. Place a support on the ground to check if the holes match those on the support. Relocate and drill new holes if necessary. 4) 5) 6) Remove the expansion tube and nut from the expansion bolt. Put the guiding rib of the nut in the guiding slot of the expansion tube. Put expansion nut and expansion tube in the hole vertically. Put the guiding rib of expansion nut in the guiding slot of the tube in advance. Otherwise, the expansion nut cannot be tightened. 7) Strike the expansion tube into the hole using a rubber hammer. To ensure normal installation, the expansion tube must be buried in the cement floor. Figure 3-10 shows how to install the expansion tube and nut.

Huawei Technologies Proprietary 3-10

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

Expansion tube Guiding slot on expansion tube

Expansion nut Guide rib on expansion nut

Figure 3-10 Installing the expansion tube and nut

3.2.5 Installing Supports


This part describes how to install N800 supports on the antistatic floor, which includes the following: Adjusting the Support Height Assembling Slide Rails Fixing Supports Installing Floor Support Accessories For description of the N800 support, see 3.2.1 Introduction to N800 Series Supports

I. Adjusting the Support Height


To adjust the support height, do as follows: 1) Tune the height of the support. Ensure that the height indicators on the support are on the same level as the antistatic floor. 2) Screw the height-locking bolts in the middle and then those on both sides to 45 N$m with a torque spanner. Figure 3-11 shows how to adjust the support height.

Huawei Technologies Proprietary 3-11

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

Height-locking bolt (middle) Height-locking bolt (at two sides)

Height-locking bolt (middle)

Height-locking bolt (at two sides)

Figure 3-11 Adjusting the support height

II. Assembling Slide Rails


To assemble a support with a slide rail, do as follows: 1) 2) 3) Assemble the support with the slide rail together using M 12x30 bolts, spring washers, and flat washers. Adjust the support location to ensure that the diagonal lines (A and B in Figure 3-12) of the two slide rails are equal in length. Screw all bolts.

Figure 3-12 shows how to assemble a support with a slide rail.

Huawei Technologies Proprietary 3-12

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

B A

3 4 5

1 Support 5 Flat washer

2 Slide rail

3 Bolt M 12x30

4 Spring washer

Figure 3-12 Assembling a support with a slide rail

III. Fixing Supports


To fix a support, do as follows: 1) 2) 3) 4) 5) Align the mounting holes on the support with the holes on the ground. Fit the spring washers and flat washers on the M 12x60 bolts. Insert bolts through the holes on the support into the holes on the ground vertically. Adjust the support location. Screw the bolts to 45 N$m.

Figure 3-13 shows how to fix a support on the floor.

Huawei Technologies Proprietary 3-13

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

3 4 5

6 7

1 Support 5 Flat washer

2 Slide rail 6 Expansion tube

3 Bolt M12x60 7 Expansion nut

4 Spring washer

Figure 3-13 Fixing a support on the floor

When installing supports for a row of cabinets, ensure that the front sides of all supports are in a line, and the spacing between adjacent supports is 128 mm, as shown in Figure 3-14.

128 128
Figure 3-14 Supports for a row of cabinets

Huawei Technologies Proprietary 3-14

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

IV. Installing Floor Support Accessories


Floor support accessories include: Pallets Fixing brackets The pallets support the antistatic floor around the cabinets, and the fixing brackets secure the pallets. A fixing bracket is needed for each slide rail. Before laying cabinets in place, secure the fixing brackets with the slide rails, as shown in Figure 3-15..

4 5 3 6

1 Support 5 Spring washer

2 Slide rail 6 Flat washer

3 Fixing bracket for pallet

4 Bolt M12x30

Figure 3-15 Installing floor support accessories

3.2.6 Fixing Cabinets

Caution: Use insulation plates between cabinets and supports, and insulation coverings on the expansion bolts. Install insulation parts correctly to ensure good insulation between the equipment and the ground.

Huawei Technologies Proprietary 3-15

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

To fix the cabinet, do as follows: 1) Lift the cabinet onto the slide rails. Ensure the front side of the cabinet is correct. 2) 3) 4) 5) 6) Remove the caps on the mounting holes. Align the four mounting holes on the cabinet with the four holes on the slide rails. Put the insulation plates on the slide rails under the cabinet. (Use two insulation plates for each cabinet.) Check the levelness of the cabinet using a level bar on the cabinet top. Add washers to tune the level of the cabinet. Fix washers between the insulation plate and the slide rail. Otherwise, insulation plates do not work. 7) Fit the spring washers on M 12x45 bolts. Note that the big flat washers and insulation coverings are already installed in the cabinet. 8) 9) Insert bolts vertically through the lower enclosure frame of the cabinet into the holes on the slide rails. Fit the flat washers and nuts. 10) Screw the bolts to 45 N$m. Screw the bolts alternately to reduce stress between the bolts and the cabinet. Figure 3-16 shows how to fix a cabinet.

Huawei Technologies Proprietary 3-16

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

5 6

7 8 9 10 2 3

1 Cabinet 5 Spring washer 9 Flat washer

2 Slide rail 6 Insulating washer 10 Nut

3 Support 7 Insulation plate

4 Bolt 8 Washer

Figure 3-16 Fixing a cabinet

3.2.7 Testing the Insulation


To test the insulation of the cabinet, do as follows: 1) 2) Set the multimeter to the mega-ohm scale. Measure the resistance between the support and the cabinet. If the measured resistance exceeds five mega-ohms, the insulation effect is good. Otherwise, perform the following: a) b) c) d) Dismount all components. Check if there is any uninstalled or damaged insulation part. Reinstall the cabinet. Measure the insulation again.

Huawei Technologies Proprietary 3-17

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

3.2.8 Connecting Multiple Cabinets


When installing two or more cabinets side by side, connect them by connecting plates on the top. The connecting plates are installed on the cabinet top before delivery, as shown in Figure 3-17. To connect two adjacent cabinets, do as follows: 1) 2) Remove the connecting plates of two adjacent cabinets. Connect the two adjacent cabinets with the plates.

Figure 3-17 shows how to connect two adjacent cabinets.


1 2 3

Figure 3-17 Connecting two adjacent cabinets

Huawei Technologies Proprietary 3-18

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

3.2.9 Restoring the Antistatic Floor


This part describes how to restore the antistatic floor, which includes the following: Installing Pallets Adjusting the Height of Pallets Cutting and Restoring the Antistatic Floor

I. Installing Pallets
Fix the horizontal pallet onto the fixing bracket using M 12 bolts, spring washers, and flat washers. Then fix the side pallet onto the horizontal pallet. For a row of cabinets, install pallets at both ends only. Figure 3-18 shows how to install pallets.

2 3

1 Cabinet 5 Washer 12 9 Side pallet

2 Slide rail 6 Flat washer 12

3 Support 7 Horizontal pallet

4 Bolt M 12x30 8 Fixing bracket for pallet

Figure 3-18 Installing pallets

II. Adjusting the Height of Pallets


Adjust the height of pallets to ensure that the pallets securely contact the antistatic floor.
Huawei Technologies Proprietary 3-19

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

III. Cutting and Restoring the Antistatic Floor


Cut and restore the antistatic floor based on the actual conditions. Figure 3-19 shows a row of cabinets installed on the antistatic floor.

Figure 3-19 Cabinets installed on the antistatic floor

Huawei Technologies Proprietary 3-20

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

3.3 Installing N68-22 Cabinets on the Cement Floor


3.3.1 Overview
This section describes how to install N68-22 cabinets on the cement floor, which includes the following: Installation Procedure Determining the Installation Position of Cabinets Fixing Cabinets Testing the Insulation Connecting Multiple Cabinets

3.3.2 Installation Procedure


Figure 3-20 shows the procedure for installing N68-22 cabinets on the cement floor.
Start Determine the installation position of cabinets Install cabinets

Test the insulation

Test pass? Yes Connect multiple cabinets

No

End

Figure 3-20 Procedure for installing an N68-22 cabinet on the cement floor

Huawei Technologies Proprietary 3-21

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

3.3.3 Determining the Installation Position of Cabinets


Determine the installation position of cabinets based on the construction engineering drawings. Reserve enough space for maintenance in front and at the back of the cabinet, as shown in Figure 3-21 and Figure 3-22. This part describes how to determine the installation position of cabinets, which includes the following: Marking Reference Lines Drilling Holes Installing Expansion Bolts

I. Marking Reference Lines


To mark the reference lines, do as follows: 1) 2) 3) 4) 5) Determine the positions of expansion bolts based on the construction engineering drawings. Mark a few points using a long tape and draw two straight lines, with a spacing of 687 mm, in parallel with the benchmarks. Determine the positions of the expansion bolts for the first cabinet. Mark the mounting holes of expansion bolts for other cabinets based on those of the first one. Check the bolt positions.

Figure 3-21 shows the mounting holes of expansion bolts when only one cabinet is installed.

Huawei Technologies Proprietary 3-22

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

800 800

Cabinet contour line 687 4 - 16 Mounting hole 800

413 800 600 800

Figure 3-21 Mounting holes of expansion bolts for one N68-22 cabinet

Figure 3-22 shows the mounting holes of expansion bolts when several cabinets are installed in a row.

Huawei Technologies Proprietary 3-23

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

800 800

Cabinet contour line 16 Mounting hole

687 800

413 800 600

413 600

413 600 800

Figure 3-22 Mounting holes of expansion bolts for N68-22 cabinets in a row

You can also use the line drawing template to mark the mounting holes of expansion bolts. The procedure is as follows: 1) 2) Place the line drawing template on the floor. Mark the positions of expansion bolts on the floor using the template. Mark four positions of expansion bolts for each cabinet. Figure 3-23 shows how to mark the mounting holes of expansion bolts using the line drawing template. (The half-circle gap on the template indicates the face of the cabinet.)

Huawei Technologies Proprietary 3-24

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

687

800

Mounting hole

413 600

Figure 3-23 Line drawing template (for installation on the cement floor)

II. Drilling Holes


M 12 expansion bolts are used to fix the cabinet onto the ground, so you must use a 16 percussion drill to make holes for the expansion bolts. To drill holes on the floor, do as follows: 1) Keep the drilling bit vertical to the ground and hold tight the drillstock to drill holes 52 mm to 60 mm deep. The depth of the holes must be within 52 mm to 60 mm. Otherwise the expansion bolts cannot be tightened. If the ground is too hard or too smooth to settle the drill bit, use a chisel to punch a pit before drilling. 2) 3) Clean the dust inside the holes using a vacuum cleaner. Measure the depth of the holes to ensure that the depths are the same.

Huawei Technologies Proprietary 3-25

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

Note: Correct line drawing and hole drilling are essential to quality hardware installation.

III. Installing Expansion Bolts


To install an expansion bolt, do as follows: 1) 2) Check if the dust inside and around the holes are cleaned. Check the hole spacing. Relocate and drill new holes if necessary. 3) 4) 5) 6) Remove the expansion tube and nut from the expansion bolt. Put the guiding rib of nut in the guiding slot of the expansion tube. Put expansion nut and expansion tube in the hole vertically. Strike the expansion tube into the hole using a rubber hammer.

3.3.4 Fixing Cabinets

Caution: Use insulation plates between cabinets and supports, and insulation coverings on the expansion bolts. Install insulation parts correctly to ensure good insulation between the equipment and the ground.

To fix the cabinet, do as follows: 1) 2) 3) 4) 5) 6) 7) Place the cabinet on the specified position, and align anchors of the cabinet with the mapping holes on the ground. Adjust anchors to raise the cabinet and put insulation washers under anchors until the truckles are 5 mm off the ground. Check the levelness of cabinet using a level bar on the cabinet top. Adjust the anchors to level the cabinet. Fit the insulation tubes on anchors, and the spring washers, big flat washers, and insulation washers on bolts M 12x80. Insert the bolts through anchors into the holes on the support vertically Screw the bolts to 45 N$m. Screw the bolts alternately to reduce stress between the bolt and the cabinet.

Huawei Technologies Proprietary 3-26

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

Figure 3-24 shows how to fix a cabinet.

1 2 3

4 5

1 Bolt M 12x80 4 Insulation plate

2 Spring washer 12 5 Washer

3 Insulation washer

Figure 3-24 Fixing a cabinet

3.3.5 Testing the Insulation


To test the insulation of the cabinet, do as follows: 1) 2) Set the multimeter to the mega-ohm scale. Measure the resistance between the expansion bolt and the cabinet. If the measured resistance exceeds five mega-ohms, the insulation effect is good. Otherwise, perform the following: a) b) c) d) Dismount all components. Check if there is any uninstalled or damaged insulation part. Reinstall the cabinet. Measure the insulation again.

Huawei Technologies Proprietary 3-27

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 3 Cabinet Installation

3.3.6 Connecting Multiple Cabinets


When installing two or more cabinets side by side, connect them by connecting plates on the top. The connecting plates are installed on the cabinet top before delivery, as shown in Figure 3-25. To connect two adjacent cabinets, do as follows: 1) 2) Remove the connecting plates of two adjacent cabinets. Connect the two adjacent cabinets with the plates.

Figure 3-25 shows how to connect two adjacent cabinets.


1 2 3

Figure 3-25 Connecting two adjacent cabinets

Huawei Technologies Proprietary 3-28

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 4 Internal Component Installation

Chapter 4 Internal Component Installation


4.1 Introduction to the Chapter
Internal components (ICs) configured for a cabinet depend on uses of the cabinet. This chapter presents the procedures of installing ICs.

4.2 Precautions
When installing ICs, comply with the following: Place each component gently onto corresponding guide rails in cabinets, and insert it slightly into cabinets. For cabinet stability and convenience in operation, install components from the bottom up. When fastening ICs and dummy panels, do as follows: 1) 2) Put bolts into the installation holes on the mount angles of each component. Screw the component on the mount angles at both sides of cabinets.

If you use more than four bolts for a component, first fasten the four bolts at the four corners in the diagonal direction, and then other bolts in turn. Fix dummy panels on the mount angles at both sides of cabinets using lockers. To pull out a dummy panel, first press down and loose lockers. Keep mount angles in a correct order. Keep even space between components, between dummy panels, and between components and dummy panels.

4.3 Installation Procedure


Install the following in turn from bottom to top into their positions in the integrated configuration cabinet and service processing cabinet: iGWB server BAM server Hard disk array (IBM server) LAN Switch KVMS Basic subrack Expansion subrack Figure 4-1 and Figure 4-2 show the full configuration of an integrated configuration cabinet.

Huawei Technologies Proprietary 4-1

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 4 Internal Component Installation

Power distribution subrack (2U)

Expansion subrack (9U)

Air deflector (2U)

Basic subrack (9U)

Air deflector (2U) Blank filler panel (1U) KVMS (1U) LAN Switch 1 (1U) Cabling trough (1U) LAN Switch 0 (1U) Cabling trough (1U) Blank filler panel (3U) BAM (2U) Standby iGWB (2U) Active iGWB (2U) Blank filler panel (3U) Blank filler panel (2U) Blank filler panel (2U)

Figure 4-1 Full configuration of integrated configuration cabinet (HP server)

Huawei Technologies Proprietary 4-2

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 4 Internal Component Installation

Power distribution subrack (2U)

Expansion subrack (9U)

Air deflector (2U)

Basic subrack (9U)

Air deflector (2U) Blank filler panel (1U) KVMS (1U) LAN Switch 1 (1U) Cabling trough (1U) LAN Switch 0 (1U) Cabling trough (1U) Hardware disk array (3U) BAM (2U) Standby iGWB (2U) Active iGWB (2U) Blank filler panel (3U) Blank filler panel (2U) Blank filler panel (2U)

Figure 4-2 Full configuration of integrated configuration cabinet (IBM server)

Huawei Technologies Proprietary 4-3

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 4 Internal Component Installation

Figure 4-3 shows the full configuration of two service processing cabinets.
Service processing cabinet 1 Power distribution subrack (2U) Service processing cabinet 2 Power distribution subrack (2U)

Expansion subrack (9U)

Expansion subrack (9U)

Air deflector (2U)

Air deflector (2U)

Expansion subrack (9U)

Expansion subrack (9U)

Air deflector (2U)

Air deflector (2U)

Expansion subrack (9U)

Expansion subrack (9U)

Air deflector (2U)

Air deflector (2U)

Expansion subrack (9U)

Expansion subrack (9U)

Blank filler panel (2U)

Blank filler panel (2U)

Figure 4-3 Full configuration of service processing cabinets

Huawei Technologies Proprietary 4-4

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 4 Internal Component Installation

Figure 4-4 shows the flowchart of installing ICs.


Start

Install iGWB and BAM servers

Install hard disk array

Install LAN Switches

Install KVMSs

Install fan boxes in service subracks Install boards in service subracks

End

Figure 4-4 Flowchart of installing internal components

Note: The LAN Switches, fan boxes, boards, cable troughs, and dummy panels have been installed before delivery.

4.3.1 Installing iGWB and BAM Servers

Note: In common cases, guide rails for ICs are mounted before delivery. You do not need to use the guide rails delivered with the servers.

Huawei Technologies Proprietary 4-5

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 4 Internal Component Installation

To install iGWB and BAM servers, proceed as follows: 1) 2) Put the iGWB and BAM servers in the integrated configuration cabinet. Fasten the servers in the cabinet with panel screws.

4.3.2 Installing Hard Disk Array


To install the hard disk array when the iGWB adopts the IBM server, proceed as follows: 1) 2) Put the hard disk array in the integrated configuration cabinet. Fasten the hard disk array in the cabinet with panel screws.

4.3.3 Installing LAN Switches:

Caution: Do not use the mount angles delivered with LAN Switches. Instead, use those packed alone, in purplish grey compatible with the color of the whole equipment.

To install a LAN Switch, proceed as follows: 1) 2) 3) Fix mount angles at both sides of the front panel of LAN Switch. Insert the LAN Switch into corresponding guide rails. Fasten the mount angles at both sides of the LAN Switch front panel onto the mount angles on the side columns in the cabinet front using panel screws.

4.3.4 Installing KVMSs:


To install a KVMS, proceed as follows: 1) 2) 3) Insert the KVMS into the corresponding position in an integrated configuration cabinet. Fasten the mount angles at both sides of the KVMS front panel onto the mount angles on the side columns in the cabinet front using panel screws. Install anti-tilt angles on the two rear sides of the KVMS and screw the anti-tilt angles onto the mount angles on the side columns at the cabinet back. Thus, you can avoid tilt of the rear part when the liquid crystal display (LCD) or keyboard is pulled out of the cabinet.

Huawei Technologies Proprietary 4-6

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 4 Internal Component Installation

4.3.5 Installing Fan Boxes in Service Subracks


To install a fan box at the bottom of a service subrack, proceed as follows: 1) 2) Insert the fan box along the guide rails until the power plug on the fan box is inserted into the power socket of the subrack. Screw the fan box in the subrack.

4.3.6 Installing Boards in Service Subracks

Caution: Before installing boards in basic subrack and expansion subracks, ensure that cabinets are grounded reliably. For the methods about connecting protection ground cables, see Chapter 5 "Installation of Protection Ground Cables and Power Cables". Insert a board into a subrack only when the eject levers contact well with the upper and lower beams of the subrack. Forced insertion will wear the eject levers and may damage the slot pins on the subrack backplane.

I. Preparations for Installing Boards


Circuit boards are sensitive to electrostatic discharge (ESD). When handling boards, observe the following rules: Check that the equipment is securely grounded according to requirements. Always wear an ESD wrist strap during the operation. Tighten the writs strap around your wrist so that the metal tab makes good contact with your bare skin, and attach the ground core of the wrist strap to the designated grounding point, as shown in Figure 4-5.

Figure 4-5 Wearing an ESD wrist strap correctly

Huawei Technologies Proprietary 4-7

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 4 Internal Component Installation

Check the validity and functionality of the wrist strap. Its resistance value must be within 0.75 M to 10 M. If the validity period (usually two years) of the wrist strap expires or the resistance value fails to meet requirements, use a functioning wrist strap. Avoid touching boards with your clothing, because the touching generates static electricity beyond the protection scope of the wrist strap. Wear antistatic gloves and place the board on an antistatic pad when replacing board software or chips. Use antistatic tweezers or extraction tools to replace chips. Do not tough chips, circuits, or pins with your bare hands. Keep the boards and other ESD sensitive parts to be installed in antistatic bags. Place removed boards and components on an antistatic pad or other antistatic materials. Do not use non-antistatic materials such as white foams, common plastic bags, or paper bags to pack boards or let them touch boards. Wear an ESD wrist strap when operating the ports of boards because they are also ESD-sensitive. Discharge the static electricity of cables and protective sleeves before connecting them to the ports. Reserve some materials for board installation (such as antistatic boxes and bags) in the room for future use.

II. Procedures to Install a Board


Figure 4-6 shows how to install a board in a service subrack.

Figure 4-6 Installing a board Proceed as follows: 1) 2) 3) 4) 5) Make sure the slot where you install the board. Unscrew the dummy panel and remove it from this slot. Wear an ESD-preventive strap. Take out the board to be installed. Hold tight the ejector levers on the board with both hands, turn them outward, and then insert the board along the guide rails smoothly until the positioning pins on the front panel contact the positioning holes on the subrack.

Huawei Technologies Proprietary 4-8

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 4 Internal Component Installation

6) 7)

Turn the ejector levers inward to let the positioning pins on the front panel go smoothly into the positioning holes on the base plate. Screw the board.

Huawei Technologies Proprietary 4-9

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 5 Installation of Protection Ground Cables and Power Cables

Chapter 5 Installation of Protection Ground Cables and Power Cables


5.1 Introduction to the Chapter
Stable power supply system and grounding system are the basis of normal operation of the whole system. This chapter presents the procedures of installing PGND cables and power cables.

5.2 Introduction to Power Supply System and Protection Grounding System


5.2.1 Introduction to Power Supply System
I. Power Supply Path of Power Distribution Subrack
The MSOFTX3000 uses N68-22 cabinets. Generally, an MSOFTX3000 cabinet is powered by two independent 48V DC power supplies. The power of the components in the cabinet is controlled by the power distribution subrack on the top of the cabinet. See Figure 5-1 for the power supply path of the power distribution subrack.
-48V1 -48V2

Power distribution subrack

SW1

SW2

SW3 SW4

SW5

SW6

Figure 5-1 Power supply path of power distribution subrack To enhance the reliability of the power supply to internal components of the cabinet, the power distribution subrack combines two input power into one with a large-power diode, and exports to the six power switches (SW1SW6) on its panel through a power bus cable. Each of the six switches powers some of the components in the cabinet. When one of the input power supplies fails, the other can still power the internal components of the cabinet.

Huawei Technologies Proprietary 5-1

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 5 Installation of Protection Ground Cables and Power Cables

II. Power Supply Path in Cabinet


The MSOFTX3000 cabinets include integrated configuration cabinet and service processing cabinet. As each type of cabinet is installed with different components, the internal power supply paths (48V power supply system) are also different. Figure 5-2 shows the connection of power cables from power distribution subrack to internal components. Table 5-1 shows the relationships between cable numbers and cable names, and Table 5-2 shows the relationships between switches (SW1 to SW6) on the front panel of the power distribution subrack and the power supplies of the internal components.

(1) Integrated configuration cabinet (4) Disk array (7) Expansion subrack 2 (10) Expansion subrack 5

(2) Service processing cabinet (3) Power distribution subrack (5) Basic subrack 0 (6) Expansion subrack 1 (8) Expansion subrack 3 (9) Expansion subrack 4

Figure 5-2 Connection of 48V DC cables from power distribution subrack to cabinet components

Huawei Technologies Proprietary 5-2

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 5 Installation of Protection Ground Cables and Power Cables

Table 5-1 Corresponding relationships between cable numbers and cable names Serial No. 1 2 3 4 5 6 7 8 9 10 11 Cable No. 9 20 W2 W5, W7, W8 6.7, 6.8 W11 1, 2 W9, W10 5.3, 5.5, 6.3, 6.5 W12 3.3, 3.5, 4.3, 4.5, 5.4, 5.6, 6.4, 6.6 W13, W14 W1, W6 Cable name Power cables for MSOFTX3000 service subracks Protection grounding cables for MSOFTX3000 service subracks Power cables for KVMS Protection grounding cable for KVMS Power cables for LAN Switch Protection grounding cables for LAN Switch Power cables for BAM server Protection grounding cable for BAM server Power cables for iGWB server Protection grounding cables for iGWB Protection grounding cables for power distribution subrack

Caution: Relations between cabinet components and switches of the power distribution subrack are listed in Table 5-2. The relations between them may vary with different equipment. Take labels on the power distribution subrack of the actual delivered equipment as the correct relation indications.

Huawei Technologies Proprietary 5-3

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 5 Installation of Protection Ground Cables and Power Cables

Table 5-2 Relations between cabinet components and switches of the power distribution subrack Cabinet type Switch SW5, SW6 SW4, SW5 SW3 SW6 Integrated configuration cabinet SW5 SW1, SW6 SW2, SW3 SW2, SW3 SW1, SW2 SW1, SW2 SW1, SW2 SW2, SW3 Service processing cabinet SW3, SW4 SW5, SW6 Component SUBRACK-1 (Expansion subrack 1) SUBRACK-0 (Basic subrack 0) KVMS LANS-1 LANS-0 ARRAY (Hard disk array) SERVER-3 (BAM) SERVER-2 (iGWB 1) SERVER-1 (iGWB 0) SERVER-0 (A server for other services, Optional) SUBRACK-3 (Expansion subrack 5) SUBRACK-2 (Expansion subrack 4) SUBRACK-1 (Expansion subrack 3) SUBRACK-0 (Expansion subrack 2)

To avoid misoperation, the maintenance staff should carefully check and confirm the relations between the power distribution subrack and the components before installation.

5.2.2 Introduction to Protection Grounding System


The MSOFTX3000 equipment adopts joint grounding mode. The protection grounding cables for each cabinet are connected to DC power distribution cabinet that conducts grounding, and all cabinets are connected by protection grounding cables as an equipotential system. The protection grounding cables of the internal components of a cabinet are interconnected through the grounding bars on the side columns of cabinets. Through the protection grounding cables of the cabinet, the grounding bars are connected to the PGND of the DC power distribution cabinet, which is connected with the protection grounding bus in equipment room.
Huawei Technologies Proprietary 5-4

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 5 Installation of Protection Ground Cables and Power Cables

The protection grounding cables of a cabinet include: Protection grounding cables for service subracks, Protection grounding cable for KVMS, Protection grounding cables for LAN Switches, Protection grounding cables for iGWB and BAM servers, Protection grounding cables for cabinet doors, Protection grounding cables for connecting grounding bars of adjacent cabinets. For details about the appearance, sizes, and specifications of protection grounding cables, see HUAWEI MSOFTX3000 Mobile SoftSwitch Center Hardware Description Manual.

5.3 Installation Principles


Installation of PGND cables and power cables must conform to the following principles: Generally, DC power distribution cabinets are provided by the customer. The installation method of DC power distribution cabinets is similar to that of N68-22 cabinets. For details, see Chapter 3 "Cabinet Installation". The PGND bar of DC power distribution cabinet must be correctly connected to the nearest PGND bar offered by the customer through main PGND cables. PGND cables use green and yellow plastic insulation copper core wires whose core area is the same as that of power cables. Internal power cables of N68-22 cabinets are connected to connecting terminals on power distribution boxes (PDBs) before delivery. After installing internal components, connect the other end of power cables to the components. Before installation, mark or stick labels on both ends of each PGND cable and power cable, to indicate connected devices and ensure correct connection. For details, see Appendix D "Facture of Cable Labels".

5.4 Installation Procedure


Figure 5-3 shows the general procedure of installing PGND cables and power cables.

Huawei Technologies Proprietary 5-5

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 5 Installation of Protection Ground Cables and Power Cables

Start

Install PGND cables within cabinets

Install power cables within cabinets

Install PGND cables between cabinets

Install PGND cables and power cables between DC distribution cabinets and MSOFTX3000 cabinets

Install power bus cables between DC distribution cabinets and DC switchboards

End

Figure 5-3 Flowchart of installing PGND cables and power cables

5.4.1 Installing PGND Cables Within Cabinets


The following describes how to install PGND cables within cabinets.

I. Installing PGND Cables for Service Subracks


On the upper beam of each service subrack rear, there is one ground terminal at either side. To install PGND cables for a service subrack, use a 10 AWG PGND cable (green and yellow) to connect the ground terminal of service subrack to the ground bar at the closest side of the cabinet, that is, only one bar is connected. In terms of cabling orderliness, you are recommended to install PGND cables at one side of a cabinet for the subracks in the same cabinet.

II. Installing PGND Cables for KVMS


To install a PGND cable for a KVMS, proceed as follows: 1) 2) Screw the OT terminal of the cable on the proper position of the PGND bar nearby. Fasten the UT terminal of the cable on the PGND terminal "F.G" of the KVMS, as shown in Figure 5-4.

Huawei Technologies Proprietary 5-6

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 5 Installation of Protection Ground Cables and Power Cables

Figure 5-4 Connection positions of a power cable and a PGND cable for a KVMS

III. Installing PGND Cables for LAN Switches


The ground screw of a LAN Switch is on the back panel of the LAN Switch shell, as shown in Figure 5-5.

NEG(-) RTN(+)

(1)

(1) Grounding point

Figure 5-5 Position of the ground screw on a LAN Switch shell To install a PGND cable for a LAN Switch, proceed as follows: 1) 2) Connect one end of the cable to the ground screw of the LAN Switch. Connect the other end of the cable to the PGND bar of the cabinet or a nearby metallic part of the cabinet.

IV. Installing PGND Cables for iGWB and BAM Servers (HP server)
The PGND cable and the power cable of the iGWB/BAM are the same. For appearance and installation methods of the PGND cable, see section 5.4.2 IV. Installing Power Cable for iGWB or BAM Server (HP Server).

V. Installing PGND Cables for iGWB and BAM Servers (IBM server)
To install PGND cable for the iGWB or BAM servers, proceed as follows: 1) 2) Connect the UT terminal of a green and yellow PGND cable to the grounding point of the servers, as shown in Figure 5-8. Connect the OT terminal to the PGND bar of the cabinet.
Huawei Technologies Proprietary 5-7

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 5 Installation of Protection Ground Cables and Power Cables

5.4.2 Installing Power Cables Within Cabinets


The following describes how to install power cables within cabinets.

I. Installing Power Cables for Service Subracks


Service subracks include basic subracks and expansion subracks. To install power cables for a service subrack, proceed as follows: 1) Insert the cord end terminal of blue cable into the 48 V output connection hole on the PDB, and the cord end terminal of black cable into the RTN (or called BGND previously) output connection hole on the PDB. 2) 3) Route the power cables along the outer side of the right cable trough and bind them evenly. Connect the OT terminal of blue cable to the 48 V cable post, and the OT terminal of black cable to the RTN cable post.

II. Installing Power Cables for KVMSs


To install power cables for a KVMS, proceed as follows: 1) Insert the cord end terminal of blue cable into the 48 V output connection hole on the PDB, and the cord end terminal of black cable into the RTN (or called BGND previously) output connection hole on the PDB. 2) 3) Route the power cables downward along the left cable trough and bind them evenly. Connect the other end of blue cable to the 48 V cable post, and the black cable to the RTN cable post on the KVMS, as shown in Figure 5-4.

III. Installing Power Cables for LAN Switches


The power input module of the LAN Switch is located at the left-back of the LAN Switch shell, as shown in Figure 5-6.

NEG(-) RTN(+)

(1)

(1) DC power input

Figure 5-6 Position of the power input module on a LAN Switch shell To install a power cable for a LAN Switch, proceed as follows: 1) Insert one end of the cable into the output connection hole on the PDB.

Huawei Technologies Proprietary 5-8

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 5 Installation of Protection Ground Cables and Power Cables

2) 3)

Use a cross screwdriver to loosen off panel screws that fix the LAN Switch on two sides of the rack. Then take off the mount angles on two sides of the LAN Switch. Standing at the cabinet rear, grasp the LAN Switch, and slowly and horizontally pull it out until you can use the screwdriver to loosen off captive screws on the power supply entrance of the equipment.

4) 5) 6)

Insert the other end of the cable into the plastic power input socket of the LAN Switch and fix the screws. Push the whole LAM Switch into the cabinet and install the mount angles. Then use the cross screwdriver to fix the panel screws. Route the power cable along the inside of the left column. Bind the redundant around the bundling bar nearby.

IV. Installing Power Cable for iGWB or BAM Server (HP Server)
The power input socket of iGWB or BAM server is at the rightmost on the back of server, and there are two power modules for dual power supplies. To install the power cable, do as follows: 1) Insert the cord end terminals of the blue cable into the 48V output connection hole on the PDB and the cord end terminals of the black cable into the RTN (or called BGND previously) output connection hole on the PDB. Fasten the screws. 2) 3) 4) 5) Connect the OT terminal of the protection grounding cable with the grounding bar of the cabinet, and fasten the fastening screws. Lay out the power cable downward along the cabling trough at the right side and bind it properly. Insert a 3V3 female connector into the 3V3 socket of the server, and fasten the plastic screws on the connector. Check and ensure that the connector is firmly locked by the fastener at the right of the socket. Figure 5-7 shows the power cable connection location and 3V3 socket.

Figure 5-7 Connection of power cable at server side

Huawei Technologies Proprietary 5-9

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 5 Installation of Protection Ground Cables and Power Cables

V. Installing Power Cables for iGWB and BAM Servers (IBM server)
Figure 5-8 shows the connection positions of power cables on a server. The DC power input socket of iGWB or BAM is at the rightmost of the server rear. A server has two power modules for dual power supplies.
A B C D P E F

K J

A PCI extended socket (unequipped) B RJ45 network card interface 2 C DB-15 alarm interface D PCI extended socket (equipped) E Input DC power supply(active) F Input DC power supply (standby) G Power module (standby) H Power module (active) I USB port 2 J Serial port 2 (RJ45 interface) K PB/2 interface contacts with the keyboard and the mouse. The mouse and the keyboard can contacted to PS/2 together by Y-shape KVMS. L RJ45 network card interface 1 M SCSI device interface (U320) N monitor interface O USB port 1 P Grounding bolt

Figure 5-8 Connection positions of power cables on an IBM server To install power cables for an iGWB or BAM server, proceed as follows: 1) Insert the cord end terminal of the blue cable into the 48V output connection hole on the PDB, route the power cable downward along the right cable trough, and connect the other end of the cable to a port marked "-" in the power module of the IBM server. 2) Insert the cord end terminal of the black cable into the RTN (or called BGND previously) output connection hole on the PDB, route the power cable downward along the right cable trough, and connect the other end of the cable to a port marked "+" in the power module of the IBM server. 3) Screw the OT terminal of the yellow and green cable on the ground bar of the cabinet. Connect the other end of the cable to the grounding point of the IBM server.

VI. Installing Power Cables for Hard Disk Array


The hard disk array has two power modules for dual power supplies. Each power module corresponds to one power input port marked "J1" as shown in Figure 5-9.

Huawei Technologies Proprietary 5-10

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 5 Installation of Protection Ground Cables and Power Cables

Figure 5-9 Power input port in hard disk array To install power cables for the hard disk array, proceed as follows: 1) Insert the cord end terminals of 48V cable and +RET cable into the power output connection holes on the PDB. Table 5-3 lists the mapping relation between the power cable terminals and the connection holes on the PDB. Table 5-3 Mapping relation between the power cable terminals and the connection holes on the PDB Power Module Power Cable Terminal 48V Left Power Module +RET 48V Right Power Module +RET RTN6 RTN1 48V6 Connection Hole on PDB 48V1

2)

Connect the OT terminal of the GND cable to the ground bar of the cabinet as shown in Figure 5-10.

Huawei Technologies Proprietary 5-11

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 5 Installation of Protection Ground Cables and Power Cables

Figure 5-10 GND connection 3) 4) Route the power cable along the cable trough to the hard disk array. Insert the other end of the power cable into power input port J1.

5.4.3 Installing PGND Cables Between Cabinets

Caution: For the convenience of installing and bundling other cables, connect ground bars of adjacent cabinets after installing all cables.

Use shorted lines to connect upper, middle, and lower parts of PGND bars of neighbor cabinets, as shown in Figure 5-11. The lines are 300 mm long, with the core area of 10 AWG.

5.4.4 Installing PGND Cables and Power Cables Between DC Distribution Cabinets and MSOFTX3000 Cabinets
If DC distribution cabinets are delivered with MSOFTX3000 devices, you must do in the following sequence: Install DC distribution cabinets. Through main PGND cables, securely connect the DC distribution cabinets with nearby PGND bars provided by the customer. Install PGND cables and power cables between the DC distribution cabinets and MSOFTX3000 cabinets.

Huawei Technologies Proprietary 5-12

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 5 Installation of Protection Ground Cables and Power Cables

Note: In an equipment room without DC distribution cabinets, install PGND cables and power cables as follows: Connect power cables led from 48V1 and 48V2 connecting terminals of MSOFTX3000 cabinets to 48 V DC negative line banks of DC switchboard or DC supply. Connect power cables led from RTN (or called BGND previously) connecting terminals of MSOFTX3000 cabinets to 48 V DC positive line banks of DC switchboard or DC supply. Connect PGND cables in the same way as in an equipment room with DC distribution cabinets.

Figure 5-11 shows the connection of PGND cables and power cables between DC distribution cabinets and MSOFTX3000 cabinets.

(2)
-48V1 -48V2 GND GND PGND -48V2 -48V1 RTN PGND -48V2 -48V1 RTN PGND -48V2 -48V1 RTN PGND

(1)

(3)

(3)

(3)

(4)
(1) To DC power switchboard (3) MSOFTX3000 cabinet (2) DC power distribution cabinet (4) Protection grounding bar in equipment room

Figure 5-11 Cable connection between a DC distribution cabinet and MSOFTX3000 cabinets

Huawei Technologies Proprietary 5-13

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 5 Installation of Protection Ground Cables and Power Cables

Caution: RTN in the present device is called BGND previously. Be sure to use connecting terminals of a DC distribution cabinet from top to bottom and from left to right (viewed from the front side) one by one. Similarly, use terminals for positive line banks and lightning protection ground one by one from left to right. However, if you lead power cables from power distribution cabinets, use terminals in a converse principle, that is, from bottom to top and from right to left.

To install PGND cables and power cables between a DC distribution cabinet and a MSOFTX3000 cabinet, proceed as follows: 1) Prepare cables. a) Measure the exact distance between the DC distribution cabinet and connecting terminals on the cabinet PDB. b) Prepare long enough cables. If you need a longer cable when routing cables, use a new long enough one and reroute it instead of splicing or soldering cables. 2) Mount connecting terminals for power cables. Mount OT terminals at the power cable ends connecting with the DC distribution cabinet in the following way: a) b) Mount heat shrinkable tubes. Apply soldering tin. For heavy-section power cables, you can skip over this step. c) Solder or crimp OT terminals firmly. Be sure that the heat shrinkable tubes fully cover bare wires and OT terminal shafts. For details about how to mount connecting terminals for power cables, see Appendix C "Assembly of Cable Connectors". 3) Route cables for the DC distribution cabinet. a) b) Lead cables in from the cable outlet on the cabinet top. Route them along the lateral columns of cabinet, and then along the cabinet beam to a bus bar. Figure 5-12 shows the upward cabling in a DC distribution cabinet.

Huawei Technologies Proprietary 5-14

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 5 Installation of Protection Ground Cables and Power Cables

Figure 5-12 Upward cabling in a DC distribution cabinet 4) Route cables for the MSOFTX3000 cabinet. Upward cabling a) b) Connect PGND cables to cable posts on the cabinet top. Connect 48 V power cables and RTN (or called BGND previously) cables to PDB terminals through the cable outlet on the cabinet top. Downward cabling a) Lead PGND cables and power cables into the cabinet through the rotten-proof net at the cabinet bottom. b) Route cables along cable troughs on lateral columns, and through the cable outlet to the cabinet top. c) The next steps are the same as those of upward cabling.
Huawei Technologies Proprietary 5-15

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 5 Installation of Protection Ground Cables and Power Cables

5)

Connect PGND cables (yellow or yellow and green). Rout the PGND cable (sourced from the GND copper bus bar of PDB) from the cabling rack to the top of the cabinet, and connect the PGND cable to the ground bolt on the top of the cabinet.

6)

Connect 48 V power cables (blue). Connect the cord end terminals to the connecting terminals marked with "48V1" and "48V2" on the cabinet PDB, and the other ends respectively to the 48V1 and 48V2 output terminals of DC distribution cabinet. Figure 5-13 shows connecting terminals in a DC distribution cabinet.

6 9 5

6 2 3

10

(1) GND lead-in terminal block (2) 48V1 power lead-in terminal block (3) 48V2 power lead-in terminal block (4) PGND lead-in terminal block (5) 48V1 output terminal block (6) 48V2 output terminal block (7) GND output terminal block (8) PGND output terminal block (9) GND lead-in terminal block for downward cabling of the system

Figure 5-13 Connecting terminals in a DC distribution cabinet 7) Connect ground cables (black). a) Insert the cord end terminal into the socket of connecting terminal marked with "RTN (or called BGND previously)" on the cabinet PDB and tighten screws. b) Connect the other end to the GND output terminal on the DC distribution cabinet. 8) Protect cables.

Huawei Technologies Proprietary 5-16

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 5 Installation of Protection Ground Cables and Power Cables

Cut a proper rubber cover to seal the left space of the cable outlet on the cabinet top. 9) Bind cables. a) b) c) Separate cables in different colors. Tidy them up. Bind them every 200 mm.

10) Stick labels on both ends of cables, 30 mm apart from cable roots. 11) Check that cabling conforms to the following principles: Outside cabinets, PGND cables and power cables are routed and bound separately from other cables. Inside cabinets, power cables and ground cables are bound along inside cable troughs, whereas, signal cables along outside cable troughs. The routed cables are smooth without cross, rounded off at turnings. Reserved cable margins are proper. Flat washers and spring washers are added orderly for connecting OT terminals to GND copper bus bars or 48 V cable post.

5.4.5 Installing Power Bus Cables Between DC Distribution Cabinets and DC Switchboards
Power bus cables between DC distribution cabinets and DC switchboards include 48 V cables (blue) and ground cables (black), provided by the customer. Their specifications depend on engineering survey results.

Note: For how to count the core areas of these power bus cables, see Appendix B "Core Area Calculation of Power Bus Cables". If the sectional area of one existing power bus cable fails to meet the design requirement, combine two or more.

A DC distribution cabinet uses two groups of primary power supplies through five power bus cables: one 48V1 cable, one 48V2 cable, two ground cables, and one PGND cable. To connect these cables, proceed as follows: 1) Prepare cables. a) Measure the exact distances: Between the DC distribution cabinet and DC switchboard or DC supply Between the DC distribution cabinet and PGND bridge

Huawei Technologies Proprietary 5-17

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 5 Installation of Protection Ground Cables and Power Cables

b)

Prepare long enough cables. If you need a longer cable when routing cables, use a new long enough one and reroute it instead of splicing or soldering cables.

2)

Mount connecting terminals for power bus cables. Mount OT terminals at the power bus cable ends connecting with the DC distribution cabinet in the following way: a) b) Mount heat shrinkable tubes. Apply soldering tin. For heavy-section power bus cables, you can skip over this step. c) Solder or crimp OT terminals firmly. Be sure that the heat shrinkable tubes fully cover bare wires and OT terminal shafts. For details about how to mount connecting terminals for power bus cables, see Appendix C "Assembly of Cable Connectors".

3)

Route cables for the DC distribution cabinet. a) b) Lead cables in from the cable outlet on the cabinet top. Route them along the lateral columns of cabinet, and then along the cabinet beam to a bus bar. For upward cabling in a DC distribution cabinet, see Figure 5-12.

4)

Route cables for the DC switchboard. See step 3).

5)

Connect PGND cables (yellow or yellow and green). Securely connect the PGND bar of DC distribution cabinet to the PGND bar in the equipment room through main PGND cables.

6)

Connect 48 V power bus cables (blue). Connect one end respectively to the 48V1 and 48V2 input terminals on the cabinet PDB, and the other ends respectively to the 48 V DC negative line banks of DC switchboard or DC supplies. For connecting terminals in a DC distribution cabinet, see Figure 5-13.

Note: For the equipment with single power supply, connect both 48V1 and 48V2 input terminals of DC distribution cabinet to the 48 V output terminals of DC switchboard or DC supply.

Huawei Technologies Proprietary 5-18

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 5 Installation of Protection Ground Cables and Power Cables

7)

Connect GND cables (black). Connect one end of the GND cable to the GND input terminal on the cabinet PDB, and the other end to the 48 V DC positive line bank of DC switchboard or DC supplies. For connecting terminals in a DC distribution cabinet, see Figure 5-13.

8)

Bind cables. a) b) c) Separate cables in different colors. Tidy them up. Bind them every 200 mm.

9)

Stick labels on both ends of cables, 30 mm apart from cable roots. Cables within cabinets are smooth without cross, bound in the same colors. Reserved cable margins are proper. As needed, cables are bound by ties of different types. The cable ties are in the same direction, sheared without sharp ends. Flat washers and spring washers are added for securely fixing OT terminals, as shown in Figure 5-14.
(1)

10) Check that cabling conforms to the following principles:

(2)

(6)

(5) (3)

(5) (4)

(1) Cable (4) Spring washer

(2) Heat-shrinkable tube (3) Nut (5) Flat washer (6) Connection bolt

Figure 5-14 Mounting an OT terminal If you connect two or more power bus cables to a cable post, OT terminals must be mounted crosswise or back to back rather than overlapped.

Huawei Technologies Proprietary 5-19

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 5 Installation of Protection Ground Cables and Power Cables

If you must overlap OT terminals, the terminals must be bent by 45 or 90. Moreover, the biggest OT terminal is at the lower position. Figure 5-15 shows how to install two OT terminals.
45 90

2 3 (4)

2 3

60

1 (5)

2 3

123 (6)

(1) Flat washer (4) 45 degree or 90 degree of bending (6) Cross installation

(2) Spring washer (3) Nut (5) Back-to-back installation

Figure 5-15 Mounting two OT terminals

Huawei Technologies Proprietary 5-20

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 6 Signal Cable Installation

Chapter 6 Signal Cable Installation


6.1 Introduction to the Chapter
This chapter introduces signal cable types, and requirements and procedures of installing signal cables.

6.2 Introduction to Signal Cables


Signal cables include internal and external signal cables. Among external signal cables, clock cables and trunk cables are optional, depending on actual hardware configuration.

6.2.1 Signal Cable Types


I. Internal Signal Cables
Internal signal cables include: Straight through cables between LAN Switches Straight through cables between LAN Switches and iGWB or BAM servers Straight through cables between LAN Switches and WHSCs Straight through cables between WHSCs and WSIUs Serial cables between iGWB servers Data cables between iGWB and hard disk array Cables between servers and KVMS PDB monitoring serial cables Internal clock cables (optional)

II. External Signal Cables


External signal cables include: Trunk cables (optional) External clock cables (optional) External Ethernet cables Optical fiber cables

6.2.2 Connection of Internal Signal Cables


I. When HP Servers Are Used as iGWBs
Figure 6-1 shows the method for connecting internal cables installed on site, and Table 6-1 shows the relationships between numbers and names of internal cables.

Huawei Technologies Proprietary 6-1

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 6 Signal Cable Installation


(1)

-48V1

BGND1 -48V2

BGND2 -48V3

BGND3 -48V4

BGND4 -48V5

BGND5 -48V6

BGND6

QW11WSTB COM1 COM2

23 24

WHSC WSIU

WHSC WSIU 48

WEPI

WEPI

(2)

2M-A

2M-A 2M-B 8k-B

50 40 25 44 26 39
2M-B 8k-B

43

27

28

E1/T1 8k-A

E1/T1 8k-A

46

45

WCKI
BITS1 BITS2 LINE1 LINE2

WCKI
BITS1

WHSC WSIU WHSC WSIU 47 49 50

WEPI

WEPI

(3)

47 48

BITS2 LINE1 LINE2

2M-A

2M-A 2M-B 8k-A


E1/T1

49 29 23
8k-A

43 44

45

46

42

2M-B

41

24

E1/T1

8k-B

30

31

32

8k-B

W9

W10

W8

KVMS
41 39

LAN Switch1
34 42 36 38 40

LAN Switch0

33

35

37

BAM
33 34 W8

35 36 52

iGWB(S)
W9

iGWB(M)
37 38 W10

(1) Power distribution subrack

(2) Expansion subrack

(3) Basic subrack

Figure 6-1 Connection of internal cables in an integrated configuration cabinet

Huawei Technologies Proprietary 6-2

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 6 Signal Cable Installation

Table 6-1 Correspondence between numbers and names of internal cables in an integrated configuration cabinet Serial No. 1 2 3 4 5 6 7 8 Cable number 52 3338 3942 2324 4750 4346 2532 W8W10 Cable name A serial cable between iGWB servers Straight through cables between LAN Switches and the iGWB/BAM servers Straight through cables between WHSCs and LAN Switches PDB monitoring serial cables 2 MHz clock cables 8 kHz clock cables FE cable between WHSC and WSIU Cables between servers and KVMS Quantity 1 6 4 2 4 4 8 3

Note: Except those for LAN Switches, the cables shown in Figure 6-1 are all connected at the back of the cabinet. Figure 6-1 does not show the straight through cable between LAN Switches.

II. When IBM Servers Are Used as iGWBs


Figure 6-2 shows the connection of internal cables installed on site.

Huawei Technologies Proprietary 6-3

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 6 Signal Cable Installation

-48V1 BGND1 -48V2

BGND2 -48V3

BGND3 -48V4

BGND4 -48V5

BGND5 -48V6

BGND6

QW11WSTB COM1 COM2

(1)

23 24

WHSC WSIU

WHSC WSIU 48

WEPI

WEPI

(2)

2M-A

2M-A 2M-B 8k-B

50 40 25 26 39 44
2M-B 8k-B

43

27

28

E1/T1 8k-A

E1/T1 8k-A

46

45

WCKI
BITS1 BITS2 LINE1 LINE2

WCKI
BITS1

WHSC WSIU WHSC WSIU 47 49 50 49 42 29 23 41

WEPI

WEPI

(3)

47 48

BITS2 LINE1 LINE2

2M-A 2M-B 8k-A

2M-A 2M-B 8k-A


E1/T1

43 44

45

46

24

E1/T1

8k-B

30

31

32

8k-B

W9

W10

W8

KVMS
41 39

LAN Switch1
34 42 36 38 40

LAN Switch0

33

35

37

(4)
W3 W2

34 33 W8 36 35 W9 38 37 W10 52

BAM

iGWB(S)

iGWB(M)

(1) Power distribution subrack

(2) Expansion subrack

(3) Basic subrack

Figure 6-2 Connection of internal cables in an integrated configuration cabinet

Huawei Technologies Proprietary 6-4

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 6 Signal Cable Installation

Table 6-2 provides the correspondence between the cable numbers in Figure 6-2 and cable names. Table 6-2 Correspondence between numbers and names of internal cables in an integrated configuration cabinet Serial No. 1 2 3 4 5 6 7 8 9 Cable number 52 3338 3942 2324 4750 4346 2532 W2W3 W8W10 Cable name A serial cable between iGWB servers Straight through cables between LAN Switches and the iGWB/BAM servers Straight through cables between WHSCs and LAN Switches PDB monitoring serial cables 2 MHz clock cables 8 kHz clock cables Straight through cables between WHSCs and WSIUs Data cables between iGWB and hard disk array Cables between servers and KVMS Quantity 1 6 4 2 4 4 8 2 3

Note: Except those for LAN Switches, the cables shown in Figure 6-2 are all connected at the back of the cabinet. Figure 6-2 does not show the straight through cable between LAN Switches.

6.3 Installation Requirements


This section presents requirements and modes of cabling.

6.3.1 Cabling Requirements


Route signal cables in accordance with the following requirements: Before installing a cable, mark it or stick engineering labels to it at both ends to indicate connected devices and its sequence. For details, see Appendix D "Facture of Cable Labels". Separately route and bind cables of different types, such as power cables, signal cables, and ground cables. When routing cables inside a cabinet, bind power

Huawei Technologies Proprietary 6-5

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 6 Signal Cable Installation

cables and ground cables along inside cable troughs, whereas, bind signal cables along outside cable troughs. When routing cables vertically, route and bind them along left and right columns. When routing cables horizontally, route and bind them along bundling bars. If you route power cables and signal cables in a same groove, maintain at least 50 mm between them and bind them separately. Ensure that joint parts of connectors are secure and in good contact. Bind cables tidily and with proper tightness.

6.3.2 Cabling Modes


There is one rectangle cable hole at each of the four corners on the top and at the bottom of a cabinet, as shown in Figure 6-3. All the cable holes are equipped with plastic rodent-proof bags.

Huawei Technologies Proprietary 6-6

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 6 Signal Cable Installation

Figure 6-3 Positions of cable holes on a cabinet You must lead cables into or out of N68-22 cabinets from the back. With respect to actual conditions of an equipment room, you can route cables upward on cable racks or downward on the floor.

Huawei Technologies Proprietary 6-7

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 6 Signal Cable Installation

Caution: When routing cables through the cable holes equipped with plastic rodent-proof bags, lead cables through the bags. After cabling, tie the plastic rodent-proof bags and ensure no space left around the cables. Be sure to tidy up cables and bind them in coils. Leading cables into or out of cabinets only differ in directions.

Upward cabling Route cables as follows: 1) 2) Lead cables into the cabinet through the two back cable holes on the top of the cabinet. Route them down along the side columns of the cabinet to connected devices. Downward cabling Route cables as follows: 1) 2) Lead cables into the cabinet through the two back cable holes at the bottom of the cabinet. Route them up along the side columns of the cabinet to connected devices.

Downward cabling is fit for antistatic floors. You need to route external cables through cable troughs or racks. For detailed methods, see Appendix A "Cabling Rack Installation".

6.4 Installing Internal Signal Cables


This session presents the procedures of installing internal signal cables.

6.4.1 Installation Procedure


Figure 6-4 shows the flowchart of installing internal signal cables.

Huawei Technologies Proprietary 6-8

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 6 Signal Cable Installation

Start

Install straight through cables between LAN Switches

Install straight through cables between LAN Switches and iGWB/BAM servers

Install straight through cables between LAN Switches and WHSCs

Install straight through cables between WHSCs and WSIUs

Install serial cables between iGWB servers

Install data cables between iGWB and hard disk array

Install cables between servers and KVMSs

Install PDB monitoring serial cables

Install internal clock cables

End

Figure 6-4 Flowchart of installing internal signal cables

6.4.2 Installing Straight Through Cables Between LAN Switches


Through straight through cables, the active and standby LAN Switches in an integrated configuration cabinet can: Detect heartbeat signals. Work in redundancy mechanism. Ensure data security. To install a straight through cable between an active and a standby LAN Switch, proceed as follows:
Huawei Technologies Proprietary 6-9

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 6 Signal Cable Installation

1) 2) 3) 4)

Insert the RJ-45 connectors at both cable ends respectively into the Ethernet ports on the FE modules in the front of the LAN Switches. Tidy up the cable and bind it along cable troughs. Make and stick labels. Check that the cable is correctly connected.

6.4.3 Installing Straight Through Cables Between LAN Switches and iGWB/BAM Servers
An integrated configuration cabinet is configured with two iGWB servers and one BAM server. Two straight through cables connect a server respectively with the active and standby LAN Switches. Because the ports of LAN Switches are arranged on the front panels, while the ports of the servers are arranged on the back panels, it is required to lay the network cables which connect the servers and LAN Switches through cabling trough to the back.

Note: BAM is configured with four network adapters before delivery: network adapters 0 to 3. (The numbering principle is from left to right and from bottom to top.)

I. When HP Servers Are Used as iGWBs/BAM


The port configuration scheme is as follows: The network port of network adapter 1 (position: upper left) is connected to LAN Switch 0, and the network port of network adapter 2 (position: on the left of the rightmost network adapter) is connected to LAN Switch 1, as shown in Figure 6-1. To install the cables, proceed as follows: 1) In accord with the port configuration scheme, insert the RJ-45 connectors at one end of the cables into the associated Ethernet ports on the front panels of LAN Switches. 2) Route the cables along the cable tray under each LAN Switch to the cabinet rear. Separate the cables and route them down along the vertical cable troughs at the sides. 3) 4) 5) 6) Evenly bind the cables, with some margins reserved at turnings. Insert the RJ-45 connectors at the other end of cables into associated ports of servers, as shown in Figure 6-5. Make and stick labels. Check that the cables are correctly connected.

Huawei Technologies Proprietary 6-10

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 6 Signal Cable Installation

Figure 6-5 Connection positions of straight through cables on HP server

Note: Straight through cables also connect the BAM server and emergency workstations with hubs. In this way, emergency workstations can periodically back up BAM data. Install two straight through cables between an emergency workstation and the active and standby LAN Switches. When the BAM server works normally, the two cables are disconnected. In case of BAM failure, connect the two cables for the emergency workstation to assume the functions of BAM server.

II. When IBM Servers Are Used as iGWBs/BAM


The port configuration scheme is as follows: The network port of network adapter 1 (position: upper left) is connected to LAN Switch 0, and the network port of network adapter 2 (position: lower right) is connected to LAN Switch 1, as shown in Figure 6-2. To install the cables, proceed as follows: 1) In accord with the port configuration scheme, insert the RJ-45 connectors at one end of the cables into the associated Ethernet ports on the front panels of LAN Switches. 2) Route the cables along the cable tray under each LAN Switch to the cabinet rear. Separate the cables and route them down along the vertical cable troughs at the sides. 3) 4) Evenly bind the cables, with some margins reserved at turnings. Insert the RJ-45 connectors at the other end of cables into associated ports of servers, as shown in Figure 6-6.
Huawei Technologies Proprietary 6-11

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 6 Signal Cable Installation

5) 6)

Make and stick labels. Check that the cables are correctly connected.

Figure 6-6 Connection positions of straight through cables on IBM server

Note: Straight through cables also connect the BAM server and emergency workstations with hubs. In this way, emergency workstations can periodically back up BAM data. Install two straight through cables between an emergency workstation and the active and standby LAN Switches. When the BAM server works normally, the two cables are disconnected. In case of BAM failure, connect the two cables for the emergency workstation to assume the functions of BAM server.

6.4.4 Installing Straight Through Cables Between LAN Switches and WHSCs
Each of the active and standby WHSCs in a basic or an extension subrack has six 10/100 Mbit/s Ethernet ports. By using straight through cables, the ports marked "10/100BT6" at the uppermost of the active and standby WHSCs are connected to the active and standby LAN Switches respectively. Thus, the service processing subsystem can communicate with the BAM, and service processing subracks can interconnect with each other. To install straight through cables between LAN Switches and WHSCs, proceed as follows: 1) 2) Insert the RJ-45 connectors at one end of two cables respectively into the uppermost ports 10/100BT6 of the active and standby WHSCs. Route the cables in the following ways:

Huawei Technologies Proprietary 6-12

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 6 Signal Cable Installation

If the active and standby WHSCs reside in an integrated configuration cabinet, route the cables along their subrack beams, then down along the vertical cable troughs at the sides, and along the cable trough under each LAN Switch to the front panels of LAN Switches. If the active and standby WHSCs reside in a service processing cabinet, lead the cables connecting WHSCs with the LAN Switches in the integrated configuration cabinet out of the service processing cabinet. For the methods of leading cables into or out of cabinets, see section 6.3.2 "Cabling Modes". 3) 4) 5) 6) Evenly bind the cables, with some margins reserved at turnings. Following the port configuration scheme, insert the RJ-45 connectors at the other end of the cables into the Ethernet ports on the front panels of LAN Switches. Make and stick labels. Check that the cables are correctly connected. That is, the WHSC in slot 7 connects with the LAN Switch in slot 1 and the WHSC in slot 9 with the LAN Switch in slot 0.

6.4.5 Installing Straight Through Cables Between WHSCs and WSIUs


To install a straight through cable between a WHSC and a WSIU, proceed as follows: 1) 2) 3) 4) Insert the RJ-45 connectors at the ends of the cable respectively into the Ethernet ports of the WHSC and WSIU, as shown in Figure 6-7. Tidy up the cable and bind it along cable troughs. Make and stick labels. Check that the cable is correctly connected.

WHSC
10/100 10/100

WSIU

WHSC
10/100 10/100 10/100 10/100

WSIU

BT1 BT2 BT3 BT4 BT5 BT6

10/100 COM3+ COM3 10/100

BT1 BT2 BT3 BT4 BT5 BT6

10/100 COM3+ COM3 10/100

10/100 10/100

BT1

10/100 10/100

10/100 10/100

Figure 6-7 Connection positions of straight through cables between WHSCs and WSIUs

Huawei Technologies Proprietary 6-13

BT2

BT2

BT1

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 6 Signal Cable Installation

6.4.6 Installing Serial Cables Between iGWB Servers


To ensure the dual backup working mode and security of iGWB servers, connect the two iGWB servers in the integrated configuration cabinet through a serial cable. The cable also serves as the second transfer path of heartbeat signal for the dual backup of iGWB servers.

I. When HP Servers Are Used as iGWB/BAM


To install a serial cable between iGWB servers, proceed as follows: 1) 2) 3) 4) Connect the two ends of the cable respectively to the RS232 serial ports at the back of the iGWB servers. Tidy up the cables and bind them along cable troughs. Make and stick labels. Check that the cables are correctly connected.

Note: The active and standby iGWB servers are connected with the bill console or network management devices through a hub. The external network cable connecting with the hub also serves as the first transfer path of heartbeat signal for the dual backup of iGWB servers. An RS232 serial port resides on the right of the KVMS port at the back of an iGWB server, as shown in Figure 6-5.

II. When IBM Servers Are Used as iGWB/BAM


To install a serial cable between iGWB servers, proceed as follows: 1) 2) 3) 4) Connect the two ends of the cable respectively to the RJ45 serial ports at the back of the iGWB servers. Tidy up the cables and bind them along cable troughs. Make and stick labels. Check that the cables are correctly connected.

Huawei Technologies Proprietary 6-14

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 6 Signal Cable Installation

Note: The active and standby iGWB servers are connected with the bill console or network management devices through a hub. The external network cable connecting with the hub also serves as the first transfer path of heartbeat signal for the dual backup of iGWB servers. An RJ45 serial port resides on the right of the KVMS port at the back of an iGWB server, as shown in Figure 6-6.

6.4.7 Installing Data Cables Between iGWB and Hard Disk Array
The two data cables between the iGWB and the hard disk array are delivered with the hard disk array. To install cables between the iGWB and the hard disk array, proceed as follows: 1) 2) Connect one end of a data cable to the SCSI port in the hard disk array as shown in Figure 6-8. Connect the other end of the data cable to extended SCSI port in the PCI of the iGWB as shown in Figure 6-9.

Figure 6-8 Connection position of a data cable on the hard disk array

Figure 6-9 Connection position of a data cable on the iGWB

Huawei Technologies Proprietary 6-15

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 6 Signal Cable Installation

6.4.8 Installing Cables Between Servers and KVMS


The KVMS transmits keyboard, mouse, and video signals to different servers for the convenience of equipment O&M. To install cables between servers and a KVMS, proceed as follows: 1) Insert a set of cables between a server and the KVMS, including a keyboard cable, a mouse cable, and a display cable, respectively into associated ports on the KVMS. 2) 3) 4) 5) 6) Lead the cables down along the side columns of cabinet. Bind the signal cables tidily apart from power cables, with redundant parts around adjacent bundling bars. Combine the three cables into one at the server end and insert its D-shape connector into the OUT port on a server. Make and stick labels. Check that the cables are correctly connected. Figure 6-10 shows the cable connection between servers and a KVMS: BAMPC1, iGWB(M)PC2, and iGWB(S)PC3.

KVMS

-48V GND PGND PC4 PC3 PC2 PC1

BAM

iGWB(S)

iGWB(M)

Figure 6-10 Cable connection between servers and a KVMS

6.4.9 Installing PDB Monitoring Serial Cablesserial cable


To install a PDB monitoring serial cable, proceed as follows: 1) 2) Connect one end of the cable to the serial port socket of power distribution monitor and control unit (WDMC) at the PDB rear. Route the cable along the outer side of right cable trough at the cabinet rear and bind it.

Huawei Technologies Proprietary 6-16

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 6 Signal Cable Installation

3) 4) 5)

Connect the other end of the cable to the monitoring port COM3 of a WSIU. Make and stick labels. Check that the cables are correctly connected.

Note: In an integrated configuration cabinet, monitoring serial cables connect the PDB with the WSIUs in the basic subrack. In a service processing cabinet, monitoring serial cables connect the PDB with the WSIUs in the lowest service subrack.

6.4.10 Installing Internal Clock Cables


Internal clock cables between service subracks include 2 MHz and 8 kHz clock cables.

I. Installing 2 MHz Internal Clock Cables


Use two 2 MHz clock cables to connect two WCKIs with the active WEPI in the basic subrack. Proceed as follows: 1) 2) 3) 4) Insert the two ends of a cable respectively into one WCKI and the active WEPI. Route the cable along the cable troughs in the subrack and bind it. Make and stick labels. Check that the cable is correctly connected, as shown in Figure 6-11.

WCKI
BITS1 BITS2 LINE1 LINE2
1 3 5 7 9 11 13 15 2 4 6 8 10 12 14 16

WCKI
BITS1 BITS2 LINE1 LINE2
1 3 5 7 9 11 13 15 2 4 6 8 10 12 14 16

WEPI WEPI

WEPI WEPI

2M-A

2M-A

2M-A

2M-A

2M-B 8K-A

2M-B 8K-A

2M-B 8K-A

2M-B 8K-A E1/T1 8K-B

E1/T1 8K-B

E1/T1 8K-B

E1/T1 8K-B

Figure 6-11 Connection of 2 MHz clock cables

Huawei Technologies Proprietary 6-17

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 6 Signal Cable Installation

Note: If a basic subrack is configured with more than one pair of WEPIs, use two 2 MHz clock cables to connect another active WEPI to the ports LINE2 of the active and standby WCKIs.

II. Installing 8 kHz Internal Clock Cables


Proceed as follows: 1) 2) Insert one end of clock cables into the WCKIs in the basic subrack. Route the cables in the following ways: If the extension subrack resides in an integrated configuration cabinet, a) b) Lead the cables out of the WCKIs and vertically into the cable trough in the subrack. Separate the cables along the two sides of cabinet up to the extension subrack. If the extension subrack resides in a service processing cabinet, see section 6.3.2 "Cabling Modes". 3) 4) 5) 6) Tidy up the cables and bind them. Insert the other end of the cables into the WEPIs in an extension subrack. Make and stick labels. Check that the cables are correctly connected, as shown in Figure 6-12.

WCKI
BITS1 BITS2 LINE1 LINE2
1 3 5 7 9 11 13 15 2 4 6 8 10 12 14 16

WCKI
BITS1 BITS2 LINE1 LINE2
1 3 5 7 9 11 13 15 2 4 6 8 10 12 14 16

WEPI WEPI

2M-A

2M-A

2M-B 8K-A

2M-B 8K-A E1/T1 8K-B

E1/T1 8K-B

Figure 6-12 Connection of 8 kHz clock cables

Huawei Technologies Proprietary 6-18

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 6 Signal Cable Installation

6.5 Installing External Signal Cables


This session presents the procedures of installing external signal cables. MSOFTX3000 external signal cables include trunk cables, external clock cables, external Ethernet cables, and Optical fiber cables. Cables of the first two types are optional, depending on actual networking configuration.

6.5.1 Installation Procedure


Figure 6-13 shows the flowchart of installing external signal cables.
Start

Install external clock cables (optional)

Install trunk cables (optional)

Install external Ethernet cables

Install fiber-optic cables

End

Figure 6-13 Flowchart of installing external signal cables

Note: Normally, route trunk cables and external clock cables in the same way and bind them together. Therefore, it makes no difference which type of cable is installed first.

6.5.2 Installing Clock Cables Between the MSOFTX3000 and BITS Devices
Devices of the building integrated timing supply system (BITS) provide 2 MHz analog and 2 Mbit/s digital clock signals. Through the ports BITS1 and BITS 2, the WCKI extracts clock signals from the BITS. To install a pair of clock cables, proceed as follows:

Huawei Technologies Proprietary 6-19

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 6 Signal Cable Installation

1) 2) 3) 4) 5) 6)

Connect one end of the cables respectively to the SMB ports BITS1 and BITS2 of a WCKI in the basic subrack. Route the cables in the same way as routing trunk cables. For details, refer to 6.5.3 2). Tidy up the cables and bind them. Connect the other end of the cables respectively to the BITS clock source. Make and stick labels. Check that the cables are correctly connected.

WCKI
BITS1 BITS2 LINE1 LINE2
1 3 5 7 9 11 13 15 2 4 6 8 10 12 14 16 1 3 5 7 9

WCKI
BITS1 BITS2 LINE1 LINE2
2 4 6 8 10 12 14 16

BITS1

BITS2

11 13 15

Figure 6-14 Connection of external clock cables

6.5.3 Installing Trunk Cables Between the MSOFTX3000 and DDF


Route trunk cables in conformity to the following principles: Before cabling, measure the exact length needed. If cables are not long enough during actual cabling, reroute proper cables. If you need to lengthen cables, do not solder cables. Instead, splice cables using dedicated coaxial cable connector. In an equipment room with the antistatic floor, downward cabling is preferred. Bend cables at cabinet bottoms or tops and reserve some margins. Lead them into the cabinet, and lay them along both sides of the cabinet. Distribute them to the subracks one by one. Other cabling positions or directions are not allowed. For upward cabling, lay cable racks over cabinets for routing cables.
Huawei Technologies Proprietary 6-20

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 6 Signal Cable Installation

When cables go out of cable racks, lead them from the side of racks rather than between rack rungs. If the distance between cable racks and cable troughs on cabinet tops is within 0.8 m, cables can directly go from cable racks to cable troughs. If the distance between cable racks and cable troughs on cabinet tops is over 0.8 m, use downward cable ladders to fix cables.

Note: The WEPI is configured in the active-standby mode. However, only the active WEPI connects with trunk cables.

To install a trunk cable, proceed as follows: 1) Connect the DB50 connector of trunk cable to the 50-pin socket on the active WEPI, as shown in Figure 6-15.
WEPI

(1) 50-pin socket

(2) DB50 connector

(3) E1 cable

Figure 6-15 Connection of a trunk cable and a WEPI 2) Route the cable in the following way: a) b) c) Lead the cable out of the WEPI panel. Route it up or down along the left side column at the cabinet rear and then out of the cabinet. Route it along cable racks or troughs to the distribution frame in the equipment room. For the methods of upward or downward cabling, see section 6.3.2 "Cabling Modes". 3) 4) Tidy up the cable and bind it. Connect the other end of the cable to a digital distribution frame (DDF). If the cable is a 75-ohm coaxial cable, insert its SMB connector.

Huawei Technologies Proprietary 6-21

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 6 Signal Cable Installation

If the cable is a 120-ohm twisted pair, use a dedicated cable fixture to fix the cable on the cable distribution box of DDF. 5) 6) Make and stick labels. Check that the cable is correctly connected.

6.5.4 Installing External Ethernet Cables


External Ethernet cables connect external networking devices to external Ethernet ports on back interface boards of the MSOFTX3000 devices. Table 6-3 provides the port connecting information of the WBFI (single port, double ports) Table 6-3 Network port connecting information of the WBFI (single network port, double network ports) Pairing relation of boards WBFI (double network ports) + WIFM (750C board series) WBFI (single network port) + WIFM (750C board series) Port to Connect on the WBFI 10/100BT2 10/100BT

Note: For the differences between 750C board series and 750B board series, refer to Appendix A of MSOFTX3000 Hardware Description.

To install an external Ethernet cable for a MSOFTX3000 device, proceed as follows: 1) 2) 3) 4) 5) Locate the external device and connect the cable to it. Route the cable in the same way as routing trunk cables. For details, see 6.5.3 2). Tidy up the cable and bind it. Make and stick labels. Check that the cable is correctly connected.

6.5.5 Installing Optical Fibers


I. Connecting Optical Fibers
The WBAI is the optical interface board of MSOFT3000, and it has two optical interface subboards. Each subboard provides one 155 Mbit/s port. One the front panel of optical interface subboard, "TX" indicates transmitting and "RX" indicates receiving. Generally, the optical fibers are marked "1" and "2" or "A" and "B" on one end. "1" or "A" is connected to the transmitting port on optical interface subboard, and "2" or "B" is connected to the receiving port of optical interface subboard. The other end of the optical fiber is connected to the optical distribution frame (ODF).
Huawei Technologies Proprietary 6-22

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 6 Signal Cable Installation

II. Laying Optical Fibers


To install the optical fibers, use corrugated tube delivered with the equipment to cover them. For the optical fibers from the ODF to MSOFTX3000, lead the optical fibers into the cabinet from the top or bottom of the cabinet according to the specific cabling mode on site. The fibers inside the cabinet do not need to be covered with corrugated tube. Pay attention to the following items when you lay optical fibers: Do not fold, stretch or press the optical fibers. Never fold the optical fiber to right angle. If necessary, make circular arc to curve the fiber. The diameter of the circular arc must not be less than 80 mm, and fibers in pair must be bound neatly. To lay the optical fibers, use curves as few as possible, and do not tighten cable ties. If fibers are laid between rows and columns, lay the fibers through cabling bridge and use corrugated plastic tubes when cabling bridge is adopted. Lay the optical fibers conforming to their nature. Do not force to pull or stretch the fibers. The fibers on horizontal lever must be bound every 150 mm with proper strength. The labels at both ends of an optical fiber must be clear indicating the corresponding numbers and relations between cabinets and between cabinet rows.

Caution: Be careful to insert and pull out optical fiber. Use a little strength to insert the fiber until the fiber snaps in the place. To pull fibers out, do not force to pull them. First, pinch the handle of the connector, push it in softly and then pull it out. Direct pulling might damage the optical connector. Take care of laser components and end surface of optical connector. Use absorbent cotton with alcohol to clean them when necessary. Do not look at the end surface of the fiber powered on. Cover the optical fiber with a dust-proof cover when the fiber is not in use.

Huawei Technologies Proprietary 6-23

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 7 Cabinet Fittings Installation

Chapter 7 Cabinet Fittings Installation


7.1 Introduction to the Chapter
This chapter describes how to install cabinet fittings. It consists of the following sections: Cabinet Door Assembly Installation Procedure Installing Side Panels Installing Front and Back Doors Installing PGND Cables for Cabinet Doors

7.2 Cabinet Door Assembly


The cabinet door assembly includes the following: Side panels Front door and back door

Huawei Technologies Proprietary 7-1

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 7 Cabinet Fittings Installation

Figure 7-1 shows the cabinet door assembly.


3 2 1

1 Left front door

2 Right front door

3 Side panels

Figure 7-1 Cabinet door assembly

Huawei Technologies Proprietary 7-2

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 7 Cabinet Fittings Installation

7.3 Installation Procedure


Figure 7-2 shows the flowchart of installing cabinet doors.
Start

Install side panels

Install front and back doors

Install PGND cables for cabinet doors

End

Figure 7-2 Flowchart of installing cabinet doors

7.4 Installing Side Panels


Install side panels on both sides of a cabinet row. To install a side panel, do as follows: 1) 2) 3) 4) 5) Loosen the M 6x16 combination screws for installing the side panel. Fit the mounting slot of the side panel into the M 6x16 combination screws from the top down. Buckle the doors panel onto the open slot of the mount bracket for lintels. Align the mounting holes. Use two M 6x12 countersunk screws to fasten the panel.

Huawei Technologies Proprietary 7-3

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 7 Cabinet Fittings Installation

Figure 7-3 shows how to install a side panel.

4 1 2

1 M 616 combination screw 3 M 6x12 countersunk screws

2 Mounting slot of the side panel 4 Rack

Figure 7-3 Installing a side panel

7.5 Installing Front and Back Doors

Note: Moving pins are installed on door panels before delivery. After installing front and back doors for a cabinet, stick product brands in the concave on the front door upside.

The front door and back door of the cabinet are double swing doors. The installations of the front door and the back door are the same. The following takes the installation of the front door for example. To install the front door, do as follows: 1) Align the lower pin of the door panel with the pin hole on the lower enclosure frame.
Huawei Technologies Proprietary 7-4

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 7 Cabinet Fittings Installation

2) 3) 4) 5)

Fix the lower part of the panel. Pull down the triangular hook pin at the upper part of the door panel. Align the hole of the hook pin with the pin hole on the upper enclosure frame. Release the hook pin. The hook pin bounces back to the original position and locks the panel on the cabinet.

Figure 7-4 shows how to install the front door.


2

A
Figure 7-4 Installing the front door

Huawei Technologies Proprietary 7-5

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 7 Cabinet Fittings Installation

7.6 Installing PGND Cables for Cabinet Doors


After installing side, front, and back doors, install PGND cables near lower pins to securely ground cabinet door panels. Figure 7-5 shows the ground point on a door panel and the ground screw on a cabinet base.

1 5 2 8 3 4 9 7

10

1 3 5 7 9

Front or back door Cabinet base Ground bar on a side column Ground point on a front or back door PGND cable for side doors

2 Side door 4 Ground point on the base 6 Ground point on a side door 8 PGND cable for cabinet base 10 PGND cable for front or back doors

Figure 7-5 Connection of PGND cables for cabinet door panels You must install four PGND cables for side doors as shown in Figure 7-5 at the downside of a cabinet. They respectively connect the ground points of four side doors with those on the cabinet base. You also need to install four PGND cables for front or back doors at the cabinet downside. The cables connect the ground points of front and back doors with those on the cabinet base.

Huawei Technologies Proprietary 7-6

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 8 Peripheral Installation

Chapter 8 Peripheral Installation


8.1 Introduction to the Chapter
This chapter tells about the procedures of installing peripherals.

8.2 Installation Procedure


Figure 8-1 shows the flowchart of installing peripherals.
Start

Install terminal devices

Install alarm devices

Route cables for terminal devices

End

Figure 8-1 Flowchart of installing peripherals

8.3 Installing Terminal Devices


The MSOFTX3000 may connect with multiple computers, that is, workstations (WSs). They respectively act as O&M terminals, billing terminals, alarm terminals, and emergency WSs. The terminals communicate with the BAM by means of: Direct connection through Ethernet cables Remote access through Modems

Huawei Technologies Proprietary 8-1

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 8 Peripheral Installation

Figure 8-2 shows the connection of a remote terminal system.

LAN Switch 1

NI 3 NI 2 NI 1 NI 0 SP1 SP2 Emergency workstation

LAN Switch 0

NI 3 NI 2 NI 1 NI 0

External LANSwitch

Alarm box

Local client

BAM

MODEM

PSTN

MODEM

Remote client

Figure 8-2 Connection of a remote terminal system Remote maintenance terminal access through iWEB Compared with the traditional dial-up access through Modems, this access mode is more efficient in remote maintenance and encrypted data transmission. It ensures the security of the equipment. In Figure 8-2, the dotted lines indicate two Ethernet cables. Disconnect the two cables when the BAM works normally. In case of BAM failure, connect them with the active and standby LAN Switches at once. Thus, the emergency WS can assume the BAM functions.

Note: You can connect an emergency WS with an alarm box by running the program convert.exe.

Huawei Technologies Proprietary 8-2

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 8 Peripheral Installation

8.4 Installing Alarm Devices


Serial cables connect alarm boxes with clients. Figure 8-3 shows the structure and connection of MSOFTX3000 alarm system.
Power alarm Environment alarm Collected alarm 10 Mbit/s ALU SMU BAM 10 Mbit/s WS RS232 Alarm box

Figure 8-3 Structure of an alarm system Figure 8-4 shows a universal alarm box.

Figure 8-4 A universal alarm box For details about alarm box installation and cable connection, see Universal Alarm Box User Manual delivered with alarm boxes.

Huawei Technologies Proprietary 8-3

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 8 Peripheral Installation

8.5 Routing Cables for Terminal Devices


The alarm box, Hub, Modem and other terminals (workstations) are generally installed in the maintenance room.

Caution: To ensure the safety of personnel and devices, the power system must be reliably grounded.

To route cables for a terminal device, proceed as follows: 1) 2) 3) 4) 5) Connect one end of a cable to the terminal device. Connect the other end of the cable to the device in the maintenance room. Connect other cables in the same way. Tide up and bind the cables. Check that the cables are correctly connected.

8.6 Grounding Requirements of Terminal Devices

Caution The terminals are usually powered by 200 VAC. The power supply system must have a protection grounding end, and use the 3-core plug and socket.

The following cables can link the terminal device with the MSOFTX3000. RJ45 network cable RS232 serial port cable RS422 serial port cable The grounding requirements of the terminal devices are as follows: Connect the protection grounding cables with the same protection grounding bar of the MSOFTX3000 cabinet. The cross-sectional area should be more than or equal to 4 mm2.

Huawei Technologies Proprietary 8-4

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 9 Hardware Installation Checks

Chapter 9 Hardware Installation Checks


9.1 Introduction to the Chapter
With all hardware installed, you need to make an overall check and checks on electrical performance. Thus, upcoming software installation and system commissioning can smoothly go ahead.

9.2 Overall Check


You need to check the hardware overall, involving cabinets, cables, connectors, sockets, labels, and onsite environment.

9.2.1 Checking Cabinets


Check that: Rows of cabinets align. All cabinets are in correct positions. All screws and bolts are secure, with flat washers and spring washers in correct directions. Cabinet fittings and cables are all intact, with correct, clear, and complete labels. Each cabinet inside is clean and tidy without waste. Front and back doors, and side panels are clean. Cable outlets are covered with small cover plates on cabinet tops and bottoms.

9.2.2 Checking Cables


Check that: The connection between cables and devices are secure and tight. Cables are smooth, without cross in cabinets. Cables outside cabinets are bound according to different connected cabinets. Cables are connected in the right positions. Cable labels provide actual location information. Power cables and signal cables are bound apart. Cable ties are in correct positions with proper spacing. Cables are properly bent at turnings. Cables are all intact in the sheath.

Huawei Technologies Proprietary 9-1

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 9 Hardware Installation Checks

9.2.3 Checking Connectors and Sockets


This section describes how to check connectors and sockets.

I. Checking Connectors
Check that: Lockers of cable connectors are locked. Connectors of coaxial cables are tightened.

II. Checking Sockets


Check trunk cable sockets, Ethernet cable sockets, and sockets for backplanes. They must have no missing or bent pins.

9.2.4 Checking Labels and Equipment Room Environment


This section describes how to check labels and equipmemt room environment.

I. Checking Labels
All labels must be tidy and clear, in correct positions.

II. Checking Equipment Room Environment


Check that: All waste is cleared. The room is clean and tidy.

9.3 Electrical Performance Check


In view of power supply relationship, you must check electrical performance as follows: 1) 2) 3) Checking Power Supply to Cabinets Checking Power Supply to Subracks Checking Working Statuses of Trial Boards

9.3.1 Checking Power Supply to Cabinets


Check that: No electrical failure such as short circuit occurs to output power cables of the DC distribution cabinet. The input DC voltages of cabinets are normal. Each cabinet PDB has a normal audible and visual alarm function. Proceed as follows:

Huawei Technologies Proprietary 9-2

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 9 Hardware Installation Checks

1) 2) 3) 4) 5) 6) 7) 8)

Confirm that the input power of DC distribution cabinet is closed. Check that no short circuit occurs between the output power supplies of the DC distribution cabinet and RTNs (BGNDs in the earlier devices) or PGNDs. Set a multimeter to the ohm range. Measure the resistance. Confirm that power switches of PDBs are all set to "OFF". Power on the DC distribution cabinet. In case of no load, use the multimeter to check that the output voltage of DC distribution cabinet is within the normal range 57 V to 40 V. Check that the red indicator "ALM" on each PDB is blinking and the power alarm buzzer is buzzing.

If any of the above items does not meet the requirements, find out causes and remove faults before the next step.

9.3.2 Checking Power Supply to Subracks


Check that: No electrical failure such as short circuit occurs to output power cables of PDBs. The input DC voltages of internal components are normal. Proceed as follows: 1) 2) Check that no board is configured in any slot of each subrack. Set the power switches of PDBs to "ON". If on each PDB, the green indicator "RUN" is blinking, the red indicator "ALM" is off, and the power alarm buzzer is silent, it indicates no power alarm. Go on with the next step. 3) Check that the input voltages of internal components, service subracks and other devices in cabinets are within the normal range 57 V to 40 V. If any of the above items does not meet the requirements, find out causes and remove faults before the next step. For details about power distribution boxes, see HUAWEI MSOFTX3000 Mobile SoftSwitch Center Hardware Description Manual.

9.3.3 Checking Working Statuses of Trial Boards


You can know the working status of a powered-on board by observing indicators on the front panel of the board.

Huawei Technologies Proprietary 9-3

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Chapter 9 Hardware Installation Checks

Caution: If all board indicators of a subrack are off, it indicates that the power boards of the subrack are faulty. If short circuit occurs to a device or output terminals of the device are wrong connected, the power switch on a PDB automatically resumes "OFF" when set to "ON".

Proceed as follows: 1) 2) 3) 4) 5) 6) 7) 8) 9) Check that 48 V DC input cables of service subracks are connected correctly and securely. Set the power switches on PDBs to "OFF". Insert power boards into service subracks. Set the power switches on PDBs to "ON". Check that the power boards and fans in subracks are working normally. Set the power switches on PDBs to "OFF" again. Insert other boards into service subracks and fasten their front panels. Set the power switches on PDBs to "ON". Check that all boards are working normally.

For details about board indicators, see HUAWEI MSOFTX3000 Mobile SoftSwitch Center Hardware Description Manual.

Huawei Technologies Proprietary 9-4

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix A Cabling Rack Installation

Appendix A Cabling Rack Installation


This chapter describes the method and procedure for installing the cabling rack. The following lists the contents of this chapter: Introduction to Cabling Rack, A-1 Installing Process, A.2 Installing Indoor Cabling Rack, A.3 Connecting Cabling Ladders, A.4 Installing Cabling Trough (Optional), A.5 Installing Outdoor Cabling Rack, A.6 Installing Accessories,A.7

Note: The cabling rack consists of cabling ladder and cabling trough (optional). In overhead cabling mode, install the cabling rack in the equipment room. If no cabling rack is required, skip this chapter. Huawei recommends the 400 mm cabling ladder without the cabling trough to facilitate cabling and heat dissipation.

A.1 Introduction to Cabling Rack


A.1.1 Specifications
Select the cabling trough for the cabling ladder as follows: For the 200 mm wide cabling ladder, select the 200 mm wide cabling trough. For the 400 mm wide cabling ladder, select the 400 mm wide cabling trough. For the 600 mm wide cabling ladder, select the 400 mm + 200 mm wide cabling troughs. For delivery, the cabling ladder is 2.5 m long and the cabling trough is 2 m long.

A.1.2 Components
Table A-1 shows the components for installing a cabling rack.

Huawei Technologies Proprietary A-1

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix A Cabling Rack Installation

Table A-1 Components for installing a cabling rack

U-shaped connecting piece Cabling ladder

Bracket angle

Cable manager

Connecting clip Triangular support

Fixing clip

Cabling trough

Movable bushing

End cover

Rectangular frame

U-steel

Huawei Technologies Proprietary A-2

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix A Cabling Rack Installation

A.2 Installing Process


Figure A-1 shows the process for installing the cabling rack.
Start

Where to install the cabling rack?

Indoor

Outdoor

Ceiling/Floor installing

Wall installing

Over-cabinet installing

Wall installing

Ground installing

Install the cabling ladder

Cabling trough required? Yes Install the cabling trough

No

Install the accessories

End

Figure A-1 Process for installing the cabling rack

Huawei Technologies Proprietary A-3

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix A Cabling Rack Installation

A.3 Installing Indoor Cabling Rack


The cabling rack can be installed in three ways: Ceiling Installing or Floor Installing Wall Installing Over-Cabinet Installing

Caution: The cabling rack shall be insulated from the floor, ceiling, or wall.

A.3.1 Ceiling Installing or Floor Installing


I. Cautions
Note the following cautions for the ceiling or floor installing: The spacing between suspending lever and support lever must be an integral multiple of 50 mm. The recommended value is 1250 mm, that is, each cabling segment is supported by two suspending levers or two support levers. For ceiling installing or floor installing, be sure to install the suspending lever or supporting lever outside the cabling ladder for easy installation of cabling trough. Add the insulating pad and insulating washer during installing. When fixing the bracket angle to the ceiling or floor with the expansion bolts, replace the flat washer on the expansion bolt with the large flat washer 8. Use the bolt M6 x 20 to connect the bracket angle with the suspending lever. If the cabling trough is selected, install the bolt as top as possible, and space the bolt at least 40 mm from the cabling ladder, as shown in Figure A-2.

II. Concepts
When the cabling rack is not installed against the wall, you can select the ceiling installing or floor installing. For ceiling installing, use the suspending lever to connect to the ceiling. For floor installing, use the support lever to connect to the floor.

III. Procedure
Ceiling installing and floor installing are similar. The following takes the ceiling installing for example to describe the installing procedure.

Huawei Technologies Proprietary A-4

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix A Cabling Rack Installation

To install the cabling rack to the ceiling, proceed as follows: 1) 2) 3) 4) 5) 6) 7) Determine the position for installing the cabling rack according to the engineering files. Determine and mark the position for installing the suspending lever according to the cabling rack position. Select a 10 bit to drill holes at the marked positions, with the hole depth of 60 mm to 65 mm. Screw on the nut M8 anticlockwise to the top of the expansion bolt M8 x 80, and put them into the holes vertically. Knock the expansion bolt with a claw hammer until the tube is knocked completely into the ceiling. Take off the flat washer, spring washer and nut from the expansion bolt. Cut the U-steel with a proper length as the suspending lever according to the height of the cabling rack and equipment room.

Note: When the required length exceeds 2.5 m, you can connect two U-steels together. For the connection method, refer to section A.4.1 Remember to paint the cut area. "Assembling Cabling Ladders."

8) 9)

Use the bolt M6 x 20 and nut M6 to install bracket angles on to both ends of the suspending lever. Put the insulating pad on the expansion bolts, and then put the expansion bolts through the holes in the bracket angle.

10) Add the insulating washers, large flat washers 8, spring washers 8 and nuts M8 onto the expansion bolts. Screw on the nut M8 to fasten the suspending lever. 11) Use the bolt M8 x 20 and nut M8 to connect the cabling ladder and the suspending lever.

Huawei Technologies Proprietary A-5

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix A Cabling Rack Installation

Figure A-2 shows the ceiling installing.


Expansion bolt M8 x 80 Insulating pad Insulating washer Large flat washer 8 Spring washer 8 Nut M8

Bolt M6 x 20

Nut M6

Nut M8

Bolt M8 x 20

Figure A-2 Installing the cabling rack to the ceiling 12) When the ceiling has an obstacle or the support span is too wide, you can add a U-steel to connect the two suspending levers and fix it to the cabling ladder, as shown in Figure A-3.

Nut M8

Nut M6

Bolt M8 x 20

Bolt M8 x 20

Bolt M6 x 20

Nut M8

Figure A-3 Installing the cabling rack to the ceiling which has an obstacle

Huawei Technologies Proprietary A-6

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix A Cabling Rack Installation

A.3.2 Wall Installing


You can install the cabling rack against the wall if necessary.

I. Cautions
Note the following when using the triangular support for wall installing: When fixing the triangular support to the wall, be sure to add insulating pad and insulating washer for insulation between support and wall. When using the expansion bolt to fix the support to the wall, you need to use large flat washer 8 instead of the washer of the expansion bolt. The spacing between two adjacent triangular supports must be an integer multiple of 50 mm. Otherwise, the cabling ladder and the support cannot be fixed. The recommended value is 1250 mm, that is, each cabling segment is supported by two triangular supports.

II. Procedure
To install the cabling rack to the wall, proceed as follows: 1) 2) 3) 4) 5) 6) 7) 8) 9) Determine the position for installing the cabling rack according to the engineering files. Determine and mark the position for installing the triangle support. Mark the positions for drilling holes on the wall through the triangle support. Install two triangle supports for each cabling ladder segment and keep the distance of 1250 mm between every two supports. Select a 10 bit to drill holes at the marked positions, with the hole depth of 60 mm to 65 mm. Screw on the nut M8 x 80 anticlockwise to the top of the expansion bolt, and put them into the holes. Knock the expansion bolt with a claw hammer until the tube is knocked completely into the wall. Take off the flat washer, spring washer and nut from the expansion bolt, while put on the insulating pad. Put the triangle support through its holes on to the expansion bolt, and add the insulating washer, large flat washer 8, spring washer 8 and nut M8 on to the expansion bolt. 10) Screw on the nut M8 to fasten the triangle support against the wall, as shown in Figure A-4.

Huawei Technologies Proprietary A-7

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix A Cabling Rack Installation

0 125

mm

Triangular support

Expansion bolt Insulating pad M8 x 80

Nut M8

Spring washer 8 Large flat washer8 Insulating washer

Figure A-4 Fastening the triangular support against the wall 11) Put the cabling ladder directly on the horizontal beam of the triangular support. 12) Align holes in the U-steel lower side of the ladder with those in the horizontal beam of the triangular support, and then use the bolt M6 x 20 and nut M6 to fix the ladder to the triangular support, as shown in Figure A-5.

Nut M6

Bolt M6 x 20

Figure A-5 Fixing the ladder to the support

Huawei Technologies Proprietary A-8

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix A Cabling Rack Installation

A.3.3 Over-Cabinet Installing


When the cabling rack runs over the cabinet, use the over-cabinet installing mode. To improve heat dissipation, do not use the cabling trough in the over-cabinet installing mode.

I. Fixing the Support


To fix the over-cabinet support to the cabinet top, proceed as follows: 1) 2) Prepare the over-cabinet support. Install the support to the cabinet top through two bolt holes in the cabinet top.

Figure A-6 shows how to fix the over-cabinet support.


Screw Spring washer Flat washer Over-cabinet support

Cabinet

Figure A-6 Fixing the over-cabinet support

II. Fixing the Cabling Ladder


Use bolt M6 x 20 and nut M6 to fix the cabling ladder to the support, as shown in Figure A-7.

Nut M6

Bolt M6 x 20

Figure A-7 Fixing the cabling ladder


Huawei Technologies Proprietary A-9

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix A Cabling Rack Installation

A.4 Connecting Cabling Ladders


In practice, you may: Assemble two cabling ladders horizontally Turn the cabling ladder upright Install the cabling ladder to the wall Lay the cabling ladder upward or downward Their detailed methods are described in this section, as follows: Assembling Cabling Ladders Turning Cabling Ladder Connecting Cabling Ladder to the Wall Jointing Cabling Ladders

A.4.1 Assembling Cabling Ladders


To assemble a long cabling ladder: Use U-shape connecting pieces to connect several cabling ladders together. Use three grounding cables to connect two adjacent cabling ladders to ensure reliable grounding of the cabling rack. Figure A-8 shows how to assemble the cabling ladders. The bolts are connected as follows: Ground the first and fourth bolts with grounding cable, which are used to connect the cabling ladder and the U-shape connecting piece. Connect the second or third bolt to the second or third bolt at the other side with grounding cables.

Note: If the length of the cabling ladder is not an integer of 2.5 m, you can cut off the redundant part. After cutting the ladder, remember to paint the cut area for rust protection and nice appearance.

Huawei Technologies Proprietary A-10

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix A Cabling Rack Installation

Nut M8 Toothed pad Bolt M8 x 20 Grounding cable

Figure A-8 Assembling the cabling ladders

A.4.2 Turning Cabling Ladder at the Same Level


If both the cabling ladders are installed with/without cabling trough, the turning methods are the same. Use bracket angle, bolt, and nut to connect both cabling ladders, and ensure the two ladders are in the same level. Figure A-9 shows how to turn the ladder at the same level.

Nut M8

Nut M6

Bolt M8 x 20

Bolt M6 x 20

Figure A-9 Turning the ladder at the same level (without cabling trough)
Huawei Technologies Proprietary A-11

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix A Cabling Rack Installation

A.4.3 Turning Cabling Ladder at Different Levels

Caution: During installing, if one cabling ladder is installed with cabling trough but the other not, ensure the cabling ladder and the cabling trough of the other cabling ladder are in the same level after installing.

If the cabling ladder to be turned has a cabling trough segment, use bracket angle, bolt, and nut to connect the two cabling ladders. Figure A-10 shows how to turn the ladder at different levels.

Nut M6 Bolt M6 x 20

Nut M8

Bolt M8 x 20

Figure A-10 Turning the cabling ladder at different levels

Huawei Technologies Proprietary A-12

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix A Cabling Rack Installation

A.4.4 Connecting Cabling Ladder to the Wall


Use bracket angle, insulating pad, insulating washer, spring washer, flat waster, and expansion bolt to connect the cabling ladder to the wall. Figure A-11 and show how to connect the cabling ladder to the wall.

Nut M6

Expansion bolt M8 x 80 Insulating pad Bolt M6 x 20 Nut M8 Large flat washer 8 Insulating washer Spring washer 8

Figure A-11 Connecting the cabling ladder to the wall

A.4.5 Jointing Cabling Ladders


To joint cabling ladders, proceed as follows: 1) 2) Select a segment of cabling ladder as the climbing ladder. Use bracket angle, bolt, and nut to joint climbing ladder and cabling ladder.

The climbing ladder and cabling ladder can be jointed in the following three modes.

Huawei Technologies Proprietary A-13

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix A Cabling Rack Installation

I. Front Jointing
Figure A-12 shows the front jointing.
Nut M6 Bolt M6 x 20 Bolt M8 x 20

Nut M8

Figure A-12 Front jointing of cabling ladders

II. Side Jointing


Figure A-13 shows the side jointing.

Nut M6 Bolt M6 x 20 Bolt M6 x 20 Nut M6

Figure A-13 Side jointing of cabling ladders

Huawei Technologies Proprietary A-14

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix A Cabling Rack Installation

III. Oblique Jointing


Figure A-14 shows the oblique jointing.

Nut M8

Bolt M8 x 20

Nut M8

Bolt M8 x 20

Figure A-14 Oblique jointing of cabling ladders

A.5 Installing Cabling Trough (Optional)


A.5.1 Overview
This section describes how to connect cabling troughs and how to install a cabling trough. The cabling trough has two types: 200 mm wide and 400 mm wide, so a cabling trough can be installed on: A 200 mm or 400 mm wide cabling ladder A 600 mm wide cabling ladder When installing a bracket to a cabling ladder, if the cabling ladder needs to be lengthened, first lengthen it, and then fix it.

A.5.2 Connecting Cabling Troughs


Because the cabling trough has taper, you can just insert the smaller end of the cabling trough to the larger end of the other, as shown in Figure A-15. The insertion depth shall be smaller than 250 mm.

Huawei Technologies Proprietary A-15

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix A Cabling Rack Installation

Figure A-15 Connecting cabling troughs

A.5.3 Installing Cabling Trough on 200 mm or 400 mm Wide Cabling Ladder


To install the cabling trough on the 200 mm or 400 mm wide cabling ladder, proceed as follows: 1) 2) 3) Select the 200 mm or 400 mm wide cabling trough. Put the cabling trough onto the cabling ladder. Use fixing clip to fix the cabling trough to the cabling ladder. Each cabling trough segment needs four clips, two on each side of the trough. Figure A-16 shows how to install the cabling trough on the 200 mm or 400 mm wide cabling ladder.

Fixing clip Nut M8 Bolt M8 x 20

Figure A-16 Installing the cabling trough on a 200 mm or 400 mm cabling ladder

A.5.4 Installing Cabling Trough on 600 mm Wide Cabling Ladder


To install the cabling trough on a 600 mm cabling ladder, proceed as follows: 1) 2) Combine a 200 mm cabling trough with a 400 mm cabling trough to build up a 600 mm cabling ladder. Use the connecting clips to connect cabling troughs, three for each segment of trough.

Huawei Technologies Proprietary A-16

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix A Cabling Rack Installation

3)

Fastening the cabling trough to the cabling ladder using fixing clips. Each cabling trough needs four clips, two on each side of the trough.

Figure A-17 shows how to install the cabling trough on the 600 mm wide cabling ladder.

Connecting clip

Fixing clip

Figure A-17 Installing the cabling trough on a 600 mm cabling ladder

A.5.5 Installing Cabling Trough Obliquely

Note: The slope of the cabling trough can be smaller than the required.

To install the cabling trough obliquely, proceed as follows: 1) Cut off the upper side of the triangle aperture in the cabling trough, as shown in Figure A-18. Paint where the upper side is cut.

Figure A-18 Cutting off the upper side of the triangle aperture

Huawei Technologies Proprietary A-17

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix A Cabling Rack Installation

2)

Bend one part of the cabling trough with the marking line as the axis to the desired angle, as shown in Figure A-19.

Figure A-19 Bending one part of the cabling trough 3) Use the fixing clip to fix the cabling trough onto the cabling ladder.

Figure A-20 shows the cabling trough installed obliquely onto the cabling ladder.

Figure A-20 Cabling trough installed obliquely onto the cabling ladder

Huawei Technologies Proprietary A-18

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix A Cabling Rack Installation

A.6 Installing Outdoor Cabling Rack


You can install the outdoor cabling rack against the wall or on the ground.

Note: When using the rectangular frame to determine the position for the cabling rack, put the rectangular frame in the correct direction, as shown in Figure A-21.

Cabling ladder connection hole Ground connection hole

Wall connection hole

Figure A-21 Outline of the rectangular frame

A.6.1 Wall Installing


If the cabling rack goes along the wall, you can install it against the wall. To install the cabling rack against the wall, proceed as follows: 1) 2) 3) 4) 5) 6) 7) 8) Determine the position for installing the cabling rack according to the engineering files. Determine the position of the rectangular frame. Mark the positions for drilling holes on the wall through the two wall connection holes in the rectangular frame. Install two rectangular frames for each segment of cabling ladder and keep the distance of 1250 mm between every two frames. Select a 10 bit to drill holes at the marked positions, with the hole depth of 60 mm to 65 mm. Screw on the nut M8 x 80 to the top of the expansion bolt, and put them into the holes in the wall. Knock the expansion bolt with a claw hammer until the tube is knocked completely into the wall. Take off the flat washer, spring washer and nut from the expansion bolt, and put the insulating pad on to the expansion bolt.

Huawei Technologies Proprietary A-19

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix A Cabling Rack Installation

9)

Put the rectangular frame to the expansion bolts through the wall connection holes.

10) Add the insulating washer, large flat washer 8, spring washer 8 and nut M8 to the expansion bolt in sequence. 11) Fasten the nut to the expansion bolt to fix the rectangular frame to the wall, as shown in Figure A-22. 12) Put the cabling ladder directly onto the rectangular frame. 13) Align the holes in the lower side of the U steel of the cabling ladder with the cabling ladder connection holes of the rectangular frame, and connect them with the bolt M6 x 20 and the nut M6, as shown in Figure A-22.
Insulating washer Large flat washer 8 Insulating pad Expansion bolt M8 x 80 Spring washer 8 Nut M8

Nut M6

Bolt M6 x 20

Figure A-22 Installing the outdoor cabling rack against the wall

A.6.2 Ground Installing


If the cabling rack does not go along the wall, you can install it on the ground. To install the cabling rack on the ground, proceed as follows: 1) 2) 3) 4) 5) 6) 7) Determine the position for installing the cabling rack according to the engineering files. Determine the position of the rectangular frame. Mark the positions for drilling holes on the ground through the two ground connection holes in the rectangular frame. Install two rectangular frames for each segment of cabling ladder and keep the distance of 1250 mm between every two frames. Select a 10 bit to drill holes at the marked positions, with the hole depth of 60 mm to 65 mm. Screw on the nut M8 x 80 to the top of the expansion bolt, and put them into the holes in the ground. Knock the expansion bolt with a claw hammer until the tube is knocked completely into the wall.
Huawei Technologies Proprietary A-20

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix A Cabling Rack Installation

8) 9)

Take off the flat washer, spring washer and nut from the expansion bolt, and put the insulating pad on to the expansion bolt. Put the rectangular frame to the expansion bolts through the ground connection holes.

10) Add the insulating washer, large flat washer 8, spring washer 8 and nut M8 to the expansion bolt in sequence. 11) Fasten the nut to the expansion bolt to fix the rectangular frame to the ground, as shown in Figure A-23. 12) Put the cabling ladder directly onto the rectangular frame. 13) Align the holes in the lower side of the U steel of the cabling ladder with the cabling ladder connection holes of the rectangular frame, and connect them with the bolt M6 x 20 and the nut M6, as shown in Figure A-23.

Nut M6

Bolt M6 x 20

Nut M8 Spring washer 8 Large flat washer 8 Insulating washer Insulating pad Expansion bolt M8 x 80

Figure A-23 Installing the outdoor cabling rack on the ground

A.7 Installing Accessories


A.7.1 Overview
This section describes how to install accessories, including: Cable manager End cover, baffle ring and trough rim

Huawei Technologies Proprietary A-21

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix A Cabling Rack Installation

A.7.2 Installing Cable Manager


Cable managers are often installed on the cabling ladder over the cabinet. The quantity and installing positions of cable managers are based upon the actual situation.

Note: To align the cable manager with the cabling rack: If there is the cabling trough, fasten the cable manager to the cabling ladder through lower holes in the cable manager. If there is no cabling trough, fasten the cable manager to the ladder through upper holes in the cable manager.

Figure A-24 shows the cable manager installed to the cabling rack without the cabling trough.

Cable manager

Cabling rack

Bolt M8 x 20

Figure A-24 Cable manager installed to the cabling rack without the cabling trough

Huawei Technologies Proprietary A-22

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix A Cabling Rack Installation

Figure A-25 shows the cable manager installed to the cabling rack with the cabling trough.

Cable manager

Cabling trough Cabling ladder

Bolt M8 x 20

Figure A-25 Cable manager installed to the cabling rack with the cabling trough

A.7.3 Installing Trough Rim, End Cover and Baffle Ring


I. Installing the Trough Rim and End Cover
The trough rim and end cover can protect cables from being damaged. The installing requirements for the trough rim and end cover are as follows: The trough rim covers the bottom edge of the cabling trough. All the exposed bottom edges at the end of the cabling trough shall be covered by the trough rim. The end cover is used at the end of the cabling ladders. Install end covers for all cabling ladders if possible. Parts and in Figure A-26 show how to install the trough rim and end cover.

II. Installing the Baffle Ring


The baffle ring is installed on both sides of the cabling trough to increase the height of the trough and to hold cables inside the trough. Each segment of cabling trough uses four baffle rings, evenly installed on both sides. Part in Figure A-26 shows how to install the baffle ring.

Huawei Technologies Proprietary A-23

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix A Cabling Rack Installation

Figure A-26 Installing the trough rim, end cover and baffle ring

Huawei Technologies Proprietary A-24

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix B Core Area Calculation for Power Bus Cables

Appendix B Core Area Calculation for Power Bus Cables


B.1 Introduction to the Appendix
Power bus cables with standard core areas ensure the quality and stability of the power supply. This appendix briefs the formula and method of computing core areas of power bus cables.

B.2 Computing Core Areas of Power Bus Cables


The core area (mm2) of a power bus cable is given by the following formula: S = I x L / ( x K) Where, I (unit: A): total current through a cable L (unit: m): length of cable loop, that is, the distance between the power distribution cabinet and the equipment multiplied by 2 (unit: V): allowable voltage drop, generally less than 1 V K: conductive coefficient (Kcopper = 57 and Kaluminium = 34)

B.3 Computing Core Areas of Battery Bus Cables


Computing the core area of a battery bus cable involves such factors as: Load current Distance between battery and power distribution cabinet Allowable voltage drop between battery and power distribution cabinet Battery capacity The core area (mm2) of a battery bus cable is also given by the formula: S = I x L / ( x K) The allowable lowest voltage for MSOFTX3000 is 40 V, and the battery protection voltage of power supply specified by Huawei is 43.2 V. Thus the allowable maximum voltage drop is 0.8 V for the power bus cable between the power supply and the device. Generally, the voltage drop is 3.2 V.

Huawei Technologies Proprietary B-1

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix B Core Area Calculation for Power Bus Cables

Note: In terms of design, the total current through a cable is computed when the equipment is in full configuration. If the distance is short, a very small voltage drop is acceptable.

B.4 Giving an Example


If the total current is 200 A, and the loop between the power distribution cabinet and the equipment is 10 multiplied by 2 m, the sectional area of the copper cable is: S = (200 x 10 x 2) / (57 x 0.8) = 88 (mm2) Power bus cables include the following types: 4 mm2, 16 mm2, 25 mm2, 35 mm2, 50 mm2, 70 mm2, 95 mm2, 120 mm2, and 150 mm2. In this case, you can select 95 mm2 copper cables.

Huawei Technologies Proprietary B-2

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix C Assembly of Cable Connectors

Appendix C Assembly of Cable Connectors


C.1 Introduction to the Appendix
This appendix details the methods and procedures of mounting cable connectors.

C.2 Mounting Power Cable Connectors


This section introduces the methods of mounting naked crimping connectors for 50 mm2 to 240 mm2 power cables.

C.2.1 Using and Maintaining Crimping Tools


The methods of using crimping tools vary with tool types. Figure C-1 shows a common crimping tool SS-325 for heavy-section power cable connectors.
2

(1) Fixing handle (4) Fixing rod

(2) Hydraulic head (5) Hydraulic switch

(3) Hand level

Figure C-1 SS-325 parts

I. Crimping Cables

Caution: Improper pressure pieces, stressed pieces, or fixed levers will shorten the service life of a crimping tool.

Huawei Technologies Proprietary C-1

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix C Assembly of Cable Connectors

To crimp a cable, proceed as follows: 1) Select crimping parts as needed. If bad contact, or core wire distort or damage happens during cable crimping, reselect proper crimping parts. 2) 3) Fit the pressure piece, stressed piece, and fixed handle together. Make the following preparations for cable crimping: Loosen the fixed handle and put the crimping tool at a place good for operation. Open the hydraulic selector and push the manual lever. 4) 5) Put in the cable to be crimped. Crimp the cable using the manual lever. If a black line is displayed at the hydraulic selector, cable crimping ends. 6) Close the hydraulic selector. After crimping cables, close the hydraulic selector and remove the crimping parts.

Note: If no black line is displayed after you crimp a cable, you need to have the tool repaired. The SS0325 tool does not show such a black line. After using the tool, place it in a cool and ventilated place unreachable for children. Meanwhile, avoid direct sunshine.

II. Maintaining Crimping Tools


You must regularly oil the crimping components, hydraulic switch and the tool body, and replace oil in tools every two years. To add or replace oil for a tool, proceed as follows: 1) 2) 3) 4) Close the hydraulic selector. Remove the fixed lever to show up the oil embolus. Place the oil embolus upward and unscrew the oil plug. Add oil using a small oil can. a) After pouring oil into the can for a while, tap the tool against something hard to expel the air inside it. b) c) Continue pouring oil. Repeat steps a and b until the pot is full.

Huawei Technologies Proprietary C-2

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix C Assembly of Cable Connectors

Caution: Wear gloves when filling oil. Eye contact or skin contact of the oil may cause inflammation. The oil is inedible. Put it in the place unreachable for children. In the case of eye contact, wash eyes with clean water within 15 minutes and seek medical assistance as soon as possible. In the case of skin contact, wash the area thoroughly with clean water. Dispose it according to the requirements of the related law for environmental protection.

C.2.2 Mounting Naked Crimping Connectors


Figure C-2 shows the flowchart of mounting naked crimping connectors.
Start

Cut cables

Mount hot shrinkable tubes

Strip cables

Crimp cables

Shrink hot shrinkable tubes

Check connectors

End

Figure C-2 Flowchart of mounting naked crimping connectors The following details how to mount a naked crimping connector for a power cable.

Huawei Technologies Proprietary C-3

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix C Assembly of Cable Connectors

I. Cutting the Cable


Proceed as follows: 1) Place and roll a cable coil on brackets, as shown in Figure C-3.
1

(1) Rolling direction

Figure C-3 Measuring cables 2) 3) Measure the cable according to the cable layout of the project design. Cut off the cable.

Note: A power cable comprises many fairly fine and soft core wires. Therefore, use a denticulate arm saw with a denticulate diameter of 0.8 mm or use a wire clipper of model KT35 to cut power cables.

II. Mounting a Heat Shrinkable Tube


Mount a required heat shrinkable tube through the stripped end onto the cable.

III. Stripping the Cable

Caution: When stripping a cable, cut off any oxidized or corroded part of its core wires.

Huawei Technologies Proprietary C-4

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix C Assembly of Cable Connectors

Use a special cable stripper, or an electrical knife, or an AM35 round cable stripper to strip cables. Proceed as follows: 1) Count the cable length to be stripped. The length depends on the crimping sleeve length behind the naked crimping connector. Figure C-4 shows a stripped cable with a JG naked crimping connector commonly used by Huawei. The length is computed using the formula: L1 = L2 + (2 mm to 3 mm) Where, L1: length of the stripped cable L2: length of the effective crimping area of JG connector

L1 L2

(1) Crimping sleeve

Figure C-4 A stripped cable 2) 3) Remove the insulation layer. Twist the naked core wires at the ends in the same direction as the original core wires.

IV. Crimping the Cable


Use a pair of crimping pliers or a special mould to crimp cables. Proceed as follows: 1) Insert the core wires of the cable into the crimping sleeve of the connector, with 2 mm to 3 mm of the core wires bared, as shown in Figure C-5.

Huawei Technologies Proprietary C-5

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center


2

Appendix C Assembly of Cable Connectors

23mm

(1) Bare pressure terminal

(2) Heat-shrinkable tube

Figure C-5 Inserting cable core wires into a connector crimping sleeve 2) Select a pressing mould with a proper cross section. Figure C-6 shows the pressing moulds used for four types of power cables.

60

1 2

60~100

60

80

150

200

60~100
2

60~100
2

150~325 120mm
2

150~325 240mm
2

50mm

95mm

(1) Bearing device

(2) Compressing device

Figure C-6 Pressing moulds used for power cables 3) 4) 5) Place the cable at the connecting position, with the contact surface of the connecting end parallel to the power cable. Adjust them by holding the connector end with a pair of wire pliers. Make sure the crimping position is as shown in Figure C-7.

Huawei Technologies Proprietary C-6

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix C Assembly of Cable Connectors

Figure C-7 Crimping a cable 6) Crimp the cable.

V. Shrinking the Heat Shrinkable Tube

Caution: The heat shrinkable tube on a cable must wrap up the whole crimping sleeve of the naked crimping connector, including the joint between the connector and the cable.

1) 2)

Mount the heat shrinkable tube onto the joint between the connector and the cable. Blow the tube with a heat gun until the tube shrinks tight, as shown in Figure C-8.

(1) Shrank heat-shrinkable tube

Figure C-8 A pinched heat shrinkable tube

VI. Checking the Connector


1) 2) Check that no oxidation or damage occurs to connector or cable surfaces. Check the tensile strength.

Table C-1 provides the normal tensile strength of ready-made cables.

Huawei Technologies Proprietary C-7

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix C Assembly of Cable Connectors

Table C-1 Tensile strength standards of ready-made cables Cable 50 mm 95 mm


2 2 2 2

Normal tensile strength 1 KN 2 KN 2.5 KN 5 KN

120 mm 240 mm

C.3 Mounting RJ-45 Connectors


Figure C-9 shows the flowchart of mounting RJ-45 connectors.
Start

Strip cables

Insert cables into connectors

Crimp connectors

Check connectors

End

Figure C-9 Flowchart of mounting RJ-45 connectors The following describes how to mount an RJ-45 connector for an Ethernet cable.

I. Stripping the Cable


Proceed as follows: 1) Measure the cable length to be stripped. The length is L plus 2 mm to 3 mm, as shown in Figure C-10. The 2 mm to 3 mm is reserved for cable cutting and arrangement.

Huawei Technologies Proprietary C-8

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix C Assembly of Cable Connectors

L+(2~3mm)

Figure C-10 Measuring the length of to-be-stripped cable 2) Strip the cable sheath. Make sure to strip the end of the sheath neatly, with the stripping line vertical to the cable. If you strip sheaths from shielded cables, avoid damage to shielding layers. 3) Fold the shielding layer. Fold the shielding layer into double layers and backwards to the root of cable sheath, as shown in Figure C-11.
L

(1) Folded shielding layer

Figure C-11 A segment of shielded cable 4) Cut the core wires. a) b) Spread out core wires evenly. Cut them neatly as shown in Figure C-12, especially for round communication cables.

Figure C-12 Neatly-cut core wires 5) Check the cable stripped end. The size of stripped cable must meet the requirement shown in Figure C-12. That is, their core wires are equal to "L" in length.

Huawei Technologies Proprietary C-9

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix C Assembly of Cable Connectors

II. Inserting the Cable into the Connector


Proceed as follows: 1) Sort the core wires by color. Figure C-13 shows the wire sequence of crossover cables, and Figure C-14 shows that of straight through cables.
1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8

Brown

Orange and white

Green and white

Figure C-13 Wire sequence of crossover cables

Green and white

Brown and white

Brown

Orange

Green

Brown and white

Blue and white

Orange

Orange and white

Green

Blue and white 1 2 3 4 5 6 7 8

blue

blue

RJ45

RJ45 3 6 1 4 5 2 7 8

Huawei Technologies Proprietary C-10

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center


1 2 3 4 5 6 7 8 1

Appendix C Assembly of Cable Connectors


2 3 4 5 6 7 8

Green

Green

Brown Brown and white

Brown Brown and white

Figure C-14 Wire sequence of straight through cables 2) 3) Insert the cable into the connector until the core wires are flush with the end, as shown in Figure C-15. Check the connector as shown in Figure C-15. Check that: The cable shielding layer clings to point A of the connector. The shielding layer contacts well with the built-in shielding plate at the tail of the connector.

Orange Orange and white

Orange Orange and white

Green and white

Green and white

Blue and white blue

Blue and white blue

RJ45
1 2 3 4 5 6 7 8

RJ45
1 2 3 4 5 6 7 8

Huawei Technologies Proprietary C-11

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix C Assembly of Cable Connectors

L
1

3 8

7 4 6

(1) Shielding piece (2) External shielding piece (4) Built-in shielding piece (5) Point A (7) Core wires flushing with cable end

(3) Cable insertion direction (6) Locking piece (8) Metal cutter

Figure C-15 An RJ-45 connector

III. Crimping the Cable


Use a pair of RJ-45 crimping pliers to crimp connectors. Figure C-16 shows a mounted RJ-45 connector.

Figure C-16 A mounted RJ-45 connector Crimping an RJ-45 connector must conform to the following principles: Before crimping the connector, place it right in the slot of the crimping pliers. Be sure to crimp the connector fully. That is, after the crimping, the metal cutter must be below the plane of the connector head.

Huawei Technologies Proprietary C-12

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix C Assembly of Cable Connectors

In addition, if you crimp a shielded RJ-45 connector for a shielded cable, you must also ensure that the built-in shielding plate of the connector securely connects with the folded shielding layer of the cable.

IV. Checking the Connector


Proceed as follows: 1) Check the appearance carefully. Check that: The connector is intact. The cable is inserted into the right position. 2) Check the wire sequence. The wire sequence must meet the design requirements. 3) Test the cable continuity. The continuity ratio must be 100%. No short circuit arises between the core wires.

Note: For shielded cables mounted with shielded RJ-45 connectors, you must test the continuity between shielding shells of connectors and shielding layers of cables.

C.4 Mounting SMB Connectors


Figure C-17 shows the flowchart of mounting SMB connectors.

Huawei Technologies Proprietary C-13

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix C Assembly of Cable Connectors

Start

Mount hot shrinkable tubes and crimping sleeves

Strip cables

Weld pins

Crimp cables

Shrink hot shrinkable tubes

Check connectors

End

Figure C-17 Flowchart of mounting SMB connectors The following describes how to mount an SMB connector for a coaxial cable.

I. Mounting a Heat Shrinkable Tube and a Crimping Sleeve


Figure C-18 shows a mounted heat shrinkable tube and a mounted crimping sleeve.
1 2

(1) Heat-shrinkable tube

(2) Crimping sleeve

Figure C-18 A mounted heat shrinkable tube and crimping sleeve

Huawei Technologies Proprietary C-14

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix C Assembly of Cable Connectors

II. Stripping the Cable

Caution: When stripping cables, do not damage shielding layers or inner conductors of cables.

To strip the cable, proceed as follows: 1) Use a cable stripper to strip the cable sheath and inner insulation layer. Figure C-19 shows the recommended size of stripped cable.
4.5 (1) (2) (3)

2.3 (4) 11

(1) Sheath (3) Inner conductor

(2) Inner insulation layer (4) Shielding layer

Figure C-19 A stripped cable 2) Cut the end face of cable sheath and inner insulation layer neatly.

III. Welding a Pin

Caution: When welding a pin for a cable, do not scald the inner insulation layer. In addition, avoid the welding tin flowing out to the exterior surface of the pin. Clear up any outflow lest it should affect the next step.

To weld a pin, proceed as follows: 1) Insert the inner conductor of the cable into the central hole at the pin end until the boss at the pin end contacts the inner insulation layer of the cable, as shown in Figure C-20.

Huawei Technologies Proprietary C-15

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix C Assembly of Cable Connectors

(1) Inner insulation layer (2) Boss

Figure C-20 A welded pin 2) Use the soldering tin with the melting point of over 125C to weld the pin with the inner conductor of the cable together.

IV. Crimping the Cable

Caution: Before crimping the cable, check the SMB connector. Trim the shield cable if there is any part bared outside the crimping sleeve. Be sure to place the SMB connector in the right place to match with the pressing mould in the crimping pliers.

To crimp the cable, proceed as follows: 1) Insert the knurled column of the SMB connector between the inner insulation layer and the shielding layer of the cable. a) b) Attach the shielding layer evenly to the knurled column. Make sure that the needle lug butts against the inner insulation core of the connector. See Figure C-21.
1 2 3

(1) Shielding layer covering the knurled cylinder evenly (2) Inner insulation core of the connector (3) Pin (4) Coaxial connector

Figure C-21 Crimping an SMB connector onto a coaxial cable

Huawei Technologies Proprietary C-16

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix C Assembly of Cable Connectors

2) 3)

Push the crimping sleeve to fully cover the shielded cable. Use a pair of SMB crimping pliers to crimp the cable.

V. Shrinking the Heat Shrinkable Tube


Proceed as follows: 1) 2) Mount the heat shrinkable tube onto the joint between the connector and the cable. Use a heat gun to evenly blow the heat shrinkable tube until the tube shrinks tight and evenly, as shown in Figure C-22.
1

(1) Shrinking

Figure C-22 A pinched heat shrinkable tube

VI. Checking the Connector


Proceed as follows: 1) Check the cable appearance to make sure that: No shielded cable part is bare. The pin is installed in the right position. 2) Test the cable insulation. Measure the cable using a multimeter to make sure that no short circuit occurs to the inner and outer conductors. 3) Test the cable continuity. Measure the cable using the multimeter to make sure the following continuity: Between the connector pin and the inner conductor of the coaxial cable Between the connector surface and the shielding lay of the coaxial cable 4) Check the tensile strength. Draw the inner pin with proper force (about 60 N). The pin must hold the line.

Huawei Technologies Proprietary C-17

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix D Facture of Cable Labels

Appendix D Facture of Cable Labels


D.1 Introduction to the Appendix
The engineering label is a kind of equipment identification for correct and orderly onsite installation and convenient future maintenance.

Note: The power cables involved in this appendix exclude power bus cables. You can fill labels at the request of the customer to ensure the consistency of all labels in an equipment room. In this case, you must state it in the self-check report. The orientations described in this appendix are with respect to the positions of onsite engineers, other than the descriptions about printer setup.

This appendix consists of the following parts: Introduction to Labels Precautions Deciding Label Contents Deciding Information Places on Labels Printing or Writing Labels Sticking or Binding Labels Checking Labels

D.2 Introduction to Labels


This section introduces labels from their features, types, and structures.

D.2.1 Label Materials and Features


Required labels feature the following: They are 0.09 mm thick. Their color is white. They use polyester (PET) as materials, certificated by Underwriter Laboratories Incorporation (UL) and the Canadian Standards Association (CSA). They are applicable to the temperature from 29C to +149C. They can be used for laser printing and written by oil markers.

Huawei Technologies Proprietary D-1

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix D Facture of Cable Labels

D.2.2 Label Types and Structures


Engineering labels fall into signal cable labels and power cable labels.

I. Signal Cable Labels


Signal cable labels are in the flap-type structure of fixed size (unit: mm), as shown in Figure D-1.
84.0 7.5 7.0 5.5

5.5

11.0
TO:

10.0 (2) 1.5 (1) 0.6


5.5 7.0

11.0

(1)

5.5 (2) 1.0

7.5

37.0 2.0

(1) Dividing line

(2) Cut dotted line

Figure D-1 Signal cable label paper Dividing lines on a label help specify more clearly the position of a cable. For example, a dividing line lies between a cabinet number and a subrack number, and another one between the subrack number and a slot number. A dividing line is 1.5 mm x 0.6 mm in size, with the color of Pantone 656c (light blue). A cut dotted line helps fold a label when sticking the label. The line is 1.0 mm x 2.0 mm in size.

Note: There is a mark TO: (upside down in the figure) at the lower right corner of the label. The mark is used to identify the opposite end of the cable on which the label is affixed.

Huawei Technologies Proprietary D-2

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix D Facture of Cable Labels

II. Power Cable Labels


A power cable label is symmetric on both sides. It is stuck on the middle area of the identification plate on a cable tie. Around the label is an embossment (0.2 mm x 0.6 mm). Figure D-2 shows the label paper for power cables.
26.2 12.2 0.6 11 (2) 10
TO:

R1.0

25

1.5 (1) 100 (3) 0.6

(1) Cable tie

(2) Label

(3) Dividing line on the label

Figure D-2 Power cable label paper

D.3 Precautions
When using a label, pay attention to the following: Keep labels clean. Avoid using ink-jet printers to print or using pens to write on label paper, which is damp proof and waterproof. Stick labels tidily. Bind cable ties on the same height, with identification plates in the same direction.

D.4 Facture Procedure


Figure D-3 shows the flowchart of making labels.

Huawei Technologies Proprietary D-3

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix D Facture of Cable Labels

Start

Decide label contents

Decide information places on labels

Print or write labels

Stick or bind labels

Check labels

End

Figure D-3 Flowchart of making labels

D.5 Deciding Label Contents


Before making labels, you must decide label contents according to cable types and cable routing.

D.5.1 Labels for External Cables of Alarm Box


The external cables of alarm box are connected with the first subscriber cabinet of each row (used for power distribution). Labels pasted on the first cabinet of each row shows which equipment is using the access terminal. Labels are not needed on the equipment side unless there is special requirement. In this case, only Area 2 of the label is filled in, as shown in Figure D-12. Table D-1 shows the information on the labels of alarm box external cables.

Huawei Technologies Proprietary D-4

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix D Facture of Cable Labels

Table D-1 Information on labels affixed to the external cables of alarm box Content Meaning Example M: The cabinet rows from front to back are numbered from A to Z. N: The cabinet columns from left to right are numbered from 01 to 99. For example, A01 indicates a cabinet at Row A, Column 01.

MN

MN: serial number of the cabinet in the equipment room

Note: Generally, the above numbering method is enough to identify the position of a specific cabinet. If cabinets are installed in a back-to-back manner, the facing direction of the cabinet must be specified, the numbering method like MNO is used. Here, O means the direction of the cabinet, which can be A or B. On the cable labels described below, this numbering method is used, unless otherwise stated.

Figure D-4 shows a label on the alarm cable, on which A01 shows that the alarm cable is connected from the first cabinet to the cabinet at Row A, Column 01 in the equipment room.

Figure D-4 Example of the label on the alarm cable

Note: The label on the alarm cable carries simple information, and only part of the text area needs to be filled in. It is recommended to keep the whole length of the label instead of cutting out the blank area.

D.5.2 Labels for Ethernet Cables


Labels of this type apply to Ethernet cables connecting such devices as boards, LAN Switches, servers, and routers.

TO: A01

Huawei Technologies Proprietary D-5

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix D Facture of Cable Labels

I. Facture Principles
For Ethernet cables between LAN Switches and servers, between LAN Switches and routers, or between other devices, their label contents depend on actual environment. For an Ethernet cable between a LAN Switch and a server

On the label stuck on the LAN Switch end, mark the cabinet number and subrack number of the LAN Switch, and the LAN Switch number.

On the label stuck on the server end, mark the cabinet number and subrack number of the server, and the specific location of the server if it is separately placed.

For an Ethernet cable between a LAN Switch and a router Mark the Ethernet port number on the label stuck on the router end. For how to mark cabinet numbers and subrack numbers on labels, see Table D-2. If a LAN Switch resides separately rather than in a subrack or cabinet, mark the location of the LAN Switch on the related labels. Fill labels with the actual LAN Switch number, Ethernet port number, and server location.

II. Label Contents


Table D-2 describes label contents of Ethernet cables between boards. Table D-2 Label contents for Ethernet cables Label contents Meaning MN: cabinet number B: subrack number MN-B-C-D C: slot number D: Ethernet port number MN: cabinet number Two-digit numbers, from up to down and left to right. For example, 01. Sequence of Ethernet ports, from up to down and left to right. For example, 01. For example, B02. Actual location number of terminal device. For example, the location number of a router in a cabinet, B02-03-12, sequentially indicating the cabinet number and subrack number of the router, and Ethernet port number. If the cable connects with the network management system (NMS), mark the specific location of the NMS. For example, A01. Two-digit numbers, from down to up. For example, 01. Example

MN-Z Z: location number

Huawei Technologies Proprietary D-6

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix D Facture of Cable Labels

III. Label Example


Figure D-5 shows a label example for an Ethernet cable.

A01

03

10 12

05 TO: B02 03

Figure D-5 A label example for an Ethernet cable In Figure D-5, The "A01-03-10-05" indicates the local end of this cable connects to Ethernet port 5 of the board in slot 10, subrack 3 of the cabinet in row A column 01. The "B02-03-12" indicates the peer end of this cable connects to Ethernet port 12 on the third device in the cabinet of row B column 02.

D.5.3 Labels for Trunk Cables


Trunk cables include 75-ohm and 120-ohm E1 cables, 100-ohm T1 cables, trunk cables for converting 120 ohm into 75 ohm, and clock cables. Labels for trunk cables fall into two types: For trunk cables connecting devices Trunk cables of this type connect trunk boards with built-in transmission devices and other trunk boards. Stick labels at either end of a cable, indicating the locations of this cable on two devices. For trunk cables connecting devices with DDFs For trunk cables of this type, stick labels at either end of a cable, indicating the locations of this cable on the device and the DDF.

I. Labels for Trunk Cables Between Devices


Label contents Table D-3 describes label contents for a trunk cable between two devices. Table D-3 Label contents for trunk cables between devices Label contents MN-B-C-D-R/T Meaning MN: cabinet number B: subrack number Example For example, A01. Two-digit numbers, from down to up. For example, 01.

Huawei Technologies Proprietary D-7

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix D Facture of Cable Labels

Label contents

Meaning C: slot number D: cable number R: Receiving optical port T: transmitting optical port

Example Two-digit numbers, from up to down and left to right. For example, 01. Two-digit numbers, from up to down and left to right. For example, 12.

Label example Figure D-6 shows a label example for a trunk cable between two devices.

G01 R

01 01 10

05

12 01

T TO: D02

Figure D-6 A label example for a trunk cable between two devices In Figure D-6, The "G01-01-05-12-T" indicates that the local end of the trunk cable connects to the transmitting end of trunk cable 12 in slot 5 of subrack 1 in the cabinet of row G column 01. The "D02-01-01-10-R" indicates that the peer end of the trunk cable connects to the receiving end of trunk cable 10 in slot 1 of subrack 1 in the cabinet of row D column 02.

II. Labels for Trunk Cables Between Devices and DDFs


Label contents Table D-4 describes label contents for a trunk cable between a device and a DDF. Table D-4 Label contents for trunk cables between devices and DDFs Label contents MN-B-C-D-R/T Meaning MN: cabinet number B: subrack number Example For example, A01. Two-digit numbers, from down to up. For example, 01. Two-digit numbers, from up to down and left to right. For example, 01.

C: slot number

Huawei Technologies Proprietary D-8

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix D Facture of Cable Labels

Label contents

Meaning D: cable number R: receiving optical port T: transmitting optical port

Example Two-digit numbers, from up to down and left to right. For example, 05.

M: A to Z, for each row of cabinets in an equipment room from front to back. MN: row and column numbers of the DDF DDF-MN-B-C-D/R/T B: row number of the terminal C: column number of the terminal D: A or B DDF-MN-B-C-D/R/T R: receiving optical port T: transmitting optical port N: 01 to 99, for each column of cabinets in an equipment room from left to right. For example, G01, that is, the DDF in row G column 01. Value range: 01 to 99. For example, 01-01. Such a mark is on each DDF. A: indicates that this group of DDF terminals connects with optical network devices. B: indicates that this group of DDF terminals connects with switching devices.

Label example Figure D-7 shows a label example for a trunk cable between a device and a DDF.

A01 AR

03 01 01

01

01

Figure D-7 A label example for a trunk cable between a device and a DDF In Figure D-7, A01-03-01-01-RThe "A01-03-01-01-R" indicates that the local end of the trunk cable connects to the receiving port of trunk cable 1 in slot 1, subrack 3 of the cabinet in row A column 01.

TO: DDF G01 Huawei Technologies Proprietary D-9

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix D Facture of Cable Labels

The "DDF-G01-01-01-AR" indicates that the peer end of the trunk cable connects to the receiving port of the A-direction terminal in row 1 column 1 of row G DDF in column 01.

D.5.4 Labels for DC Cables


Labels of this type apply to the AC cables for AC supply to cabinets, including 48 V, RTN (BGND in the earlier devices), and PGND cables. You must stick only on one side of the identification plate on a cable tie. Table D-5 describes the label contents for DC cables. Table D-5 Label contents for DC cables Label contents MN(BC)-48V1 MN(BC)-48V2 MN(BC)- RTN (BGND in the earlier devices) Description MN (BC): The location of "BC" is right below "MN". At the equipment cabinet side, use "MN" only, identifying the cabinet number. At the power distribution cabinet side, "MN" indicates the row and column numbers of power distribution devices such as control cabinet and cable distribution box. "BC" indicates the row and column numbers of 48 V connecting terminals on power distribution devices. If you can identify devices at either side without row and column numbers, leave "BC" blank. You do not need to mark row or column numbers on labels for RTN (BGND in the earlier devices) and PGND cables.

MN(BC)-PGND

A label for a DC cable contains only the location information of peer device. Figure D-8 shows only the label contents for two 48 V DC supplies. You can fill labels for PGND and RTN (BGND in the earlier devices) cables in a similar way.

TO: A01 B08

TO: -48V2 B03 -48V2

(1)

(2)

(1) Label contents on the cable end connecting with the equipment cabinet, that is, the location information at the power distribution cabinet side (2) Label contents on the cable end connecting with the power distribution cabinet, that is, the location information at the equipment cabinet side

Figure D-8 An example of label contents for DC cables

Huawei Technologies Proprietary D-10

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix D Facture of Cable Labels

In Figure D-8, The "A01/B08-48V2" indicates that the 48V2 cable comes from connecting terminal 8 on the 48 V busbar of row 2 in the power distribution cabinet of row A column 01. The "B03-48V2" indicates that the 48V2 cable comes from the equipment cabinet in row B column 03.

Note: Each terminal on the 48 V busbar has a numeric identification, like "08" in "A01/B08-48V2" in the above example. You only need to fill labels for PGND or RTN (BGND in the earlier devices) cables with the row and column numbers of power distribution cabinet. For example, "A01-RTN (BGND in the earlier devices)" on a label at the equipment cabinet side indicates that the RTN (BGND in the earlier devices) cable connects to the RTN (BGND in the earlier devices) busbar in the power distribution cabinet of row A column 01.

D.5.5 Labels for AC Cables


Labels of this type apply to the AC cables for AC supply to cabinets, including power, RTN (BGND in the earlier devices), PGND cables. Fill labels for AC cables with only cabinet numbers and "AC". Stick them only on one side of the identification plate on a cable tie. Table D-6 describes the label contents for AC cables. Table D-6 Label contents for AC cables Label contents Description MN: cabinet number or location number of power lead-in. MN-AC Mark the actual location of power lead-in. If you can identify socket locations by rows and columns, use the method numbering cabinets. If you cannot, mark specific locations to avoid confusing different socket locations.

A label for an AC cable contains only the location information of peer device, as shown in Figure D-9.

Huawei Technologies Proprietary D-11

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix D Facture of Cable Labels

TO:

TO:

A01 AC

B01 AC

(1)

(2)

(1) Label contents on the cable end connecting with the equipment cabinet, that is, the location information at the power distribution cabinet side (2) Label contents on the cable end connecting with the power distribution cabinet, that is, the location information at the equipment cabinet side

Figure D-9 An example of label contents for AC cables In Figure D-9, The "A01-AC" indicates that the cable connects to the power socket in row A column 01. The "B01-AC" indicates that the cable connects to the equipment cabinet in row B column 01.

D.5.6 Labels for Optical Fibers


Labels of this type apply to optical fibers that connect optical ports in subracks or stand-alone boxes. Labels for optical fibers fall into two types according to the types of optical fibers: Optical fibers connecting devices Optical fibers connecting devices with optical distribution frames (ODFs)

I. Labels for Optical Fibers Between Devicesbetween devices


Label contents Table D-7 describes label contents for an optical fiber between two devices. Table D-7 Label contents for an optical fiber between two devices Label contents MN-B-C-D-R/T Meaning MN: cabinet number B: subrack number Example For example, A01. Two-digit numbers, from down to up. For example, 01. Two-digit numbers, from up to down and left to right. For example, 01. Two-digit numbers, from up to down and left to right. For example, 05.

C: slot number

D: optical port number

Huawei Technologies Proprietary D-12

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix D Facture of Cable Labels

Label contents

Meaning R: receiving optical port T: transmitting optical port MN: cabinet number B: subrack number C: slot number

Example

They mean the same as those described in the above columns. If the peer and local devices reside in different equipment rooms, "MN" can be the name of the equipment room.

MN-B-C-D-R/T

D: optical port number R: receiving optical port T: transmitting port optical

Label example Figure D-10 shows a label example for an optical fiber between two devices.

A01 T

01 01 01

05

05 01

R TO: G01

Figure D-10 A label example for an optical fiber between two devices In Figure D-10, The "A01-01-05-05-R" indicates that the local end of the optical fiber connects to receiving optical port 05 in slot 05 of subrack 1 in the cabinet of row A column 01. The "G01-01-01-01-T" indicates that the peer end of the optical fiber connects to transmitting optical port 01 in slot 01 of subrack 1 in the cabinet of row G column 01.

II. Labels for Optical Fibers Between Devices and ODFsbetween devices and ODFs
Label contents Table D-8 describes label contents for an optical fiber between a device and an ODF.

Huawei Technologies Proprietary D-13

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix D Facture of Cable Labels

Table D-8 Label contents for an optical fiber between a device and an ODF Label contents Meaning MN: cabinet number B: subrack number Example For example, A01. Two-digit numbers, from down to up. For example, 01. Two-digit numbers, from up to down and left to right. For example, 01. Two-digit numbers, from up to down and left to right. For example, 05.

C: slot number MN-B-C-D-R/T D: optical port number R: receiving optical port T: transmitting optical port

M: A to Z, for each row of cabinets in an equipment room from front to back. MN: row and column numbers of the ODF N: 01 to 99, for each column of cabinets in an equipment room from left to right. For example, G01, that is, the ODF in row G column 01. ODF-MN-B-C-R/T B: row number of the terminal C: column number of the terminal R: receiving optical port T: transmitting optical port Value range: 01 to 99. For example, 01-01.

Label example Figure D-11 shows a label example for an optical fiber between a device and an ODF.

ODF G01 05 05 R

01

01 01

R TO: A01

Figure D-11 A label example for an optical fiber between a device and an ODF

Huawei Technologies Proprietary D-14

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix D Facture of Cable Labels

In Figure D-11, The "ODF-G01-01-01-R" indicates that the local end of the optical fiber connects to the receiving optical port on the terminal of row 01 column 01 on the ODF of row G column 01. The "A01-01-05-05-R" indicates that the peer end of the optical fiber connects to transmitting optical port 5 of the board in slot 5, subrack 1, row A cabinet in column 01.

D.6 Deciding Information Places on Labels


This section introduces how to decide information places on a label based on the information on the label.

I. Power Cable Labels


Stick power cable labels only on one side of identification plates. A power cable label contains only location information about the peer end of a cable, like the location of peer control cabinet, cable distribution box, or power socket.

II. Signal Cable Labels


The two sides of the label stuck on a signal cable contain location information about the ports connected to both ends of the cable. You must fill a label in the right places, as shown in Figure D-12.
Area 1 Area

Figure D-12 Parts on a signal cable label Fill area 1 with information about the local end of a cable. Fill area 2 with information about the peer end of the cable. There is a typeface "TO: " in area 2. Leave area 3 blank. It is the folded part. Seen from the leading-out end of a cable, the text part of its label is on the right side of the cable. The side with "TO:" that faces outside contains the peer location information. The other side contains the local location information. Therefore, the information in area 1 at one end of a cable is the same as the information in area 2 at the other end. In other words, the local information at one end is called the peer information at the other end.

TO:

Area 2

Huawei Technologies Proprietary D-15

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix D Facture of Cable Labels

D.7 Printing or Writing Labels


You can print or write information on labels. Printing is more efficient and more pleasing to eyes.

D.7.1 Printing Labels


The following describes how to print labels.

I. Obtaining the Print Template


You must use the print template to print labels. By the following means, you can obtain the print template: Download it from http://support.huawei.com/default.asp. Ask Huaweis local office for it.

II. Setting the Print Template


When setting the print template, conform to the following principles: Directly change the contents on the template in accord with the actual cable locations. However, be sure not to change template specifications such as the settings of centered characters, directions, or fonts. Zoom out characters only when they are too many to be held. Make sure that the printouts are clear and legible.

III. Setting Printer Properties

Caution: If a prompt box is displayed as shown in Figure D-13, click <Ignore> to continue printing. You must set printer properties as above mentioned for the first use of the print template. After setup, you can save the settings and invoke them when needed. Labels are made up of special materials. Auto paper feeding may cause paper jam. Therefore, you must manually feed paper one piece after another.

Figure D-13 Prompting overstepped margins in the process of printing


Huawei Technologies Proprietary D-16

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix D Facture of Cable Labels

Before printing labels, set up pages, and adjust page settings by trial printing. Proceed as follows: 1) 2) 3) 4) 5) Use a laser printer of any model. Check that the settings of printer properties such as "Paper size" and "Direction" are correct. Print on blank ordinary print paper. Put the printed paper on a piece of standard label paper. Check whether they match. If yes, print property setup ends. If no, go on with step 6. 6) 7) 8) Select [File/Page Setup]. Change the specifications under the tab [Margins]. Repeat steps 2 to 4 until the printout matches a standard label.

IV. Checking Print Effects


Check that printed labels meet the following requirements: All printouts are within writable cells on labels. Center the contents in each cell. In a single line printout, avoid printing characters on dividing lines and the typeface "TO:". If you must merge several cells and print a piece of information in several lines, adjust the positions of printed contents to avoid overlapping characters on labels.

D.7.2 Writing Labels


When writing information on labels, conform to the following principles: Use black oil markers delivered with the device. Write labels with the smaller nib of a black oil marker. Write labels in accord with the standard typefaces as listed in Table D-9. Table D-9 Standard typefaces 0 9 I R 1 A J S 2 B K T 3 C L U 4 D M V 5 E N W 6 F O X 7 G P Y 8 H Q Z

Write characters in proper size, and in the direction as shown in Figure D-14.

Huawei Technologies Proprietary D-17

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix D Facture of Cable Labels

1
05

A01
1 5

A
B02

06
TO: 0
Cable Fold down Stick side Cable Stick side

Figure D-14 A label example

D.8 Sticking or Binding Labels


After printing or writing labels, stick or bind them on cables as required.

I. Sticking Signal Cable Labels


Proceed as follows: 1) Decide where to stick labels. Usually, stick them 2 cm away from connectors.

Note: Avoid sticking labels at bent parts of cables or any other location that may affect cable installation. In such special cases, you can flexibly decide label locations. Anyway, you must stick labels in the same style.

2)

Stick labels. a) b) Fold label tails around cables as shown in Figure D-15. Stick label tails.

Fold to right

Figure D-15 Folding label tails 3) Fold labels along cut dotted lines as shown in Figure D-16.

Huawei Technologies Proprietary D-18

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center


Cable Stick side

Appendix D Facture of Cable Labels


Cable

Fold up

Stick side

Fold to right

Figure D-16 Folding labels along cut dotted lines 4) Check label appearances. Check that labels are stuck in accord with specifications and in the same style, as shown in Figure D-17.
Cable

Cable

TO: 1 A01 2

TO: 1 A01 2

A 06

A 06

(a)

(c)

(d)

(b)

(a) The identification plate on a horizontally routed cable faces up (seen from the cable front). (b) The identification plate on a horizontally routed cable faces up (seen from the cable ends). (c) The identification plate on a vertically routed cable faces right (seen from the cable front). (d) The identification plate on a vertically routed cable faces right (seen from the cable ends).

Figure D-17 Stuck labels

II. Binding Power Cable Labels


Proceed as follows: 1) Decide where to bind labels. Usually, bind cable ties 2 cm away from connectors.

Huawei Technologies Proprietary D-19

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix D Facture of Cable Labels

Note: Avoid binding labels at bent parts of cables or any other location that may affect cable installation. In such special cases, you can flexibly decide cable tie locations. Anyway, you must bind labels in the same style.

2)

Stick labels. Stick labels on one side of identification plates on cable ties. You must stick labels in an equipment room in the same style. Stuck labels must be within the rectangle ruts of identification plates.

3) 4)

Bind the cable ties. Check label appearances. Check that all identification plates are facing right or up. That is, those on horizontally routed cables are facing up and those on vertically routed cables are facing right, as shown in Figure D-18.
Cable

B03 -48V2

TO:

TO: B03 -48V2

Cable

(a)

(b)

(a) The identification plate on a horizontally routed cable faces up. (b) The identification plate on a vertically routed cable faces right.

Figure D-18 Bound labels for power cables

D.9 Checking Labels


Check that: All information on labels is correct. Labels are stuck or bound in accordance with criteria.

Huawei Technologies Proprietary D-20

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix E Environment Requirements for Equipment Operation

Appendix E Environment Requirements for Equipment Operation


E.1 Observed Standards
The document is based on the standards of the Peoples Republic of China. If the onsite situation is not consistent with the document, refer to the local standards and regulations.

E.2 Requirements for Equipment Room


E.2.1 Site Requirements
The communication equipment should run in a good environment. Its equipment room should be located at a place free from high temperature, dust, toxic gases, explosive materials or instable voltage, and away from great vibrations, strong noise or power transformer stations. During project designing, such factors as hydrographic, geological, seismic, power supply and transportation should be taken into account, and the site should be selected in line with the engineering and environmental requirements. The construction, structure, heating and ventilation, power supply, lighting, and firefighting designs of the equipment room are done by specialized construction designers, and the environment design requirements of the switch should be strictly met. The equipment room shall be designed in line with the industrial, environmental protection, fire-fighting and civil defense requirements, as well as the current standards/regulations of the local country or region and the requirements of special technical process for building construction design. Site requirements are as follows: The site should be kept away from pollution sources. For sources of heavy pollution such as the smeltery and coal mine, keep a distance of 5 km. For sources of medium pollution such as the chemical, rubber and galvanization industries, keep a distance of 3.7 km. For sources of light pollution such as food and tanner industries, keep a distance of 2 km. If the sources of pollution cannot be avoided, the equipment room must be in the perennial upwind direction of the pollution sources. Besides, quality equipment room or protection product must be adopted. The ventilation port for air exchange of the equipment room must be kept away from the exhaust of city waste pipes, big cesspools and sewage treatment tanks. The equipment room should be kept in the positive pressure state lest the

Huawei Technologies Proprietary E-1

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix E Environment Requirements for Equipment Operation

corrosive gases enter the equipment room and erode components and circuit boards. The equipment room should be kept away from the industrial and heating boilers. It is best to locate the equipment room in or above the second floor. If this requirement cannot be met, the ground for equipment installation in the equipment room shall be at least 600 mm above the maximum flood level in the local record. The equipment room should be kept away from livestock farms. If this requirement cannot be met, it should be located in the perennial upwind direction of the livestock farms. The equipment room should be kept 3.7 km away from the seaside or salt lake. If this requirement cannot be met, the equipment room should be airtight with cooling facilities. Besides, the alkalized soil cannot be used as the construction material. Otherwise, the equipment applicable in atrocious environment must be adopted. The old livestock room or the chemical fertilizer warehouse cannot be used as the equipment room. The equipment room should be solid enough to withstand wind and downpour. The equipment room should be kept away from the road or sand field with dusts flying around. If this requirement cannot be met, the windows and doors of the equipment room should be kept away from the sources of pollution

E.2.2 Equipment Room Composition


The equipment room is used to install main communication devices, communication transmission devices, power supply devices, and other auxiliary devices. To facilitate maintenance and management, it is required to install them in different room. Figure E-1 shows the layout of equipment room.
Control room Diesel generator

Transmission room

Switching room Communication cable and optical fiber Power cable

Power distribution room

Battery room

Power transformation room

Figure E-1 Equipment room layout The overall layout principles are as follows:

Huawei Technologies Proprietary E-2

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix E Environment Requirements for Equipment Operation

The equipment room layout meets the requirements for laying communication cables, power cables, and maintenance. Make the cable routes as short as possible to facilitate maintenance, reduce line cost and communication faults, and improve work efficiency.

E.2.3 Building Requirements


Table E-1 shows the requirements for the building specifications of the equipment room. Table E-1 Requirements for building specifications of the equipment room Item Area Net height Specification The equipment room can hold the whole equipment. The indoor minimum height is the net height under beam or air pipe. The net heath must not be less than 3 meters. It is required that the floor is semi-conducting and dust-free. Generally, it is required to pave ESD-preventive floor. The floor blocks must be paved securely, and the error per square meter must not be more than 2 mm. If there is not raised floor, it is required to use static-conducing material (size to impedance 7 10 ratio is 1.0 x 10 to 1.0 x 10 ). The static-conducting material or raised floor must be well connected to grounding device through current-limited resistance and connection cable. The impedance of current limit resistance is 1 M. More than 600 kg/m
2

Indoor floor

Floor load bearing capacity

Door and window

The door is 2 meters high and 1 meter wide. It is OK to use one door panel. It is required to seal the door and window by dust-proof rubber tape, and use double-layer windows and seal them. It is possible to paste wall paper or paint lusterless paint on the wall, but chalked paint is not recommended. Groove is used to lay cables. It must be clean inside. The reserved length, width, the number of holes, the hole positions and hole size must comply with the requirements for the layout of optical synchronous transmission devices. The power supply pipe, drainage pipe and rain pipe must not pass through the equipment room, and fire extinguisher should be equipped where it is easy to find and access, such as corridor or staircase, instead of in the equipment room. The installation place must be separated from the door of the equipment room. The partition panel will be helpful to prevent some dust. The partition is shown in Figure E-2. The outlet air of the air conditioner must not directly point to the equipment.

Wall surface

Indoor groove

Water supply and drainage

Partition in equipment room Air conditioner position

Huawei Technologies Proprietary E-3

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix E Environment Requirements for Equipment Operation

Item Other requirements

Specification In the equipment room, specific measures must be taken to prevent epiphyte and mildew, as well as rodent animals, such as mouse.

(1) (2)

(3)

(1) Air conditioner

(2) Equipment

(3) Partition panel

Figure E-2 Partition in equipment room

E.2.4 Humidity and Temperature Requirements


To ensure that the equipment operates in good condition, the humidity and temperature must be kept within a certain range in the equipment room. Table E-2 shows the specific requirements. Table E-2 Humidity and temperature requirements Temperature Long term +5 C +45 C Note: The measurement points of temperature and humidity refer to the values measured 1.5 m above the floor and 0.4 m away from the front side of the cabinet when there are no protection panels in the front and back of the cabinet. Short term means that the consecutive working duration is not more than 96 hours and that the accumulated working duration of a year is not more than 15 days. Short term 5C +55C Long term 5% 85% Relative humidity Short term 5% 95%

To meet the above requirements, the following measures must be taken in the equipment room:

Huawei Technologies Proprietary E-4

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix E Environment Requirements for Equipment Operation

The temperature control facility is equipped in the equipment room. Humidifier can be used in dry areas. It is also possible to use wet mop to mop the floor to keep the humidity. In areas with high humidity, desiccating machine can be used.

E.2.5 Air Cleanness Requirements


The dust accumulated on the equipment may cause static attached, which might cause metal connectors or metal contacts in bad contact. This will affect the life of the equipment, and bring the equipment with faults. In the equipment room, there must not exist explosive, conducing, magnetic-conductive, or erosive dust. Table E-3 shows the requirements on dust density. Table E-3 Dust particle limit in the equipment room Mechanically active material Dust particle Unit 310 particle/m
4

Content (There is no visible dust on desk within 3 days)

Note: Dust particle: diameter 5 m

To meet the above requirements, the following measures must be taken in the equipment room: Dust-free materials must be used on the floor, walls, and ceiling. Door screen and window screen must be used for the doors and windows toward outdoors. The windows must have dust-proof function. The equipment room and dust filter of the equipment must be cleaned periodically (every 3 months). People entering the equipment room must wear ESD-preventive shoes, ESD-preventive suits, and ESD-preventive wrist straps.

E.2.6 Erosive Gas Condition Requirements


Besides dust-proof measures, erosive gas proof measures must be taken in the equipment room to prevent such gases as SO2, H2S, and NH3. Table E-4 shows the requirements on the density of erosive gases.

Huawei Technologies Proprietary E-5

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix E Environment Requirements for Equipment Operation

Table E-4 Erosive gas density limit Chemically active material SO2 H2S NH3 Cl2 mg/m mg/m mg/m mg/m Unit 0.20 0.006 0.05 0.01 Content

To meet the above requirements, the following measures must be taken in the equipment room: The equipment room must be far away from the areas with high density of erosive gases, such as chemical plants. The air inlet must be against the pollution sources. The storage batteries must be placed separately in an independent room. It is required to ask professional company to inspect the environment periodically.

E.2.7 Electromagnetic Requirements


Table E-5 shows the electromagnetic requirements. Table E-5 Electromagnetic range Environment electromagnetic Low-frequency magnetic field Amplitude-modulation radio-frequency electric field Pulse-modulation radio-frequency electric field Frequency (Hz) Ampl. A/m (rms) Frequency (MHz) Ampl. V/m (rms) Frequency (GHz) Ampl. (V/m (peak)) Parameter 50 to 20,000 10 to 0.025 0.009 1,000 3 1 20 3

The following measures can be taken to suppress the interference signals: The equipment must be far away from transformer, high-voltage electricity transmission lines, and high-current devices. For example, there is no AC transformer within 20 square meters, or high-voltage electricity transmission lines within 50 square meters. The equipment must be far away from high-power broadcast transmitter, for example, there is no high-power broadcast transmitter within 500 square meters. If there is mobile communication transmitter in the equipment building, the interference must comply with related requirements, and shielding measures must be taken to prevent the interference.
Huawei Technologies Proprietary E-6

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix E Environment Requirements for Equipment Operation

In the equipment room, it is prohibited to use wireless handy set near the equipment.

E.2.8 ESD-Preventive Requirements


The absolute voltage of electrostatic must be less than 1000 V. To meet the above requirement, the following measures must be taken in the equipment room: All operators must be trained on ESD prevention knowledge. The humidity must be kept within a certain range to reduce the effect by electrostatic. The equipment room must have ESD-preventive floor. People entering the equipment room must wear ESD-preventive shoes and ESD-preventive suits. ESD-preventive tools like ESD-preventive wrist straps, ESD-preventive tweezers, and extraction tools must be used. Conductors (including computers) in the equipment room must be grounded, and the ESD-preventive workbench must be set up. Electrostatic resources like non-ESD-preventive plastic bags, non-antistatic foam, and rubber must be at least 30 cm away from ESD-sensitive components and boards.

E.2.9 Lightning Protection Requirements


Table E-6 shows the lightning protection requirements. Table E-6 Lightning protection requirements Item Description It is better that the equipment building is of reinforced concrete structure. Building requirements The equipment building must have lightning arrester. The ground for lightning arrester of the equipment building and the protection ground of the equipment room share the same group of grounding bodies. The communication office has dedicated power transformer. The power cables must have metal bushing or insulation bushing, and are led in to the office through metal pipe under ground. The metal bushing or metal pipe must be grounded at both ends. The length under group must be not less than 15 meters. The three phase lines at the low-voltage side of the AC transformer in the communication office must have separate gapless zinc oxide lightning protector. The shell of the transformer, the AC neutral line at the low-voltage side, and the metal bushing of the power cable connected to transformer shell must be grounded nearby.

AC power supply system adopts TN-S power supply

Huawei Technologies Proprietary E-7

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix E Environment Requirements for Equipment Operation

Item

Description It is not allowed to lead in or out the AC or DC power cables to/from communication office in overhead way. After low-voltage power cables are led into the equipment room, lightning protector must be installed for the power cables in the AC voltage regulator and AC switchboard, and the lightning protector must be grounded nearby. In the city, it is recommended to use power lightning protector with nominal discharge current of more than 20 kA. In the suburbs with more lightning dangers, it is recommended to use power lightning protector with strike through-flow of more than 60 kA. In mountains or higher buildings in the city, it is recommended to use power lightning protector with strike through-flow of more than 100 kA. The length of grounding cable for power lightning protector must be less than 1 meter. The DC working ground of the communication office (positive of 48V or negative of 24V) must be connected to the indoor grounding bus nearby, and the grounding cable must satisfy the requirements for the maximum load of the equipment. The power supply devices for the communication office must have DC working grounding cable connected to the grounding bus in the communication building or the protection grounding bar in the equipment room. The communication equipment and auxiliary devices, such as mobile base station, transmission device, switching device, power supply device, and cable distribution rack, must be well grounded. Their protection grounds must be connected to the grounding bar in the equipment room. The working ground and protection ground of the communication equipment in the equipment room share the same ground net. The cabling rack, suspension metal bracket, cabinet or shell, metal air vent and metal doors and windows must be well grounded.

Lightning protector for incoming power cable

DC power distribution grounding

Equipotential connection

Grounding requirements

It is prohibited to connect the neutral line of AC power cable to protection ground of the communication equipment. It is prohibited to use fuse or switch on the grounding cables. All grounding cables must be as short and straight as possible. The grounding impedance is recommended to be not more than 10.

Grounding impedance requirements

The upper part of the grounding body must be more than 0.7 m from the ground. In cold areas, the grounding body must be buried under frozen soil layer. It is required to measure the grounding impedance periodically, to ensure the validity of grounding.

Huawei Technologies Proprietary E-8

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix E Environment Requirements for Equipment Operation

Item

Description In the communication office, signal cables must be laid underground.

Signal cable layout requirements

The communication cables must have metal bushing or be laid in metal pipe when they are led in or out of the communication office. The grounding cable for lightning protector must be as short as possible, and unused wires in the cables must be well grounded in the equipment room. The grounding bus can be realized in grounding ring mode or grounding bar mode.

Grounding bus requirement

The grounding cable must not be aluminum. When different kinds of metals are connected, correct measures must be taken to prevent couple corrosion. The grounding bus cable is made of copper bar with sectional area 2 of not less than 120 mm or zinc-coated steel with the same impedance. The grounding bus cable must be insulated from the steel of the building. The grounding lead-in cable must not be longer than 30 meters, and it is recommended to use zinc-coated steel with sectional area of 40mm x 4mm or 50mm x 5mm as the material.

Grounding lead-in cable requirement

E.3 Requirements for Power Supply


E.3.1 Requirements for AC Power Supply
I. Generic Requirements on AC Power Supply
Adopt the centralized AC power supply model of mains, uninterrupted power supply (UPS), and a reserved diesel generator. Ensure simplicity in cable connection, security in operation, flexibility in scheduling, and convenience in maintenance. Adopt three-phase and five-wire, or monophase three-wire AC power for low-voltage power supply system. Table E-7 lists the nominal voltage and rated frequency of low-voltage power supply system. Table E-7 Specifications of AC voltage and frequency Nominal voltage 110/127/220/380 V 50 Hz Rate frequency

Adopt UPS for the backup AC power supply. Keep it the same phase with mains. Set the switching time between mains and UPS less than 10 ms; otherwise, the product will reboot or reset itself.
Huawei Technologies Proprietary E-9

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix E Environment Requirements for Equipment Operation

Ensure that the equipment runs well below nominal current; never in the threshold of failure. For the AC power supply for the equipment room, consider the current when the devices are working or at fault. Use a separate AC power supply protection unit for a piece of separate device. The rated current to trigger the protection should be greater than the sum of the rated current for all the lower lever devices. When designing the DC power supply system, consider the maximum static and dynamic load of the system. Always keep sufficient room for the two thresholds. Choose the model of the power cables by the maximum load of power supply. The diesel generator set of the office automatically functions in case of power failure, automatically supply when the mains is insufficient, and automatically stops functioning when power restores. It can be tested and controlled remotely in standard interface and communication protocols.

II. Power Supply Specifications of AC-Powered Equipment


Here are the power supply specifications of AC-powered equipment: Voltage fluctuation of communications equipment: 10% +5% of rated voltage. Voltage fluctuation of power supply equipment and important buildings:15% +10% of rated voltage. Frequency fluctuation:4% +4%. Aberration rate of voltage sine wave: 5%.

III. Specifications of Power Cables


Here are the specifications of the power cables: Use the neutral line of the same cross-sectional area as the live line. Select the DC power feeder according to the long-term payload. If the cross section exceeds 95 mm2, use the hard bus cable. If there is a great difference between the recent and long-term payload, make the cabling by stages. Use fire-resistant AC cables. Route cables according to the local regulations, and set the low-voltage power distribution room according to the local regulations.

E.3.2 Suggestions on AC Power Supply


When the voltage of mains power supply is not stable, use the voltage regulator in any of the following conditions: Powered by mains, the voltage fluctuation of communications equipment exceeds the rated threshold (10% +5% of rated voltage). Powered by mains, the voltage exceeds the rated voltage fluctuation of communications equipment. Not directly powered by mains, the voltage fluctuation exceeds the rated threshold (15% +10% of rated voltage).

Huawei Technologies Proprietary E-10

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix E Environment Requirements for Equipment Operation

The voltage exceeds the rated AC voltage fluctuation of DC power supply equipment. Use UPS or inverter to prevent interruption or surge of power supply. Use a diesel generator set when the mains is faulty. The capacity of the generator set should 1.5 to 2 times of the capacity of UPS. Use two groups of storage batteries in parallel. Use one group of UPS storage batteries. The batteries can be working in parallel or serial connection. Use main inverter based on the maximum power. Keep a backup one.

E.3.3 Requirements for DC Power Supply


Ensure stable power supply. Close the power supply equipment to the communications equipment to minimize the feeder line. The voltage level between battery and the equipment should be less than 3.2 V. When there are more than two switching systems, use two or multiple independent power supply systems. Set up multiple independent power supply systems for important communication centers, each of which powers a separate equipment room. For ordinary offices, adopt the model of a centralized power supply room plus a battery room. For small-capacity offices, adopt the centralized power supply model. Always prevent the boards from the erosive chemicals given out from batteries. Table E-8 specifies the requirements on DC power supply. Table E-8 DC power supply specifications Item Voltage fluctuation of 48-V input end Anti-surge current capability 40 V 57 V Should be 1.5 times greater than the rated load current capability. When the AC input voltage range is from 85% to 110% of the rated value, and the load current is from 5% to 100% of the rated value, the output voltage of the current stabilizer is an integral value between 56.4 and 46.0 V. The variance is less than equal to 1%. Less than equal to the integral value of DC output value 5% 200mV The recovery time is less than 200 ms. The exceeding amount should not be more or less than 5% of the rated DC output voltage. Specifications

Voltage stability

Voltage surge at power-on and power-off Peek-to-peek noise voltage Dynamic response

Huawei Technologies Proprietary E-11

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Appendix E Environment Requirements for Equipment Operation

E.3.4 Suggestions on DC Power Supply


Use the distributed power supply model. Scatter the power supply systems to multiple sites. Adopt standard DC power supply system. The output voltage of the power supply equipment should meet the requirement of the communications equipment. Enhance the reliability of the power supply system. Optimize the capacity of the storage batteries. In small-capacity offices, when it is difficult to maintain the reliability of the power supply system, expand the capacity of the storage batteries. The total configuration of high-frequency switch rectifier should meet the load power of communication and the recharging power of the storage batteries. Adopt the redundant configuration model for the rectifier module. Use a standby rectifier for less than ten active ones; and add one rectifier for every additional ten active ones. Equip the storage batteries in two or multiple groups. The total capacity is determined by the power feeding duration. Ensure at least one hour of power supply capability for the storage battery group.

Huawei Technologies Proprietary E-12

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Index

Index
Numerics
2 Mbit/s digital clock signal, 6-19 2 MHz analog clock signal, 6-17, 6-19 2 MHz internal clock cables, 6-17 8 KHz analog clock signal, 6-18 8 KHz internal clock cables, 6-18 power cable connector, C-1 RJ-45 connector, C-8 SMB connector, C-13 cable fitting installation installing PGND cables for cabinet doors, 7-6 cable manager, A-2 cabling mode, 6-6

A
accessories installing baffle ring, A-23 installing cable manager, A-22 installing rough rim and end cover, A-23 alarm cable, D-5 alarm system, 8-3 assembly of cable connectors mounting power cable connectors, C-1 mounting RJ-45 connectors, C-8 mounting SMB connectors, C-13

requirement, 6-5 cabling ladder, A-2 assembling, A-10 connecting to wall, A-13 jointing, A-13 turning at different levels, A-12 turning at the same level, A-11 cabling mode downward cabling, 6-8 upward cabling, 6-8 cabling rack components, A-1

B
BAM server, 4-5 BITS. see the building integrated timing supply system board, 4-7 bracket angle, A-2

installing process, A-3 specifications, A-1 cabling trough, A-2 connecting, A-15 installing obliquely, A-17 installing on 200 mm or 400 mm wide cabling ladder, A-16

C
cable between servers and KVMSs, 6-16 cable route, E-3 crimping, C-1, C-5, C-12, C-16 cutting, C-4 stripping, C-4, C-8, C-15 cable connection between a DC distribution cabinet and MSOFTX3000 cabinets, 5-13 cable connector

installing on 600 mm wide cabling ladder, A-16 calculating core area of power bus cable AC cable, B-1 DC cable, B-1 example, B-2 centralized power supply, E-11 checking the connector, C-7, C-13, C-17 clock cable external clock cable, 6-19 internal clock cable, 6-17 connecting clip, A-2 Huawei Technologies Proprietary i-1

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center connecting terminals in a DC distribution cabinet, 5-16 connection of a remote terminal system, 8-2 connection of a trunk cable and a WEPI, 6-21 connection position of a power cable and a PGND cable for a KVMS, 5-7 criming tool crimping cables, C-1 maintainance, C-2 SS-325 parts, C-1 crimping a cable, C-1, C-5, C-12, C-16 crimping sleeve, C-14 cutting a cable, C-4 precaution, D-3 printing or writing labels, D-16 procedure, D-3 sticking signal cable labels, D-18 fan box, 4-7 fixing cabling ladder, A-9 fixing clip, A-2 fixing support, A-9 flowchart hardware installation, 1-4 installing cabinet fittings, 7-3 installing external signal cables, 6-19 installing internal components, 4-5 installing internal signal cables, 6-9 installing peripherals, 8-1

Index

D
data cable between iGWB and hard disk array, 6-15 distributed power supply model, E-12

installing PGND cables and power cables, 5-6 making labels, D-4 mounting naked crimping connectors, C-3 mounting RJ-45 connectors, C-8 mounting SMB connectors, C-14

E
electrical performance check checking power supply to cabinets, 9-2 checking power supply to subracks, 9-3 checking working statuses of trial boards, 9-3 end cover, A-2 environmental protection, C-3 equipment installation hardware installation, 1-1 software installation, 1-1 system commissioning, 1-1 ethernet cable, 6-22 crossover cables, C-10 straight through cables, C-11 external signal cable, 6-19

front jointing, A-14

G
grounding grounding bus, E-9 grounding lead-in cable, E-9

H
hard disk array, 4-6 hardware installation assembly of cable connectors, C-1 core area calculation for power bus, B-1 facture of cable labels, D-1 hardware installation checks, 9-1 installation procedure, 1-3 internal component installation, 4-1

F
facture of cable labels binding power cable labels, D-19 checking labels, D-20 deciding information places on labels, D-15 deciding label contents, D-4

overview, 1-1 peripheral installation, 8-1 power cable installation, 5-1 prerequisite, 1-5 protection ground cable installation, 5-1 signal cable installation, 6-1

Huawei Technologies Proprietary i-2

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center hardware installation check checking cabinets, 9-1 checking cables, 9-1 checking connectors and sockets, 9-2 checking labels and equipment room environment, 9-2 checking power supply to cabinets, 9-2 checking power supply to subracks, 9-3 checking working statuses of trial boards, 9-3 electrical performance check, 9-2 overall check, 9-1 hardware system BAM, 1-2 iGWB, 1-2 OSTA platform, 1-1 service subrack, 1-2 heat shrinkable tube mounting, C-4, C-14 shrinking, C-7, C-17 power bus cable, 5-17 power cable, 5-1, 5-8, 5-12 protection ground cable, 5-1 signal cable, 6-1 installing external signal cables installing clock cables, 6-19 installing external ethernet cables, 6-22 installing trunk cables, 6-20 procedure, 6-19 installing internal signal cables installing 2 MHz internal clock cables, 6-17 installing 8 KHz internal clock cables, 6-18

Index

installing cables between servers and KVMSs, 6-16 installing data cables between iGWB and hard disk array, 6-15 installing internal clock cables, 6-17 installing PDB monitoring serial cables, 6-16 installing serial cables between iGWB servers, 6-14

I
iGWB server, 4-5 indoor cabling rack ceiling/floor installing, A-5 over-cabinet installing, A-9 wall installing, A-7 information places on labels power cable label, D-15 signal cable label, D-15 install peripheral grounding requirement, 8-4 installing BAM server, 4-5 board, 4-7 fan box, 4-7 hard disk array, 4-6 iGWB server, 4-5 internal component, 4-1 KVMS, 4-6 LAN switch, 4-6 peripheral, 8-1 PGND cable, 5-6, 5-12

installing straight through cables between LAN switches, 6-9 installing straight through cables between LAN switches and iGWB/BAM servers, 6-10 installing straight through cables between LAN switches and WHSCs, 6-12 installing straight through cables between WHSCs and WSIUs, 6-13 procedure, 6-8 installing PGND cables within cabinets installing for a BAM server, 5-7 installing for a KVMS, 5-6 installing for a LAN switch, 5-7 installing for a service subrack, 5-6 installing for an iGWB server, 5-7 installing for hard disk array, 5-10 installing power cables within cabinets installing power cables for BAM servers, 5-10 installing power cables for hard disk array, 5-10 installing power cables for iGWB servers, 5-10 installing power cables for KVMSs, 5-8 installing power cables for LAN switchs, 5-8

Huawei Technologies Proprietary i-3

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center installing power cables for service subracks, 5-8 Integrated configuration cabinet, 4-2 internal component, 4-1 internal component installation installing a KVMS, 4-6 installing boards in service subracks, 4-7 installing fan boxs in service subracks, 4-7 installing hard disk array, 4-6 installing iGWB and BAM servers, 4-5 installing LAN switchs, 4-6 precaution, 4-1 procedure, 4-1 internal signal cable connection, 6-1 correspondence between numbers and names, 6-3, 6-5 content, D-11 example, D-12 labels for DC cables content, D-10 example, D-10 labels for ethernet cables content, D-6 examle, D-7 facture principle, D-6 labels for optical fibers content, D-12, D-13 example, D-13, D-14

Index

labels for optical fibers between devices, D-12 labels for optical fibers between devices and ODFs, D-13 labels for trunk cables content, D-7, D-8

K
KVMS, 4-6

example, D-8, D-9 labels for trunk cables between devices, D-7 labels for trunk cables between devices and DDFs,

L
label bounding, D-20 feature, D-1 folding, D-18, D-19 labels for AC cables, D-11 labels for DC cables, D-10 labels for ethernet cables, D-5 labels for optical fibers, D-12 labels for trunk cables, D-7 material, D-1 power cable label, D-3 printing, D-16 signal cable label, D-2 structure, D-2 stucking, D-19 type, D-2 writing, D-17 label paper power cable, D-3 signal cable, D-2 labels for AC cables

D-8 LAN switch, 4-6 lightning arrester, E-7 lightning protector, E-8

M
mounting crimping sleeve, C-14 heat shrinkable tube, C-4, C-14 naked crimping connector, C-3 mounting naked crimping connectors checking the connector, C-7 crimping the cable, C-5 cutting the cable, C-4 mounting a heat shrinkable tube, C-4 shrinking the heat shrinkable tube, C-7 stripping the cable, C-4 mounting OT terminal an OT terminal, 5-19 two OT terminals, 5-20 mounting power cable connectors mounting naked crimping connectors, C-3

Huawei Technologies Proprietary i-4

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center using and maintaining criming tools, C-1 mounting RJ-45 connectors checking the connector, C-13 crimping the cable, C-12 inserting the cable into the connector, C-10 stripping the cable, C-8 mounting SMB connectors checking the connector, C-17 crimping the cable, C-16 mounting a crimping sleeve, C-14 mounting a heat shrinkable tube, C-14 shrinking the heat shrinkable tube, C-17 stripping the cable, C-15 welding a pin, C-15 movable bushing, A-2 pin, C-15 position

Index

position of the ground screw on a LAN Switch shell, 5-7, 5-8 power bus cable, 5-17 AC cable, B-1 DC cable, B-1 power cable, 5-1, 5-8, 5-12 Power cable for iGWB or BAM server, 5-9 power cable installation installation principle, 5-5 installation procedure, 5-5 installing power bus cables between DC distribution cabinets and DC switchboards, 5-17 installing power cables within cabinets, 5-8

N
naked crimping connector, C-3

power supply system, E-9 monophase three-wire, E-9 three-phase and five-wire, E-9

O
oblique jointing, A-15 open standards telecom architecture, 1-1 OSTA platform. see open standards telecom architecture OT terminal, 5-19, 5-20 outdoor cabling rack ground installing, A-20 wall installing, A-19 overall check checking cabinets, 9-1 checking cables, 9-1 checking connectors and sockets, 9-2 checking labels and equipment room environment, 9-2

Power supply system, 5-2 pressing mould, C-6 printing label ckecking print effects, D-17 obtaining the print template, D-16 setting printer properties, D-16 setting the print template, D-16 proof erosive gas proof, E-5 ESD-preventive requirement, E-7 protection ground cable, 5-1 protection ground cable installation installation principle, 5-5 installation procedure, 5-5 installing PGND cables between cabinets, 5-12 installing PGND cables between DC distribution

P
peripheral, 8-1 peripheral installation installing alarm devices, 8-3 installing terminal devices, 8-1 routing cables for terminal devices, 8-4 PGND cable, 5-6, 5-12, 7-6

cabinets and MSOFTX3000 cabinet, 5-12 installing PGND cables within cabinets, 5-6 installing power cables between DC distribution cabinets and MSOFTX3000 cabinet, 5-12 Protection grounding system, 5-4

Huawei Technologies Proprietary i-5

Installation Manual Hardware Installation HUAWEI MSOFTX3000 Mobile SoftSwitch Center

Index between LAN switches and iGWB/BAM servers, 6-10 between LAN switches and WHSCs, 6-12 between WHSCs and WSIUs, 6-13 stripping the cable, C-4, C-8, C-15

R
rectangular frame, A-2 remote terminal system, 8-2 RJ-45 connector, 6-10, 6-11

S
serial cable between iGWB servers, 6-14 monitoring serial cable, 6-16 service processing cabinet, 4-4 shrinking the heat shrinkable tube, C-7, C-17 side jointing, A-14 signal cable external signal cable, 6-1 installation requirement, 6-5 installing, 6-1 installing external signal cable, 6-19 installing internal signal cables, 6-8 internal signal cable, 6-1 introduction, 6-1 site requirement, E-1 storage battery, E-6 straight through cable between LAN switches, 6-9

structure alarm system, 8-3 MSOFTX3000, 1-3 service subrack, 1-1

T
the building integrated timing supply system, 6-19 triangular support, A-2 trunk cable, 6-20

U
universal alarm box, 8-3 upward cabling in a DC distribution cabinet, 5-15 U-shaped connecting piece, A-2 U-steel, A-2

W
welding a pin, C-15

i.

Huawei Technologies Proprietary i-6

Anda mungkin juga menyukai